R-9 - July 12, 2018 - Peace River Regional District
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
R-9 July 12, 2018
UPDATE R-9 Further to the SWC recommendation from June 7, 2018, the aerial topographic survey of the Bessborough Landfill was completed this month and the remaining airspace calculated for Phases 1 and 2. The airspace in Phase 2 has been consumed and the remaining airspace in Phase 1 was determined to be 26,600m3. Using disposal and waste compaction rates from 2017, this volume corresponds to approximately the 10 months of remaining airspace in Phase 1 being consumed by the end of March 2019. Discussions with the Landfill Contractor, Green for Life Environmental, indicated that based on their experience with the operation and filling of landfills, the top deck of Phase 1 could accommodate an additional layer or “lift” of solid waste of 3 m thickness. The Bessborough Landfill closure design consultant, GHD Limited (GHD) was requested to redesign the final grades for the Phase 1 cell to increase the final elevation and determine the additional airspace resulting from the minor modification of the final cover grades. A conceptual design of the modified final grades for Bessborough Landfill Phase 1 prepared by GHD is provided in the attached Memorandum. The modified final grades for Phase 1 would provide an additional 20,000m3 of airspace. This additional airspace along with the current remaining airspace would indicate that the PRRD would have until November 2019 to complete the construction of the Phase 3A cell. Staff recognized that this would provide sufficient additional time for retendering if possible. Accordingly, staff submitted a request to modify the final grade design for the closure of the Bessborough Landfill Phase 1 cell to the Ministry of Environment (MoE) which has been approved. Staff has also reviewed other options for the site and provide the following information: " Delaying construction for a year by redirecting waste from the Bessborough landfill to the North Peace Regional Landfill to provide sufficient time for retendering. o Primary costs for this option were grouped into two categories: " Waste from the manned transfer stations/unmanned transfer sites in the South Peace being trucked into NPRL would be in excess of $450,000 for one year. " Waste from all customers coming into the Bessborough landfill would be trucked to NPRL via roll-off bin at an estimated cost of $1,540,000 for one year. This option is clearly costly to the PRRD as well as impractical. As such, staff does not recommend this option. " Surface filling (ie, no excavation, basic grubbing to begin piling waste in cells at existing ground surface) o When we review the Design and Operations Plan for Bessborough, we note that the leachate system which is built into the south end of Phase 3 needs to tie into future Phases 4 and 5 (immediately north). Surface filling would cripple the ability of the landfill to manage leachate without installing additional apparatus in Phases 4 and 5 to pump leachate up to the surface and tie into the future leachate impoundment system which is destined to manage leachate for the entire site. Additionally, this action would shave 5-10 years off of the usable life of the landfill. Staff did not pursue this option any further as it is not best practice in landfill operations and construction to hamper airspace capacity and leachate management. July 12, 2018
R-9 The delay of the construction of the Bessborough Landfill expansion project for 2019 will allow ample time for retendering the construction project. Staff envision splitting the two year construction project into two separate projects that will be tendered separately in 2018 and 2019 for construction in 2019 and 2020 respectively. It is anticipated that providing significant lead time for contractors to plan for the first project in 2019 will result in the receipt of bids that are more competitive than what was received when the project was initially tendered as a two-year construction project. Retendering for construction in 2019 will encompass the work that absolutely needed to be taken care of in 2018. CONCLUSION The chief takeaway from this exercise is that the risk of running out of airspace at the Bessborough landfill is significantly reduced, allowing for time to build Phase 3A in 2019 instead of 2018 as originally envisioned. Therefore, staff recommend retendering in 2018 for construction of Phase 3A in 2019. ALTERNATIVE OPTIONS: 1. That the Regional Board recommend that the Bessborough Landfill Phase 1A/1B and Phase 2 Closure, Phase 3A/3B Expansion Contract No. 13-2018 be awarded to Brocor Construction Ltd. at the cost of $4,002,811.12 (excluding taxes) and that the Chair and Acting Chief Administrative Officer be authorized to sign the contract on behalf of the Regional District. 2. That the Board provide alternative direction to staff regarding the award of the Bessborough Landfill Phase 1A/1B and Phase 2 Closure, Phase 3A/3B Expansion Contract No. 13-2018. STRATEGIC PLAN RELEVANCE: Ensure that the Solid Waste Management Plan is operating on a fiscally defensible basis. Ensure effective execution of Public Safety and Emergency Services initiatives. Foster Collaboration on services with municipalities and electoral areas. Establish a strategy for coordinated advocacy on identified issues. Manage parks and trails in the region. Support the agricultural industry within the regional district. Not Applicable to Strategic Plan. FINANCIAL CONSIDERATION(S): The splitting of the construction project into two separate years along with the tendering of each construction project separately in 2018 and 2019 will provide firm budgetary costs that can be adequately accommodated in the 2019 and 2020 solid waste budgets. COMMUNICATIONS CONSIDERATION(S): None foreseen OTHER CONSIDERATION(S): The Solid Waste Committee met on July 5, 2018 and approved the recommendations for consideration by the Board: Attachment: A – GHD Memorandum (Bessborough Landfill: Phase: 1 Conceptual Final Contours for Increased Capacity). Page 3 of 3 July 12, 2018
R-9 Attachment 1 June 21, 2018 To: Phillip Kovacs Ref. No.: 11102726- From: David Engstrom/sz/09 Tel: 604-214-0510 C C : D e a c o n L i d d y Subject: Bessborough Landfill: Phase 1 Conceptual Final Contours for Increased Capacity 1. Introduction GHD Limited (GHD) has prepared this memorandum to identify options for continuing to landfill in Phase 1 at the Bessborough landfill and delay the construction of Phase 3. Based on discussions with the Peace River Regional District (PRRD), if sufficient capacity can be identified through a revised final contours plan for Phase 1, the PRRD would prefer to delay the construction of Phase 1 and Phase 2 final cover and Phase 3 expansion until 2019. 2. Conceptual Final Contours Design Constraints The following design constraints from the 2016 British Columbia Landfill Criteria were used to determine the increase in capacity of Phase 1: " The maximum slope of final contours must be 3 horizontal to 1 vertical (3:1) to meet stability requirements. " Surface water control benches are required every 15 m vertical or less. " The minimum slope of the plateau must be 10 horizontal to 1 vertical (10:1). The design constraints included in the Design, Operation, and Closure Plan prepared by AECOM in 2012 allowed 4 percent minimum slopes for the final cover. In accordance with the 2016 British Columbia Landfill Criteria, the minimum slope must be 10:1 unless the final cover system includes a durable geomembrane or composite barrier layer with overlying drainage layer. The 10:1 slope will increase the Phase 1 capacity and will provide improved drainage over a 4 percent slope. Increase in Capacity and Lifespan Revised conceptual final contours for Phase 1 are shown on the sketch in Attachment A. The top of the 3:1 slope was increased from approximately elevation 855 m to elevation 866 m, which was the maximum GHD 10271 Shellbridge Way Suite 165 Richmond British Columbia V6X 2W8 Canada T 604 214 0510 F 604 214 0525 W www.ghd.com July 12, 2018
R-9 Attachment 1 vertical height allowed so that surface water control benches are not needed. The 10:1 slope of the plateau raised the final contours from approximately elevation 856 to elevation 859. The increased waste capacity of Phase 1 was estimated to be approximately 20,000 m 3. The annual surveys in 2017 and 2018 indicated an airspace utilization of 35,412 m 3 over 400 days. The average monthly (30-day) consumption rate based on the surveys is 2,655.9 m 3. At this rate of consumption, the estimated increase in Phase 1 lifespan would be approximately 7.5 months. 3. Conclusions The capacity of Phase 1 can be increased by 20,000 m3 using the conceptual design sketch shown in Attachment A. Phase 1 was expected to reach capacity in April 2019 as estimated in the 2015 Annual Report prepared by GHD. The increased lifespan for Phase 1 would delay this until November 2019; therefore, the expansion of Phase 3, or portion thereof, could be delayed until the June to October construction season in 2019. 2 July 12, 2018 11102726Memo-09
R-9 Attachment 1 Att achment A Sketch of Revised Conceptual Phase 1 Final Contours GHD | 11102726Memo-09-ATT-TPs July 12, 2018
R-9 X LEGEND PROPERTY LINES 845 CONTOURS (m AMSL) EXISTING LANDFILL LIMIT OF WASTE FENCE LINE MAINENTRANCE Attachment 1 U.P . CULVERTS UTILITY POLES GHDLimited 841 L. S . LIGHT STANDARDS BM#1 10271 Shellbridge Way Suite 165 PHASE 3 SURVEY CONTROL POINT Richmond British Columbia V6X 2W8 Canada 845 PROPOSED CONTOUR (m AMSL) T 604 214 0510 F 604 214 0525 W www.ghd.com . P PROPOSED FENCE LINE POND PROPOSED DITCH BM#1 LIMIT OF FINAL COVER PROPOSED SPOT ELEVATION /GRADE BREAK A' X WASTETRANSFER SECTION LOCATION STATION C-06 LS .. Reuse of Documents PHASE 1 PERIMETER This document and the ideas and designs incorporated herein, as an instrument of C-06 DITCH #1 B BM#3 professional service, is the property of GHD and shall not be reused in whole or in part for WHITEGOODS SEE DETAIL BESS-BH103 any other project without GHD's written authorization. © 2016 GHD UP .. 1 SCALE HOUSE PROPOSED DITCH C-16 PROPOSED DITCH BESS-BH102 UP .. 0 000 AND SCALE PROPOSED DITCH PROPOSED DITCH WITH TRM BESS-BH101PROPOSED DITCH U.P. 32.88m @ 1.1% PHASE 1 LANDFILL WITH TRM 152.34m @ 1.4% 58.0m @ 2.2% ACCESS ROAD WITH TRM LS .. 175.03m @ 2.8% 22.0m @ 4.7% UP .. 0 025 U.P U.P. SEDIMENT UP .. LS .. UP .. FOREBAY UP .. PROPOSED 16.75m 300mmØ UP .. LS .. BESS-BH106 HDPE CULVERT @ 1.6% SEE DETAIL BESS BH107 0 10 20 30m 100.0 1 CONNECTION TO 13 0 050 LEACHATE STORMWATER POND SCRAPTIRES C-17 STORAGE BASIN PROPOSED DITCH WITH TRM PROPOSED DITCH 21.75m @ 3.5% 0 075 102.00m @ 1.0% PROPOSED DITCH WITH TRM A Cle i nt A' 28.67m @ 3.9% UP .. C-06 0 100 C-06 PEACE RIVER REGIONAL DISTRICT DAWSON CREEK, B.C. 0400 0425 0450 0000 0025 0050 0075 0200 0225 0250 0275 0300 0325 0350 0375 0100 0125 0150 0175 BESS-MW7 859 LANDFILL Project 858 PHASE1 0 125 LEACHATE PUMPING ACCESS BESSBOROUGH LANDFILL 857 PIPE. EXTEND AS REQUIRED TO EXECUTE WORKS PHASE 1 & 2 CLOSURE AND 856 PHASE 3 EXPANSION BESS-MW3A BESS-MW3 0 150 PROPOSED DITCH 176.08m @ 0.6% BM#2 0 175 2 90% DESIGN REVIEW D.C. D.L. 10/30/2017 PHASE1BOUNDARY NOTE: LANDFILL GAS RELIEF DITCH SEGMENTS WITH 1 50% DESIGN REVIEW D.C. D.L. 08/24/2017 VENT (TYP.) SLOPES GREATER THAN 2% PHASE 1 PERIMETER SEE DETAIL TO BE LINED WITH TRM. UP .. PROPOSED DITCH No. Issue Drawn Approved Date 53.29m @ 2.5% PROPOSED DITCH DITCH #2 SEE DETAIL 19 WITH TRM 0 200 C-18 PROPOSED DITCH BESS-MW6 129.37m @ 2.7% 2 Drawn D. CORKILL Designer D. CORKILL 132.19m @ 1.7% C-16 PROPOSED FENCE Drafting S. STURGEON Design Check Check S. STURGEON C-06 B' Project D.LIDDY Date Jul31,2017 Manager This document shall not be used for construction unless signed and sealed Scale 1:1_1 for construction. Original Size Bar is 20mm on original ANSI D 0 size drawing 20mm SW 1/4 SECTION 5 ProjectNo. 11102726-0020 Ttie l Sketch of Revised Conceptual Phase 1 Final Contours PHASE 1 GRADING PLAN TOP OF FINAL CONTOURS SheetNo. C-06 Sh e et 7 o f 20 Plot Date: 15 December 2017 - 10:12 AM Plotted By: Dylan Corkill CAD File: I:\CAD\8-chars\11------\1110----\111027--\11102726\11102726-REPORTS\11102726-0020(004)\11102726-0020(004)CI\11102726-0020(004)CI-OT005.dwg July 12, 2018
You can also read