STOCKINBINGAL TO PARKES COMMUNITY BRIEFING: ONLINE SESSION - 1 December 2020
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
ACKNOWLEDGMENT TO COUNTRY I wish to acknowledge the traditional owners of the land on which we meet today and pay my respects to elders, past present and emerging Inland Rail Community Briefing 1 December 2020
AGENDA Acknowledgement of Country Introduction Project Overview Project Timings Design Update Heritage Considerations Community and Stakeholder Engagement Inland Rail Community Briefing 1 December 2020
ABOUT INLAND RAIL Inland Rail is a once-in-a-generation project that will enhance supply chains and complete the backbone of the national freight network by providing for a transit time of 24 hours or less for freight trains between Melbourne and Brisbane via regional Victoria, New South Wales and Queensland. Comprising of 13 individual projects and spanning more than 1,700km, Inland Rail is the largest freight rail infrastructure project in Australia and one of the most significant infrastructure projects in the world. Construction of Inland Rail commenced in late 2018 and is expected to be completed in 2025. Inland Rail will provide greater freight carrying capacity, as it is designed for double-stacked trains up to 1,800m long, each of which will be able to carry the same volume of freight as 110 B-Double trucks. Inland Rail Community Briefing 1 December 2020
BENEFITS OF INLAND RAIL Road competitive service Reducing Congestion Reducing Burden Globally Competitive Connecting 1/3 of the fuel of road For producers Cities, farms, mines and ports Inland Rail Community Briefing 1 December 2020
INLAND RAIL PROGRAM STATUS NSW/QLD BORDER P2N COMPLETE N2NS PROJECTS IN DELIVERY T2A G2H H2C C2K PROJECTS IN PROCUREMENT PROJECTS A2I I2S S2P N2N NS2B B2G K2ARB YET TO BE PROCURED Inland Rail Community Briefing 1 December 2020 6
PROJECT PROGRESS PROJECTS PROJECT STAGES CONCEPT REFERENCE DETAILED PROJECT VICTORIA CONSTRUCTION OPERATION ASSESSMENT DESIGN DESIGN APPROVAL 1 Tottenham to Albury CONCEPT REFERENCE DETAILED PROJECT NEW SOUTH WALES CONSTRUCTION OPERATION ASSESSMENT DESIGN DESIGN APPROVAL LEGEND 2 Albury to Illabo CURRENT STATUS 3 Illabo to Stockinbingal Q3 2020 4 Stockinbingal to Parkes 5 Parkes to Narromine 6 Narromine to Narrabri 7 Narrabri to North Star North Star to NSW/Qld Border 8 CONCEPT REFERENCE PROJECT DETAILED QUEENSLAND CONSTRUCTION OPERATION ASSESSMENT DESIGN APPROVAL DESIGN NSW/Qld Border to Gowrie 9 10 Gowrie to Helidon PUBLIC PRIVATE PARTNERSHIP (PPP) 11 Helidon to Calvert These three Queensland projects will be constructed under a single PPP. 12 Calvert to Kagaru Kagaru to Acacia Ridge and 13 Bromelton Inland Rail Community Briefing 1 December 2020
STOCKINBINGAL TO PARKES (S2P) An enhancement project of specific sites along the 173kms existing rail corridor from Stockinbingal to Parkes (S2P) Enhancement Projects require horizontal and vertical clearances at specific sites to accommodate the operation of double stacked container trains and does not include upgrade or improvement works The environmental assessment for the S2P project is via Four Review of Environmental Factors (REF) October 2020 awarded contract to new consultant service provider WSP Australia WSP Australia will support the finalisation of the reference and detailed design and environmental approvals We expect to tender for first packages of work for the Stockinbingal to Parkes project in late 2021. Inland Rail Community Briefing 1 December 2020
WHERE IS THE PROJECT UP TO? We are here Phase 1 Phase 2 Phase 3 Phase 4 Operate Concept Design Approval Construct Design includes: Investigations include: Community consultation Ecological surveys Site Investigations Geotechnical surveys Reference and detailed design Cultural heritage surveys Review of Environmental factors Utility identification surveys Noise, air quality, vibration surveys etc Inland Rail Community Briefing 1 December 2020
PROJECT TIMINGS DATE PROJECT ACTIVITY Q3 2020 WSP Australia commences as new consultant service provider Reference & Detailed Design Community Engagement Q4 2020 to Q4 2021 Environmental Approvals Public Exhibition Q3 & Q4 2021 Procurement Q1 2022 – Q3 2023 Construction Inland Rail Community Briefing 1 December 2020
S2P ENHANCEMENT SITES Site Detail Proposed Solution Daroobalgie • Crossing loop • Construct new crossing loop • Wyndham Avenue Bridge • Track lowering Forbes • Forbes Railway Station • Clearance works and track slew • Lachlan River Bridge • Modification or new structure • Wirrinya (Forbes Shire Council) • Track Slew Horizontal and vertical • Redbend (Forbes Shire Council) • Track Slew clearance works • Caragabal (Weddin Shire Council) • Track Slew • Quandialla (Weddin Shire Council) • Clearance works • Bribbaree (Hilltops Council) • Track Slew • Milvale (Hilltops Council) • Clearance works Inland Rail Community Briefing 1 December 2020
LEVEL CROSSINGS IN SOUTHERN NSW Not within S2P scope to grade separate any road/rail interface Assessments of road/rail interface underway All new and upgraded level crossings (LX) must comply with the Australian Level Crossing Assessment Model (ALCAM) ALCAM considers road traffic numbers, vehicle types, train numbers, speeds and sighting distances Private LX: we work closely with each landowner to understand individual access requirements and safety issues ~2.5 minutes: estimated wait times for Inland Rail freight trains at level crossings in towns Inland Rail Community Briefing 1 December 2020 12
DAROOBALGIE CROSSING LOOP Proposed works New Crossing Loop Construct new crossing loop on eastern side of existing track Approx. 2.2km of new track Daroobalgie Road upgraded for road trains requires upgrade to existing Level Crossing from passive to active Above: Proposed location of new crossing loop at Daroobalgie looking north Inland Rail Community Briefing 1 December 2020
WYNDHAM AVENUE BRIDGE Proposed works Track Lowering Vertical clearance of 5755 mm - a required vertical clearance shortfall of 1430mm Further design work required for collision Track Lower 1.43m protection for bridge piers Above: Wyndham Avenue Bridge from the Southern side looking north Inland Rail Community Briefing 1 December 2020
LACHLAN RIVER BRIDGE Issue Options assessment required to determine preferred solution which may include; Vertical clearance required Modify existing bridge Local Heritage Status Replace existing bridge with new bridge Existing Bridge Inland Rail Community Briefing 1 December 2020
INDICATIVE EXAMPLES ONLY Option 1 – Modify existing bridge Option 2: Build new bridge Inland Rail Community Briefing 1 December 2020
FORBES STATION Issue Options Assessment Horizontal Clearance works required Modify Awning on Station Platform Local and State Heritage Listed Track slew required further along Goods Siding – possible removal Existing Indicative Drawing: Trim Awning Inland Rail Community Briefing 1 December 2020
MILVALE Issue Horizontal Clearance works required Local Heritage listing Options Assessment Removal or modification of water tank Minimise impacts to heritage listed water tank Inland Rail Community Briefing 1 December 2020
HORIZONTAL CLEARANCE SITES Track Slew or Clearance Works 1. Red Bend 2. Wirrinya 3. Caragabal 4. Quandialla Red Bend Caragabal Caragabal 5. Bribbaree A track slew is a slight movement of the train track, to allow for improved horizontal clearances Wirrinya Quandialla Inland Rail Community Briefing 1 December 2020
HERITAGE CONSIDERATIONS There are three heritage listed sites; the Lachlan River Railway Bridge, Forbes Railway Station Group; and the Milvale Water Tank. Protected under the Heritage Act 1977 and Environmental Planning & Assessment Act 1979. Inland Rail is engaging technical advisors to inspect and assess these heritage sites Once the options are finalised, regulatory authorities will be consulted, and appropriate permits will be sought to carry out any works as required. Community will also have the opportunity to provide feedback Inland Rail Community Briefing 1 December 2020
S2P COMMUNITY ENGAGEMENT 2020 - 2021 Snapshot Engagement To Date 10 community information sessions since September 2018 1 regional supplier briefing 70+ face to face and group project meetings to date Upcoming Engagement 2020 Project update & Design Progress 1 & 3 December – Online 4 & 5 December – Face to Face in Forbes Workforce Participation in Forbes 2021 Regional Supplier Briefing – Q1 2021 Capability Development Workshops – Q2 & Q3 2022 Inland Rail Community Briefing 1 December 2020
WORK WITH US Inland Rail Community Briefing 1 December 2020
INLAND RAIL & THE COMMUNITY Sponsorships & Donations Program To date approx. $20k in grant funding awarded to community initiatives, e.g. Taste on Templar, laptops for Forbes Public School, new equipment for CanAssist, sporting equipment for Wirrinya Progress & Sports Association Four grants available annually, up to $4,000 each round Pictured above: two students with the laptops purchased by Forbes Public School Inland Rail Community Briefing 1 December 2020
S2P NEXT STEPS TIMING ACTIVITY December 2020 Community Consultation – gain feedback from the community on the multicriteria assessment sites and detailed designs. January – February Investigations to inform development of Reference Design & 2021 primary approvals documentation e.g. biodiversity February 2021 Multicriteria Assessment Workshop to determine design solution for heritage sites March/April 2021 Detailed & Reference Design Community Engagement Supply Chain Briefing Inland Rail Community Briefing 1 December 2020
HAVE YOUR SAY W We invite community feedback to help inform the decision- making process through the following channels; Social Pinpoint https://maps.inlandrail.com.au/s2p#/ Contact us directly Eleanor Falkiner Efalkiner@artc.com.au Amanda Dunn Adunn1@artc.com.au 1800 732 761 Inlandrailnsw@artc.com.au Attend our Community Information 4 DEC, 6 – 8pm sessions Club Forbes, Templar Street 5 DEC, 9 - 11am Rankin St, Forbes Public exhibition Q4 2021 Inland Rail Community Briefing 1 December 2020
FOR FURTHER INFORMATION Eleanor Falkiner Stakeholder Engagement Lead efalkiner@artc.com.au 0419 835 944 Amanda Dunn Stakeholder Engagement Advisor adunn1@ARTC.com.au 0436 349 387 THANK YOU
You can also read