GAUTRAIN RAPID RAIL LINK
          PPP

  Africa Regional PPP Conference
      14-15 November 2011
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
HISTORY OF THE PROJECT
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
Gautrain Management Agency
• The Gautrain Rapid Rail Link Project is a transport infrastructure
  project, developed, operated and maintained through a Public-
  Private Partnership agreement, signed with Bombela
  Concession Company, on the 28th of September 2006;

• It is the first modern, ‘state-of-the-art’ Rapid Rail Link transport
  project for Africa, consisting of approximately 80km of railway
  line, 10 stations, and approximately 125 buses in its dedicated
  feeder and distribution system;

• It is expected that the system will transport approximately
  100,000 passengers per day when fully operational. It is
  anticipated to become fully operational before the end of March
  2012.
•   The Project has two distinct phases:-
        - PHASE I: 5 Year Development Period (2006 to 2011)
        - PHASE II: 15 Year Operational Period (2011 - 2027)
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
SOURCES OF FUNDING
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
SOURCES OF FUNDING
• The South African National Government undertook to fund 50%
  of the total development costs of the project (R12.4 bn), 100% of
  the foreign exchange variances incurred on the foreign
  component of construction milestone payments, and 50% of the
  inflation related increases on the rand component of
  construction costs, through the granting of a DoRA Conditional
  Grant. (specific purpose grant)
• The remainder of the development costs have been funded
  through, amongst others:

    – MTEF Provincial Grant Funding (25%)
    – Provincial borrowings (18%)
    – Private Sector Equity (2%)
    – Private Sector Borrowings (9%)
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
PROJECT COSTS
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
PROJECT COSTS – APPLICATION OF FUNDS
• In September 2011, the Gautrain Project reached the end of its
  60th month (20th quarter) of development.
• The Independent Certifier certified the achievement of 996 of
  the 1042 interim payment Schedule 12 milestones (96% of the
  number of milestones).
• At the end of the last financial year, the total project expenditure
  incurred to date, in the following categories, were:
 Category                              Expenditure to Date
 Schedule 12 Milestones                R 25.7 bn
 (Construction costs)
 Variations and related costs          R 200 m
 Operational & Support Costs           R 2.2 bn
 TOTAL COSTS                           R 28.1 bn
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
PROFITABILITY & EQUITY
    DISTRIBUTION
GAUTRAIN RAPID RAIL LINK PPP - Africa Regional PPP Conference 14-15 November 2011 - IFC
EQUITY DISTRIBUTION & CONSTRAINTS

                                 Equity Distributions and Constraints
1 600 000

1 400 000

1 200 000

1 000 000

       800 000
Zar' 000s

       600 000

       400 000

       200 000

            0
                 2006
                 2007
                 2008
                 2009
                 2010
                 2011
                 2012
                 2013
                 2014
                 2015
                 2016
                 2017
                 2018
                 2019
                 2020
                 2021
                 2022
                 2023
                 2024
                 2025
                 2026
                 2027
                 2028
                 2029
                 2030
                 2031
                 2032
                 2033
                 2034
                 2035
                 2036
                 2037
                 2038
                 2039
                 2040
                 2041
   (200 000)

   (400 000)
                      Dividend Declared                          Total Shareholder Loan Stock Servicing
                      Loan Stock Cash Sweep                      Retained Income/(Accumulated Loss)
                      Cash Available to Pay Dividends and STC    Profit/(Loss) Attributable to Shareholders
SOCIO-ECONOMIC
  DEVELOPMENT
SOCIO-ECONOMIC DEVELOPMENT PERFORMANCE
 • The Gautrain’s measurable objectives are linked to its overall
   strategic objectives, one of which is the contribution to
   accelerated economic growth, with an emphasis on job creation,
   local skills development, and investment in black economic
   empowerment.
 • The Concessionaire is contractually obliged to achieve against
   SED obligations through 21 SED elements included in the CA.
 • The cumulative performance of the Concessionaire up to the
   end of the 20th quarter is shown in the table below:
SOCIO-ECONOMIC DEVELOPMENT: PROGRESS
                                                                        Verified % Compliance
          SED01:Shares held by BEEs/ Black Persons                  100%
                SED02:Shares held by Black Women                           119%
      SED03:Procurement from BEEs/ Black Persons                                           169%
                      SED04:Sub-contracting to BEE                                                             221%
  SED05:Procurement & sub-contracting to New BEE                                                       197%
   SED06:Procurement & sub-contracting to SMMEs                                                                                                                     447%
                SED08:Employment of Local People                                                178%
               SED09:Procurement of RSA Materials                                                 184%
      SED10:Procurement of RSA Plant & Equipment                                           167%
                   SED11:HDI staff seconded by SPG                                              181%
SED12:Expenditure by SPG on Plant & and Equipment                             124%
 SED13:Procurement from, or Sub-contracting to SPG                                                        212%
               EEP01:HDIs in Management Positions                                                                           255%
            EEP02:Women in Management Positions                                                                                                            397%
                 EEP07:HDIs in Occupational Level C                                                                                               362%
                             EEP03:HDIs employed                                                              215%
                          EEP04:Women employed                                                                               261%
            EEP05:People with Disabilities employed                            132%
EEP06:Expenditure on Human Resource Development                         110%
             EEP08(a): Women trained & mentored                         97%
   EEP08(b):Women Learners employed & mentored                                           157%

                                                      0%   50%   100%             150%            200%               250%           300%   350%          400%     450%     500%
PUBLIC TRANSPORT
  INTEGRATION
INTEGRATION PROGRESS
•   Various applications for developments around stations have been
    submitted to municipalities. This will lead to densification of land use
    around the stations.
•   The DFDS services supporting the system operation, currently around
    9 stations has linked major commercial and residential nodes in
    Gauteng.
•   Development around the stations, which is in progress, will support
    physical integration and convenient transfers to/ from adjacent PRASA
    (metro-rail) stations.
•   Planning of physical interfaces between Gautrain stations and Rea
    Vaya bus stations in close proximity to stations have been completed.
    Rea Vaya will play a role in distributing Gautrain passengers to the JHB
    CBD, and the north-western suburbs.
•   Development of a public transport interchange including a major taxi
    rank, on top of Sandton Station, is complete.
•   A taxi-owned company, Alexandra Transport Solutions, has been
    contracted to operate a shuttle service comprising 2 mini-bus taxis
    from the Marlboro Station into Linbro Park. Shuttle services are
    planned to be rolled out at other stations, supporting integration.
Thank You
www.gautrain.co.za