Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021

Page created by Kim Bates
 
CONTINUE READING
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Fire Response Recovery Concepts

Draft #2 for Discussion

July 16, 2021
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Context

• On	
  June	
  30	
  Ly+on	
  BC	
  experienced	
  a	
  devasta9ng	
  fire	
  resul9ng	
  in	
  the	
  loss	
  of	
  approximately	
  
  90%	
  of	
  the	
  community’s	
  structures	
  

• This	
  included	
  the	
  loss	
  of	
  key	
  community	
  buildings,	
  many	
  residen9al	
  homes	
  and	
  
  infrastructure	
  

• Kanaka	
  Bar	
  has	
  also	
  been	
  impacted	
  by	
  these	
  fires	
  in	
  many	
  different	
  ways,	
  however,	
  the	
  
  community	
  itself	
  remains:	
  
    • Safe	
  from	
  current	
  fires	
  
    • A	
  FireSmart	
  Community	
  	
  
    • Home	
  to	
  opera9ng	
  community	
  infrastructure	
  	
  
          • E.g.	
  Water,	
  power,	
  telcom	
  	
  
    • Ready	
  to	
  advance	
  projects	
  that	
  support	
  our	
  friends	
  and	
  family	
  in	
  this	
  tough	
  9me	
  

• Therefore,	
  Kanaka	
  Bar	
  is	
  proposing	
  to	
  offer	
  temporary	
  housing	
  and	
  administra9ve	
  
  buildings	
  to	
  help	
  those	
  in	
  need	
  
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Four Potential Sites in Kanaka

Thus far, Kanaka’s team has considered four key sites:
•   Lot 4
•   HWY 1
•   Lot 16
•   Areas in Upper Kanaka

Proposed concepts aim to expedite construction, align with long-term projects,
and be as cost effective as possible

Based on efforts to date focus is on HWY 1 and Lot 4

Working to advance a concept for Lot 16
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Locations of Proposed Recovery Projects
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Highway 1 – Community Recovery Centre

Purpose:
-   Provide a temporary service hub for the region

Proposed Recovery Concept:
-   A large community resource building with meeting space, kitchen, dinning area,
    and multi-purpose rooms (e.g. daycare, small store).
     -      building can be re-scoped to include a temporary housing solution

-   Two additional multipurpose buildings that can be customized to meet the
    specific needs of the Lytton Fire recovery effort
     -      To be used for essential services such as RCMP, first aid, etc. based on regional need

-   A fueling station (if required)	
  

     	
  
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
HWY 1: Visualization of Recovery Project Proposal

                                                                                                                1.1	
  /1.2	
  

      Community	
  Resource	
  Building	
  

                                              Mul9-­‐purpose	
  Office	
  Space	
  and	
  Fueling	
  Sta9on	
  
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
HWY 1: Floor plan for 5 unit Kitchen/Diner/Rec Building
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Project Cost Estimate for Highway 1 Concept

Highway	
  1	
  Recovery	
  Project                  Estimate                   NOTES
PROFESSIONAL	
  SERVICES	
  AND	
  PERMITTING
Geohazard	
  Review                                                 $10,000 Allowance	
  -­‐	
  i nitiated
Civil	
  and	
  planning                                            $25,000 Allowance
Contract	
  Administration	
                                        $15,000 Allowance
Project	
  Management                                               $15,000 Allowance
	
  Professional	
  Services	
  Sub-­‐Total	
                       $65,000
SITE	
  WORKS
                                                                            2	
  x 	
  200	
  AMP	
  service	
  (requires	
  further	
  upgrade	
  post	
  
Electrical                                                          $25,000 recovery)

Water	
  (longer	
  term	
  solution)                             $505,000 Optional	
  -­‐	
  based	
  on	
  2020	
  cost	
  e stimate	
  (with	
  ClearFlow)
Sanitary                                                                $0 Holding	
  tank	
  (assumed	
  to	
  be	
  i n	
  building)
Type	
  2	
  B	
  Driveway                                        $115,000 Confirm	
  with	
  MOTI	
  i f	
  needed	
  for	
  temp	
  solution
Other                                                              $25,000
	
  Site	
  Works	
  Sub-­‐Total	
                                $670,000
BUILDINGS
Fuel	
  station	
                                                  $30,000 based	
  on	
  preliminary	
  quotes
East	
  Side	
  Buildings                                         $654,000 5	
  unit	
  Kitchen	
  /	
  Diner	
  complex	
  (Seko)
                                                                           2	
  generic	
  buildings	
  on	
  West	
  Side;	
  fueling	
  station	
  
West	
  Side	
  Buildings                                         $100,000
                                                                           (Seko/NRB)	
  
Buildings	
  Sub-­‐Total                                          $784,000
	
  Sub	
  total	
  without	
  Contingency	
  	
                $1,519,000
	
  Project	
  Contingency	
  (10%)	
                             $151,900
Estimated	
  Total	
  Project	
  Cost	
                         $1,670,900
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Lot 4: Residential Area for Regionally Displaced Residents

Purpose:
-       Provide a temporary safe, secure and pleasant living environment for those who have
        lost their homes.

Proposed Recovery Concept:
-       A 19 bedroom unit (scalable) with a shared kitchen, dinning area and recreational
        space
-       A 10 to 19 bedroom building with individual washrooms and a shared kitchen a living
        area and customizable space for resident use
-       Areas for longer-term RV/trailer use, or additional modular housing units

Long-term:
-       50 bedrooms as part of the 24 affordable units (shovel ready) as part of Kanaka’s long-
        term housing strategy
	
  
Fire Response Recovery Concepts Draft #2 for Discussion July 16, 2021
Lot 4: Visualization of Recovery Project Proposal

                                                                                                                                2.0	
  

                          Temporary	
  Residen9al	
  Buildings:	
  29-­‐38	
  rooms	
  
TCP	
  24	
  units	
                                                                      TCP	
  laydown	
  /	
  RV	
  area/
                                                                                          addi9onal	
  units*	
  

                                         TCP	
  Sanitary/Solar	
  Field	
                          Available	
  for	
  expansion	
  
The Crossing Place

    The Crossing Place
    24 units / 50 beds
Floor plan for 19 bedroom (NRB) on Lot 4
Floor plan for 10 bedroom (Seko) on Lot 4
Project Cost Estimate

Lower	
  Kanaka	
  Recovery	
  Project               Estimate                  NOTES
PROFESSIONAL	
  SERVICES	
  AND	
  PERMITTING
Civil	
  and	
  planning                                           $15,000 Allowance
Arch	
  monitoring                                                 $20,000 Allowance
Contract	
  Administration	
                                       $15,000 Allowance
Project	
  Management                                              $15,000 Allowance
	
  Professional	
  Services	
  Sub-­‐Total	
                      $65,000
SITE	
  WORKS
                                                                           Required	
  upgrades	
  for	
  Lot	
  4	
  (Allowance	
  -­‐	
  recommended	
  from	
  BCH)	
  and	
  
Electrical                                                        $200,000 temp	
  generator
                                                                           Longer-­‐term	
  based	
  on	
  Kanaka	
  water	
  plan	
  ($500,000	
  +	
  temp	
  water	
  
Water	
  (long-­‐term)                                                  $0 treatment)
Water	
  (short-­‐term)                                            $30,000 T-­‐	
  from	
  e xisting	
  potable	
  l ine	
  i n	
  Lower	
  Kanaka	
  (may	
  cause	
  disruption	
  l ater)
Sanitary                                                                $0 Holding	
  tanks
Road                                                              $430,000 Required	
  for	
  TCP	
  (Kanaka	
  Station	
  Road,	
  HWY	
  1	
  i mprovement	
  and	
  Egress)
Strip	
  Topsoil                                                   $26,000 calculated	
  as	
  $5/m2	
  for	
  5,200	
  m2
Gravel	
  Pad                                                      $50,000 Allowance	
  i f	
  needed	
  
Site	
  Reclamation                                               $100,000 Removal	
  and	
  return	
  to	
  agriculture
	
  Site	
  Works	
  Sub-­‐Total	
                                $836,000
BUILDINGS
19	
  bedroom	
  "drill	
  camp"                                  $450,000 NRB	
  -­‐	
  19	
  bedroom	
  complex	
  
10	
  bedroom	
  residential                                      $726,000 Seko	
  -­‐	
  10	
  bedroom	
  complex
Permits                                                            $10,000
Building	
  Sub-­‐Total                                         $1,186,000
	
  Sub	
  total	
  without	
  Contingency	
  	
                $2,087,000
	
  Project	
  Contingency	
  (10%)	
                             $208,700
Estimated	
  Total	
  Project	
  Cost	
                         $2,295,700
Lot 16: Housing and RV Spaces

                              3.1/
                              3.2	
     •   Proposing to:
                                             – bring up existing home up to
                                               code
                                             – create new spaces RVs

                                        •   This can help create space for
                                            another five families

                       Reno	
           •   Initial costs estimates $250,000 +
   RV	
  areas	
       home	
  
   (benches)?	
                             water servicing improvements
                                             –   Still under review
Anticipated Operational Costs

•    Based on initial estimates and assumptions

           Anticipated	
  Operational	
  Cost                      Allowance
      Power	
  Residential                           $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  40,000
      Power	
  Community	
  Buildings                $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  15,000
      Sanitary	
  pump	
  outs                       $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  60,000
      Water	
  Operations                            $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  20,000
      Janitorial	
                                   $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  175,200
      Security	
                                     $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  262,800
      Grounds	
  maintenance                         $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  22,000
      Insurance                                      $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  25,000
      Pest	
  control                                $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  20,000
      Project	
  management	
                        $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  75,000
      Management,	
  Legal	
  and	
  Professionals   $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  150,000
      Telcom	
  (internet/phone)                     $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  20,000
      Waste	
  management                            $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  15,000
      Generator	
  +	
  fuel                         $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  100,000
       Annual	
  operating	
  allowance              $	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  1,000,000
Proposed Schedule

•   Project funding approval: July 16, 2021
     – Total estimated cost: $4 million

•   Place order for building structures: July 16, 2021

•   Site works: July 19 – August 1

•   Buildings arrive to Kanaka: August 2

•   Installation and commissioning: August 9 - 20
Summary of Kanaka’s Recovery Offer of Support

•   Total number of temp. beds: 38
     – With room for more as needed

•   Spaces for RVs/Trailers: 10-15

•   Estimated temp. population: 70-100

•   4 buildings serving regional essential services

•   Delivered in approximately 4-5 weeks

•   Estimated development cost: Approx. $4 million

•   Operating allowance: Approx. $1 million
Next Steps

•   Review initial concepts with Kanaka, regional partners and incorporate
    feedback

•   Prepare revised concepts and advance applicable planning and
    engineering work
     – Update cost estimates and schedule based on input and specific regional
       needs

•   Formally secure Federal/Provincial emergency funding support

•   Advance construction
KWUKWSCEMXW!
You can also read