East Area Renovation – WP16 Primary and Experimental Areas Access Systems (PPS – Personnel Protection System) Report at EAR Meeting 26.07.2019 E. Sanchez-Corral, BE-ICS EDMS 2211100 1
OUTLINE • WP16 scope • EA1-EA2 Primary Areas PPS EAR modifications • EA1-EA2 PPS ECR approval • EA Experimental Areas EAR modifications • Installation and Commissioning Planning • Open issues and Conclusion 7/26/2019 Document reference 2
WP16 SCOPE • EAR16.1: EA1- EA2 Primary Zones PPS (Personnel Protection System) • PLAN Id 11287 • New EA1 machine layout -> new access sectors to minimize dose rates to personnel, RP veto managed per sector • Inter-machine door EA1-EA2 -> emergency exit EA1EA2 • EIS-Beam/External interfaces: • EA1 and EA2 beam stoppers and power converters upgrade, • EA1 new ventilation system: safety conditions for ACCESS/BEAM due to activated air • EAR16.2: EA Experimental Areas PPEs (Personnel Protection Entry) • PLAN Id 11288 • T09, T10 and T11: PPEs re-located • T09-10: new zone -> new PPE • New function: veto management and chain tests remote CCC operation • Access control EA B157 control rooms/buffer zones and storages: dismantled, re-located, new 3
WP16 Cost and Schedule - EVM • Cost and Schedule Review II EAR Apr 2018: EAR16 • -> EVM • EDMS 1961227: C&S Review WP16 and cost reduction study (Feb 2019) Total Cost Possible Cost Reduction Possible estimate KCHF Actions (Study Feb 2019) Cost Reduction WP16.1 PPS EA1-EA2 – PLAN Id 210 Grouping BEAM STOPPERS 20 11287 signals WP16.2 Access systems 117 Reduce scope: not implement 35 Experimental Areas (T09, T10, T11, new function of remote mgt new T09-10) & from CCC of vetos & tests Access control SUSI/SALTO EA Experimental locals - PLAN Id 11288 WP16 327 5 % Contingency 16 WP16 + 5% Contingency 343 • Planning: EAR Baseline Planning EDMS1831134 v.4, Oct-18 • -> Integrate last version of WP16 planning (Jul 2019) 4
EA1-EA2 PPS ECR Approval Approval with minor comments/remarks: 1- Safety Link Person CPS: F. Chapuis -> V. Barbet 2. EA1-EA2 Patrol procedure shall be updated (V. Barbet) 3. Clarification requested by BE-ASR (DDSO Ch. Gaignant) concerning new ventilation system interface with the PPS. - PPS allows and maintains the BEAM ON as long as the “OK-FOR-BEAM” signal from the ventilation system on the pressure level is correct -> BEAM OFF if “OK-FOR-BEAM” lost during BEAM ON 4. Minor wording suggestions (L. Gatignon) 7/26/2019 Document reference 5
WP16 Applicable and Reference documents REF EDMS Document Title Type Org. Unit 1 Spécification des éléments d'Accès et Inter Technical BE-ICS 990209 verrouillage de la zone East Area Specification 2 Spécification des éléments d'Accès et Inter Technical BE-ICS 990210 verrouillage de la zone IRRAD Specification 3 Pre acceptance of the work package for the Technical EA primary zone access safety systems Specification, BE-ICS 1946347 (EA1 - EA2) as part of the EAR project -> ECR 2149919 ECR EA1-EA2 PPS for EAR 4 Schemas zones secondaires East Hall Electrical BE-ICS 1388684 drawing 5 Evacuation distances in Primary, mixt and User experimental area in the East Area (B.157) Requirements EN-EA 1892798 after LS2 6 Modification of the experimental areas User EN-EA 1948473 access system and SUSI systems update Requirements 7 1145498 Intégration du point d'accès et RP bunker Integration - BE-ICS zone EAST HALL YEA01.EA1=157 Drawing 8 1871830 East Area Primary Zone Ventilation System Technical EN-CV Specification 9 1871447 Functional Specification of PROTON Technical EN-SMM SYNCHROTRON (PS) BEAM STOPPERS Specification 10 Interface EIS entre les convertisseurs de Technical 1288346 puissance et les nouveaux systèmes d'accès Specification TE-ECP du complexe PS 11 1266676 Synoptique des liaisons Zone EAST AREA Electrical BE-ICS (EA1) Drawing 12 1266671 Synoptique des liaisons Zone IRRAD (EA2) Electrical BE-ICS Drawing 13 1182293 Définition et inventaire des EIS-Faisceau et Technical BE-ASR EIS-machine Report 7/26/2019 Document reference 6
WP16.1 – EA1 current & future PPS Access Sectorisation PPS EA1 ECR Today: 1 single access sector (S1) accessible from the Access Point, 1 blind sector (S2) only accessible from EA2 via an end zone door -> Future: - 3 access sectors (S2 mixed area, S1 & S3 hot area) - no more a blind sector as shielding opening from EA1 and giving access to EA2 external envelop -> End zone door converted into a inter-machine door -> EA1-EA2 emergency exit - EIS-Beam: 2 Beam Stopper replaced by 5 new ones - New external interface with ventilation system 7/26/2019 Document reference 7
WP16.1: EA1 Access Point and RP BZ current layout Integration studies to be done for future layout ! By EN-EA EAR project 7/26/2019 Document reference 8
WP16.1 – EA2 current & future PPS Access Sectorisation PPS EA2 ECR - EIS-Beam: - 3 Beam Stopper replaced by 5: 3 existing upgrade, 2 new - 2 Magnets: power converters upgrade - EA1-EA2 inter-machine door provides emergency exit between EA1 and EA2 7/26/2019 Document reference 9
WP16.2 - EA Experimental Areas future layout 7/26/2019 Document reference 10
WP16 Installation and Commissioning • Strategy and Constraints: - EA1 PPS operational during LS2 till EA1 des-classified as Limited Stay Controlled Rad. Area) to separate from the rest of the hall (Supervised Radiation Area.) - Installation works in 1Q2021 at the end of EAR works in order to ensure readiness of required EN-EL infrastructure and EIS interfaces - Readiness of EN-EL services (cabling, power supply, FO) required for installation completeness - Readiness if EIS-beam/external required for PPS installation completeness and commissioning - EIS equipment groups (EN-CV , EN-SMM, TE-EPC, EN-CV) shall implement the defined interfaces with the PPS: ventilation system (EDMS 1871830), beam stoppers (EDMS 1871447), magnets power converters (EDMS 1288346) - EIS “ready for tests” for PPS functional (1-2 days) and DSO tests - Access constraints/not possible during PPS tests - To be studied requirements related to PS: - EIS-beam located in PS, readiness end 2020 for PS BEAM start - Access to PS required during EA PPS commissioning -> to be minimised ! 7/26/2019 Document reference 11
WP16 Installation and Commissioning Planning WP16 I & C EA1-EA2 Primary Zones EA Exp. Areas Dismantling Aug 2019 Mid-Nov 2018 Development & Tests in Test 2S2020 4Q2020 Platform Requirements for Installation: Doors & Jan 2021 Dec 2020 Grids installation (EN-ACE) EN-EL infrastructure (FO, control cables, power supply) Site Installation Jan-Feb 2021 Jan 2021 Requirements for Commissioning: Feb 2021 Jan 2021 Readiness if EIS-beam/external (beam stoppers, magnets power converters, EA1 ventilation system) Commissioning: Feb 2021 Feb 2021 Electrical, EIS interfaces, integration (PPS supervision and During PPS functional tests: TIM technical alarms) tests - NO Access in EA1-EA2 Functional tests (1day x 2) - Access to PS might be required, PS BEAM perturbations EA HW Tests: March 2021 7/26/2019EA DSO Tests : April 2021 Document reference 12
WP16 – Open Issues and Constraints - EA1 Access Point and new doors & grids integration studies to do - By EAR project (EN-EA) - Doors and grids: - Construction by EN-EA, site installation fully integrated in EAR planning -> EN-EA to ensure readiness prior to PPS installation - Supervised by BE-ICS - EN-EL services (cabling, power supply, FO) - Installation fully integrated in EAR planning -> EN-EA to ensure readiness prior to PPS installation - Readiness if EIS-beam/external required for PPS installation completeness and commissioning -> EN-EA to ensure readiness of EIS for PPS functional and DSO tests - EAR requirements for the EA Experimental Areas Access Safety Systems - To be finalised by EN-EA: - Interlock logic for managing the new area T9-10 and its impact on the upstream areas: intrusion in T10 shall interlock T9-10 only or also EA1 ? - Final list of doors to be equipped with access control 13