We Energies' First Utility-Scale Wind Farm - Feature Blue Sky Green Field Wind Energy Center
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Feature Blue Sky Green Field Wind Energy Center We Energies’ First Utility-Scale Wind Farm The Towns of Calumet and Marshfield, WI Photography by Christine Coates, Editor, Wind Today 18 WIND TODAY Second Quarter 2009
If you look closely at the blades of Calumet and Marshfield in northeast Facility the wind turbines operating at the Blue Fond du Lac County, in east central Highlights Sky Green Field Energy Center in Wisconsin. Location: Near the towns of Calumet Wisconsin, you might see that one of We Energies leases 6,500 acres of and Marshfield in northeast Fond those 264 blades is decorated with property from 51 landowners for the du Lac County, WI community members’ signatures. wind farm. The site includes 50 miles of Size: 88 wind turbines Developer: We Energies “In December 2007, during our collector system cabling and 20 miles of Owner: We Energies construction phase, we held a commu- access roads. Project capacity: 145 MW nity event so our neighbors could see Individual landowners receive a Power contract: We Energies some of the blades and rotors up close fixed lease payment each year as well Project cost: Approximately $300 million before they were erected,” says Tanya as benefits received by their communi- Connector & Transmission System: Holler Muench, special projects ties. According to Barry McNulty, American Transmission Company coordinator, We Energies. manager of media relations and Utility: We Energies We Energies, Milwaukee, WI (414- special projects at We Energies, the Commercial operation: May 19, 221-2345), is the trade name of the towns of Marshfield and Calumet each 2008 Wisconsin Electric Power Co. and receive annual payments of approxi- Wisconsin Gas LLC, the principal mately $120,000 per town plus another Turbine Features Turbines: Vestas V82, 1.65 MW utility subsidiaries of Wisconsin $300,000 or more every year for the Tower: 262 ft. Energy Corporation. county. Blade length: 134 ft. We Energies owns the 145 megawatt “Our relationship with the commu- Operational RPMs: 14.4 Cut in wind speed: 8 mph (MW) wind farm. nity is important to We Energies,” says Rated wind speed: 30 mph During the community event, says Holler Muench. Cut out wind speed: 54 mph Holler Muench, guests signed a wind In order to facilitate open communi- turbine blade which was later put into cations, the wind farm hosts open Key Personnel: production on one of the wind farm’s houses. “We try to open up the wind Manager-Renewable Resources: 88 Vestas V82 1.65 MW turbines. farm twice each year so people can see Mark Noah Project Manager: Andy Hesselbach the operation for themselves and get a Director-Construction: Dan Blue Sky Gr Sky een Field Energy Green better understanding of what we do Pobloskie Center here,” says Holler Muench. Manager of Alternative Energy The Blue Sky Green Field energy Mark Noah, manager-renewable Strategy: Richard O’Conor center is located near the towns of 19
We Energies built the Blue Sky Green Field energy center’s substation adjacent to ATC’s substation. resources for We Energies, energy market in June 1999 when the manages the wind farm. Noah company erected two Vestas V47 wind says more than 1,000 people turbines by the side of Highway 41 attended an event at Blue Sky near Byron, WI. Green Field last September. “The Byron turbines were We “We didn’t know how many guests Energies’ initial foray into the wind to expect since it was a cold, rainy energy field,” says Holler Muench. She Saturday,” says Noah. “We were explains that in their 10 years of surprised at the number of people who operation the two wind turbines have lined up more than 200 ft. waiting their demonstrated good numbers related to turn for a tour.” their capacity factor and electricity Holler Muench says We Energies’ production. commitment to open communications The positive experience with those The Blue Sky with the community has proven turbines led the company to consider Green Field energy center beneficial to the project. acquiring wind farms to increase its is located “We’ve come into this community ownership of renewable energy. near the and are operating on their property,” “We decided to invest in wind towns of Calumet and Fond du Lac says Holler Muench. “It’s important energy in response to the state Renew- Marshfield in County, WI that we operate as partners with the able Portfolio Standard (RPS), as well as northeast Fond people who live here.” to meet our customers’ demand for Du Lac County, During the permitting and construc- renewable energy,” says Noah. WI. tion process, says Holler Muench, We An electric and gas utility, We Energies representatives met with Energies serves customers in Wisconsin landowners, held community meetings, and the Michigan Upper Peninsula. The wind farm is comprised of and maintained a project hotline. Currently, We Energies’ supply 88 wind turbines standing on Noah says that hiring technicians portfolio includes approximately 3% 6,500 acres of land. from the local community further from renewable energy. aids in community relations. “The According to Noah, wind energy is technicians who live around here the least expensive of the company’s know the issues that are being renewable energy options for new, discussed and can help us better large-scale production. The utility also anticipate any concerns that might purchases renewables from other come up,” says Noah. generating companies. The wind farm employs 13-15 people Customer demand. Noah says the for operations and maintenance. At the utility’s Energy for Tomorrow renewable peak of construction, says Noah, about energy program allows customers to 450 workers were employed by the pay a premium to assure that a percent- project. age of their electricity is generated by We Energies has a multi-year O&M renewable sources. contract with Vestas which has hired In March 2009, an average 750 mostly local residents. kilowatt per hour customer would be “Vestas’ technicians have done a expected to pay $2.57 extra for 25% great job with O&M services,” says renewable energy. Customers who Noah. “I’m especially impressed with want 100% of their electricity to come the amount of training the company from renewables would pay an provides their employees,” he states. additional $10.28. As of March 2009, says McNulty, Development Dev 19,624 We Energies customers subscribe We Energies first entered the wind to this program. 20 WIND TODAY Second Quarter 2009
Renewable Portfolio Standard. Pipe and wire were buried approxi- link the turbines—eight separate Wisconsin’s RPS was established in mately four feet below ground to avoid circuits—to the SCADA system. 2003 by Senate Bill 459. The legislation interrupting cropland as much as Baumhardt Sand & Gravel, Eden, WI requires utilities to produce 10% of all possible. Several thousand feet of (920-477-2511), provided aggregate their electricity from renewable energy directional boring was done in areas products and services. sources by 2015. where trenching was prohibited. According to Noah, geotextile In 2002, We Energies issued a Fiber optic lines were installed to fabric was installed as a base for Request for Proposals (RFP) for wind energy and in 2003 signed two 80 MW Power Purchase Agreements (PPA) with Navitas Energy, Minneapolis, MN, the original developer of this project. In June 2005, We Energies purchased engineering, leases, and some permits for development of the Blue Sky Green Field energy center from Navitas. Since the developer already had land leases and agreements with the towns in place, We Energies was able to start their part of the permitting process in 2006 and received approval by January 2007. Construction began in June 2007. Construction According to Noah, the Blue Sky Green Field energy center cost approxi- mately $300 million. Alliant Energy’s RMT WindConnect, Madison, WI (608-831-4444), was the Balance of Plant (BOP) contractor. Boldt Construction, Appleton, WI (920-739-6321), put in the turbine foundations and installed the turbines. Noah says the foundations required 324 yards of concrete weighing 650 tons plus another 10 tons of rebar and steel. Hooper Corporation, Madison, WI (608-249-0451), installed the under- ground collector system at the wind farm. Hooper Corp’s Director of Business Development Steve Lindley says the contractor installed approximately 50 miles of medium voltage under- ground power cable between the 88 wind turbines using 156,941 linear feet of 1/0 and 4/0 cable, 81,004 feet of 750 MCM, and 17,141 feet of 1000 MCM cable. Response No. 211 21
the stone so it won’t sink into the soil. The second week of the year, the across the land without damaging the The access roads also required area had 50° temperatures and thunder- fields. This reduced the amount of drainage culverts to make sure water storms with 1½ inches of rain, says remedial soil reclamation required to moves through fields as it did prior to Noah. That shut down construction for return the properties back to their the wind farm’s construction. about a week before the ground froze original condition. “We want to make sure the farmer’s again. In spite of the short delay, the wind fields experience no undue impact Noah explains that construction had farm was completed by May 19, 2008, because of our wind turbines,” says been scheduled through the winter less than a year after the start of Noah. months so cranes—including two construction, concludes Noah. Michels Wind Energy, Brownsville, Manitowac 16000 cranes—could move Christine Coates, editor WI (920-583-3132), provided electrical services. Waukesha Electric Systems, Blue Sky Gr Sky een Fields Energy Green Waukesha, WI (800-835-2732), manufac- tured and installed the main substation Center Supplier List transformer. Bolts & Fasteners ................................................................................. Fastenal The power produced at the Blue Sky Certification & Testing .............................. STS-AECOM, URS Corporation Green Field energy center is connected Concrete Services ............................................................................................... to the grid via lines owned and .............................. Carew Concrete, United Concrete, Boldt Construction operated by the American Transmis- Consulting ....................... RMT, STS-AECOM, Ruekert Mielke, J.E. Arthur sion Company, Waukesha, WI (ATC/ 262-506-6700). Crane Rental ....................... Dawes, United Rentals, Wave Wind, Hennes “The siting here was very fortu- Data Collection & Analysis ....................................... SGS Inc., STS AECOM itous in that ATC’s 345 kilovolt (kV) Electrical Contractor .......................................................................................... transmission lines already ran ..................................... SPE, Michels Wind Energy, Hooper Corp., Zuerhn through the middle of the project,” Electrical Interconnection ............... Hooper Corp., Michels Wind Energy says Noah. Electrical System Design ....................................... RMT, AMSC, GE Energy He says ATC put in their substation, Engineering & Planning .......................................................................... RMT We Energies installed the wind farm’s Environmental Consulting ............................................. STS-AECOM, RMT substation adjacent to that, and no Excavation Services .............. Andrews Excavating, Edgerton Contractors overhead line work was required. Fiber Installation ......................................................... Hooper Corp., Vestas “The only real challenges we Field Services ................................................................................ STS AECOM experienced in construction of this Foundations .............................. Boldt Construction, Michels Foundations wind farm are related to logistics and Generator Services .................................................. Generac Power Systems the weather,” says Noah. Grid Connection Equipment ................................. AMSC, ABB, GE Energy Logistics. According to Noah, in 2007 Legal Service ... Michel Best and Friedrich, Quarles & Brady, Stoel Rives component shipments were required to Lubricants & Filtration Equipment .......... Mobil One, Corey Oil Services be delivered to the wind farm laydown Permitting ..................................................................................... STS AECOM yard at night. At 6:00 a.m. the next Substation Design ........................................................................... GE Energy morning, workers could re-load the Surveying & Mapping ......................................................... J.E. Arthur, RMT components and transport them to their Tower Erection ................................................................. Boldt Construction respective sites. Transformer ....................................................... Waukesha Electric Systems “Since then, we’ve worked out a Transmission Services ......................... American Transmission Company better plan for the timing of deliver- Transportation & Logistics ............... Hennes Services, Lonestar Trucking ies,” says Noah. Turbine Performance Monitoring ............................................... GEC/DNV Weather. Weather conditions Wind Assessment ........................................................................... GEC/DNV interrupted construction briefly due to Wind Turbines ........................................................................................ Vestas an unexpected thaw during the first week of January 2008. 22 WIND TODAY Second Quarter 2009
You can also read