2018 Colorado City Major Storm Event - ONCOR ELECTRIC RESTORATION EFFORT
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
INTRODUCTION • Brandon Campbell – Senior Engineer (Oncor) • Jerry Murphree – M&C Supervisor (Oncor) • Josh Holder – Project Manager (Primoris) tsdos.org
MAJOR STORM EVENT • Snyder, Loraine, & Colorado City TX-84 • Began @ 11pm on June 7th, 2018 SNYDER • 85-120mph wind speeds recorded I-20 – Straight-line; no tornadoes reported LORAINE • 10” of rain causing flash flooding COLORADO CITY tsdos.org
OVERALL IMPACT • 6x Oncor T-lines tripped to lock out w/in 47 min • 170x str.’s damaged • Miles of downed wire – CR’s, I-20, & UPRR • Major D-line impact tsdos.org
RESPONSE • FCC’s from other regions rendered aid • 160 const. contract personnel mobilized • Numerous internal groups utilized • Temporary kitting yard/emergency office est. in Colorado City, Texas tsdos.org
• The 4-69 kV line designs, were all similar, single pole and a total of 50 structures were replaced. Also all were located beside a paved roadway. • No conductor was damaged during this event tsdos.org
9-138 kV structures had to be replaced with 65’ wood poles and 30’ steel cross arm These structures were located in an open field and very wet conditions tsdos.org
TONKAWA – MORGAN CREEK • 21.3 miles of 345 kV line • (2) 795.9 ACSR & 2x 3/8” EHS Shield wire • H-frame lattice towers – height range = 72’ - 87’ • Constructed in 1982 • Kickers (16)/storm guys (2) installed in 2005 tsdos.org
TONKAWA – MORGAN CREEK WITH KICKERS ORIGINAL tsdos.org
TONKAWA – MORGAN CREEK • 17.3 miles initially effected • 92x structures damaged – 87x failed; 5x long. deflection tsdos.org
345 kV INVESTIGATION • 138 kV line (S. of I-20) tripped approx. 30 sec. after 345 kV • ≈ 500 ft/sec fall rate • Mode = Leg buckling • AHF3 (TESCO-1961) – NO longitudinal load requirements from NESC (5th Edition) tsdos.org
RESTORATION • 6919X-family lattice towers • Developed during CREZ • 959.6 ACSS/TW/HS “Suwannee” • 48-count OPGW & 7/16” EHS tsdos.org
TONKAWA – MORGAN CREEK POWER SECURE PRIMORIS tsdos.org
RESTORATION EFFORT Primoris T&D Services is one of 22 well-funded companies within Primoris Services Corporation, with approximately 1,800 employees. tsdos.org
PROJECT SEQUENCING - BEGAN WITH MOBILIZATION & WRECK OUT Mobilization: June 8th, 2018 • Dispatching, crews were sent for initial assessment after notification of the event • Scope, Construction procedures were determined • Crew/equipment assignment • ROW installation Wreck out, Removals • Road clearing to allow traffic to flow on roadways • Disassembly, removal of retired structures • Haul off, removing steel from ROW • Disposal of retired steel • Retired foundation removal tsdos.org
Project Sequencing Continues Foundations: • Engineering designs received • Vendors notified • Material ordered • Material Receiving • Rebar assembly • Drilling • Crews: set up, pouring, and wreck out • Production expectation tsdos.org
Project Sequencing Continues Steel • Engineering designs received • Material Receiving • Hauling • Assembly crew make up • Structure setting • Production rates tsdos.org
Project Sequencing Completed – Project Success Wire • Engineering • Material receiving • Material Spotting • Wire stringing efforts • Fiber stringing efforts • Production rates tsdos.org
Project Sequencing Completed – Project Success tsdos.org
OVERALL PROJECT SUCCESS! tsdos.org
tsdos.org
tsdos.org
345 kV Hardening Initiative • 230 miles of existing H-frames • Complete by end of 2021 • Tier 1: Major Highway/RR – 2x deadends • Tier 2: Minor Highways – 1x deadends • Tier 3: 10-mi. sections – 1x deadends tsdos.org
LESSONS LEARNED • Importance of communication • Cascading failure mechanisms • Material procurement details • Focused training necessary for better overall understanding tsdos.org
LESSONS LEARNED • Residual tension retained in “failed” structure • Proximity of still-standing structures • Amount of recoil when cut • Location/direction to snub- off tsdos.org
tsdos.org
CONCLUSION & QUESTIONS tsdos.org
You can also read