LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...

Page created by Bruce Delgado
 
CONTINUE READING
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
LS2 North Experimental Area Consolidation
Ongoing activities / Where are we?

F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko,
M. Wilhelmsson (EN-EA-PE)
EACM, September 24th, 2019
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
PPS Access point BA80 replacement done
  • PAD/MAD installed 3 weeks ago
  • Tuesday 10th: functional test by
    BE-ICS.
  • From Wednesday 11th September:
    “en service”
  • Team moves to next installation in
    BA81

- Ongoing: instrumentation of the doors YDPS02.80o, YDPS01.800, YDPV01.800,
  YDPV02.800
Remaining work:
- March - April 2020 :EIS instrumentation & Test (access occasionally perturbated)

                                           F. Gautheron et al. - EACM September 24th, 2019   2
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
PPS Access point BA81 replacement ongoing
• Activity for replacement started on
  September 11th
• Mechanical parts almost done
• This week and next week: connection
  to electrical and communication
  networks.
• Tests and validation: 7-11th October
• Expected “en service” on October 14th

• Aug - Sept 2020 :EIS instrumentation &
  Test (access occasionally perturbated)

                                     F. Gautheron et al. - EACM September 24th, 2019   3
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
Access point SPS-PPS TCC8 & lift
• Replacement of the access point bldg. 912
• Replacement of the lift AS516
• Co-activities organized – No conflict expected
   • W43 [21-25 October]: removal of actual PAD (turnstile)
   • W44 – 47: removal of the old lift, extraction of big pieces, install. new lift
   • W48: installation of the new PAD/MAD
   • From W49: adaptation to punctual necessities between teams (EN-HE/BE-ICS)

• Sept – Oct. 2020 :EIS instrumentation & Test (access occasionally
  perturbated)

                                           F. Gautheron et al. - EACM September 24th, 2019   4
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
ECN3: renovation activities starting soon
• SPS PSS access point in bldg. 911
 • Actual BE-ICS planning indicates work
   during [mid-October / mid-November]
• EN-HE rails replacement for the
  crane in ECN3 [21/10 – 01/11].
 • Time slot confirmed long time ago.
 • Use of the pit/crane to transfer long rails
 • -> Safety issue since access point and pit
   are close to each other
 • BE-ICS is revising its time slot to adapt the
   intervention. Discussion ongoing with the
   contractor. No feedback yet.
• Oct – Nov. 2020 :EIS instrumentation
 & Test (access occasionally perturbated)

                                            F. Gautheron et al. - EACM September 24th, 2019   5
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
Crane consolidation in 888 (EHN2)
• August 12-21: old 5t crane removed, new 10t crane installed
• Work on the 40t crane started 4 weeks ago, should last until end of
  September.

                            Load test (40 t) September 19th

                                  F. Gautheron et al. - EACM September 24th, 2019   6
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
TA 852 ventilation door (TCC8) - Air tightness
• Aluminum sheets fixed on the door 2
  weeks ago
• Passage of pipes through the fence
  to be closed
• Cables trays not yet closed since an
  optical fiber has still to be pulled,
  foreseen by EN/EL week 42
• Access restricted w43 – w52
   • Replacement of the access point SPS-PPS
   • Replacement of the local lift
• Air tightness work on cable trays
  and around pipes to be terminated
  beginning of 2020

                                       F. Gautheron et al. - EACM September 24th, 2019   7
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
No further free access to galleries post LS2
Recommendations from the safety
review & DSO for ODH & CO2 risks
• All gallery access to be locked
• EHN1 already done
• EHN2 ongoing
 • Caged ladder (Saleve side) to be locked
 • Jura side fenced and locked (by end of 2019)
 • Saleve side access through BA82
• Procedure put in place:
IMPACT -> TRAKA (EHN1) -> key +
ODH &CO2 portable detectors

                                             F. Gautheron et al. - EACM September 24th, 2019   8
LS2 North Experimental Area Consolidation Ongoing activities / Where are we? - F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M ...
Gas Network Consolidation
• Only EHN1 Saleve side during LS2 due to budget cuts
• Reduction of the number of mixing areas : 2
• One mixing area already modified, new rack under design, waiting for the instruction
  (TSO) for the second mixing area.
• All gas patch panels already produced, half of them in placed in PPE’s but not connected
   • 887/R-K52 (PPE 146), 887/R-P40 (PPE 138), 887/R-P58 (PPE 158), 887/R-L75 (PPE 168)
   • Racks produced & to be transported 887/R-K56 (PPE 156) & R-M84 (H8 beam dump area)
• Gas barrack 907: waiting for a final offer for racks.
• Check valves (EATM request): to equip all the distribution racks (EHN1, EHN2, ECN3)
   • Might require 2 -3 weeks of service interruption (looking for a possibility of sectorization instead)
• Flowmeters to monitor networks, installation foreseen this year
• ATEX extraction bldg. 907 during LS2. Bldg. 909 postponed after LS2

                                                F. Gautheron et al. - EACM September 24th, 2019     9
Flammable Gas Detection & ODH
• EHN1– Saleve side (Jura side already migrated & operational)
 • Barrack gas 907 already equipped (no flammable gas actually in use)
 • ODH in Galleries (GHN 14,15,16) with previous sensors (No CO2 detection)
 • FG sensors to be installed once new gas distribution in place (1st semester 2020)
  • Mixing gas areas
  • Experimental areas
  • PPE168 pending – area to be reorganized, no further news.
 • Cabling once EN-EL manpower available, ~ September 2020
 • Commissioning will follow
 • Old system deactivated, but racks not yet removed
• EHN2, ECN3
 • EHN2 : 2020: BE-ICS OK, budget available (optical fiber ordered by EN-EL-FC)
 • ECN3 : to be migrated to Syntel system – 2020. BE-ICS OK, budget available

                                        F. Gautheron et al. - EACM September 24th, 2019   10
Cooling & Ventilation - EN-CV
• Consolidation of control towers CT2:
   • Electrical consolidation ongoing (foreseen by the end 2019)
   • Control system replaced in 2020 (delivery foreseen beginning of April 2020)
• Underground technical galleries ventilation study ongoing
   • Safety review “Install a ventilation system in the gallery in order to avoid local
     accumulation of gas”
• Ongoing study of cooling in BAs for the PSU of Beam lines magnets
   • Option with H2O cooling for SIRIUS PSU
   • Option with Air cooling for APOLO PSU

                                          F. Gautheron et al. - EACM September 24th, 2019   11
Radioprotection HSE-RP
• CROME deployment in NA
  • March 2020 : TDC2 (9 monitors)
  • Avril 2020 : TCC2 (13 monitors)
  • May/June 2020 : EHN1 (46 monitors)
  • Beginning of August 2020 : TT84/TT85 (2 monitors)
  • End of August 2020 : EHN2 : (4 monitors)
 • Commissioning : August to December 2020
 • RP tests: October 2020 to February 2021
• Access control to transversal underground galleries (EHN1 & EHN2)
 • Generalize fences in EHN1 (2/6 actually) all with padlocks (keys in CCC)
 • EHN2: Dose rate exceeds limits on Jura side (RP survey 2018) : “close gallery
   GHN21 in addition to GHN22 with EN/EA padlock to prevent access to Jura side”
  • Access through IMPACT -> TRAKA (in EHN1). Same rule than for ODH/CO2 risks

                                        F. Gautheron et al. - EACM September 24th, 2019   12
Power converters – TE-EPC
• Ongoing studies for new PSU (SIRIUS vs APOLO) for beam line magnets
• DCCT + FGC3 ordered for VERTEX 1,2 and ATLAS-Morpurgo (EHN1)
• Components to be integrated in the new PSUs during LS2 – Lab work
• PSU installation foreseen in 2021 (YETS 2021/2022)

                                    F. Gautheron et al. - EACM September 24th, 2019   13
Magnets – TE-MSC
• Exchange of water distribution manifolds for magnets cooling
• 180 Single connections & new water hoses
• EN-CV in charge
• Not started !

                                F. Gautheron et al. - EACM September 24th, 2019   14
Beam Instrumentation (EN-EA & BE-BI)
• Renovation of 26 VME crates + extender interfaces in EHN1 needed
  for compatibility with BE-CO control systems > LS2 => concerns all
  beam instrumentation signals => material ordered / consolidation
  ongoing
• Foreseen for LS2 – urgent needs:
  • 10 XCET (gas panels, gas control system, windows, vacuum pipes),
  • 5 CEDAR (obsolete gas control system),
  • 40 XSCI (voltage dividers)
  • 1 Longitudinal spill detector (new electronics)
• Foreseen in 2020: cabling for BLMs, BTVs, vacuum,.. In NA primary
  beam line TT20 + TDC2

                                        F. Gautheron et al. - EACM September 24th, 2019   15
Beam intercepting devices
• 2019:
 • Renovation 4 block collimators : study ongoing (EN-EA)
 • Define technical specifications for XTDV tables
 • Purchase material (motors+ mechanics) for 5 Magnetic collimators XCMV, XCMH (M2)
• 2020:
 • 2 & 4 block collimators consolidation
  • 2 collimators 2 blocks (reserve ) & 4 collimators 2 blocks installed (TT81, TT82)
  • 1 collimator 4 blocks (reserve) + 4 collimators 4 blocks (installed)
 • Various spare parts for TCC2/TCC8 targets
 • TCSC leaky cooling circuit
 • XTDV elevating table for beam dumps (total 8; 4 in 2020) - purchase
 • Micro-collimator (1) maintenance

                                            F. Gautheron et al. - EACM September 24th, 2019   16
Civil Engineering (SMB-SE)
• EHN1 drain siphons renovation => done
• Roof repair of gas barracks :
   • 907: pending
   • 908: done
   • 909: pending
   • 920: pending
• Buffer zones completed
• Other activities currently under discussion with SMB-SE

                                  F. Gautheron et al. - EACM September 24th, 2019   17
TE-VSC
• Cabling for vacuum controls in TDC2/TCC2
  • No removal of ancient irradiated cables
• Replacement of damaged :
  • Ion pumps, connectors, gauges, …
  • 3 window valves for beam line vacuum sectorization

                                       F. Gautheron et al. - EACM September 24th, 2019   18
NA Safety concerns …
• In addition to the safety improvements already listed :
   • Flammable gas, ODH, CO2
   • New “CROME” RP detection deployment network
   • Underground galleries access control
   •…

• Identified electrical non-conformities from periodic safety visits
   • Accessible parts under power
   • Lack or incorrect differential protection                             Priority to what
   • Grounding issues                                                      jeopardizes the safety
                                                                           of personnel
   • AUL cutoff range not indicated or not fully defined
   •…

                                         F. Gautheron et al. - EACM September 24th, 2019       19