Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager

Page created by Bradley Wallace
 
CONTINUE READING
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Ikamva Deepening Project

         Environmental Engineering Planning

                                  10 June 2021

Enver Hoosen – Environmental Engineering Manager
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Introduction – Kloof Operation

•     The Kloof Operation is situated in the Magisterial District of Westonaria, some 60 km
      west of Johannesburg at latitude 26˚ 24’S and longitude 27˚ 36’E, in the Gauteng
      Province of South Africa.
•     Kloof consists of five Shafts, Main, 3, 4, 7 and 8 Shafts. The deposit is accessed from
      surface using underground mining methods to 45 Level (the lowest working Level) at
      No.4 Shaft, approximately 3,347 m below surface.

                                                                                        2

    www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Introduction – Ikamva Shaft Deepening Project

•     Kloof Ikamva Shaft (K4) has mining infrastructure down to 45 Level. Mining currently
      takes place between 39 and 45 Levels.

•     The Kloof No. 4 Shaft Deepening Project targets the Ventersdorp Contact Reef
      (VCR) from 45 level down to 47 level and to the north of the 51 line, which is situated
      below current infrastructure.

•     The project fits into the Kloof Strategic plan by accessing below infrastructure
      ground thus extending the life of No. 4 Shaft and adding to the Kloof Ore Reserve
      base.

•     Various concept designs were considered and the selected method to access 46
      and 47 Level was through an access ramp extending from 45 Level in the current
      workings.

•     Once in position on 47 Level a raise-bored decline shaft would be established for
      the permanent hoisting of rock and material with the access ramp being equipped
      with a chairlift for personnel transport to and from 46 and 47 Level.

                                                                                        3

    www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Ikamva Shaft Location

                            4

www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Project Original Design Isometric View

                                                                                               Winder Installation

 45 to 46 Level - Mechanised development -
 100 chairlift decline (equipped with a chairlift
 for men access in the permanent condition)

                                                                                         46 Level (First cross-
                                                                                         cut to reef)

                                                                            46.5 Level

      46 to 47 Level - Mechanised development -100
      chairlift decline(equipped with a chairlift for men                           46.5 to 47.5 Level RBH
      access in the permanent condition)                                            shaft -34º

                                                   47 Level (First cross-
                                                   cut to reef)

                                                                                                                  5

www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Problem Statement

•     Only one end was mined in the Ikamva Deepening section prior to August 2019.

•     This increased to two ends in August 2019 and three ends in November 2019.

•     Four ends were mined in December 2019.

•     The increase in the number of ends being mined resulted in an increase in the
      ventilation and cooling requirements, which continued as the ends advanced.

•     Two ends were mined simultaneously since February 2020 due to ventilation and
      cooling constraints.

                                                                                      6

    www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Summary of Heat Generated and Short Term Cooling Installed

 • The sum of equipment introduced over and above the original design
   equalled to 900Kw.

 • During this period additional cooling over and above original design equalled
   to 454Kw.

 • This resulted in a short-fall of 446Kw cooling.

 • Additional cooling planned for 278Kw in workshop on 45 Level to reduce intake
   temperature.

 • The cooling deficit to achieve original design criteria is 168Kw.

 • The above would accommodate mining to December 2020.

                                                                                   7
www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Ventilation Layout – 45 Level

                                8
www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Ventilation Layout – 46 Level and Below

                                          9

www.sibanyestillwater.com
Ikamva Deepening Project Environmental Engineering Planning 10 June 2021 - Enver Hoosen - Environmental Engineering Manager
Key Ventilation Design Parameters

 • Sibanye Stillwater battery limit for temperature 31.0º wet bulb and / or 37.0ºC
   dry bulb.

 • Temperature >31.0 and  206 W/m2.

 • Virgin Rock Temperatures (VRT) > 54ºC.

 • Compliance to Airborne Pollutant COP (Silica and Diesel Particulate Matter
   exposure).

                                                                                     10

www.sibanyestillwater.com
Ventilation and Cooling Constraints

•     Failure of the hexagon ducting used in sections of the decline resulted in excessive
      leakage into the return airway.

•     Only service water available for cooling, at a temperature of 14ºC, with limited
      return pumping capacity.

•     The use of 6-7 vehicles (2 on 45 Level and 5 below 45 Level) resulted in high heat
      loads, especially since the introduction of the dump truck in November 2019.

•     Air used to ventilate the development on 46 Level is re-used to ventilate the
      decline.

•     The ventilation layout could not support the mining of additional ends on 46 Level
      due to the above.

•     An action plan was implemented to improve conditions, including investigating
      various ventilation layout scenarios using VUMA modelling software to simulate
      progressive development stages.

•     VUMA modelling to be used to determine the number of ends which could be
      mined under current conditions, as well as following completion of planned actions
      during the different development stages.

                                                                                         11

    www.sibanyestillwater.com
Short Term Action Plan

                                                                                  Planned         Actual
      Concern/Item/Hazard                       Action Required
                                                                               Completion date Completion date

    Additional heat load from
                                        Move compressor to RAW position            Dec 19          Dec 19
     compressor in decline

                                        Install spot cooler above 46 Level        07 Feb 20       07 Feb 20
No additional cooling available in
                                        Install spot cooler below 46 Level        03 Jun 20       03 Jun 20
            decline
                                            Install spot cooler on 46 Lev         14 Jul 20       14 Jul 20

Failure of hexagon vent columns,                Replace ducting
 causing excessive leakage into                                                   21 Aug 20      21 Aug 20
               RAW                               Replace bends

 Spot cooler failure on 45 Level              Replace spot cooler                 20 Jul 20       20 Jul 20

                                      Install closed loop piping between 45
Lack of chilled water for cooling                                                  Jan 21
                                                   and 46 Levels

Ventilation layout not supporting    Confirm layout for 46 Level development
                                                                                  20 Jul 20       20 Jul 20
   mining of additional ends                (VUMA stage modelling)

                                                                                                              12
  www.sibanyestillwater.com
Mine Ventilation Simulation Software

 • Various mine ventilation simulation software packages are available.
 • Used in the planning, design, energy optimisation, management and real-time
   monitoring of mine ventilation networks across the globe.
 • Software utilises a combination of thermodynamic and aerodynamic,
   interactive mine-network modelling algorithms that can be customised for any
   mining system or orebody.
    Solving complex ventilation systems with many features.
    Fan selection and optimum fan location selection.
    Determining airflow requirements.
    Determining effect of improvements / changes to overall system.
 • A number of reports can be generated for different parameters.
 • Network simulation provides airflow distribution throughout the network and the
   pressure required.
 • Software is designed to accurately simulate airflow, heat loads, gases
   (including radon), dust, blast clearance and fires.
 • Allows engineers to plan, design, operate and control the ventilation and
   cooling systems.

                                                                                13
www.sibanyestillwater.com
Kloof Integrated VUMA Model

             Effect of changes at an individual shaft can be simulated for the entire mine.
                                                                                              14

 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 1
Development with short term changes
August 2020                                             December 2020

             Decline                                           Decline
                             46.5 Ramp                                   46.5 Ramp

                                    46/52 XCN Reverse                                  46/52 XCN Reverse

                             46/52 FWD N
                                                                         46/52 FWD N

       Available ends reduce in December 2020 due to environmental conditions.

                                                                                                  15

 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 2
Effect of raise boring vertical dam between 46 and 46.5 Levels
October 2020 – No Raise boring                               October 2020 – Raise boring 46-46.5 Levels

                             46.5 Ramp                               Decline       46.5 Ramp
             Decline

                                         46/52 XCN Reverse                                 46/52 XCN Reverse

                             46/52 FWD N                                          46/52 FWD N

Introduction of the raise borer on 46 Level affects all ends except the footwall drive.

                                                                                                          16

 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 3
Vent Hole between 45 and 46 Levels
November 2020

                             Decline                 Proposed position of vent
                                                     hole – completion November
                                                     2020

                                                           Original position of vent hole
                                                           – completion April 2021

                                       46/52 FWD N

Commissioning of the vent hole results in improved environmental conditions on 46
Level as well as development below 46 Level.

                                                                                            17

 www.sibanyestillwater.com
Vuma Modelling of Decline Project – Scenario 3
Vent Hole between 45 and 46 Levels
November 2020

Commissioning of the vent hole results in improved environmental conditions on 46
Level as well as development below 46 Level.

                                                                                18

 www.sibanyestillwater.com
Verification of Scenario 3 – 46 Level and Below

                                                  19

  www.sibanyestillwater.com
Environmental Conditions Post Completion of Vent Hole

               Working Place          Previous Temp (ºC)             Current Temp (ºC)
 46/52 FWD Nth                            30.0/33.0                      29.5/35.5
 46/52 Tippler XC                         31.0/35.0                      30.0/32.0
 46 Lev Workshop                          30.0/33.0                      28.0/34.5
 46/52 Dam                                30.0/33.0                      29.0/34.0
 46/52 Decline                        31.5/34.5 (Stopped)                29.0/31.0
 46.5 Ramp                              Stopped (>32.5)                  30.0/34.0

  Note:
  • Previous conditions were measured with not all working places being ventilated /
    available concurrently, and with three cooling cars operating in the decline.
  • Current conditions are with all working places being ventilated and available, two
    cooling cars operating with the third being relocated to the 46.5 Ramp. Not all ends
    were working when measured.

www.sibanyestillwater.com
Conclusion

•   The use of simulation software proved to be a valuable planning tool for improving
    environmental conditions in the Decline Project area.

•    Simulation assisted with the design and selection of project fans (high efficiency).

•   The number of available ends increased after scenario 3 was implemented.

•   Reliability of simulation proven – high level of confidence.

•   Multi – shift blasting scenario to be used as part of risk assessment.

•   Conventional planning to be verified using simulation software.

www.sibanyestillwater.com
You can also read