GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
INTRODUCTIONS 1. Overview 2. Progress Made To Date 3. What To Expect Next 4. The Finish Product 5. Questions 2
SPORTS FACILITIES Pitches Grass football pitches x 9 (x3 youth & x 6 adult ) Floodlit 3G artificial grass pitches x 2 Cricket pitches x 3 Rugby Pitch x 1 Floodlit tennis courts x8 Sports Hub Sports hall Changing rooms Gym and studio Café Education/meeting room 4
SPORTS HUB Vision To create and provide sport and physical activity facilities that cater to the needs of residents in LBE & LBH now and in the future. 5
WHAT ARE WE CURRENTLY DOING? Main Building. Sports Pitches & External The main building is a steel framed Works. construction that will be clad with timber panels at high levels and We will be constructing a number gabion walling at the lower level. of pitches for cricket and football. There will also be a terraced area with a colonnade at the front of the The football pitches have been set building. out and can be viewed from Facilities will include a sports hall, footpath. fitness suite, education zone and In addition we will be forming a associated changing rooms. swale (small open channel) to aid drainage across the site. 7
WHAT ARE WE CURRENTLY DOING? External Cladding We are forming the external envelope of the building. The system that we are using is an insulated panel that will have timber cladding applied at high level and gabion walls at low level. 8
WHAT ARE WE CURRENTLY DOING? Roofing The roof will comprise of a series of insulated membranes. There will be a number of ventilation points within the roof as well as a bank of photovoltaic panels on both high level roofs. The lower level roof will be planted out. 9
WHAT ARE WE CURRENTLY DOING? Inside the sports hall With the roof decking and the majority of the cladding panels in place this allows us to progress applying additional intumescent coatings to the steelwork. 10
WHAT ARE WE CURRENTLY DOING? Internal Blockwork Walls With the roof decking and the majority of the cladding panels in place this allows us to progress applying additional intumescent coatings to the steelwork. 11
12
WHAT NEXT? Main Building. Sports Pitches & External As our bricklaying subcontractor Works. starts to complete the walls, our The next phase will be to excavate building services subcontractor will be commencing on Monday to start the swale and to transport the soil installation of their works. excavated to form the cricket pitches. Over the next few weeks, the We will be commencing this cladding and gabion walling will be element once the ground is dry installed. enough for the excavation works to proceed. 13
WHAT NEXT? Car Park We are currently completing the demolition of the former PHS walled garden site. From May onwards we will be completing the construction of the new car park. 14
WHAT NEXT? Artificial Grass Pitches Tiger Turf UK Ltd. have been appointed through the Football Foundation’s framework to deliver the two full sized floodlit artificial grass pitches. Tiger Turf UK Ltd. are a reputable sports pitch specialist and have delivered the two full sized floodlit artificial grass pitches in Rectory Park, Northolt. 15
TENNIS COURTS Tennis construction was completed in October 2017 16
TIMELINE Pavilion construction works are now well The pavilion will be underway and on track commissioned and for a summer 2019 the site operator will completion, however the The artificial grass complete their fit programme has slipped pitch works will out in slightly since the last commence in April August/September public update meeting 2019 2019 Demolition works will The natural turf Site open September commence in March pitch works will 2019 2019 and the car park recommence in April will be constructed 2019 thereafter 17
QUESTIONS 18
GUNNERSBURY PARK LONDON
You can also read