Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15

Page created by Morris Green
 
CONTINUE READING
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Stage 2
Project Update
   Kitchissippi Ward 15
    April 7, 2022
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
O-Train Network

                  2
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Update
                       Scott Street Detour
June 26th, the Transitway between Tunney’s
Pasture and Kìchì Sìbì Station will close
• Construction of the detour facilities along Scott
  Street will be completed prior or the detour
  including the temporary Transitway and temporary
  bus bridge west of Churchill
• The Detour will be operational until the end of the
  Project and OC Transpo’s mirrored bus service.

                                                        3
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Connectivity
                                  Scott Street Detour
• 4-metre westbound sidewalk & cycle track on the north side

• New sidewalk and eastbound cycle track on the south side

• New protected intersections at:
    • Churchill Street North & Scott Street
    • Scott Street & Goldenrod Bridge/Smirle Avenue

• New traffic signals with bus priority phasing and complementary
  bus priority lane (between Lanark Avenue and Island Park Drive)

• Westboro Station bus stops, relocated to Scott Street

                                                                    4
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Golden Rod Bridge

                    5
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Sidewalk and Cycle Track

                           6
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Temporary Westboro Station

                             7
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Utility Works
                                    Westboro Station
Water services and electrical work: 2-week road closure - early May
• Scott Street between Churchill and Athlone closed to eastbound traffic
• Pedestrian detour on the north side of Scott Street

                                                                           8
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Churchill Avenue

                   9
Stage 2 Project Update - April 7, 2022 Kitchissippi Ward 15
Pedestrian Underpass
Churchill Underpass: late 2023

                                                        10
Temporary Bridge

                   11
Footprint
Kìchì Sìbì Station

                     12
Kìchì Sìbì Station
• Ongoing/Upcoming works:
   • Electrical work upgrading conduit for Kìchì Sìbì Station
   • Rock breaking and line drilling April through June,
     approximately
   • Station construction to being late summer/early fall
• Construction fact:
   • Kìchì Sìbì Station is being constructed in same footprint
     described in EA and Planning Phase
   • Kìchì Sìbì Station will require a slight widening of the
     trench to accommodate the head house
   • The alignment east and west of Kìchì Sìbì Station is
     consistent with EA and Planning Phase

                                                                 13
Electrical Works
              Kìchì Sìbì Station
• Existing ductbank requires upgrade to provide power
  to Kìchì Sìbì Station
• Schedule: week of May 2nd - week of May 30th
• Hydro Ottawa does not anticipate any outages
• Hydro Ottawa will excavate a ~1-metre-wide trench
  and backfill as work progresses
• Hydro Ottawa will provide steel plates over trench to
  affected homeowners
• Hydro Ottawa will reinstate impacted lawns and
  driveways

                                                      14
Alignment & Pathways
                        Kìchì Sìbì Station

                              At-grade signalized crossing

                                                    Kìchì Sìbì Station
                      Track Alignment
Start of ramp to
Parkway Tunnel

                    South side pathway

                                                                         15
Parkway Tunnel

                 16
Parkway Tunnel
45% of excavation is complete

                                                 17
Parkway Tunnel

                 18
Sherbourne Station

damon.berlin@ottawa.ca

                             19
SJAM Connectivity
                                               Churchill Avenue
The Stage 2 Project is enhancing               Pedestrian Underpass
connectivity in the area through
the introduction of 4 new
                                         At-Grade Signalized Crossing
crossings of the Sir John A
                                         near Kìchì Sìbì Station
Macdonald Parkway at:
1. Pedestrian Underpass at
   Churchill Avenue                 At-Grade Signalized
2. Signalized Crossing near         Crossing at Rochester Field
   Kìchì Sìbì Station
3. Signalized Crossing at
   Rochester Field                 Cleary Avenue
4. Pedestrian Underpass at         Pedestrian Underpass
   Cleary Avenue

                                                                        20
                                                                             20
Pathways and Connectivity
• NCC Pathway on the north side of the Parkway will
  continue to remain open throughout construction
• NCC Pathway on the south side of the Parkway
  between Cleary Avenue and Kìchì Sìbì Station to
  be closed during construction
   • Section of pathway between Kìchì Sìbì Station and
     Rochester Field will be constructed this spring
• Richmond Road north sidewalk to remain open
  throughout construction
• Byron Avenue south sidewalk to remain open
  throughout construction

                                                         21
Connectivity
Richmond Road

                  22
SJAM Parkway

               23
Community Impacts
• Increased level of construction vehicles travelling
  through the area and trucks will use approved
  routes
• Noise and vibration from trucks and heavy
  equipment should be expected
• Noise and vibration levels are continuously
  monitored and reported to the City
• Generators and pumps will be required periodically
  and are required to be in use day and night.
• Street sweeping has resumed and will be ongoing
  along construction routes.

                                                        24
Construction Hours
• Majority of KEV work 7:00 a.m. to 6:00 p.m., Monday to Friday

• 2022 will see an increase of intermittent overnight and weekend

 work
   • Fueling & maintenance of equipment - overnight 7 days/week

   • Construction lighting is required, will not be directed into residences

• Night work is necessary to accommodate work that requires

 traffic closures that cannot be done during the day, thus

 mitigating impacts on the travelling public

                                                                               25
Stakeholder Relations
• Stage 2 is committed to providing:
  • Rapid response to public inquires
  • Proactive communications through: newsletters, online
    articles, video, social media updates, public notices
  • Providing dedicated presentations to affected groups

                 Stakeholder Relations
                       Ethel Craft
                   ethel.craft@ottawa.ca
                      613-809-3749
   ottawa.ca/Stage2 - to sign up for e-newsletter

                                                            26
Questions?