INTRODUCTIONS
1.   Overview
2.   Progress Made To Date
3.   What To Expect Next
4.   The Finish Product
5.   Questions

                                 2
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
GUNNERSBURY 2026 - MASTERPLAN

                                3
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
SPORTS FACILITIES
Pitches
 Grass football pitches x 9
  (x3 youth & x 6 adult )
 Floodlit 3G artificial grass pitches x 2
 Cricket pitches x 3
 Rugby Pitch x 1
 Floodlit tennis courts x8
Sports Hub
 Sports hall
 Changing rooms
 Gym and studio
 Café
 Education/meeting room

                                             4
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
SPORTS HUB
  Vision
 To create and
  provide sport and
  physical activity
  facilities that cater
  to the needs of
  residents in LBE &
  LBH now and in
  the future.

                                       5
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
MEET THE KIER TEAM

                     6
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
WHAT ARE WE CURRENTLY DOING?

 Main Building.                            Sports Pitches & External
 The main building is a steel framed        Works.
  construction that will be clad with
  timber panels at high levels and          We will be constructing a number
  gabion walling at the lower level.         of pitches for cricket and football.
  There will also be a terraced area
  with a colonnade at the front of the       The football pitches have been set
  building.                                  out and can be viewed from
 Facilities will include a sports hall,     footpath.
  fitness suite, education zone and         In addition we will be forming a
  associated changing rooms.
                                             swale (small open channel) to aid
                                             drainage across the site.

                                                                                    7
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
WHAT ARE WE CURRENTLY DOING?

 External Cladding
 We are forming the external
  envelope of the building.
 The system that we are using is an
  insulated panel that will have timber
  cladding applied at high level and
  gabion walls at low level.

                                          8
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
WHAT ARE WE CURRENTLY DOING?

 Roofing
 The roof will comprise of a series of
  insulated membranes.
 There will be a number of
  ventilation points within the roof as
  well as a bank of photovoltaic panels
  on both high level roofs.
 The lower level roof will be planted
  out.

                                          9
GUNNERSBURY PARK LONDON PUBLIC UPDATE - Sports Hub Update 07/11/2018
WHAT ARE WE CURRENTLY DOING?

 Inside the sports hall
 With the roof decking and the
  majority of the cladding panels in
  place this allows us to progress
  applying additional intumescent
  coatings to the steelwork.

                                       10
WHAT ARE WE CURRENTLY DOING?

 Internal Blockwork Walls
 With the roof decking and the
  majority of the cladding panels in
  place this allows us to progress
  applying additional intumescent
  coatings to the steelwork.

                                       11
12
WHAT NEXT?

  Main Building.                          Sports Pitches & External
  As our bricklaying subcontractor         Works.
   starts to complete the walls, our
                                           The next phase will be to excavate
   building services subcontractor will
   be commencing on Monday to start         the swale and to transport the soil
   installation of their works.             excavated to form the cricket
                                            pitches.
  Over the next few weeks, the            We will be commencing this
   cladding and gabion walling will be      element once the ground is dry
   installed.                               enough for the excavation works
                                            to proceed.

                                                                                  13
WHAT NEXT?

  Car Park
  We are currently completing the
   demolition of the former PHS
   walled garden site.
  From May onwards we will be
   completing the construction of the
   new car park.

                                        14
WHAT NEXT?

              Artificial Grass Pitches
              Tiger Turf UK Ltd. have been
               appointed through the Football
               Foundation’s framework to deliver
               the two full sized floodlit artificial
               grass pitches.
              Tiger Turf UK Ltd. are a reputable
               sports pitch specialist and have
               delivered the two full sized floodlit
               artificial grass pitches in Rectory
               Park, Northolt.

                                                        15
TENNIS COURTS

 Tennis construction was completed in October 2017

                                                      16
TIMELINE

  Pavilion construction
   works are now well                                                                              The pavilion will be
 underway and on track                                                                             commissioned and
    for a summer 2019                                                                             the site operator will
completion, however the                              The artificial grass                           complete their fit
 programme has slipped                                pitch works will                                    out in
   slightly since the last                           commence in April                             August/September
  public update meeting                                     2019                                           2019

                             Demolition works will                            The natural turf                             Site open September
                              commence in March                               pitch works will                                     2019
                             2019 and the car park                          recommence in April
                               will be constructed                                  2019
                                    thereafter