Build the Beach for Us by Us!

• Welcome/Community Agreement
• Project Overview

• Upcoming Bid Opportunities

• Women & Minority Owned Businesses (WMBE)

• Q&A
• What’s Next
Rainier Beach High School
• I instead of we: Don't make generalizations about a

  COMMUNITY                                         group, one person does not speak for a whole
                                                    community
                                                  • Safe space: Acknowledge that this space is for
                                                    everyone to share their thoughts and feelings

  AGREEMENT                                         without fear of judgment
                                                  • Limited time: We want to give space to Q+A so we
                                                    may have to move conversations forward in interest
                                                    of time.

• Yo en lugar de nosotros: No hagas               •   Halkii ay aheyd innanga: Koox si guud ahaan ah ha
  generalizaciones sobre un grupo, una persona        isugu duubin, qof kaliya uma hadli karo bulsho
  persona no habla por toda la comunidad              dhammaanteed
• Espacio seguro: Reconozca que este espacio es   •   Goob nabdoon: Oggolow in goobtani tahay meel qof
  para que todos compartan sus pensamientos y         kasta kula wadaagi karaan fakarkooda iyo
  sentimientos sin temor a ser juzgados               dareenkooda iyagoon ka cabsan in la xukumo
• Tiempo limitado: Queremos dar espacio para      •   Waqti kooban: Waxan dooneynaa inaan ku siinno
  preguntas y respuestas, pero es posible que         goob su’aalo iyo jawaabo (S+J) si wada hadalka hore
  tengamos que avanzar las conversaciones en          loogu wado iyadoo waqtiga la eegayo. Haddii aanan
  areas del tiempo                                    heli faalladaada/su’aashaada, halkan waxa ah waxa
                                                      aad sameyn karto
Rainier Beach High School
We would like to acknowledge that we are standing on sacred land
belonging to the Duwamish Tribe.

We would also like to take a few minutes to recognize all the
exertion the community members have put into RBHS.
Rainier Beach High School
Project Overview
Rainier Beach High School
Meet Your Construction Team
Lydig Construction – General Contractor        The Vida Agency – Communications
   o Patrick McGlothlin – Project Manger          o Amalia Martino, President
   o Tim Casad – Chief Estimator/VP               o Marcela Diaz, Director of Equity
      Preconstruction                               and Engagement
Alec Stephens Consulting – Inclusion Expert       o Elise Van Deventer, Project
   o Alec Stephens                                  Coordinator

Darling Nava – MWBE Outreach                   Community Leaders

DNI Solutions – Workforce Inclusion               o Virginia Bethea, Seattle Public Schools

   o Rick Dimmer Workforce diversity manager
Rainier Beach High School
Four Areas of Focus
Overall     1) Rainier Beach Community Engagement

Inclusion   2) Student Body Engagement
            3) Minority & Women Owned Business
Approach       (MWBE) Participation
            4) Workforce Inclusion (SCWA)
Rainier Beach High School
Rainier Beach High School
Project
    Overview
•   Complete replacement of
    existing high school
•   Multi-phased project
•   Occupied campus
•   290,000 sq. ft. new school
•   Includes:
     ◦ New athletics facility
     ◦ Theater
     ◦ Classroom wing
     ◦ Commons
     ◦ Skills center
•   Student & Community
    Workforce Agreement (SCWA)
Rainier Beach High School
SITE PLAN

Project Phasing

    Phase 1 & 2

• April 2022 - September
  2022
  o Geothermal Wells
  o Temporary Existing
    Building Alterations

    Phase 3 & 4

• Fall 2022 - Fall 2025
  o Main Building
    Construction
Build the Beach for Us by Us!

2021                           2022                                     2025
SPRING                         SPRING                                   FALL
• Outreach                     • Start of early site work               • Final completion
• Scope development            • Bidding Temporary Existing Bldg T.I.
• Bid package development
                               SUMMER
WINTER                         • Bidding
• Bidding of Early Site Work
                               FALL
                               • Start of main construction
Scope of Work for
Temporary Existing
Building Alterations
• Gym & Theater Bldg
Area of Temporary
Existing Building
Alterations

    Construction Schedule
                                    • Classroom Bldg

    July 2022 – Sept 2022
SOW’s for Temporary Building Alterations
•Abatement
•Demolition
•Structural Steel / Rebar
•Framing / Sheetrock
•Misc. Specialties Supply
•Doors, Frames, Hardware (supply & install)
•Insulation
•ACT Ceilings
•Painting
•Carpet & Resilient Flooring
•Earthwork & Paving
Bidding Timeline
Bidding Timeline

Early March       Late March     Early July

  Bid Documents                  Expected Start of
                      Bids Due
    Published                      Construction
Q&A
MWBE Resources
1:1 Sessions
•Mondays, between 3pm – 5pm

•Great Opportunity to:
 • Meet & Greet
 • Ask project questions
 • Inquire about bidding process
 • Connect on bidding opportunities

•Contact Darling to schedule now!
MWBE Certification Assistance
Are you a Minority or Women owned business, but not yet
certified?
 • We are here to help!!!

Assistance available:
 • City of Seattle, self-identified: https://web6.seattle.gov/fas/registration/
 • State of Washington OMWBE Certified: https://omwbe.wa.gov/
Q&A
What’s next…
Save the Date!
•   Tune into the Converge Media
    Morning Update Show!
•   Tuesday, March 15th at 11 am
•   Watch live on the Converge Media
    YouTube or whereweconverge.com
•   Featuring Carpentry Pre-
    Apprenticeships and information from
    the Northwest Carpenters Institute
    (NWCI)
        Check out our WEBSITE for previous meetings, Converge segments, and
                      more: www.buildthebeachforusbyus.com
CONTACT US!
Lydig Construction                     Community Outreach
• Patrick McGlothin, Project Manager   • Elise Van Deventer
     o PMcGlothin@lydig.com                o Elise@thevidaagency.com

Minority & Women Owned Businesses      Student Engagement
• Darling Nava, MWBE Consultant        • Virginia Bethea, Family Support Coordinator
    o outreach@darlingnava.com             vowens@seattleschools.org

Workforce Inclusion
• Rick Dimmer, Workforce Consultant
    o thednisolutions@gmail.com
Thank you, have a great night!
(BACK UP SLIDES)
How You Build a School

    DESIGN PHASE         CONSTRUCTION PHASE