LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan

Page created by Jay Keller
 
CONTINUE READING
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
LBNF NBI Replan Progress

                             Jonathan Paley, Mandy Kiburg

                                   March 24, 2021
                        LBNF Beamline/NSCF Integration Meeting

1   Jonathan M. Paley
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
Neutrino Beam Instrumentation

• In order to reduce risk, the Project moved all non-DOE tasks that had no
  commitments from Partners back on to the Project. This includes all
  Neutrino Beam Instrumentation (NBI) for alignment and monitoring.
• We’ve been working to replan:
  • New WBS elements (broken into different components) and planning
    packages
  • The planning packages and schedule will aim to fit within the existing
    budget and schedule (eg, start dates in 2021 and end dates in 2026):
    • HADeS: $2M
    • MuMS: $3M
    • THI (Crosshairs + TPT): $1.67M
    • HLS (new, Horn Leveling System): $0.8M
  • Meet all milestones from other WBS
  • General strategy is to baseline on NuMI-style detectors

2    Jonathan M. Paley
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
Hadron Alignment Detector System (HADeS)

• UT Austin (Karol Lang, PI) has agreed to deliver the
  detector
    • Provided detailed spreadsheet with costs for a
      5x5 pad detector they are now building for NuMI
    • I have scaled M&S and Labor costs up assuming
                                                                                      Original 7x7 hadron monitor
      a 13x13 detector configuration for LBNF: $350k                                  built by UT Austin
    • Note: labor is extremely inexpensive. Anywhere
      else will raise the labor cost by a factor of 4-5x.
• Major difference with NuMI            LBNF Absorber, Hadron Monitor inside shielding block
                                                      Concrete
                                                                                               Concrete
  detector is that HADeS will be                      blocks-R
                                                                                               Block -C

  retractable (and sit outside of
  beam most of the time).
                                         Shielding
                                         block                                                            Hadron
• Fermilab will provide remote            Steel
                                                                                        Chain drive
                                                                                        mechanism
                                                                                                          Monitor
                                          shielding
  handling, Vladimir has some            Absorber
                                                                              Hadron
                                                                              Monitor
  initial concepts.                      core

3     Jonathan M. Paley                                    DUNE-docdB 12541
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
Horn Leveling System (HLS)

• Jim Hylen presented (Sept. 26, 2019)
  the concept of using a HLS to monitor
  the vertical positions of the horns.
• Sudeshna Ganguly has taken the lead
  on this and has done an amazing job.
                     • HowCERN
    • In discussions with      many sensors?
                                               experts,                                                                                                  Reference HLS
                         2 inside PBE (near BPMs) + 2 from PBE to TH                                                                                     Target hall floor
      technology identified.
                         floor (the one on TH floor is the reference one) +
                         1 at Utility corridor (same elevation as TH floor)
                                        + 5 inside battlement (at the same elevation as

    • Nearly complete M&S cost estimate TH floor) + 4 on bunker wall (same height as of
                                        the ones on top of horns) + 16 inside target
                                        chase + 1 on the other side of the utility corridor
                                        = 31
      ($300k + cost of floor stands for
                   If we consider Keith’s nook:
      sensors).
                                        2 inside PBE (near BPMs) + 1 in the nook (same            Utility Corridor
                                        elevation as the elevation on sensors at BPMs) +
    • Labor costs are being worked on   1 at Utility corridor (same elevation as TH floor)
                                        + 5 inside battlement (at the same elevation as
                                                                                                                              These will be sitting on
                                                                                                                               a stand, as the same
                                                                                                                               elevation as TH floor
                                        TH floor) + 4 on bunker wall (same height as of
                                        the ones on top of horns) + 16 inside target
                                        chase + 1 on the other side of the utility corridor                                                                     Water Lines
                                        = 30

                                        8 units [above horn C and horn B, if we have
                                        stands at two different heights to make up 9 ft or
                                        5 ft: that would add 4 (on horn C) + 4 (on horn B)]

                                        1 channel per sensor, 2 splitters,1 for building                                             Invar rods
                                        reference interferometer, 1 for splitting among
                                        39 channels (31 channels+if extra 8 channels
                                                                                              The sensors in red will be at the same height as the ones on the stand
                                        needed)
         Jonathan M. Paley                                                                    above horn modules. Run 4 Invar rods from Target Hall floor level inside
4                               Sudeshna Ganguly   5
                                                                                              battlement to the level of stand for each of sensors
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
THI: Crosshairs and Target Position Thermometer (TPT)

• Crosshairs:
    • Going with Be crosshair for the upstream end of horn B
    • Cory has designed the brackets and crosshairs. Some more work to do
      on FEA and drafting.
    • Fairly complete cost and schedule in hand.
• TPT:
    • FNAL will provide requirements and specs, and will procure and
      assemble Be components. RAL will do design and drafting.
    • May need beam studies to determine size and positions of components.
    • Labor and M&S costs are being worked on now (mostly by Cory).

5     Jonathan M. Paley
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
Muon Monitor System (MuMS)
• Planning on a NuMI-like system.
• UT Austin built these for NuMI, but has lost some expertise.
  Nevertheless, they could do this and are interested.
• We are also pursuing another detector option: electron multiplier tubes
  (EMTs)
  • Have 3 on loan from KEK
  • Beam test scheduled for end of March 2020 was canceled, hoping to do
    some tests later this year.

6    Jonathan M. Paley
LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan LBNF NBI Replan Progress - Jonathan Paley, Mandy Kiburg March 24, 2021 LBNF Beamline/NSCF Integration Meeting - LBNF NBI Replan
You can also read