TOWN OF JUPITER PRESENTATION: JUPITER PARK DRIVE RIGHT TURN LANE
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
TOWN OF JUPITER PRESENTATION: JUPITER PARK DRIVE RIGHT TURN LANE IMPROVEMENTS DATE: 03/02/2021 TO: Honorable Mayor and Members of Town Council THRU: Matt Benoit, Town Manager MB FROM: Thomas V. Driscoll, P.E., Director of Engineering, Parks & Public Works SUBJECT: PRESENTATION: JUPITER PARK DRIVE RIGHT TURN LANE IMPROVEMENTS EXECUTIVE SUMMARY: Town Staff will be providing an update and presentation on the Town’s design project for eastbound right turn lane improvements at Central Boulevard. The Town commenced design on this project in late January of 2019. In retrospect, the original scope which envisioned a relatively simple turn lane improvement to provide additional eastbound right turn storage, along with an improved maintenance condition at the intersection of Jupiter Park Drive has become more complex due to the presence of underground utilities and an existing canal. A status update on the design plans and project are as follows: 90% Roadway and Landscape Plans: We have provided copies of the most recent roadway and landscape plans, which are at the 90% phase. We have received approval for the improvements from the South Florida Water Management District. As the project did not enter into the County Right of Way, a permit from the County was not required. To discuss the 90% plans for what started out as a relatively simple scope of work, we now have to step back into the earlier design and plan development stage of this project. When 30% plans were completed and reviewed, it became evident that an existing ditch on the south edge of the Town’s right of way was in fact a canal as defined by the Florida Greenbook. Based on the roadway design speed and the distance from the outside edge of the through travel lane to the top of the canal, our design would need to provide shielding of the canal by the use of a guardrail or longitudinal barrier. This would prevent an errant vehicle from becoming submerged if it were to enter or flip over into the canal. To address this hazard, during the development of 60% plans, we considered both W-beam guardrail and a cable barrier system. Unfortunately due to location in the right of way to an existing Loxahatchee River Environmental District (LRECD) 30 inch force main (FM) and TECO gas main, both guardrail posts and cable support posts would be either over or in close proximity to these lines, with the FM being more difficult to relocate. While the cable system offered a bit more flexibility in relation to the existing FM, the existing cross slopes, proximity to the canal and required reshaping for vehicle recovery, it resulted in a system that was marginal at best for heavy vehicles. With that, we then shifted the design scheme to include filling the canal, while providing water storage via reinforce concrete pipe and an exfiltration system. As part of this scope, we will be required to remove a significant amount of existing trees, as well as mitigate trees using a plan developed by our landscape consultant architect. The 90% plans due to the tree mitigation has a more extensive landscape plan than what was originally anticipated when the project was initially scoped.
Ultimately, filling the canal and creating a flush shoulder will result in a safer roadside and with the landscaping, a more aesthetically pleasing right of way. Unfortunately for these benefits, the cost is greater than a section with W-beam guardrail. Project Cost Estimate: A detailed Engineer’s Estimate based on the 90% plans has been prepared and checked. The current estimate indicates construction costs (without a cost contingency) at $641,567. With a contingency range from (-10% to +15%), the Town could anticipate construction costs between $577,410 and $737,802. The Town currently has a CIP construction budget of $600,000. For what was to have been a simple turn lane improvement, the costs to clear and fill the canal along with the installation of storm water piping and structures is a substantial amount of the cost estimate; approximately 40%. Based on coordination and preliminary dialogue with LRECD staff, we anticipate a portion of this cost will be borne by LRECD. At this point, we estimate their costs to be approximately $48,600. With the development of the FY 2022 CIP, we will recommend increasing the construction budget to $740,000; I believe the upper end of the contingency may be realized at the time of bid due to the clearing and dewatering necessary. In addition, due to the existing FPL power line, existing front slope and limited space, the canal clearing, fill and storm water construction may be estimated at the lower end of productivity, resulting in higher than average unit prices. The Town’s increase in budget would be anticipated by $91,400 with the remainder being the LRECD cost share. LRECD JPA and Agreement: Based on the revised scope of work, the permanent construction will require easements from LRECD, and these easements are proposed to be incorporated into a Joint Participation Agreement between the Town and LRECD. The easements required include a perpetual drainage easement for the Town’s roadway/right of way storm water, a temporary construction for work and temporary dewatering onto LRECD’s project during construction, and a harmonization easement to gradually restore the property. In addition, the agreement will provide for turnover of the installed fill, piping and structures to LRECD, and for their perpetual use and maintenance; this will be done through a bill of sale. We would note that the sketches and legal descriptions for these easements are pending. In addition and as noted above, we anticipate a cost share to be approved by LRECD. Project Schedule: The timeline of the major activities for completion of design and through anticipated construction completion are as follows: Task Name Duration Start Finish Prepare Easement Sketches and Legal Descriptions 20 days Mon 3/8/21 Fri 4/2/21 Final Plans 30 days Mon 4/5/21 Fri 5/14/21 Draft JPA Documents 30 days Mon 4/19/21 Fri 5/28/21 Contract Documents 30 days Mon 5/31/21 Fri 7/9/21 LRECD and Town Legal Review 10 days Mon 5/31/21 Fri 6/11/21 LRECD Board Approval 25 days Mon 6/14/21 Fri 7/16/21 Town Council Approval 25 days Mon 7/19/21 Fri 8/20/21 Advertisement, Bidding and Contract Executive 50 days Mon 8/23/21 Fri 10/29/21 Construction Phase 153 days Tue 11/30/21 Thu 6/30/22
We will be developing a more detailed construction duration estimate based on the 90% plans; it was not completed at the time for publishing this agenda item. Given the scope of work, we would anticipate the construction duration being between 210 to 300 calendar days. In terms of the schedule, during the seasonally wet months, the canal holds a significant volume of water. Temporary dewatering to allow for the placement of pipe and structures is complicated by the fact that the canal has no outfall; it is a landlocked storage ditch. We will need to temporarily dewater onto LRECD’s property and completing this work during the dry season in order to reduce the effort and volume required. Accordingly, we recommend a project schedule that begins construction in the early winter when conditions are more amendable for this scope of work, and the proposed schedule above, reflects the same. For Council information and discussion. RECOMMENDATION: No recommendation is provided for this presentation. For Council comments and feedback to staff. Strategic Priority: Mobility Attachments: · PowerPoint Presentation · 90% Plans · Engineer’s Estimate Funding Source: Approved in Budget $600,000.00 Sources: Jupiter Park Drive at Central Blvd. Improvements 31031041-56300-E1901 Additional Funding Required $ Sources: *For more information or to request attachments, please contact Kali Beams at kalib@jupiter.fl.us or 561-741-2467.
90% Roadway and Landscape Plans • A full set of 90% Plans were distributed to the Town Council • Widening Jupiter Park Drive Eastbound Approximately 880 FT to extend the existing right turn lane at Central Blvd • Install 2 FT paved shoulder outside the limits of the lane widening in the eastbound and westbound directions to approximately Jupiter Park of Commerce
90% Roadway and Landscape Plans • Clear and fill the existing canal on the south side of the right of way • Install reinforced concrete pipe, exfiltration trench, and drainage structures • Regrade and sod the existing shoulders adjacent to the canal • Install landscaping and trees to mitigate for the loss of trees necessary to clear and fill the canal
Roadway Typical Sections
Existing Canal – Rainy Season
Existing Canal - Rainy Season
Existing Canal – Dry Season
Existing Canal – Dry Season
Canal Clearing and Filling • The canal clearing and filling is a major construction and cost element • The canal will require dewatering throughout the construction • As an outfall does not exist, temporary dewatering onto LRECD’s property will be required • Limited space and FPL distribution line will have some impact on construction • Town Staff will consider Value Engineering certain elements of the work, in an effort to reduce the cost to fill the canal
Project Cost Estimate • The current FY 2021 CIP Construction Budget is $600,000 • Based on the 90% Plans the Engineer’s Estimate is $641,567 • With a Contingency Range from -10% to +15%, the Estimate is between $577,410 and $737,802 • Staff is recommending the FY 2022 CIP Budget be increased to $740,000 • The Town’s increase would be $91,400 with LRECD’s Cost Share being $48,600
LRECD JPA and Agreement • The project will require a Joint Participation Agreement between the Town and LRECD • This agreement will incorporate a Bill of Sale granting possession of the storm water infrastructure to LRECD • LRECD will perpetually maintain the storm water infrastructure • Perpetual and Temporary Easements will be required for the project • As previously noted, it is anticipated that LRECD’s cost share will be $48,600 • Both Town Council and LRECD Board will need to approve the Agreement and Easements
Project Schedule Task Name Duration Start Finish Prepare Easement Documents 20 days Mon 3/8/21 Fri 4/2/21 Final Plans 30 days Mon 4/5/21 Fri 5/14/21 Draft JPA Documents 30 days Mon 4/19/21 Fri 5/28/21 Contract Documents 30 days Mon 5/31/21 Fri 7/9/21 LRECD and Town Legal Review 10 days Mon 5/31/21 Fri 6/11/21 LRECD Board Approval 25 days Mon 6/14/21 Fri 7/16/21 Town Council Approval 25 days Mon 7/19/21 Fri 8/20/21 Advertisement, Bidding and Contract Executive 50 days Mon 8/23/21 Fri 10/29/21 Construction Phase 153 days Tue 11/30/21 Thu 6/30/22
Jupiter Park Drive and Central Blvd • Council Comments and Questions?
You can also read