EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico

Page created by Jonathan Dennis
 
CONTINUE READING
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
EN-HE L2 – PS – PSB – TT2
works during YETS 2017-2018
C. Bertone on behalf of EN-HE
26/10/2017
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
Before the YETS-PSB (PSB-LIU)
• Manual crane, extension BRF2
 • All material delivered
 • Supports traced by SU in the vault
 • Installation foreseen in November
 • Necessary for the 2nd part of YETS
   (after cable pulling) to install the power
   converters
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
YETS-PSB-I (PSB-LIU)
• Cover for the enlarged
  tremie:
  • arrived
  • some modifications are
     necessary to adapt the
     barriers in situ (design on-
     going, soon the Impact)
  • Test for installation in
     YETS
  • It won’t remain in place (no
     need to walk on the tremie
     before LS2
  • Needs to be stored
     somewhere in the PSB
     (basement in vertical
     position?): this is an
     infrastructure belonging to
     the PSB, no need for
     transport
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
YETS-PSB-II (PSB LIU)
•   Manuel crane for BSW (IR) – to be coupled with PSB ring cranes
•   Lifting jacks and trolleys delivered
•   Delivery of crane structure in Mid November
•   Installation and tests during YETS
•   All ok for LS2
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
YETS L2-L3-PS
• No HE installations
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
LS2-PS (L4-PSB connect)
• Telescopic crane in the PS switchyard (BI-LBE-
  LBS)
• Delivery of the crane in November 2017,
  installation when needed (planned for LS2)
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
LS2-L2 (L4-PSB connect)
• Displacement of the electric + hydraulic board
  of the lift to allow SMB to poor a new shielding
  wall
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
Preventive Maintenance (cranes and hoists)
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
Preventive Maintenance (lifts)
Only usual maintenance and inspection
EN-HE L2 - PS - PSB - TT2 - works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017 - CERN Indico
Handling operations PSB in YETS
•   Power converters installation BRF2 and BAT361 (installation of temporary steel
    floor on the false floors)
•   Support to CV for ventilation duct above the ring, injection & extraction ?
• Anything else?
•   Nothing announced for Linac 2?
Handling operations PS Ring and TT2 line in
                      YETS

• Removal of 32 magnets (all) in the ATP loop + consolidation works of
  15 magnets in the TT2 (Consolidation project)*
    • Time constraint
    • Dimensions of the shaft (reduced with years) and height of the ATP
       doors are the major technical constraints that we had to address
• Installation of L3 Ion Dump: exchange of the actual vacuum pipe with a Y
  one equipped with a small dump (LIU-Ions) in the switchyard*
• Decabling of the central galleries of PS + building 368, 359, 353: support to
  EL (removal of containers….)*
•    installation New Rotatable Beam Wire Scanner Prototype**
•    Installation of 9 BPM into the injection line between LEIR and PS**

        *well in advance contact with Tech cord plus ad-hoc meeting with the owner groups
                                                          ** discovered by reading an ECR
Dismantling of ATP loop
                  •    14 PXMBHFDCWP type B190 voir lien pour détails: https://norma-
                       db.web.cern.ch/magnet/idcard/818/
                  Ces 14 aimants seront pris en charge par SMB-SC-LS et seront stockés au bâtiment
                  954. Prévoir gerbage des aimants et mis à disposition de cales de stockage mis en
                  place par SMB.
                  •    10 PXMQNCINWP type Q50 voir lien pour détails : https://norma-
                       db.web.cern.ch/magnet/idcard/1992/
                  Ces 10 aimants seront envoyés aux déchets radioactifs, pris en charge par le
                  service HSE-RP-AS.
                  •    1 PXMBXHDCWP type HB2l voir lien pour détails : https://norma-
                       db.web.cern.ch/magnet/idcard/7114/
                  •    1 PXMQNCENAP type Q42 voir lien pour détails: https://norma-
                       db.web.cern.ch/magnet/idcard/1967/
                  •    6 SPMDV__CAP type MDV voir lien pour détails: https://norma-
                       db.web.cern.ch/magdesign/idcard/558/#1
                  Ces 8 aimants seront stockés au bat 151 ou au bat. 954, à confirmer.
                  (minutes from D. Bordart)
Consolidation of ~15 quadrupoles into the
TT2 line
 • Removal of magnets (bunch of 5) from TT2 line and installation into the ATP
   loop for VCS and MSC works
 • Removal of old magnets via shaft into the AD square
 • Arrival of new magnets
 • Installation in the ATP loop for VSC and MSC works
 • Installation into the TT2 line
Transport request
• Don’t wait the last minute for making your
  transport and handling request
https://edh.cern.ch/Document/SupplyChain/TransportRequest

• Especially with TREC

• But before doing the EDH requests, please
  contact the HE contacts to discuss about your
  operation, plan and solve problems timely
Contacts
• Handling operations supervision
Yann Seraphin 160119 (Julien Fermanel 164966)

• Crane maintenance
Helder Lourenco 166012 (Gilles Roche 164084)

• Lift maintenance
Nicolas Perez 169285 (Damien Lafarge 168786)
Impacts
• For our activities (HE installations) -> to be
  created
• For handling operations -> please add the
  contaact persons as supervisor
      and use the e-groups:
      - en-dep-he-hh
      - S172-Transport-ALTEAD
Any questions or comments?
You can also read