2021 Roadway
Rehabilitation Project
  Neighborhood Pre-construction Meeting
             April 29, 2021
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Agenda

• Project communication
• Phasing and schedule
• Overview of construction process
• Frequently asked questions
• Questions?
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Project Communication

• Use InTouch to receive regular project notifications and updates
 To sign up for InTouch:
 1. Go to woodburymn.gov.
 2. Click on the              icon at the top right corner of the home page.
 3. Fill in the boxes with your email and name.
 4. Then check the box for Road Rehabilitation 2021.
 5. Finally select “subscribe” at the bottom of the page.
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Project Communication
• Project website: woodburymn.gov/roadrehab2021
• Door hangers
• Project hotline: (612) 430-2805
   • Updates, register concerns, setup appointments,
     construction questions
• Project email – woodbury2021@Bolton-menk.com
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Phasing –
Preserve
Area

            *Subject to change
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Phasing
Residential Area Construction Phasing:
• 5 - 8 Weeks / Phase
  • 1 Week:
      • Mobilization and traffic control
      • Spot utility repair and maintenance
  • 2-3 Weeks:
      • Remove and replace damaged curb
  • 1-2 Weeks:
      • Remove existing pavement
      • Grade existing gravel
      • Place bottom layer of pavement
  • 2-3 Weeks:
      • Patch driveways
      • Topsoil restoration
      • Place top layer of pavement
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Construction
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
General Project Scope - Video
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Construction Expectations
• Weather and construction schedules
• Inconveniences
• Construction area – gravel and dust
• Construction zone – safety
• Resident access
• Communication – Project Hotline
      (612) 430-2805
• Project email – woodbury2021@Bolton-menk.com
2021 Roadway Rehabilitation Project - April 29, 2021 Neighborhood Pre-construction Meeting - Woodbury, MN
Preparation Work
Utility Repair and Maintenance
Spot Curb Removal and Irrigation
Pavement Removal
Full Curb Replacement
Driveways
Finish Grading
Boulevard/Turf Restoration
Pavement Replacement and Overlay
Things to Avoid
Street and Driveway Access
Frequently Asked Questions
• Project Schedule
  • The preliminary schedule is to begin May 3. Substantial completion of the majority of the project areas
    is expected by October. Please keep in mind the schedule can be delayed by weather or other
    unforeseen circumstances. For more detailed updated information, we STRONGLY RECOMMEND
    you sign up for the city’s InTouch email notification service to receive critical construction updates
    throughout this project. No major work will occur during the Woodbury Lions Club Garage Sale.

• Will the streets be open during construction?
  • A drivable surface consisting of existing pavement or gravel will be maintained at all times during the
    construction. There will be days where street access will be difficult when the contractor is working
    directly in front of your home.
Frequently Asked Questions
• Contractor’s anticipated working hours?
  • The contractor’s work hours are from 7 a.m.-7 p.m. Monday through Saturday; however, noise
    ordinance allows work from 6 a.m.-10 p.m. which may occasionally be needed.
• Driveway access during project?
  • You should have access to your property at most times throughout the construction process.
    However, there may be times when you will not have direct driveway access and may need to park
    on your street or on an adjacent street (e.g., the contractor is working in front of your home, or if new
    curb is poured in front of your driveway). You will be notified if new curb will be poured in front of
    your driveway as you will not be able to drive across it for approximately five to seven days while the
    concrete cures.
Frequently Asked Questions
• Garbage and mail service
  • Regular garbage/recycling and mail service should be maintained throughout the project.
    Those companies will be regularly informed of the work being performed.

• Assessments
  • Special assessments have been finalized and will not be changed based on final project
    costs. City assumes all risk if final costs are higher than initial estimates.
Frequently Asked Questions
• Irrigation systems, underground dog fences, and other
  landscaping features within the city right-of-way
  • The city right-of-way for residential streets within this project area is generally 60 feet wide.
    Landscaping, sprinkler systems, underground dog fences, basketball hoops or any other private
    features that are within the right-of-way may be damaged or require modifications prior to
    construction starting. On this project, damage is most likely to occur during the removal and
    replacement of damaged concrete curb and gutter and storm sewer catch basin castings. In both
    cases, the ground is typically excavated approximately three feet behind the curb into the
    boulevard. Before construction begins, the project inspector will paint the curb that will be replaced
    by the contractor. It is then the responsibility of the property owner to determine if any private
    features are located in the right-of-way and to either remove them from the construction limits or
    assume the risk of damage and responsibility for repairs. UNDER NO CIRCUMSTANCES WILL
    THE CITY, OR THE CONTRACTOR, REPAIR OR REPLACE ANY PRIVATE FEATURES THAT
    ARE DAMAGED WITHIN THE CITY RIGHT-OF-WAY. If you have any questions regarding any
    private features that may be impacted please contact the Project Hotline number - (612) 430-2805.
Frequently Asked Questions
•   Turf restoration?
    • Curb replacement, grading, and utility work may result in the disruption of the boulevard adjacent
      to those locations. Any turf that is removed will be replaced with seed and hydro mulch. The
      contractor is responsible to warranty the establishment of the seed for 45 days after installation.
      After the warranty period ends, all future repairs will be the responsibility of the property owner.
      Watering permits may be requested online or City Hall or Public Works by homeowners if desired.

•   Will the contractor offer residential driveway repair and replacement?
    • The contractor for this project will be offering private driveway work. All work must be coordinated
      directly between homeowner and contractor. The City encourages residents to get multiple quotes
      for any driveway work. Please contact Hank DaBruzzi at mhdabruzzi@taschifsky.com to receive a
      quote from the contractor. Contractor will patch any driveway damaged during construction.
Frequently Asked Questions
• Pavement Expectations
   • Minnesota’s weather and temperature ranges will lead to cracks as early as next spring in the new pavement
     surface. These cracks are normal and expected. The surface will remain in good condition that can be maintained
     with crack filling.
Additional 2021 Roadway Construction
  Projects
• City of Woodbury
  • Settlers Ridge Parkway and Hudson Road

• Washington County
  • Woodbury Drive between I-94 and Tamarack Road
  • Woodbury Drive between Bailey Road and Dale Road

• MnDOT
  •   Manning Avenue between Hudson Road and Bailey Road

  https://woodburymn.gov/departments/engineering/road_construction_projects.php
Contacts
• Project Hotline – 612-430-2805
• Project Email – woodbury2021@Bolton-menk.com
• Project Website – woodburymn.gov/roadrehab2021
Questions