Revised Draft EIR Public Meeting Southern California International Gateway (SCIG) Project JUNE 15, 2021 5:00 pm PST
Public Meeting Instructions If you have joined online and wish to submit a written comment, please click the Q&A button ( ). Type your first and last name, then submit your written comment. If you prefer to speak, press the “Raise Hand” button to provide verbal comments ( ). • Once your name is called, it will be stated that you have been unmuted to speak. • Please state your first and last name clearly and spell your name for the Court Reporter. • Once you are done speaking, click the button labeled “Lower Hand." If you have joined by dialing in and wish to speak, please raise your hand by pressing *9. • Once it is your turn to speak, you will hear the prompt “you have been unmuted.” Please unmute yourself by pressing *6, then state your first and last name, and spell your name for the court reporter. • To lower your hand when you are done speaking, press *9 again.
Public Meeting Instructions Continued • Public comments will be limited to 3 minutes per speaker • Comments should be limited to the Revised Draft EIR, comment period now extended through July 30, 2021 • All comments received are being recorded and transcribed • Spanish interpreter is available • To listen to the meeting in Spanish, call 877-853- 5257 or 888-475-4499 / Webinar ID: 951 1292 1684
Purpose of the Public Meeting • Provide additional detailed information about two air quality issues, pursuant to a court order resolving a lawsuit under the California Environmental Quality Act (CEQA) • Present key findings of the additional detailed air quality information • Obtain public comments PLEASE FOLLOW THE INSTRUCTIONS FOR PROVIDING PUBLIC COMMENT IN THE CHAT
SCIG Project Overview • SCIG is a new near-dock intermodal rail yard facility proposed by BNSF Railway • Project location is an existing industrial site within four miles of the ports of Los Angeles and Long Beach, with direct access to the Alameda Rail Corridor • SCIG will allow trucks to travel a short distance from the ports before transferring freight to rail cars, rather than traveling more than 20 miles to rail yards near downtown Los Angeles
Environmental Review History • Environmental documents: Notice of Preparation – October 2005 Draft EIR – September 2011 Recirculated Draft EIR – September 2012 Final EIR – March 2013 • Public Outreach – 5 public meetings and various stakeholder engagement • Board of Harbor Commissioners hearing on Final EIR certification – March 2013 • City Council hearing on CEQA Appeals – May 2013
Legal Challenge • 7 lawsuits filed in June 2013 • Court of Appeal validated Final EIR except for requiring additional disclosures on two air quality issues: Frequency and duration of offsite ambient air pollutant threshold exceedances Cumulative offsite pollutant concentrations in combination with a proposal to expand the Union Pacific Railroad’s Intermodal Container Transfer Facility, or ICTF
Court Directive • Revised Draft EIR provides these additional disclosures • Rest of 2013 Final EIR remains valid • These disclosures are highly technical in nature per the Court’s directive
Revised Draft EIR Approach • Prior worst-case “composite emissions” scenario replaced with individual “Benchmark Year” scenarios: 2016, 2020, 2023, 2030, 2035, 2046/2066 • Same modeling tools, assumptions, and data used to disclose year-specific emissions rather than a single composite emissions scenario • Contour diagrams of maximum pollutant concentrations for each benchmark year and pollutant are presented for the project and alternatives, with and without mitigation
Revised Draft EIR Findings The Project and Reduced Project would exceed thresholds for 1- hour NO2 and 24-hour PM10 in all benchmark years Annual NO2, annual PM10, and 24-hour PM2.5 would exceed thresholds in some or most years Reduced Project Pollutant Project (with Mitigation) No Project (with Mitigation) 1-hour NO2 (federal and All Benchmark Years All Benchmark Years All Benchmark Years state) Annual NO2 2016, 2035, 2046/2066 None 2016, 2046/2066 24-hour PM10 All Benchmark Years 2035, 2046/2066 All Benchmark Years 2020, 2023, 2030, 2035, 2020, 2023, 2030, 2035, Annual PM10 2035, 2046/2066 2046/2066 2046/2066 24-hour PM2.5 2016, 2020, 2023 None 2016, 2020, 2023
Revised Draft EIR Findings Significant ambient air pollutant concentrations would occur primarily in industrial areas near the SCIG facility, but in some cases would affect sensitive receptors in residential areas: • Project and Reduced Project: 1-hour NO2 impacts would affect sensitive receptors in West Long Beach and Wilmington in 2016, 2020 and 2023, and a small area of West Long Beach from 2023-2066 • No Project: 1-hour NO2 impacts would extend over large areas of Long Beach and Wilmington: in 2016, impacts would extend almost to Cherry Avenue in Long Beach and include much of Wilmington as far west as I-110
Revised Draft EIR Findings Project 2016 Federal 1-Hr NO2 No Project 2016 1-Hr Federal NO2
Revised Draft EIR Findings (Continued) Significant ambient air pollutant concentrations would occur primarily in industrial areas near the SCIG facility, but in some cases would affect sensitive receptors in residential areas: • Project: Annual PM10 impacts would affect a few sensitive receptors along the western edge of West Long Beach in 2035-2066; mitigation would avoid impacts to these receptors • No Project: Annual PM10 impacts would affect residential areas along I-710 north of the Project site in 2035-2066
Revised Draft EIR Findings Project 2046 Annual PM10 No Project 2046 Annual PM10
Revised Draft EIR Findings Cumulative offsite pollutant concentrations of the Project, when combined with the ICTF project, would exceed the 1- hour federal NO2 threshold but not PM and state NO2 thresholds • Cumulative overlap of the two projects’ significant federal 1- hour NO2 impacts would mostly occur in industrial areas but also, in later years, in a small area at Willow Street and the TI Freeway that could affect one sensitive receptor • Less than significant project federal 1-hour NO2 impacts could combine to produce significant cumulative impacts in some areas outside, but near, the western edge of West Long Beach • The areas of exceedance of PM and state NO2 thresholds by the two projects were widely separated and therefore, not likely to result in significant cumulative impacts when combined
Public Comments • Verbal Comments • E-mail - send to: ceqacomments@portla.org • Mail - Submit comment card or letter by mail to the address on the next slide • Limit comments to Revised Draft EIR contents • LAHD will respond only to comments on the additional information contained in Revised Draft EIR
Written Public Comments Christopher Cannon Director of Environmental Management Los Angeles Harbor Department 425 South Palos Verdes Street San Pedro, California 90731 Review started on May 19, 2021 45-day comment period has been extended by 3 weeks COMMENTS WILL NOW BE RECEIVED THROUGH JULY 30, 2021
Public Comment Procedures If you have joined online and wish to submit a written comment, please click the Q&A button ( ). Type your first and last name, then submit your written comment. If you prefer to speak, press the “Raise Hand” button to provide verbal comments ( ). • Once your name is called, it will be stated that you have been unmuted to speak. • Please state your first and last name clearly and spell your name for the Court Reporter. • Once you are done speaking, click the button labeled “Lower Hand." If you have joined by dialing in and wish to speak, please raise your hand by pressing *9. • Once it is your turn to speak, you will hear the prompt “you have been unmuted.” Please unmute yourself by pressing *6, then state your first and last name, and spell your name for the court reporter. • To lower your hand when you are done speaking, press *9 again. Speakers will be given 3 minutes to speak Spanish interpreter is available