Vacuum pumps for the ESRF EBS project Michael Hahn - DU RESEAU TECHNOLOGIES DU VIDE 3rd Rencontres Nationales - Réseau des ...
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
3rd Rencontres Nationales DU RESEAU TECHNOLOGIES DU VIDE SEVRIER, 10–13 October 2016 Vacuum pumps for the ESRF EBS project Michael Hahn On behalf of the EBS Accelerator Project Team
OUTLINE Project definition - Machine issues and parameters - Time schedule - Logistics Vacuum pumping - UHV pump selection and constraints - Vacuum assembly, chamber issues - Installation and vacuum preparation (pre-pumping) - Vacuum pump interface and control - Bake out Conclusion Page 2
SCOPE OF THE PROJECT – ESRF TODAY Energy 6.04 GeV Storage ring circumference 844 m 10 Hz Booster Synchrotron Multibunch current 200 mA 200 MeV Horizontal emittance 4000 pm.rad Electron Linac Vertical emittance 4 pm.rad 42 Beamlines (including 14 Bending Magnet BL) Page 3 3rd rencontres vide cnrs 10 – 13 October 2016
SCOPE OF THE PROJECT Now EBS Energy (GeV) 6.04 6 Multibunch current (mA) 200 200 Circumference (m) 844.39 843.98 Horizontal emittance (pm.rad) 4000 140 EBS.. Vertical emittance (pm.rad) 4 5 - Is going to be the new photon source (6 GeV electron storage ring) of the ESRF. The brilliance of the generated X-Rays will improve by factors due to the reduced horizontal e-beam emittance. - Will contain 7 dipoles per cell (today 2), 7 x 32 = 224 dipole magnets - Will replace the existing machine in the same tunnel - Will be pre-assembled prior to installation which starts in Jan 2019 - Will contain 128 + 1 girders for magnets, vacuum chambers, etc. - Will be an in-situ bakeable machine - Will mainly use lumped (discrete) UHV pumping rather than functional coatings - Will consist of stainless steel and aluminum vacuum chambers and use conventional flanges Page 4 3rd rencontres vide cnrs 10 – 13 October 2016
SCOPE OF THE PROJECT Now EBS Energy (GeV) 6.04 6 Multibunch current (mA) 200 200 Circumference (m) 844.39 843.98 Horizontal emittance (pm.rad) 4000 140 Vertical emittance (pm.rad) 4 5 present EBS Dipoles-quadrupoles Page 5 3rd rencontres vide cnrs 10 – 13 October 2016
VACUUM PUMPS – SELECTION CRITERIA Compactness Good pumping speed for H2, N2, CO, CO2 Sufficient pumping speed for CH4, noble gases Compatibility with existing installation Reliability Failure tolerance (power cuts) Page 7 3rd rencontres vide cnrs 10 – 13 October 2016
VACUUM CHAMBERS (HIGH PROFILE) - Production of 139 aluminum chambers started at CECOM, Italy - Bi-metal Al2219/SS316LN has been selected for flanges 20 - Production of 159 HP Stainless steel chambers at FMB, Germany 20mm vert. internal height - 316LN material flow from steel suppliers to producer started - Production of 33 HP absorber chambers at Pink, Germany - 316LN material flow from steel suppliers to producer started CH3 CH14 (“absorber chamber”) CH5 Production of Al dipole chamber at CECOM (Photo D. Gibson) Page 8 3rd rencontres vide cnrs 10 – 13 October 2016
PROCUREMENT – VACUUM CHAMBERS (LOW PROFILE) - Production of 102 low profile stainless steel vacuum chambers at FMB, Germany - 316LN material flow from steel suppliers to producer started CH7 - Central curved sheet sections to be produced by deep drawing - Optimization of aspects like required thickness of some of the sheets in collaboration with supplier CH6 13 CH8 Page 9 3rd rencontres vide cnrs 10 – 13 October 2016
PROCUREMENT - INSTRUMENTATION AND CONTROL 322 NEG cartridge pumps and 21 activation controllers, contract placed with SAES, Italy - Lab test of pre-series completed - Series production to be delivered end 2016 4 channel NEG activation controller 522 sputtering ion pumps and 50 IPPS - Contract placed with AGILENT - Pre-Series delivery received 76 RGA assemblies – Company proposed by tender board, sorting remaining minor technical and contractual issues 100 l/s NEG pump - AFC approval received 294 inverted magnetron (Penning) gauges and 160 Pirani gauges 200 l/s NEG pump - Contract under preparation Page 10 3rd rencontres vide cnrs 10 – 13 October 2016
VACUUM ASSEMBLY 200 l/s NEG pump Page 11 3rd rencontres vide cnrs 10 – 13 October 2016
LOGISTICS (STORAGE AND ASSEMBLY BUILDINGS) B1 - Architect view Preliminary design in progress B2 – Temporary storage building Page 12 3rd rencontres vide cnrs 10 – 13 October 2016
INSTRUMENTATION AND CONTROL Baking controllers compatible with fixing them on cable trays 16 control loops per unit Prototype tested Mechanics for 4 additional devices (pre- series) arrived Series production of 20 more to cope with installation schedule Page 13 3rd rencontres vide cnrs 10 – 13 October 2016
GATE VALVES Dimensional and vacuum test for RF sector valves prototype OK – RF test with beam postponed RFQ Custom shaped RF All Metal gate valves for SR sector separation (pneumatic actuation) 69 units RFQ Modified catalogue all metal valves for FE separation (pneumatic actuation) 31 units DN63CF and 34 units DN100CF Proposal of tender commission approved by DM, contract with valve supplier pending AFC approval Page 14 3rd rencontres vide cnrs 10 – 13 October 2016
BAKING SYSTEM Sheathed heaters selected as primary source Tests of shaping insulation coats (aluminum coated PI) ongoing by means of foam chamber and magnet mockups CFT Thermocouples under preparation Purchase of heating collars being prepared Foam vacuum chamber in foam 316L sheathed heater in dedicated Foam vacuum chamber in foam magnet with thermal insulation (1) groove of aluminum chamber prototype magnet with thermal insulation (2) Page 15 3rd rencontres vide cnrs 10 – 13 October 2016
PREPUMPING FOR ASSEMBLY AND INSTALLATION Traditional pumping groups with Hybrid turbo- molecular pump, membrane pump, gauge controller, PLC, etc. too space demanding for EBS machine because of space constraints. This is also to comply with safety standards and European legislation (CE conformity). A more compact pumping concept had to be found.. Page 16 3rd rencontres vide cnrs 10 – 13 October 2016
PREPUMPING FOR ASSEMBLY AND INSTALLATION 6 turbomolecular pumps attached to pre-pumping valves of each vacuum sector. Backed by a dry pump. Isolation valve in the exhaust which closes when rotation speed of turbo gets low, operated by Turbo controller. A trolley will transport controllers, turbos, ACP etc., materials to be installed on cable trays to keep the walkway free. Page 17 3rd rencontres vide cnrs 10 – 13 October 2016
PRESSURE PROFILE Expected conditioning after 1, 10, 100, 1000, 3000 Ah of beam 200 l/s NEG pump Page 18 3rd rencontres vide cnrs 10 – 13 October 2016
ID14 TEST OF KEY COMPONENTS EBS Prototypes installed in a 6m ID straight section of ESRF: - Straight aluminum chamber following EBS dipole chamber production principle(1) - Bellow chamber containing two low profile RF liner assemblies(2) - All metal pneumatic RF gate valve prototype(3) - 1800mm NEG coated ESRF extruded Al ID chamber to fill up full length of SS (4) 3 1 2 4 Page 19 3rd rencontres vide cnrs 10 – 13 October 2016
PROBLEMS AND LESSONS LEARNED FROM ID14 TEST IN AUGUST 2016 - Full aluminum flanges can create problems outside lab environment - Co-incidence of vacuum and RF gaskets on the flanges complicates flange assembly - With the same fixation hole pattern, RF gaskets for low and high profile chambers could be confused - Crossing welding seams on aluminum chambers produced from two plates can create problems Aluminum prototype chamber on ID14 - Given the amount of issues identified on this small test assembly, it becomes obvious that the ‘mockup’ construction is very important View from below, with leaking CF100 aluminum flange (IP) Page 20 3rd rencontres vide cnrs 10 – 13 October 2016
CONCLUSION Contracts for the custom-shaped series production items (standard cell chambers, valves, .. ) have been placed; Design and procurement for one-of-a-kind items (injection and diagnostic chambers, straight section adaptation, ..) is ongoing; Procurement of vacuum instrumentation (UHV pumps, gauges, controllers, ..) close to completion; Still a lot of work for “consumables” ( screws, gaskets, heating collars and connectors , thermal insulation, ..) ahead; Page 21 3rd rencontres vide cnrs 10 – 13 October 2016
MANY THANKS FOR YOUR ATTENTION Page 22 3rd rencontres vide cnrs 10 – 13 October 2016
You can also read