THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018

Page created by Anne Duran
 
CONTINUE READING
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
THE ROHU PROJECT AND
THE CEE GAS MARKET
OPPORTUNITIES

Bucharest

14 June 2018

                       1
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
TRANSGAZ AND FGSZ DEVELOPS THE BRUA CORRIDOR TO SHIP BLACK SEA
PRODUCTION TO CEE MARKETS
BRUA Corridor and associated developments

                                                                 2
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
HUNGARIAN-ROMANIAN INTERCONNECTOR IS READY, PHASE I OF THE ROHU
PROJECT ENABLES THE TRANSMISSION OF 1.75 BCMA FROM 2019
ROHU project Phase I development is in progress

    PIPELINE IS READY

 • The Szeged-Arad pipeline was commissioned in
   2010 and is in operation.
 • In RO-HU direction 0.2 mcm/day and in HU-RO
   direction 4.8 mcm/day capacity is available.

    PHASE I DEVELOPMENT

 • 1.75 bcm capacities are available from 2019.
   Capacities will be sold on CAM NC auction in July
   2019.
 • Investment: two new compressor units.
 • The project is in permitting and development phase.
   Construction is ongoing.                              MOL Group Chairman-CEO Zsolt Hernádi, Prime Minister Emil Boc, Commissioner
                                                         Gunther Ottinger, Prime Minister Viktor Orbán in 2010

                                                                                                                                  3
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
ROHU PROJECT BRINGS 4.4 BCMA NEW SOURCE OF GAS TO CEE MARKETS
FROM 2022
ROHU project enables the regional shipment of Black Sea production from 2022

    PROJECT EFFECTS                                           PROJECT ROUTE

 • The project enables the shipment of Black Sea
   production, Romanian production to CEE markets
 • 4.4 bcma gateway to new, non-Russian source will
   be available from 2022.
 • The transmission of various sources will be available
   to Slovakia, Ukraine, Serbia, BiH, Croatia, and
   indirectly to Austria.
 • Supply sources and routes will be diversified on the
   CEE markets.
 • Utilization    of existing infrastructure   and
   development of missing ones lead to less cost of
   infrastructure
                                                           • The ROHU Open Season was 5-times overbooked in
                                                             December 2017. The network users have the
                                                             possibility to execute their exit rights until
                                                             14.12.2018.

                                                                                                        4
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
APPENDIX

           5
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
HUNGARY-SLOVAKIA-AUSTRIA (HUSKAT) PROJECT ENABLES THE
TRANSMISSION OF 5.2 BCMA GAS TO SLOVAKIA AND AUSTRIA
The HU-SK-AT project enables the transmission of natural gas up to 5.2 Bcm annually towards Sk and At
    PROJECT EFFECTS                                           HU-SK-AT PROJECT ROUTE

• The project enables the transmission of Black Sea
  production, Romanian and Hungarian indigenous
  production and other sources towards Slovakia,
  Austria and the opening Polish, Baltic and Finish
  markets.
• Hungarian Government approved the acquisition
  of MGT (HU-SK interconnector operator) by FGSZ.
  The acquisition is in progress.
• Up to 5.2 bcma no pipeline investment is needed.
  The required modifications of the system will be
  realized under the ROHU project by 2022.
• The project does not require the development of         • In case of 9 bcma deliveries 80km pipeline is
  the HUAT redundant infrastructure (~USD 1                 needed to be developed.
  Billion).

                                                                                                            6
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
FGSZ IS ABLE TO TRANSMIT 6 BCMA GAS TO UKRAINE
From 2022, 6.1 bcma firm capacities are available to Ukraine

     TRANSMISSION TO UKRAINE                                   PROJECT ROUTE

 • FGSZ offers 6.1 bcma (16.8 Million m3/day)
   interruptible capacity to Ukraine.
 • Network Users increase their shipment year-by –
   year to Ukraine:
    2015: 0.5 bcma
    2016: 1.0 bcma
    2017: 2.8 bcma
     HU>UA FIRM CAPACITY PROJECT
 • Traditional transportation routes need to be modified.
 • One of the two existing pipelines cannot be used for
   outbound deliveries due to contractual and regulatory
   issues outside of Hungary
 • FGSZ modifies its system under the ROHU project, to
   upgrade service quality to firm capacities to Ukraine.
 • The development includes the modification of 4 nodes
   and the development of a new metering system.
 • Ukraine can import at least 6.1 bcma gas from on a
   firm basis from 2022, to diversify its supply portfolio.
 • Various sources will be accessible for Ukraine.

                                                                               7
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
THE HUNGARY-SLOVENIA-ITALY CORRIDOR LINKS CEE MARKETS TO ITALY
The HU-SI-IT project creates new regional opportunities
                   PROJECT ROUTE

                   PROJECT EFFECTS

            • The project develops physical connection between Hungary and Slovenia and Italy.
            • The corridor establishes 2 bcma bidirectional capacity from 2022.
            • Non-binding market test may be carried out in Autumn 2018.
            • The project offers additional sources for Italian and Slovenian markets.
            • Italian LNG will be available for CEE markets.
            • Hungarian storages will be accessible for Slovenian and Italian markets
                                                                                                 8
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
VERTICAL CORRIDOR LINKS CEE AND SEE MARKETS
The Vertical Corridor enables the shipment of gas throughout the region

    PROJECT EFFECTS

 • The project links the separated gas
   markets of CEE and SEE countries.
 • The utilization of already existing
   infrastructure and the development of
   missing links enables the effective
   realization of projects.
 • Various sources, including Black Sea
   production, Azeri sources and LNG can
   flow along the corridor.
 • Supply source and route diversification
   enables the increase of liquidity and the
   decrease of prices in the region.
 • The trading environment and conditions
   will also be developed along the corridor.

                                                                          9
THE ROHU PROJECT AND THE CEE GAS MARKET OPPORTUNITIES - Bucharest 14 June 2018
GROWING MARKETS OF FINLAND, BALTIC STATES AND POLAND WILL BE
LINKED TO CEE MARKETS THROUGH PIPELINE DEVELOPMENTS
CEE cooperation with Baltic states and Finland creates a new corridor from Finland to Greece

       EASTERN CORRIDOR

    • Finland and Baltic countries are isolated markets with
      high level of prices.
    • Connecting the Baltic region to CEE countries creates an
      „Eastern corridor” from Finland to Greece.
    • A liquid trading corridor with various sources will be
      developed.
    • Sizeable Polish-Slovakian interconnector makes the
      missing link between CEE countries and enables the
      „Eastern corridor”.

               Source: Eustream, Baltic Connector                                              10
HUNGARIAN STORAGES PROVIDE FLEXIBILITY ALONG THE „EASTERN CORRIDOR”
Hungarian storages can provide flexibility for all regional countries with innovative products

                                                                     Storage sites                Mobile    Withdr.
                                                                                                    mcm     mcm/d
                                                                   MFGT sites
                                                               1   Hajdúszoboszló                   1 640      19.8
                                              1                2   Pusztaederics                      340       2.9
                                                               3   Zsana                            2 170      28.0
                                                               4   Kardoskút                          280       2.9
                                                               5   MMBF site                        1900      25.00
                                                                   Of which strategic storage        1200       20.0
      2
                                        4                          Total                            6 330      78.6
                               3   5

• Virtual storage concept provides flexibility for the market – four sites are operated under one virtual storage
• Peak storage capacities can help to manage supply disruptions and price shocks.
• Seasonality can be balanced with innovative products of storage operators.

                                                                                                                    11
REGIONAL BOOKING PLATFORM PROVIDES THE COMMERCIAL INTEGRATION
FGSZ is providing the solution for commercial integration of the region from Finland to Greece

      PLATFORMS                                                                RBP FACT SHEET

                                                                           •   Live operations since 10 December 2014
    Regional                              Trading
                      Informatic                             CEEGEX            (Csanádpalota IP)
    Booking                              Platform
                       Platform
    Platform                                                               •   8 TSOs use RBP in 7 countries
                                                                                  •   Romania: Transgaz

                   Operated by FGSZ                                               •   Croatia: Plinacro
                                                                                  •   Slovakia: eustream
                                                                                  •   Hungary: FGSZ, MGT
• Joint CAM NC
                                      • Cleared,
  capacity                                                                        •   Bulgaria: Bulgartransgaz
                   • Capacity and       anonymous
  booking
                     contract           marketplace of   • Organised              •   Greece: DESFA
  platform
                     management         BAL NC STSPs       marketplace
• Primary                                                                         •   Austria: GCA
                   • Flow               and secondary      (spot market)
  capacity
                     management         capacity                           •   122 registered network users
• Secondary
                                      • OTC market
  capacity (OTC)                                                           •   570 network points
                                                                           •   RBP conducted over 8 million capacity
                                                                               auctions
                       Network          Balancing /
    Capacity
                        usage             trading

                                                                                                                       12