Smart Grid Small Generator Interconnection Procedures (SGIP) - PSEGLI - Power Asset Management (PAM) 10/23/14

Page created by Kyle Byrd
 
CONTINUE READING
Smart Grid Small Generator Interconnection Procedures (SGIP) - PSEGLI - Power Asset Management (PAM) 10/23/14
Smart Grid
     Small Generator Interconnection
            Procedures (SGIP)
         PSEGLI - Power Asset Management (PAM)
                        10/23/14

                                                 LONG
                                                 ISLAND
LONG
                                                          1
ISLAND
Smart Grid Small Generator Interconnection Procedures (SGIP) - PSEGLI - Power Asset Management (PAM) 10/23/14
Overview of Interconnection Procedures
• Adopted June 2012
• Establishes requirements to attach any small generator
  (0 to 20 MW) to the LIPA system.
• Replaces existing “Interconnection Guide for Independent
  Power Producers”
• Generally consistent with NY Public Service Commission (“PSC”)
  small generator interconnection procedures
• Also incorporates modifications to net metering eligibility to be
  consistent with Public Service Law 66-j, which LIPA is obligated
  to follow
• Interconnections greater than 10 MW must be at transmission
  level and will fall under NYISO SGIP process.

       LONG
                                                                      2
       ISLAND
Smart Grid Small Generator Interconnection Procedures (SGIP) - PSEGLI - Power Asset Management (PAM) 10/23/14
Reasons for Modifications (NYS Mandate)
Interconnection procedures determine method for attaching
customer-owned generators to the LIPA system
 –   Generators need to attach or else they are truly “off the grid” and would have to be entirely self-
     reliant on their systems
 –   The benefits associated with solar and wind generation, as well as fossil fuel generation, are all
     predicated on operating in parallel with the LIPA Electric Grid
Interconnection procedures need to balance the interests of the
customer-generators with the interests of all other customers on
the system
 –   Shouldn’t create safety risks for line workers or the public
 –   Shouldn’t impact reliability of the delivery system for all other customers
 –   Shouldn’t impose costs on all other customers beyond what is authorized by law for net
     metering participants
Interconnection procedures help by:
 –   Standardizing and shortening the process, especially for smaller generators
 –   Conforming to common standards and processes across the state, which helps the developers
     to keep costs down and work more efficiently

           LONG
                                                                                                           3
           ISLAND
Smart Grid Small Generator Interconnection Procedures (SGIP) - PSEGLI - Power Asset Management (PAM) 10/23/14
SGIP Modifications

                                             25 kW to           2,000 kW to
        Feature        0 kW to 25 kW         2,000 kW           20,000 kW
                            Yes for            Yes for
       Fast Track      standardized, type standardized, type          No
       Timetable       tested equipment tested equipment
                                             Coordinated          Full System
     System Studies                        Electric System       Impact Study
      Requirement             No           Interconnection     based on position
                                           Review (CESIR)       in study queue
                                          $350 (refundable        $350 plus
     Applicable Fees          No           for net metering     $10,000 system
                                             projects only)    impact study fee.
     Interconnection
       Maintenance            No                 No             11.4% per year
         Charges

        LONG
                                                                                   4
        ISLAND
SGIP Interconnection Fee Structure

       LONG
                                     5
       ISLAND
SGIP Interconnection Modifications

      LONG
                                     6
      ISLAND
SGIP Process Times

         Not Applicable   Not Applicable   TBD
         10 BD            10 BD

         Not Applicable   Not Applicable   TBD

LONG
                                                    7
ISLAND
LONG
         8
ISLAND
Changes Implemented as of June 1, 2014:
Rebates Processing SEPARATED from Power Asset Management
Interconnection Processing
      Incentives Application to be submitted through NYSERDA’s system
      PAM Solar Technical Documents to be submitted via email to PAMSolarLI@pseg.com
      Only interaction is submittal of COD Letter to receive rebate
PAM Solar to request/schedule Net Meter Installation upon Initial Technical
Approval of New Solar Application within 10 business days
      Net Meter to be installed before Close Out (Final) Documents are submitted by Solar
      Contractor. In most cases, net meter will be installed before construction of project.
Use of self certification to verify inverter compliance with UL 1741 5 minute
time-out test
COD (Commercial Operation Date) Letter to be issued within one business
day of receipt and review of Close Out documents and verification of Net
Meter Installation

         LONG
                                                                                           9
         ISLAND
LONG
         10
ISLAND
LONG
         11
ISLAND
DG Screening Criteria & Tools

 –    Key Assumptions:
        LIPA Distribution System design & Operating Characteristics
        LIPA DG Interconnection Policies

 –     PAM worked with GE and internal organizations to come up with a
     screening methodology that can determine whether the DG
     interconnection request (including inverter-interfaced DG
     interconnection) should be Fast Tracked or if the particular DG (see
     below) project requires further engineering study:
         Inverter Based (Solar, Wind, etc.)
         Synchronous Generators
         Induction Generators
         Other

         LONG
                                                                            12
         ISLAND
It is a Team Effort
• Power Asset Management is the lead organization:
 –   Receive Inquires
 –   Process Applications
 –   Request Net Meter Installations
 –   Request Solar Billing Inquires
 –   Manage the Process
 –   Handle the Paperwork
 –   Monitor Process Times
 –   Respond to customer interconnection and net meter issues
• Other Groups will be called upon for:
 –   In-depth Technical Analysis and Studies
 –   Detailed Interconnection Design
 –   Cost Estimating
 –   Support to resolve customer complaint issues
         LONG
                                                                13
         ISLAND
SGIP Support for Customers
  –   Approved Final SGIP Document in place since June 2012
  –   SGIP documents on LIPA WEB
      •   Applications and forms
      •   Reference documents
      •   Process flowcharts
      •   PAM contact information
      •   DG Screening Criteria
      •   Interconnection costing guidelines for estimating purposes
      •   SGIP Interconnection Queue (Updated and posted bi-monthly)
  –   Continued evaluation and updating of SGIP to consider:
      • NYISO modifications
      • NY State PSC modifications
      • Industry standards
          –    UL 1741, IEEE 1547

              LONG
                                                                       14
              ISLAND
PAM single point of contact for:
  –   Interconnection and SGIP application status issues
  –   Net meter issues
  –   Billing issues

  Contact Info:
  – PAMSolarLI@pseg.com
  – Julia Uddin (516) 545-4792
  – Steve Cantore (516) 545-4820
  – Or in writing to:
          Steve Cantore
          Power Asset Management (PAM)
          PSEG-Long Island
          175 E. Old Country Road
          Hicksville, NY 11801

         LONG
                                                           15
         ISLAND
You can also read