Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen

Page created by Mark Estrada
 
CONTINUE READING
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Making homes happen

Land west of Ifield, Crawley
Members presentation (29th July 2019)
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Our strategic plan

At Budget 2018, we published our five-
year Strategic Plan explaining the steps
we’ll take, working collaboratively with
the community and in partnership with
stakeholders, to do this.
Ifield has been identified in the Homes
England Strategic Plan as a priority for
investment.
Within the next few years, we will have
invested over £27 billion across our
programmes.

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Our objectives

       We’ll unlock public and           We’ll ensure a range of investment        We’ll improve construction
       private land where the             products are available to support                productivity.
        market will not, to get           housebuilding and infrastructure,
       more homes built where          including more affordable housing and
          they are needed.             homes for rent, where the market is not
                                                       acting.

   We’ll create a more resilient and        We’ll offer expert support for        We’ll effectively deliver home
  competitive market by supporting          priority locations, helping to       ownership products, providing
  smaller builders and new entrants,          create and deliver more            an industry standard service to
   and promoting better design and          ambitious plans to get more                     consumers.
         higher quality homes.                       homes built.
#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Our track record

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Northstowe, Cambridgeshire

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Upton, Northamptonshire

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Burgess Hill, Mid Sussex

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Land west of Ifield

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Why here? Regional context
•     Located at the heart of the Gatwick Diamond
      economic area
•     Opportunity to work with a benefit of the
      local supply chain
•     Strategic site in an area of acute housing need

                         Growth projections
                 Population          %        Households     %
              2012        2037               2012    2037
 Crawley     107,555    132,649      23%    43,583  57,431   32%
 Horsham     129,456    151,073      17%    55,410  70,113   26%

               Affordability Index
               1998        2008          2018
 Crawley        4.1         7.2           9.1
 Horsham        4.8         9.7          13.5

#MakingHomesHappen
Land west of Ifield, Crawley Members presentation (29th July 2019) - Making homes happen
Why here? Local context
•   Strategic site in an area of acute need
•   Allows for growth based on Crawley
    neighbourhood principles
•   Supports the future of existing Town
    Centres
•   Infrastructure benefit for new and
    existing communities
•   Provides opportunities for further
    economic growth and housing need
    delivery over multiple Local Plan
    periods
•   Maintains long term defensible boundary
    between Crawley and Horsham

#MakingHomesHappen
Executive Summary
                     1. Partnering with Local
                        Authorities and
                        stakeholders

                     2. Community involvement

                     3. Long term commitment
                        to placemaking and high
                        quality design

                     4. Infrastructure delivery

                     5. Innovative solutions to
                        all technical matters

#MakingHomesHappen
Our vision

#MakingHomesHappen
3 New
                       Integrated
                                     Neighbourhoods      Range of
                     transport and                                     High quality
                                      interlinked to   employment
                       low carbon                                      placemaking
                                       form a new      opportunities
                       movement
                                      Garden Town

     Mix of                                                                             Integration
  green spaces,                                                                        with Crawley’s
  incl. Ancient                                                                           existing
    Woodland                                                                          neighbourhoods

    Crawley
    Western                                                                             Mix of high
   Relief Road                                                                        quality housing

     Sociable                                                                              Early
   and vibrant                                                                        Infrastructure
 neighbourhoods                                                                           delivery

#MakingHomesHappen
A new sustainable green neighbourhood

            All new homes
                                     5 mins walk of a bus stop   5 mins cycle of Ifield train
            located within:            10 mins walk of a high        station and existing
                                         street and schools        community facilities in
                                                                    Ifield and Ifield West

            20 mins bus journey to    55 mins train journey to     Public transport link to
             Crawley Town Centre     London Bridge from Ifield   London Gatwick, located at
                                        (half-hourly service)       the heart of Gatwick
                                      40 mins train journey to    Diamond economic area
                                       London Bridge from
                                              Crawley

#MakingHomesHappen
Crawley western relief road                                North section

• Middle section delivered in             Middle section
  partnership with Homes
  England
• North and South sections
  delivered in partnership
  with the LPA’s and Homes      South section
  England
• North section delivered
  working with Gatwick
  Airport

#MakingHomesHappen
Infrastructure delivery
  2021
                                                                      Local centre (third
                           2023                                       phase), health and
                                                                      wellbeing centre
Start first                                                           and community
neighbourhood:                                                        centre
CWRR middle                                      2025                                       Second
section, flood         First homes occupied,
                                                                                            primary
alleviation works,     secondary school
                                                                                            school
services and           (6FE) and SEND
education campus       facilities with sport                             2029
                       pitches, local centre   First primary                                          Secondary school
                       opens (first phase),    school, local centre                                   complete (10FE)
                                               (second phase),
                       Ifield Country Park
                       and linear parks,       secondary school                             2031
                       invest in existing      expansion (8FE)
                       health centres and
                       CWRR middle section                                                               2033
                       opens
  #MakingHomesHappen
Policy and planning
                        CWRR safeguarded in            Start                    Building evidence
                        Crawley Local Plan (Reg 18)    consultation             base for west of Ifield

                               2019                      2019                     2019
Outline planning
application
submitted for first                          2020                     2020                                Horsham and
neighbourhood                                                                                             Crawley Reg 19
                                                                                                          Consultation

                            2021                            2023                                          Horsham and
                                                                                                          Crawley
                                                                                                          Local Plans
                                                                                          2026            reviewed –
                         Horsham and                  Market and affordable                               delivery of second
                         Crawley Local                homes occupied in first                             and third
                         Plans adopted                neighbourhood                                       neighourhood
   #MakingHomesHappen
Engagement and Delivery

#MakingHomesHappen
Engagement

 Create an environment     Go out to speak to   Work with delivery            Publish the
  where everyone can        people who are      partners and social          outcomes and
     have their say       considered "hard to     organisations            discuss them with
                         reach" (Autumn 2019)                              Governance groups

       Engage with        Build relationships       Promotes            Feature exhibitions, pop-up
      feedback and             and trust        sustainability, local       events, workshops,
         respond                                   sourcing and         presentations, face to face
                                                   volunteering            briefings and regular
                                                                                newsletters
#MakingHomesHappen
Delivery structures
                                              Advisory Board
                                        •   HDC Cabinet members
                                        •   HDC Officers
                                        •   CBC Cabinet members
                                        •   CBC Officers
                                        •   Homes England

                          Community Board
                     •   HDC / CBC ward                         Technical Group
                         councillors                      •   HDC / CBC / WSCC
                     •   WSCC division member                 technical officers
                     •   Rusper / Colgate PC              •   Statutory consultees (as
                     •   Ifield Society                       required)
                     •   Local business groups            •   Homes England
                     •   Homes England
#MakingHomesHappen
Summary

#MakingHomesHappen
In summary
Creating a new sustainable garden community,
delivering new homes where they are most needed
•    working in partnership with Horsham District Council and Crawley
     Borough Council and other stakeholders

•    working with the community at all stages with rigorous governance
     and community oversight.

•    investing in infrastructure early

•    supporting the delivery of Crawley Western Relief Road and promoting
     sustainable transport

•     protecting wildlife and delivering increased biodiversity
#MakingHomesHappen
#MakingHomesHappen