Public Meeting Stouffville Rail Corridor Expansion Program - June 23, 2016 Agincourt Recreation Centre 31 Glenn Watford Drive, Scarborough - Metrolinx
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Stouffville Rail Corridor Expansion Program Public Meeting June 23, 2016 Agincourt Recreation Centre 31 Glenn Watford Drive, Scarborough
Meeting Agenda 6:30-6:45 Sign-in and Registration 6:45-7:00 Recap and Program Update 7:00-7:30 Community Questions 7:30-7:45 Agincourt Station Modifications 7:45-8:30 Open Discussion 2
Recap At the March 29, 2016 meeting there were questions about: • Electrification • Drainage • Construction and Noise Wall Installation • Agincourt GO Station Improvements • Safety/Crossing Improvements • Construction Impacts • Overall Program Following the meeting answers were sent out to residents on the project email list, posted to the website and are available at the registration table tonight. Since our last meeting, we’ve received questions on the project covered in tonight’s presentation. 3
Opportunities to Connect 2016 Quarterly Meetings Outreach in the Community • Today - June 23, 2016 • Community Office opens in September 2016 • September 2016 • Drop-in hours Tuesday’s from 10AM-12PM at Agincourt Community Services Association • December 2016 (ACSA) 4155 Sheppard Ave. E. Ste 100: • June 28 • July 5 • July 12 • July 19 • July 26 • August 2 • August 9 • August 16 • August 23 • August 30 4
Program Update Stouffville Corridor Overview Design: 2016 - 2017 Unionville GO 15% Complete Station Construction: 2017-2019 Design: 2016 - 2017 Milliken GO Station 15% Complete Construction: 2017-2019 Phase 1 Track work Construction: Underway - 2017 Kennedy Road to Marilyn Work sequencing generally Avenue progresses north to south Design: 2016 - 2017 Community Agincourt GO Station 15% Complete Office Construction: 2017 - 2019 Phase 2 Track work Design: Complete Sheppard Avenue to Construction: Early 2017- 2019 Scarborough Junction Kennedy GO Station Design: 2016 - 2017 Part of Eglinton Crosstown Construction: 2017 - 2021 * Dates Subject to Change 5
Program Update What’s happening now? Phase 1 Track Work • Community Office to open September 2016 Milliken GO • Site clearing and grading continues for Phase 1 (Between Milliken and Agincourt GO stations) • Phase 1 noise wall auger foundations to start Summer 2016 • Agincourt station modifications early Agincourt GO design underway Community Office • Steeles Ave grade separation EA underway by City of Toronto • Electrification public meetings underway • Phase 2 resident consultations for encroachments and trees 6
Community Questions What is the Schedule for Track Work? Phase 1 Track work Construction: Underway - 2017 Kennedy Road to Work sequencing generally Marilyn Avenue progresses north to south * Dates Subject to Change
Community Questions Noise Wall Installation Phase 1 Track Work • Phase 1 installation of the east side noise walls from Marilyn Avenue to Kennedy Avenue north of Steeles to Milliken GO begin later this summer/fall • Grading of one side of the corridor needs to happen in order to make Step 1 space for the noise wall auguring East Side equipment ~ 3 weeks behind each • East side timeline is very different backyard than the west because we need to Agincourt GO shift the tracks to do the noise wall work • Noise walls will be owned and maintained by Metrolinx 9
Community Questions Stormwater Management • Stormwater design has been completed and a copy of the report can be found on our website. • How does the final design address drainage and pooling? • How are we addressing drainage and pooling during construction? – The construction activities create a lot of sediment run-off and in order to prevent this dirt and mud from clogging the drainage system, straw bales and silt fence are used to withhold the dirt and allow the water to continue to drain – Pooling along the corridor during construction activities is to be as minimal as possible and it is the responsibility of the contractor to ensure drainage paths are maintained throughout construction – Once construction activities are completed, the final drainage channels/ditches will be graded to ensure drainage to the existing drainage outlets – New underground storm sewers are being installed along the corridor where space for a ditch is not possible, and new culverts crossing from east to west side of the tracks are being installed as well. 10
Community Questions Property Impacts • Phase 1 & 2 is being constructed within the existing rail corridor with property issues limited to encroachments and trees. • Currently Agincourt Station Redesign impacts are being assessed and Metrolinx is finalizing details over the next few months. All affected property owners will be contacted and impacts will be discussed and addressed • Impacts can be in the form of: – Acquistion (property taking – Metrolinx works with the property owner to reach an agreement on the property purchase, expropriation is typically a last resort) – Permanent Easement (Owner retains ownership, but Metrolinx would have permanent rights to access the land) – Temporary Easement (Owner retains ownership, but Metrolinx would have use of the land for a period of time to permit construction – approx. 2-3 years) – Encroachments (where the owner has private fences, sheds, etc. built within the rail corridor) 11
Community Questions Safety as a priority Safety as a priority for our operations and construction. It is mandatory that all construction contractors have a Metrolinx approved Safety Management Plan in place. The plan is also consistently monitored by a Contract Administrator. The contractor is responsible to ensure that safety orientations and job briefings are carried out prior to and during the performance of the work. • Peter Mohyla, GO Transit Safety will be conducting a presentation on behalf of Operation Lifesaver to the students at Lynnwood Heights Junior Public School on this upcoming Tuesday, June 28. • We’re also planning a back to school education campaign in September in conjunction with TDSB and TCDSB. • Over the summer we will be organizing safety advisory committee, audit walks and encourage members of the community to attend and provide insight and feedback. 12
Agincourt Station Modifications Community Focus Group Workshop and Customer Feedback 13
Station feedback to date • We are in the early stages of planning modifications to the Agincourt GO Station (currently at 30% preliminary design). • By starting discussions early in the station design process we are looking to better understand and incorporate the needs of residents and customers in guiding the final design of the station. • A Station Modification Focus Group was held at the Agincourt Recreation Centre on May 3rd, attended by 20 participants, and supported by an online survey for feedback from May 25 to June 5. • The on-line survey was promoted during the morning rush at the Agincourt Station on May 31, 2016 as well as through the Agincourt Community email distribution list. 156 responses were collected in total. 14
The majority of our respondents are both GO customers and community residents. TYPE OF RESPONDER Only take GO Transit but do not consider themselves as community residents Live in the community (Referred to as ‘Only GO around Agincourt GO Station 88% of residents have Customers’) and do not use GO Transit lived in the area for 24% (Referred to as ‘Only 10+ years. 11% Residents’) 65% 10% have lived in the Both, take GO transit and area for less than 2 consider themselves as years, 35% for 2-10 community residents years and 55% for over 10 years. Which of the following applies to you? How long have you lived in the area near the Agincourt GO Station? Base: Total respondents: n=156; Only GO Customers: n=38; Only Residents: n=17; Both: n=101 15
Agincourt Station Modifications Meeting Objective Constraints Work together to reflect • Local design issues community aspirations and maximize community building • Broadly consistent with opportunities by: Metrolinx policies • Building a shared understanding • Site conditions, engineering solutions • Developing key community factors • Advancing the work of the • Not contravene established residents association and the Provincial regulations and community staying with current budget scope 16
Agincourt Station Modifications Project Elements • New 2nd track • New relocated station building • New platform • New kiss and ride • Pedestrian tunnels/elevators • Improved community access • Platform canopy/enclosure Project Timelines • Preliminary Design – Spring 2016 • Design-build Tender – Summer 2016 • Final Design – Spring 2017 • Construction – Summer 2017 to 2019 *Dates subject to change Metrolinx is looking for input into the design of Agincourt Station and will keep you informed throughout the design and construction process 17
Agincourt GO Station Modifications Community Access points Noise Wall Landscape features New passenger pick- N and noise wall up and drop off Improved street access Improved street access New noise wall Tunnel/platform access Relocated and new station building and plaza area New pedestrian stair access New east platform, and relocated/reconstructed west platform
Agincourt GO Station Modifications New Station Building - Exterior New Station Building - Interior Existing Station Building 19
Agincourt Station Modifications Public Spaces and Community Connectivity Existing Dowry Street Approach – Looking East New Dowry Street Approach Existing south from Marilyn Avenue New Platform –south from Marilyn Avenue 20
Focus Group Feedback: Public Spaces and Community Connectivity • Like station concept for GO customers but want further consideration of community connectivity – Keep crossing at Marilyn for easy and safe access for children and seniors – Would like to see a well-lit pathway from Agincourt Drive to the platform – Like the new stair access from Sheppard Avenue on the east side of the corridor • Green space on east side of the corridor at Agincourt Drive and Sheppard Avenue with playground equipment, some benches and trees that is fenced on the south side as a safety feature – Consider reducing parking at the north end of the station and create a path and additional green space for pedestrian use • Want “Agincourt Village” signage that reflects the heritage of the Agincourt community and acts as a “gateway” – Perhaps name station (in name only, not officially) Agincourt Village GO station 21
Focus Group Feedback: Pedestrian Access and Tunnels • Community pedestrians, students, and cyclists should not need to go through parking lot access tunnels to cross corridor • Would like to see an additional tunnel at Marilyn Avenue • Concern about safety in tunnels after GO service over night – Would like to see another option besides tunnel presented so people don’t have to access tunnels overnight – Concerns about graffiti in tunnels • Tunnels should be equipped with emergency phones or buttons, surveillance cameras, good lighting 22
On-line Survey Feedback: Pedestrian Access and Tunnels • In terms of pedestrian access, the most important criteria is that it needs to be brightly lit. • Although directional, clearly visible entrance and clear signage to platforms, exit, elevators, etc. are more important to GO customers, safety (brightly lit access, CCTVs, mirrors, ) and convenience are more important to residents. • Pedestrian access that would connect Agincourt Dr. was also considered important. • Many of the community residents, including school children, use the current crossing at Marilyn Ave as a channel through which the community is connected from one side of the railway corridor to the other. 23
Agincourt Station Modifications Platform Canopy/Enclosure Sample Only – Agincourt GO – Platform Facing North Danforth GO Sample Only - New Platform Shed Concept 24
Focus Group Feedback: Platform Canopy/Enclosure • Some committee members refer open canopy design versus the enclosed concept – Concern that canopy design and overall height will darken adjacent yards or would create cloud of diesel fumes – Would like to see a more traditional design of the canopy to reflect the heritage of the Agincourt Village • Other committee members liked the enclosed canopy option if it would mitigate train noises as it entered the station. Would also mitigate noise associated with overnight snow removal and maintenance. • Would like to see canopy and platforms well-lit to discourage vagrancy • Ensure that lighting on platform is shielded so it doesn’t shine into adjacent properties • Want to have the train shed connect into noise walls • Concern that platform and retaining walls will contribute to drainage issues on adjacent properties • Want to see an integrated storm water management system • Make look and feel of retaining wall and noise wall integrated, so overall appearance is continuous • Design to ensure there is station attendant views of the platform to monitor any issues 25
On-line Survey Feedback: Platform Canopy/Enclosure • In general, the platform canopy design is appealing to most respondents. However, half of all residents find it unappealing. • Their biggest concern is that the glass structure is out of place and they would prefer a structure that would emphasize the history of the area. 26
Agincourt Station Modifications Noise Walls Resident voting will determine the look of the residential side of the noise wall. Stay Tuned for details om options and how you will Noise Wall Selected for Phase 1 Limits Product Sample Image be engaged! Concept Pattern 27
Focus Group/On-line Survey Feedback: Noise Walls Focus Group On-Line Survey • Want to make sure that all adjacent • Noise walls with vines is the most properties are contacted so that appealing design choice among all property owners have feedback to the respondents. look and feel of the noise walls • Display of art is least liked by local • On the east side, would like to see the residents. noise walls integrated into the design of the retaining wall • One of the concerns with noise walls is graffiti defacement. • Provide new, mature trees on residential side of the noise wall to preserve privacy and create a green space • Potential use of public art on the noise walls around the station 28
Stay Connected Join our distribution list for email updates, flyers, and community meeting invitations. Your feedback is important to informing this project. You will have more opportunities to have your say by; • Attending our Quarterly public meetings and filling out our comment form • E-mailing us at scarboroughmarkham@metrolinx.com • Directly connecting with a member of the Community Relations team at 416.244.5306 • Drop-in hours on Tuesday’s from 10AM-12PM at Agincourt Community Services Association (ACSA), 4155 Sheppard Ave. E. Ste 100 29
Questions? 30
31
You can also read