Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...

Page created by Arthur Rodgers
 
CONTINUE READING
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
Program Delivery Update
Project Milestones and
Accomplishments
KEVIN J. DAYTON, PE, Chief Engineer,
Asst. Secretary Regions & Mega Program
ACEC/WSDOT Annual Meeting, Bellevue, Washington
June 7, 2018
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
Delivery remains a key focus at WSDOT
Connecting Washington delivery                          1

       10 highway construction contracts (6 projects) completed, valued at $28.9
       million
               90% completed on time, on budget 3
       14 highway construction projects, with a combined value of $1.2 billion
       underway
               71% were advertised on time

Nickel and TPA Project delivery                     2

       380 highway construction projects completed, valued at $9.7 billion
               87% completed on time
               91% on budget
       6 highway construction projects, with a total value of $5.6 billion underway
               100% advertised on time
1) On time and on budget based on schedule and budget at the time of project authorization
2) On time and on budget based on schedule and the current legislative expectation at the
time the milestone was achieved
3) One Connecting Washington project was delivered over its initial budget. This was a sub-
project on the I-405 Renton to Bellevue Corridor Widening project. The overall corridor project
remains on budget.

                                                                                                  2
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
I-90 Snoqualmie Pass East
              Work this summer
              •   Finish paving new eastbound and westbound lanes
              •   Construct embankment along Keechelus Lake
              •   Finish building new bridges, including wildlife crossing
              •   Phases 1C and 2 will be finished by fall 2018, completing first 7 miles
                  of the 15-mile corridor

              What’s ahead
              •   Remaining 8 miles under design; construction in 2021
              •   Between North Bend and Snoqualmie summit – replace concrete
                  panels in eastbound lanes; repair bridge decks in westbound lanes
                    ➢ Traffic detour after Memorial Day – expected delays
              •   Paving interchanges at Easton, Thorp and Ellensburg
              •   Building detours for major Yakima River bridge work next summer at
                  Cle Elum and Ellensburg

                                                                                            3
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
SR 99 Alaskan Way Viaduct and Tunnel Replacement
Accomplishments and work under way
•   After Bertha’s disassembly in August 2017, crews installed last of
    1,152 concrete panels of the northbound (lower) deck
•   Installing, testing and commissioning tunnel operating and safety
    systems

What’s ahead
•   Tunnel could open this fall, depending on contractor’s schedules
      ➢ Connecting tunnel to SR 99 will require 3-week highway
          closure, plus 1 to 3 weeks ramp closures
•   Grand opening celebration being planned for near end of 3 week
    closure
•   Kiewit Infrastructure West Co., apparent-best-value contractor for
    $93.7 million design-build; demolish viaduct, decommission Battery
    Street tunnel; reconnect two streets across Aurora Avenue North
•   Scarsella Bros., Inc. to complete SR 99 tunnel to roadway
    connections and ramps project, started in February 2018

                                                                         4
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
I-405 Corridor Improvements
            Accomplishments and work under way
            •   Northbound Peak-Use Shoulder Lane; April 2017, $7.29 million
            •   I-405/SR 167 Direct Connector Project – 60% complete; 2019 completion
                   ➢ All in-ground shaft work for flyover ramp piers
                   ➢ Set girders for a portion of the ramp, completed deck pour
                   ➢ This summer, work on abutments, columns, girders and deck

            Upcoming work
            •   I-405 to Bellevue Widening and Express Toll Lanes project
                   ➢ Design-build contract, estimated $650-$700 million
                   ➢ Construction expected to start fall 2019; completion 2024

            •   I-405/NE 132nd Street Interchange project
                   ➢ Preliminary engineering/environmental review underway
                   ➢ Estimated construction cost: TBD
                   ➢ Construction expected to start 2021; completion 2023

                                                                                        5
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
SR 509/SR 167 Gateway Project
Accomplishments and current status
•   Connecting Washington provided $1.56 billion
•   Established Executive and Steering committees - Endorsed project scopes for SR 167 and SR 509:
      ➢ SR 167 Completion Project – Builds remaining four miles of SR 167 between Meridian
         Avenue and I-5; includes full interchange at Meridian Avenue in Puyallup
      ➢ SR 509 Completion Project – Extends SR 509 by building four new lanes between South
         188th Street and its connection with I-5 at South 221st Street; includes full interchange at South
         188th in SeaTac
•   Established Funding and Phasing Subcommittee – 18 affected jurisdictions
      ➢ Developing MOUs for local matching funds ($130M local funding required); leverage grants
      ➢ Grant applications submitted:
            o 70th Avenue East Bridge over I-5 Fife (FMSIB) – Fife, Tacoma, Port of Tacoma
            o Veterans Drive in Kent (PSRC) – City of Kent
            o SeaTac Access (PSRC) – SeaTac and Des Moines
            o Port of Tacoma Spur (PSRC) – Port of Tacoma, Tacoma and Fife
            o $111 million application to U.S.DOT (INFRA competitive grant)

                                                                                                              6
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
SR 520 Corridor
Overview
•   Rest of the West – funding approved by Legislature in 2015
     • Improvements from I-5 to Lake Washington – 3 phases
     • Ultimately, SR 520 corridor will be six lanes from I-5 to SR
         202 in Redmond, with transit and HOV in each direction
•   West Approach Bridge North opened in summer 2017
What’s ahead
•   Montlake Phase
     • West Approach Bridge South, lid in Montlake and land bridge
         over highway
     • Construction to begin in late 2018; 4 to 5 years duration
•   Portage Bay Phase
     • Portage Bay Bridge, lid in Roanoke neighborhood and I-5
         connections
     • Construction 2020 – 2022
•   Montlake Cut Crossing Phase
     • Second bascule bridge over the Montlake Cut,
     • Construction as early as 2024

                                                                      7
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
Thank you!

Kevin J. Dayton, PE, Chief Engineer
Asst. Secretary Regions & Mega Program
Washington State Department of Transportation
360-705-7032
DaytonK@wsdot.wa.gov

                                                8
Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ... Program Delivery Update - Project Milestones and KEVIN J. DAYTON, PE, Chief Engineer, Asst. Secretary Regions & Mega Program ACEC/WSDOT Annual ...
You can also read