Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 Enver Hoosen – Environmental Engineering Manager
Introduction – Kloof Operation • The Kloof Operation is situated in the Magisterial District of Westonaria, some 60 km west of Johannesburg at latitude 26˚ 24’S and longitude 27˚ 36’E, in the Gauteng Province of South Africa. • Kloof consists of five Shafts, Main, 3, 4, 7 and 8 Shafts. The deposit is accessed from surface using underground mining methods to 45 Level (the lowest working Level) at No.4 Shaft, approximately 3,347 m below surface. 2 www.sibanyestillwater.com
Introduction – Ikamva Shaft Deepening Project • Kloof Ikamva Shaft (K4) has mining infrastructure down to 45 Level. Mining currently takes place between 39 and 45 Levels. • The Kloof No. 4 Shaft Deepening Project targets the Ventersdorp Contact Reef (VCR) from 45 level down to 47 level and to the north of the 51 line, which is situated below current infrastructure. • The project fits into the Kloof Strategic plan by accessing below infrastructure ground thus extending the life of No. 4 Shaft and adding to the Kloof Ore Reserve base. • Various concept designs were considered and the selected method to access 46 and 47 Level was through an access ramp extending from 45 Level in the current workings. • Once in position on 47 Level a raise-bored decline shaft would be established for the permanent hoisting of rock and material with the access ramp being equipped with a chairlift for personnel transport to and from 46 and 47 Level. 3 www.sibanyestillwater.com
Project Original Design Isometric View Winder Installation 45 to 46 Level - Mechanised development - 100 chairlift decline (equipped with a chairlift for men access in the permanent condition) 46 Level (First cross- cut to reef) 46.5 Level 46 to 47 Level - Mechanised development -100 chairlift decline(equipped with a chairlift for men 46.5 to 47.5 Level RBH access in the permanent condition) shaft -34º 47 Level (First cross- cut to reef) 5 www.sibanyestillwater.com
Problem Statement • Only one end was mined in the Ikamva Deepening section prior to August 2019. • This increased to two ends in August 2019 and three ends in November 2019. • Four ends were mined in December 2019. • The increase in the number of ends being mined resulted in an increase in the ventilation and cooling requirements, which continued as the ends advanced. • Two ends were mined simultaneously since February 2020 due to ventilation and cooling constraints. 6 www.sibanyestillwater.com
Summary of Heat Generated and Short Term Cooling Installed • The sum of equipment introduced over and above the original design equalled to 900Kw. • During this period additional cooling over and above original design equalled to 454Kw. • This resulted in a short-fall of 446Kw cooling. • Additional cooling planned for 278Kw in workshop on 45 Level to reduce intake temperature. • The cooling deficit to achieve original design criteria is 168Kw. • The above would accommodate mining to December 2020. 7 www.sibanyestillwater.com
Key Ventilation Design Parameters • Sibanye Stillwater battery limit for temperature 31.0º wet bulb and / or 37.0ºC dry bulb. • Temperature >31.0 and 206 W/m2. • Virgin Rock Temperatures (VRT) > 54ºC. • Compliance to Airborne Pollutant COP (Silica and Diesel Particulate Matter exposure). 10 www.sibanyestillwater.com
Ventilation and Cooling Constraints • Failure of the hexagon ducting used in sections of the decline resulted in excessive leakage into the return airway. • Only service water available for cooling, at a temperature of 14ºC, with limited return pumping capacity. • The use of 6-7 vehicles (2 on 45 Level and 5 below 45 Level) resulted in high heat loads, especially since the introduction of the dump truck in November 2019. • Air used to ventilate the development on 46 Level is re-used to ventilate the decline. • The ventilation layout could not support the mining of additional ends on 46 Level due to the above. • An action plan was implemented to improve conditions, including investigating various ventilation layout scenarios using VUMA modelling software to simulate progressive development stages. • VUMA modelling to be used to determine the number of ends which could be mined under current conditions, as well as following completion of planned actions during the different development stages. 11 www.sibanyestillwater.com
Short Term Action Plan Planned Actual Concern/Item/Hazard Action Required Completion date Completion date Additional heat load from Move compressor to RAW position Dec 19 Dec 19 compressor in decline Install spot cooler above 46 Level 07 Feb 20 07 Feb 20 No additional cooling available in Install spot cooler below 46 Level 03 Jun 20 03 Jun 20 decline Install spot cooler on 46 Lev 14 Jul 20 14 Jul 20 Failure of hexagon vent columns, Replace ducting causing excessive leakage into 21 Aug 20 21 Aug 20 RAW Replace bends Spot cooler failure on 45 Level Replace spot cooler 20 Jul 20 20 Jul 20 Install closed loop piping between 45 Lack of chilled water for cooling Jan 21 and 46 Levels Ventilation layout not supporting Confirm layout for 46 Level development 20 Jul 20 20 Jul 20 mining of additional ends (VUMA stage modelling) 12 www.sibanyestillwater.com
Mine Ventilation Simulation Software • Various mine ventilation simulation software packages are available. • Used in the planning, design, energy optimisation, management and real-time monitoring of mine ventilation networks across the globe. • Software utilises a combination of thermodynamic and aerodynamic, interactive mine-network modelling algorithms that can be customised for any mining system or orebody. Solving complex ventilation systems with many features. Fan selection and optimum fan location selection. Determining airflow requirements. Determining effect of improvements / changes to overall system. • A number of reports can be generated for different parameters. • Network simulation provides airflow distribution throughout the network and the pressure required. • Software is designed to accurately simulate airflow, heat loads, gases (including radon), dust, blast clearance and fires. • Allows engineers to plan, design, operate and control the ventilation and cooling systems. 13 www.sibanyestillwater.com
Kloof Integrated VUMA Model Effect of changes at an individual shaft can be simulated for the entire mine. 14 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 1 Development with short term changes August 2020 December 2020 Decline Decline 46.5 Ramp 46.5 Ramp 46/52 XCN Reverse 46/52 XCN Reverse 46/52 FWD N 46/52 FWD N Available ends reduce in December 2020 due to environmental conditions. 15 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 2 Effect of raise boring vertical dam between 46 and 46.5 Levels October 2020 – No Raise boring October 2020 – Raise boring 46-46.5 Levels 46.5 Ramp Decline 46.5 Ramp Decline 46/52 XCN Reverse 46/52 XCN Reverse 46/52 FWD N 46/52 FWD N Introduction of the raise borer on 46 Level affects all ends except the footwall drive. 16 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 3 Vent Hole between 45 and 46 Levels November 2020 Decline Proposed position of vent hole – completion November 2020 Original position of vent hole – completion April 2021 46/52 FWD N Commissioning of the vent hole results in improved environmental conditions on 46 Level as well as development below 46 Level. 17 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 3 Vent Hole between 45 and 46 Levels November 2020 Commissioning of the vent hole results in improved environmental conditions on 46 Level as well as development below 46 Level. 18 www.sibanyestillwater.com
Verification of Scenario 3 – 46 Level and Below 19 www.sibanyestillwater.com
Environmental Conditions Post Completion of Vent Hole Working Place Previous Temp (ºC) Current Temp (ºC) 46/52 FWD Nth 30.0/33.0 29.5/35.5 46/52 Tippler XC 31.0/35.0 30.0/32.0 46 Lev Workshop 30.0/33.0 28.0/34.5 46/52 Dam 30.0/33.0 29.0/34.0 46/52 Decline 31.5/34.5 (Stopped) 29.0/31.0 46.5 Ramp Stopped (>32.5) 30.0/34.0 Note: • Previous conditions were measured with not all working places being ventilated / available concurrently, and with three cooling cars operating in the decline. • Current conditions are with all working places being ventilated and available, two cooling cars operating with the third being relocated to the 46.5 Ramp. Not all ends were working when measured. www.sibanyestillwater.com
Conclusion • The use of simulation software proved to be a valuable planning tool for improving environmental conditions in the Decline Project area. • Simulation assisted with the design and selection of project fans (high efficiency). • The number of available ends increased after scenario 3 was implemented. • Reliability of simulation proven – high level of confidence. • Multi – shift blasting scenario to be used as part of risk assessment. • Conventional planning to be verified using simulation software. www.sibanyestillwater.com
You can also read