Solar Krafte Utilities Inc. Capital Power Generation Services Inc. Strathmore Solar Project Costs Award January 6, 2021 - Decision 26107-D01-2021 ...
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Decision 26107-D01-2021 Solar Krafte Utilities Inc. Capital Power Generation Services Inc. Strathmore Solar Project Costs Award January 6, 2021
Alberta Utilities Commission Decision 26107-D01-2021 Solar Krafte Utilities Inc. Capital Power Generation Services Inc. Strathmore Solar Project Costs Award Proceeding 26107 January 6, 2021 Published by the: Alberta Utilities Commission Eau Claire Tower 1400, 600 Third Avenue S.W. Calgary, Alberta T2P 0G5 Telephone: 310-4AUC (310-4282 in Alberta) 1-833-511-4AUC (1-833-511-4282 outside Alberta) Email: info@auc.ab.ca Website: www.auc.ab.ca The Commission may, within 30 days of the date of this decision and without notice, correct typographical, spelling and calculation errors and other similar types of errors and post the corrected decision on its website.
Contents 1 Introduction ........................................................................................................................... 1 2 Submissions on the costs claim application ........................................................................ 1 3 Cyber Investments Ltd. ........................................................................................................ 2 3.1 Commission findings ..................................................................................................... 2 3.2 Total awarded to Cyber Investments Ltd. ...................................................................... 5 4 Order ...................................................................................................................................... 5 Decision 26107-D01-2021 (January 6, 2021) i
Alberta Utilities Commission Calgary, Alberta Solar Krafte Utilities Inc. Capital Power Generation Services Inc. Strathmore Solar Project Decision 26107-D01-2021 Costs Award Proceeding 26107 1 Introduction 1. In this decision, the Alberta Utilities Commission considers an application for intervener costs by Cyber Investments Ltd. for participation in Proceeding 25346 (the original proceeding). For the reasons set out below the Commission approves $62,134.02 in costs for Cyber. The approved amount, less the $25,589.55 awarded as advance funding in the original proceeding, 1 results in a balance payable of $36,544.47. 2. The original proceeding was convened by the Commission to consider an application from Solar Krafte Utilities Inc. for approval to construct and operate a 40.5-megawatt solar power plant, designated as the Strathmore Solar Project (Project). Cyber Investments Ltd. participated in the proceeding and submitted its costs claim within the 30-day timeline permitted by the Commission’s Rule 009: Rules on Local Intervener Costs. The record for this costs proceeding closed on December 7, 2020, the date reply submissions were received. 2 Submissions on the costs claim application 3. Solar Krafte expressed several concerns regarding Cyber’s cost claim. 2 It argued that no legal or expert costs should be awarded to Cyber for its pursuit of: adequacy of consultation, land use, zoning and development impacts. Solar Krafte also submitted that Cyber’s evidence and argument on the issues of: noise impacts, solar glare, visual impacts, irrigation site servicing, stormwater management, reclamation, property devaluation, and the takeover of the project by Capital Power did not contribute to a better understanding of the issues raised in the proceeding. While Solar Krafte also questioned Cyber’s evidence on emergency response, it proposed that costs in the amount of $2,000 be awarded to Cyber with respect to that issue. Finally, Solar Krafte alleged that counsel for Cyber, Mr. Langen, adopted a strategy of delay in an effort to derail the project. 4. Cyber rejected the submissions of Solar Krafte in its reply submission and maintained that it acted reasonably throughout the proceeding. 3 It submitted that Solar Krafte was conflating a successful outcome on a particular issue with the question of whether an intervener’s participation contributed to a better understanding of the issues before the Commission. Cyber noted that the Commission’s reasons were related to the expert evidence it filed, demonstrating 1 Exhibit 25346-X0058, AUC Ruling on adjournment and advance of funds request, June 30, 2020, paragraph 33. 2 Exhibit 26107-X0006, Solar Krafte Comments on Cyber’s Cost Claim (Proceeding 26107), November 30, 2020. 3 Exhibit 26107-X0007, LT AUC - Local Intervener Reply - CYBER Investments Ltd. re Proceeding 25346, December 7, 2020. Decision 26107-D01-2021 (January 6, 2021) 1
Strathmore Solar Project Solar Krafte Utilities Inc. Costs Award Capital Power Generation Services Inc. that its counsel and expert consultants contributed to a better understanding of the issues raised in the proceeding. 5. Cyber submitted that Solar Krafte’s allegations regarding intentional delay were unfounded on the record of the proceeding. It acknowledged that it made two adjournment requests but submitted that they were reasonable, as reflected by the relief granted by the Commission in each instance. Cyber strongly objected to Solar Krafte’s suggestion that its counsel, Mr. Langen, acted improperly or engaged in any misconduct in his representation of his client. Cyber pointed out that the vast majority of the work performed by Stikeman Elliott was performed by a junior lawyer at a reduced rate. Cyber also observed that the total legal fees were materially lower than projected in Cyber’s budget and submitted that this was a result of diligent efforts by counsel to ensure that its costs (and those of its expert consultants) were reasonable. 3 Cyber Investments Ltd. 6. Cyber owns land directly adjacent to the proposed power plant site, and pursued the following issues in the original proceeding: consultation, development of its lands, property value, local irrigation pipelines, emergency response, visual impacts, noise impacts, drainage and reclamation. 7. The Commission is satisfied that Cyber is a local intervener as that phrase is defined in Section 22 of the Alberta Utilities Commission Act and is eligible to recover costs in accordance with Sections 21 and 22 of that Act and Rule 009. 8. The following table summarizes Cyber’s costs claim: Hours Claimant Fees Disbursements GST Total Preparation Attendance Argument Cyber Investments Ltd. Stikeman Elliott LLP 80.66 0.00 51.73 $38,104.00 $24.10 $1,906.40 $40,034.50 CITYTREND 4 41.00 0.00 0.00 $11,275.00 $0.00 $563.75 $11,838.75 Telford Land & Valuation 30.00 0.00 0.00 $7,875.00 $203.47 $399.92 $8,478.39 Inc. Wearmouth Canada 36.00 0.00 0.00 $8,370.00 $242.00 $430.60 $9,042.60 (1951) Inc. RWDI AIR Inc. 18.00 0.00 0.00 $3,900.00 $0.00 $195.00 $4,095.00 Total 205.66 0.00 51.73 $69,524.00 $469.57 $3,495.67 $73,489.24 Less advance funding ($25,589.55) 5 awarded Net amount claimed $47,899.69 3.1 Commission findings 9. The Commission finds that Cyber generally acted responsibly in the original proceeding and contributed to the Commission’s understanding of the relevant issues. 4 Romanesky Urban Planning & Management Ltd. o/a CITYTREND. 5 Exhibit 25346-X0058, paragraph 33. Decision 26107-D01-2021 (January 6, 2021) 2
Strathmore Solar Project Solar Krafte Utilities Inc. Costs Award Capital Power Generation Services Inc. 10. The Commission finds that the costs claimed for Stikeman Elliott LLP are reasonable and approves those costs in full. The Commission finds that there is no evidence on the record of this proceeding or the original proceeding to substantiate Solar Krafte’s claim that Cyber’s counsel, Mr. Langen, engaged in intentional delay or any other misconduct. To the contrary, the Commission finds that Cyber’s counsel took reasonable steps to represent their client’s interest. The Commission notes that the proceeding raised complex issues and Cyber, through its counsel, legitimately pursued those issues. In the Commission’s view the legal costs claimed are commensurate with the scope of the proceeding and the nature of the issues raised. Accordingly, the Commission approves Cyber’s claim for fees for Stikeman Elliott in the amount of $38,104.00, disbursements of $24.10 and GST of $1,906.40 for a total of $40,034.50. 11. However, the Commission is unable to approve the full amount of the costs claimed in respect of the services performed by CITYTREND, Telford Land & Valuation Inc., Wearmouth Canada (1951) Inc. and RWDI AIR Inc. for the reasons set out below. 12. The costs claimed for consulting fees for Bryan Romanesky of CITYTREND were claimed at the rate of $275.00 per hour, 6 which is above the maximum rate allowed in the Scale of costs. Cyber’s submission has failed to persuade the Commission that a rate above scale is justified in the circumstances, and the fees claimed for Mr. Romanesky have been accordingly reduced to $11,070.00. 7 13. The Commission observes that CITYTREND was retained to assist Cyber in pursuing its concerns relating to development impacts. Although some of CITYTREND’s report was useful to the Commission, portions of the report and related submissions outlined perceived conflicts among the land use bylaws, the municipal development plan, and the proposed land use for the power plant site. Cyber relied on this report to argue that the development permit issued by the Town of Strathmore was issued erroneously as the proposed land use for the site was not consistent with the municipal development plan. The Commission finds that the evidence relating to these perceived conflicts did not assist the Commission in its understanding of the issues in the original proceeding. Cyber had also been previously cautioned that the Commission does not have jurisdiction over a municipality’s decision to approve land use bylaws or issue development permits. In addition, as the record showed, a municipal development plan is a visionary planning document that does not contain all details that may apply to a specific property for which a development permit is issued, but instead provides policies to achieve the growth and development objectives for the population envisioned by the plan. Further, this particular municipal development plan was stated to be under review. For these reasons, the Commission applies a 25 per cent reduction to the allowed consulting fees claimed for CITYTREND, resulting in an award of $8,302.50 8 in fees. Accordingly, the Commission approves Cyber’s claim for fees for CITYTREND in the amount of $8,302.50 and GST of $415.13 for a total of $8,717.63. 6 Exhibit 26107-X0001, CYBER Investments Ltd. Cost Claim re Proceeding 25346, November 20, 2020, paragraph 22. 7 $270.00 per hour * 41 hours = $11,070.00. 8 $11,070.00 * .75 = $8,302.50. Decision 26107-D01-2021 (January 6, 2021) 3
Strathmore Solar Project Solar Krafte Utilities Inc. Costs Award Capital Power Generation Services Inc. 14. Telford Land & Valuation Inc. (Telford) was retained to assist Cyber in pursuing its concerns relating to market value impacts from the development of the Project, and to determine what measures could be implemented on the Project to mitigate any impacts. Telford provided a report that detailed the predicted impacts of the Project to the value of Cyber’s land. However, as the Commission noted in its original proceeding decision “the property value evidence provided by Telford [was] of limited value because it was predicated on an uncertain development scenario.” 9 As noted in its original decision, Telford proceeded with generous assumptions on residential land values in the Town and then added assumptions about the highest and best use for Cyber’s lands changing to agricultural production at a lower dollar value if the Project was approved. More specifically, the property values estimated by Telford were premised upon contingencies associated with the development of lands not under Cyber’s control, and speculative development plans for the land which is under Cyber’s control. The Commission was not persuaded by Telford’s evidence and finds that this evidence did not contribute to a better understanding of the issues of this proceeding. For these reasons, the Commission applies a 50 per cent reduction to the consulting fees claimed for Telford, resulting in an award of $3,937.50 10 in fees. The Commission finds the disbursements claimed for Telford in the total amount of $203.47 to be reasonable. Accordingly, the Commission approves Cyber’s claim for consulting fees for Telford in the amount of $3,937.50, disbursements of $203.47 and GST of $203.05 for a total of $4,344.02. 15. Wearmouth was retained to assist Cyber in pursuing its concerns relating to reclamation. Wearmouth provided a report that detailed the costs to decommission and abandon the Project site. Cyber relied on this report to advance its position that reclamation funds should be required to be set aside prior to construction. However, as noted by the Commission in its original proceeding decision, “[t]here are currently no requirements, or an express authority, for the Commission to require reclamation deposits from power plant approval holders… In this case the land is owned by the Town and will be leased to Solar Krafte. As noted above, the terms of that lease included reclamation conditions that the landowner (the Town) found to be acceptable.” 11 While the Commission understands that reclamation can be a concern of interested parties relating to proposed developments, given the above, the Commission did not find this evidence to contribute to the understanding of the issues of this proceeding. For these reasons, the Commission applies a 35 per cent reduction to the consulting fees claimed for Wearmouth, resulting in an award of $5,440.50 12 in fees. The Commission finds the disbursements claimed for Wearmouth in the total amount of $242.00 to be reasonable. Accordingly, the Commission approves Cyber’s claim for consulting fees for Wearmouth in the amount of $5,440.50, disbursements of $242.00 and GST of $284.13 for a total of $5,966.63. 16. The Commission observes that RWDI was retained to assist Cyber in pursuing its concerns relating to noise and solar glare impacts. In it’s ruling on Cyber’s advance of funds request, 13 the Commission cautioned Cyber that it would not be persuaded by evidence on noise and solar impacts to pseudo-receptors. Despite this ruling, Cyber continued to pursue the issue of 9 Decision 25346-D01-2020: Solar Krafte Utilities Inc., Capital Power Generation Services Inc., Strathmore Solar Project, Proceeding 25346, November 27, 2020, paragraph 73. 10 $7,875.00 * .5 = $3,937.50. 11 Decision 25346-D01-2020, paragraph 105. 12 $8,370.00 * .65 = $5,440.50. 13 Exhibit 25346-X0058, paragraph 12. Decision 26107-D01-2021 (January 6, 2021) 4
Strathmore Solar Project Solar Krafte Utilities Inc. Costs Award Capital Power Generation Services Inc. pseudo-receptors in its information requests, including asking Solar Krafte to re-run noise impact assessments and solar glare hazard analyses with pseudo-receptors. While the Commission acknowledges that RWDI may have assisted Cyber in preparing its information requests, the Commission finds that this information did not assist the Commission in its understanding of the issues related to this proceeding. For these reasons, the Commission applies a 25 per cent reduction to the consulting fees claimed for RWDI, resulting in an award of $2,925.00 14 in fees. Accordingly, the Commission approves Cyber’s claim for consulting fees for RWDI in the amount of $2,925.00 and GST of $146.25 for a total of $3,071.25. 3.2 Total awarded to Cyber Investments Ltd. 17. For the reasons provided above, the Commission approves Cyber’s claim for recovery of costs in the total amount of $62,134.02. This amount consists of legal fees of $38,104.00, consulting fees of $20,605.50, disbursements of $469.57 and GST of $2,954.95. The approved amount, less the $25,589.55 awarded as advance funding in the original proceeding, 15 results in a balance payable of $36,544.47. 4 Order 18. The Commission approves Application 26107-A001, pursuant to sections 21 and 22 of the Alberta Utilities Commission Act and Rule 009, and orders as follows: (1) Solar Krafte Utilities Inc. shall pay intervener costs to Cyber Investments Ltd. in the total amount of $36,544.47 within 30 days of this Order. Payment shall be made to Stikeman Elliott LLP on behalf of Cyber Investments Ltd. Dated on January 6, 2021. Alberta Utilities Commission (original signed by) Carolyn Dahl Rees Chair 14 $3,900.00 * .75 = $2,925.00. 15 Exhibit 25346-X0058, paragraph 33. Decision 26107-D01-2021 (January 6, 2021) 5
You can also read