R-9 - July 12, 2018 - Peace River Regional District

Page created by Jorge Flores
 
CONTINUE READING
R-9

July 12, 2018
UPDATE
                                                                                                     R-9
Further to the SWC recommendation from June 7, 2018, the aerial topographic survey of the Bessborough
Landfill was completed this month and the remaining airspace calculated for Phases 1 and 2. The airspace
in Phase 2 has been consumed and the remaining airspace in Phase 1 was determined to be 26,600m3.
Using disposal and waste compaction rates from 2017, this volume corresponds to approximately the 10
months of remaining airspace in Phase 1 being consumed by the end of March 2019.

Discussions with the Landfill Contractor, Green for Life Environmental, indicated that based on their
experience with the operation and filling of landfills, the top deck of Phase 1 could accommodate an
additional layer or “lift” of solid waste of 3 m thickness.

The Bessborough Landfill closure design consultant, GHD Limited (GHD) was requested to redesign the
final grades for the Phase 1 cell to increase the final elevation and determine the additional airspace
resulting from the minor modification of the final cover grades.

A conceptual design of the modified final grades for Bessborough Landfill Phase 1 prepared by GHD is
provided in the attached Memorandum. The modified final grades for Phase 1 would provide an
additional 20,000m3 of airspace. This additional airspace along with the current remaining airspace would
indicate that the PRRD would have until November 2019 to complete the construction of the Phase 3A
cell. Staff recognized that this would provide sufficient additional time for retendering if possible.
Accordingly, staff submitted a request to modify the final grade design for the closure of the Bessborough
Landfill Phase 1 cell to the Ministry of Environment (MoE) which has been approved.

Staff has also reviewed other options for the site and provide the following information:
" Delaying construction for a year by redirecting waste from the Bessborough landfill to the North
     Peace Regional Landfill to provide sufficient time for retendering.
         o Primary costs for this option were grouped into two categories:
                 " Waste from the manned transfer stations/unmanned transfer sites in the South
                     Peace being trucked into NPRL would be in excess of $450,000 for one year.
                 " Waste from all customers coming into the Bessborough landfill would be trucked to
                     NPRL via roll-off bin at an estimated cost of $1,540,000 for one year.
     This option is clearly costly to the PRRD as well as impractical. As such, staff does not
     recommend this option.

"   Surface filling (ie, no excavation, basic grubbing to begin piling waste in cells at existing ground surface)
        o When we review the Design and Operations Plan for Bessborough, we note that the leachate
            system which is built into the south end of Phase 3 needs to tie into future Phases 4 and 5
            (immediately north). Surface filling would cripple the ability of the landfill to manage leachate
            without installing additional apparatus in Phases 4 and 5 to pump leachate up to the surface
            and tie into the future leachate impoundment system which is destined to manage leachate for
            the entire site. Additionally, this action would shave 5-10 years off of the usable life of the
            landfill.

Staff did not pursue this option any further as it is not best practice in landfill operations and
construction to hamper airspace capacity and leachate management.

                                                 July 12, 2018
R-9
The delay of the construction of the Bessborough Landfill expansion project for 2019 will allow ample time
for retendering the construction project. Staff envision splitting the two year construction project into two
separate projects that will be tendered separately in 2018 and 2019 for construction in 2019 and 2020
respectively. It is anticipated that providing significant lead time for contractors to plan for the first project
in 2019 will result in the receipt of bids that are more competitive than what was received when the project
was initially tendered as a two-year construction project. Retendering for construction in 2019 will
encompass the work that absolutely needed to be taken care of in 2018.

CONCLUSION
The chief takeaway from this exercise is that the risk of running out of airspace at the Bessborough landfill
is significantly reduced, allowing for time to build Phase 3A in 2019 instead of 2018 as originally
envisioned. Therefore, staff recommend retendering in 2018 for construction of Phase 3A in 2019.

ALTERNATIVE OPTIONS:
    1. That the Regional Board recommend that the Bessborough Landfill Phase 1A/1B and Phase 2
       Closure, Phase 3A/3B Expansion Contract No. 13-2018 be awarded to Brocor Construction Ltd. at
       the cost of $4,002,811.12 (excluding taxes) and that the Chair and Acting Chief Administrative
       Officer be authorized to sign the contract on behalf of the Regional District.
    2. That the Board provide alternative direction to staff regarding the award of the
       Bessborough Landfill Phase 1A/1B and Phase 2 Closure, Phase 3A/3B Expansion Contract
       No. 13-2018.

STRATEGIC PLAN RELEVANCE:
       Ensure that the Solid Waste Management Plan is operating on a fiscally defensible basis.
       Ensure effective execution of Public Safety and Emergency Services initiatives.
       Foster Collaboration on services with municipalities and electoral areas.
       Establish a strategy for coordinated advocacy on identified issues.
       Manage parks and trails in the region.
       Support the agricultural industry within the regional district.
       Not Applicable to Strategic Plan.

FINANCIAL CONSIDERATION(S):
The splitting of the construction project into two separate years along with the tendering of each
construction project separately in 2018 and 2019 will provide firm budgetary costs that can be
adequately accommodated in the 2019 and 2020 solid waste budgets.

COMMUNICATIONS CONSIDERATION(S):                                       None foreseen

OTHER CONSIDERATION(S): The Solid Waste Committee met on July 5, 2018 and approved the
recommendations for consideration by the Board:

Attachment:        A – GHD Memorandum (Bessborough Landfill: Phase: 1 Conceptual Final Contours
                        for Increased Capacity).
                                                                                         Page 3 of 3

                                                 July 12, 2018
R-9
                         Attachment 1

       June 21, 2018

       To:               Phillip Kovacs                                                Ref. No.:   11102726-

       From:             David Engstrom/sz/09                                          Tel:        604-214-0510

       C      C      :         D      e      a      c     o      n         L   i   d   d      y

       Subject:          Bessborough Landfill: Phase 1 Conceptual Final Contours for Increased Capacity

       1.         Introduction

       GHD Limited (GHD) has prepared this memorandum to identify options for continuing to landfill in Phase 1
       at the Bessborough landfill and delay the construction of Phase 3. Based on discussions with the Peace
       River Regional District (PRRD), if sufficient capacity can be identified through a revised final contours plan
       for Phase 1, the PRRD would prefer to delay the construction of Phase 1 and Phase 2 final cover and Phase
       3 expansion until 2019.

       2.         Conceptual Final Contours

       Design Constraints

       The following design constraints from the 2016 British Columbia Landfill Criteria were used to determine
       the increase in capacity of Phase 1:

       "     The maximum slope of final contours must be 3 horizontal to 1 vertical (3:1) to meet
             stability requirements.

       "     Surface water control benches are required every 15 m vertical or less.

       "     The minimum slope of the plateau must be 10 horizontal to 1 vertical (10:1).

       The design constraints included in the Design, Operation, and Closure Plan prepared by AECOM in 2012
       allowed 4 percent minimum slopes for the final cover. In accordance with the 2016 British Columbia
       Landfill Criteria, the minimum slope must be 10:1 unless the final cover system includes a durable
       geomembrane or composite barrier layer with overlying drainage layer. The 10:1 slope will increase the
       Phase 1 capacity and will provide improved drainage over a 4 percent slope.

       Increase in Capacity and Lifespan

       Revised conceptual final contours for Phase 1 are shown on the sketch in Attachment A. The top of the 3:1
       slope was increased from approximately elevation 855 m to elevation 866 m, which was the maximum

GHD
10271 Shellbridge Way Suite 165 Richmond British Columbia V6X 2W8 Canada
T 604 214 0510 F 604 214 0525 W www.ghd.com
                                                            July 12, 2018
R-9
           Attachment 1

vertical height allowed so that surface water control benches are not needed. The 10:1 slope of the plateau
raised the final contours from approximately elevation 856 to elevation 859. The increased waste capacity of
Phase 1 was estimated to be approximately 20,000 m 3.

The annual surveys in 2017 and 2018 indicated an airspace utilization of 35,412 m 3 over 400 days. The
average monthly (30-day) consumption rate based on the surveys is 2,655.9 m 3. At this rate of consumption,
the estimated increase in Phase 1 lifespan would be approximately 7.5 months.

3.        Conclusions

The capacity of Phase 1 can be increased by 20,000 m3 using the conceptual design sketch shown in
Attachment A. Phase 1 was expected to reach capacity in April 2019 as estimated in the 2015 Annual Report
prepared by GHD. The increased lifespan for Phase 1 would delay this until November 2019; therefore, the
expansion of Phase 3, or portion thereof, could be delayed until the June to October construction season in
2019.

                                                                                                           2
                                          July 12, 2018
11102726Memo-09
R-9

     Attachment 1

                             Att achment A
Sketch of Revised Conceptual Phase 1 Final
                                  Contours

                                    GHD | 11102726Memo-09-ATT-TPs

                    July 12, 2018
R-9
                             X                                                                                                                                                                                                                                                                                                                                                                                                                                                     LEGEND
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   PROPERTY LINES
                                                                                                                                                                                                                                                                                                                                                                                                                                                               845                 CONTOURS (m AMSL)
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   EXISTING LANDFILL LIMIT OF WASTE
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   FENCE LINE

                                                     MAINENTRANCE
                                                                                                                                                                                                                                                                            Attachment 1                                                                                                                                                                              U.P .
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   CULVERTS
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   UTILITY POLES
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    GHDLimited

                                                                                                                                                                                                                                                                                                                                                                                                      841
                                                                                                                                                                                                                                                                                                                                                                                                                                                                      L. S .
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   LIGHT STANDARDS
                                                                                                                                                                                                                                                                                                                                                                                                                                                                      BM#1                                                          10271 Shellbridge Way Suite 165
                                                                                                                                                                                                                                                                                                                                                                                                                 PHASE 3                                                           SURVEY CONTROL POINT
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    Richmond British Columbia V6X 2W8 Canada
                                                                                                                                                                                                                                                                                                                                                                                                                                                               845                 PROPOSED CONTOUR (m AMSL)                        T 604 214 0510 F 604 214 0525 W www.ghd.com

.
P
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   PROPOSED FENCE LINE
                                                                                                                                                                                                     POND                                                                                                                                                                                                                                                                          PROPOSED DITCH
                                           BM#1
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   LIMIT OF FINAL COVER
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   PROPOSED SPOT ELEVATION
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   /GRADE BREAK

                                                                                                                                                                                                                                                                                                                                                                                                                                                               A'
                                                               X

                                                                                                      WASTETRANSFER                                                                                                                                                                                                                                                                                                                                                                SECTION LOCATION
                                                                                                      STATION                                                                                                                                                                                                                                                                                                                                                  C-06
                                                                     LS
                                                                      ..

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Reuse of Documents
                                                                                                                                                                                                                                                PHASE 1 PERIMETER                                                                                                                                                                                                                                                        This document and the ideas and designs incorporated herein, as an instrument of

                                                                                                                                                                                                                                                                                                                                   C-06
                                                                                                                                                                                                                                                DITCH #1

                                                                                                                                                                                                                                                                                                                                            B
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  BM#3   professional service, is the property of GHD and shall not be reused in whole or in part for
                                                                                                                          WHITEGOODS                                                                                                            SEE DETAIL                                                                                                                                                                                                                     BESS-BH103                                any other project without GHD's written authorization. © 2016 GHD

                                         UP
                                          ..
                                                                                                                                                                                                                                                             1
                                                                           SCALE HOUSE                                      PROPOSED DITCH                                                                                                                  C-16                                                                                                            PROPOSED DITCH                                                                        BESS-BH102
                      UP
                       ..                                                                                                                                                                                                                                                                                                  0 000
                                                                           AND SCALE                                                                                                                                                                                                 PROPOSED DITCH                                             PROPOSED DITCH                     WITH TRM                                                         BESS-BH101PROPOSED DITCH
U.P.                                                                                                                           32.88m @ 1.1%                                                 PHASE 1 LANDFILL                                                                        WITH TRM                                                     152.34m @ 1.4%                58.0m @ 2.2%
                                                                                                                                                                                             ACCESS ROAD                                                                                                                                                                                                                                                     WITH TRM
                                               LS
                                                ..                                                                                                                                                                                                                                   175.03m @ 2.8%
                                                                                                                                                                                                                                                                                                                                                                                                                                                             22.0m @ 4.7%

    UP
     ..                                                                                                                                                                                                                                                                                                                    0 025
                                                                                                U.P                                    U.P.                                                                                                                                                                                                                                                                                                                                                     SEDIMENT
                                                                                                                                                                                                             UP
                                                                                                                                                                                                              ..
                                                                                                                                          LS
                                                                                                                                           ..                                                                                                                              UP
                                                                                                                                                                                                                                                                            ..                                                                                                                                                                                                                  FOREBAY
                                                                                                                                                                                                                                                                                                                                   UP
                                                                                                                                                                                                                                                                                                                                    ..
                                                                            PROPOSED 16.75m 300mmØ                                                                                                                                                                                                                                                                                        UP
                                                                                                                                                                                                                                                                                                                                                                                           ..
                                                                                                                                                                                                                                                                                                                                                                                                      LS
                                                                                                                                                                                                                                                                                                                                                                                                       ..                 BESS-BH106
                                                                            HDPE CULVERT @ 1.6% SEE
                                                                            DETAIL                                                                                                                                                                                                                                                                                                                                                              BESS BH107                                                                                             0      10                   20 30m 100.0 1
                                                                                                                                                                                                                                                                                                                                                                                                                                                               CONNECTION TO
                                                                                                 13                                                                                                                                                                                                                        0 050
                                                                                                                                                                                                                                                                                                                                                                                                                   LEACHATE                                    STORMWATER
                                                                                                                                                                                                                                                                                                                                                                                                                                                               POND
                                                         SCRAPTIRES                              C-17                                                                                                                                                                                                                                                                                                               STORAGE
                                                                                                                                                                                                                                                                                                                                                                                                                     BASIN

                                                                                                                                                                                                                                                                                                                                                                                                                                                               PROPOSED DITCH
                                                                                                                                                                                                                                                                                                                                                                                                                                                               WITH TRM
                                                                                         PROPOSED DITCH                                                                                                                                                                                                                                                                                                                                                        21.75m @ 3.5%
                                                                                                                                                                                                                                                                                                                           0 075
                                                                                           102.00m @ 1.0%

                                                                                                                                                                                                                                                                                                                                                                                                                                                               PROPOSED DITCH
                                                                                                                                                                                                                                                                                                                                                                                                                                                               WITH TRM
                                                                                                       A                                                                                                                                                                                                                                                                                                                                                                                                                 Cle
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           i nt
                                                                                                                                                                                                                                                                                                                                                                                                                                                   A'          28.67m @ 3.9%
            UP
             ..
                                                                                                      C-06
                                                                                                                                                                                                                                                                                                                           0 100
                                                                                                                                                                                                                                                                                                                                                                                                                                                   C-06
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          PEACE RIVER REGIONAL DISTRICT
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               DAWSON CREEK, B.C.

                                                                                                                                                                                                                                                                                                                                                                                                    0400

                                                                                                                                                                                                                                                                                                                                                                                                                   0425

                                                                                                                                                                                                                                                                                                                                                                                                                                         0450
                                                                                                                  0000

                                                                                                                                       0025

                                                                                                                                                        0050

                                                                                                                                                                           0075

                                                                                                                                                                                                                                                                    0200

                                                                                                                                                                                                                                                                                       0225

                                                                                                                                                                                                                                                                                                       0250

                                                                                                                                                                                                                                                                                                                    0275

                                                                                                                                                                                                                                                                                                                                         0300

                                                                                                                                                                                                                                                                                                                                                              0325

                                                                                                                                                                                                                                                                                                                                                                     0350

                                                                                                                                                                                                                                                                                                                                                                                   0375
                                                                                                                                                                                              0100

                                                                                                                                                                                                                   0125

                                                                                                                                                                                                                                   0150

                                                                                                                                                                                                                                                     0175
                                                                                                                         BESS-MW7
                                                                                                                                                                                   859                                                                                           LANDFILL                                                                                                                                                                                                                                Project
                                                                                                                                                                                                 858                                                                             PHASE1
                                                                                                                                                                                                                                                                                                                           0 125                                                                                                        LEACHATE PUMPING ACCESS                                                                      BESSBOROUGH LANDFILL
                                                                                                                                                                                                                   857                                                                                                                                                                                                                  PIPE. EXTEND AS REQUIRED TO
                                                                                                                                                                                                                                                                                                                                                                                                                                        EXECUTE WORKS                                                                               PHASE 1 & 2 CLOSURE AND
                                                                                                                                                                                                                             856                                                                                                                                                                                                                                                                                                       PHASE 3 EXPANSION
                                                                                                                                                                                                                                                                                                                                                                                                            BESS-MW3A
                                                                                                                                                                                                                                                                                                                                                                                                            BESS-MW3
                                                                                                                                                                                                                                                                                                                           0 150                                                                                  PROPOSED DITCH
                                                                                                                                                                                                                                                                                                                                                                                                                  176.08m @ 0.6%

                                                                                                                                                                                                            BM#2

                                                                                                                                                                                                                                                                                                                           0 175                                                                                                                                                                                          2 90% DESIGN REVIEW                             D.C.            D.L.       10/30/2017
                                                                                                                                                                                                                                                                                                   PHASE1BOUNDARY                                                                                                                                                              NOTE:
                                                                                                                                                                                                                                                                                                                                                                                                                LANDFILL GAS RELIEF                                            DITCH SEGMENTS WITH                         1 50% DESIGN REVIEW                            D.C.            D.L.       08/24/2017
                                                                                                                                                                                                                                                                                                                                                                                                                VENT (TYP.)                                                    SLOPES GREATER THAN 2%
                                                                                                                                                                                                                                                                                                                                                                            PHASE 1 PERIMETER                   SEE DETAIL                                                     TO BE LINED WITH TRM.
          UP
           ..
                                                                                           PROPOSED DITCH                                                                                                                                                                                                                                                                                                                                                                                                                No.                   Issue                     Drawn Approved                  Date
                                                                                              53.29m @ 2.5%                                                                                                                                                                                   PROPOSED DITCH
                                                                                                                                                                                                                                                                                                                                                                            DITCH #2
                                                                                                                                                                                                                                                                                                                                                                            SEE DETAIL                                                 19
                                                                                                                                                                                                                                                                                              WITH TRM                     0 200                                                                                                       C-18
                                                                                                                                                                                                                                   PROPOSED DITCH                      BESS-MW6               129.37m @ 2.7%                                                                                    2                                                                                                                        Drawn        D. CORKILL                        Designer       D. CORKILL
                                                                                                                                                                                                                                   132.19m @ 1.7%                                                                                                                                          C-16
                                                                                                                                PROPOSED FENCE
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Drafting     S. STURGEON                      Design
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Check                                         Check          S. STURGEON

                                                                                                                                                                                                                                                                                                                                   C-06
                                                                                                                                                                                                                                                                                                                                            B'
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Project D.LIDDY                                Date          Jul31,2017
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Manager

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         This document shall not be used for
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         construction unless signed and sealed         Scale           1:1_1
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         for construction.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Original Size
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                 Bar is 20mm on original

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    ANSI D                                       0
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       size drawing
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        20mm
                                                                                                                                                                                                                                                                                                                                                  SW 1/4
                                                                                                                                                                                                                                                                                                                                                  SECTION 5

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         ProjectNo.         11102726-0020

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Ttie
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            l

                                                                                                      Sketch of Revised Conceptual Phase 1 Final Contours                                                                                                                                                                                                                                                                                                                                                                          PHASE 1 GRADING PLAN
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   TOP OF FINAL CONTOURS

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         SheetNo.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             C-06
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               Sh e et 7 o f                20

Plot Date: 15 December 2017 - 10:12 AM                  Plotted By: Dylan Corkill        CAD File: I:\CAD\8-chars\11------\1110----\111027--\11102726\11102726-REPORTS\11102726-0020(004)\11102726-0020(004)CI\11102726-0020(004)CI-OT005.dwg

                                                                                                                                                                                                                                                                                 July 12, 2018
You can also read