Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...

Page created by Chad Cummings
 
CONTINUE READING
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
3rd Rencontres Nationales
    DU RESEAU TECHNOLOGIES DU VIDE
        SEVRIER, 10–13 October 2016

Vacuum pumps for the ESRF EBS project
           Michael Hahn
      On behalf of the EBS Accelerator Project Team
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
OUTLINE

         Project definition
         - Machine issues and parameters
         - Time schedule
         - Logistics
         Vacuum pumping
         - UHV pump selection and constraints
         - Vacuum assembly, chamber issues
         - Installation and vacuum preparation (pre-pumping)
         - Vacuum pump interface and control
         - Bake out
         Conclusion

Page 2
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
SCOPE OF THE PROJECT – ESRF TODAY

                                                                                      Energy                       6.04   GeV
                                                                                      Storage ring circumference   844      m
                                                         10 Hz Booster
                                                          Synchrotron                 Multibunch current           200     mA

                                  200 MeV                                             Horizontal emittance         4000   pm.rad
                               Electron Linac

                                                                                      Vertical emittance            4     pm.rad

                                                                            42 Beamlines
                                                                    (including 14 Bending Magnet BL)
Page 3   3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
SCOPE OF THE PROJECT

                                                               Now                EBS
                               Energy (GeV)                     6.04               6
                               Multibunch current (mA)          200               200
                               Circumference (m)               844.39           843.98
                               Horizontal emittance (pm.rad)   4000               140
 EBS..                         Vertical emittance (pm.rad)       4                 5

 -       Is going to be the new photon source (6 GeV electron storage ring) of the ESRF. The brilliance
         of the generated X-Rays will improve by factors due to the reduced horizontal e-beam
         emittance.
 -       Will contain 7 dipoles per cell (today 2), 7 x 32 = 224 dipole magnets
 -       Will replace the existing machine in the same tunnel
 -       Will be pre-assembled prior to installation which starts in Jan 2019
 -       Will contain 128 + 1 girders for magnets, vacuum chambers, etc.
 -       Will be an in-situ bakeable machine
 -       Will mainly use lumped (discrete) UHV pumping rather than functional coatings
 -       Will consist of stainless steel and aluminum vacuum chambers and use conventional flanges
Page 4    3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
SCOPE OF THE PROJECT

                                                                         Now        EBS
                              Energy (GeV)                                6.04        6
                              Multibunch current (mA)                     200        200
                              Circumference (m)                          844.39     843.98
                              Horizontal emittance (pm.rad)              4000        140
                              Vertical emittance (pm.rad)                  4          5

         present

            EBS

                                                              Dipoles-quadrupoles

Page 5   3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
MASTER PLAN

                                                         Courtesy of Pantaleo Raimondi

Page 6   3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
VACUUM PUMPS – SELECTION CRITERIA

               Compactness
               Good pumping speed for H2, N2, CO, CO2
               Sufficient pumping speed for CH4, noble gases
               Compatibility with existing installation
               Reliability
               Failure tolerance (power cuts)

Page 7   3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
VACUUM CHAMBERS (HIGH PROFILE)

   -     Production of 139 aluminum chambers started at CECOM, Italy
   -     Bi-metal Al2219/SS316LN has been selected for flanges

                                                                                                                                            20
   -     Production of 159 HP Stainless steel chambers at FMB, Germany
                                                                                                           20mm vert. internal height

   -     316LN material flow from steel suppliers to producer started

   -     Production of 33 HP absorber chambers at Pink, Germany
   -     316LN material flow from steel suppliers to producer started

                                                         CH3   CH14 (“absorber chamber”)

                           CH5

                                                                                       Production of Al dipole chamber at CECOM (Photo D. Gibson)

Page 8   3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
PROCUREMENT – VACUUM CHAMBERS (LOW PROFILE)

           -       Production of 102 low profile stainless steel vacuum
                   chambers at FMB, Germany
           -       316LN material flow from steel suppliers to producer
                   started                                                       CH7

           -       Central curved sheet sections to be produced by
                   deep drawing
           -       Optimization of aspects like required thickness of
                   some of the sheets in collaboration with supplier
                                                                          CH6

                                                         13

                                                                           CH8

Page 9   3rd rencontres vide cnrs 10 – 13 October 2016
Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
PROCUREMENT - INSTRUMENTATION AND CONTROL

            322 NEG cartridge pumps and 21 activation controllers, contract
            placed with SAES, Italy

            -       Lab test of pre-series completed

            -       Series production to be delivered end 2016                       4 channel NEG activation controller

            522 sputtering ion pumps and 50 IPPS

            -       Contract placed with AGILENT

            -       Pre-Series delivery received

            76 RGA assemblies – Company proposed by tender board, sorting
            remaining minor technical and contractual issues
                                                                              100 l/s NEG pump
            -       AFC approval received

            294 inverted magnetron (Penning) gauges and 160 Pirani gauges
                                                                                                             200 l/s NEG pump
            -       Contract under preparation

Page 10   3rd rencontres vide cnrs 10 – 13 October 2016
VACUUM ASSEMBLY

                                                          200 l/s NEG pump

Page 11   3rd rencontres vide cnrs 10 – 13 October 2016
LOGISTICS (STORAGE AND ASSEMBLY BUILDINGS)

           B1 - Architect view
     Preliminary design in progress

          B2 – Temporary storage
                 building
Page 12   3rd rencontres vide cnrs 10 – 13 October 2016
INSTRUMENTATION AND CONTROL

            Baking controllers compatible with fixing them on cable trays

                                                          16 control loops per unit

                                                          Prototype tested

                                                          Mechanics for 4 additional devices (pre-
                                                          series) arrived

                                                          Series production of 20 more to cope with
                                                          installation schedule

Page 13   3rd rencontres vide cnrs 10 – 13 October 2016
GATE VALVES

            Dimensional and vacuum test for RF sector valves prototype OK –
            RF test with beam postponed
            RFQ Custom shaped RF All Metal gate valves for SR sector
            separation (pneumatic actuation) 69 units
            RFQ Modified catalogue all metal valves for FE separation
            (pneumatic actuation) 31 units DN63CF and 34 units DN100CF
            Proposal of tender commission approved by DM, contract with
            valve supplier pending AFC approval

Page 14   3rd rencontres vide cnrs 10 – 13 October 2016
BAKING SYSTEM

                                                          Sheathed heaters selected as primary source

                                                          Tests of shaping insulation coats (aluminum
                                                          coated PI) ongoing by means of foam chamber
                                                          and magnet mockups

                                                          CFT Thermocouples under preparation

                                                          Purchase of heating collars being prepared

   Foam vacuum chamber in foam                                316L sheathed heater in dedicated         Foam vacuum chamber in foam
   magnet with thermal insulation (1)                         groove of aluminum chamber prototype      magnet with thermal insulation (2)

Page 15   3rd rencontres vide cnrs 10 – 13 October 2016
PREPUMPING FOR ASSEMBLY AND INSTALLATION

                                                          Traditional pumping groups with Hybrid turbo-
                                                          molecular pump, membrane pump, gauge
                                                          controller, PLC, etc. too space demanding for
                                                          EBS machine because of space constraints.

                                                          This is also to comply with safety standards
                                                          and European legislation (CE conformity).

                                                          A more compact pumping concept had to be
                                                          found..

Page 16   3rd rencontres vide cnrs 10 – 13 October 2016
PREPUMPING FOR ASSEMBLY AND INSTALLATION

                                                          6 turbomolecular pumps attached
                                                          to pre-pumping valves of each
                                                          vacuum sector.

                                                          Backed by a dry pump.

                                                          Isolation valve in the exhaust
                                                          which closes when rotation speed
                                                          of turbo gets low, operated by
                                                          Turbo controller.

                                                          A trolley will transport controllers,
                                                          turbos, ACP etc., materials to be
                                                          installed on cable trays to keep
                                                          the walkway free.

Page 17   3rd rencontres vide cnrs 10 – 13 October 2016
PRESSURE PROFILE

                                     Expected conditioning after 1, 10, 100, 1000, 3000 Ah of beam

                                                                                                     200 l/s NEG pump

Page 18   3rd rencontres vide cnrs 10 – 13 October 2016
ID14 TEST OF KEY COMPONENTS

             EBS Prototypes installed in a 6m ID straight section of ESRF:
             - Straight aluminum chamber following EBS dipole chamber production principle(1)
             - Bellow chamber containing two low profile RF liner assemblies(2)
             - All metal pneumatic RF gate valve prototype(3)
             - 1800mm NEG coated ESRF extruded Al ID chamber to fill up full length of SS (4)

                                                                  3

                                                          1   2        4
Page 19   3rd rencontres vide cnrs 10 – 13 October 2016
PROBLEMS AND LESSONS LEARNED FROM ID14 TEST IN AUGUST 2016

- Full aluminum flanges can create problems outside lab
environment

- Co-incidence of vacuum and RF gaskets on the flanges
complicates flange assembly

- With the same fixation hole pattern, RF gaskets for low
and high profile chambers could be confused

- Crossing welding seams on aluminum chambers
produced from two plates can create problems
                                                             Aluminum prototype chamber on ID14
- Given the amount of issues identified on this small test
assembly, it becomes obvious that the ‘mockup’
construction is very important

                                                             View from below, with leaking CF100 aluminum flange (IP)

Page 20   3rd rencontres vide cnrs 10 – 13 October 2016
CONCLUSION

                Contracts for the custom-shaped series production items (standard cell
                                chambers, valves, .. ) have been placed;

             Design and procurement for one-of-a-kind items (injection and diagnostic
                      chambers, straight section adaptation, ..) is ongoing;

          Procurement of vacuum instrumentation (UHV pumps, gauges, controllers, ..)
                                    close to completion;

           Still a lot of work for “consumables” ( screws, gaskets, heating collars and
                              connectors , thermal insulation, ..) ahead;

Page 21    3rd rencontres vide cnrs 10 – 13 October 2016
MANY THANKS FOR YOUR ATTENTION

Page 22   3rd rencontres vide cnrs 10 – 13 October 2016
You can also read