ELECTRIC ENERGY IN THE REPUBLIC OF KAZAKHSTAN - CAREC Program
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
How the power sector works in RK 1 Generating 2 High-voltage power 3 Distribution power grids and plant lines substations The power is transmitted Electric and thermal between regions to RPCs (or Regional and city RPCs reduce the voltage and power is generated directly to major consumers) electricity is transmitted to end users (wholesale and retail) 4 Consumption transmission of heat Main task of the power sector: 100% reliable provision of power to the economy depending on the state of the industry itself … …which in its turn, is determined by the technical level, level of investments and quality of management 2
Historic dynamics of power generaGon and consumpGon A"er the downturn of the economy in 2008 power genera8on has grown confidently and beginning in 2013 it exceeded the demand for electricity 3
Balance of electric power and electric capacity in the RK unGl 2030 The balance shows that the power sector saGsfies the needs of Kazakhstan's economy unGl 2030 25,000 20,000 15,000 Surplus of disposable capacity over consump8on 10,000 5,000 0 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Располагаемая мощность Disposable capacity Потребление Consump8on 4
Current state of the power sector of the RK PLANTS Power generaGon 1 111 3 billion kWh Number of power plants – 2015 2016 2017 actual actual plan 90.8 94.1 94.2 2 Installed capacity 22 055 MW 4 Total generaGon – 94,1 billion kWh As of January 1 2017 as of January 1 2016 Annual maximum load in Kazakhstan in 2016 reached In 2016 power genera8on increased by 3.6% compared to 13 990 MW whereas disposable capacity in the 2015. winter of 2017 reached 17500 MW. Hence full coverage of consump8on with a significant level of reserves. 5
Current state of the power sector of the RK POWERLINES KEGOC 110-1150 kV 74 substa8ons 31 thousands of kilometers of FuncGons: power lines 1) Ensures electrical linkages between regions of the republic and neighboring countries 2) Ensures power supply by power sta8ons and its transmission to wholesale consumers 3) Performs technical dispatching 4) Plays the func8on of a system operator above roughly RECs – 21 5000 500 0.4-220 kV substa8ons thousands of FuncGons: kilometers of power 1) Ensures electrical linkages inside the regions lines 2) Ensures transmission and distribu8on of power between retail consumers Total number of power transmission organizaGons - 160 6
100 concrete steps for implementaGon of 5 insGtuGonal reforms Within the framework of implementaGon of the "NaGon's plan - 100 concrete steps for implementaGon of 5 insGtuGonal reforms" in 2015 the department of electric energy started acGviGes to implement steps 50, 51 and 52: STEP 50. ReorganizaGon of the power sector IntroducGon of the "Single buyer" model (introduced from January 1 2019) Step 51. AggregaGon of regional energy network companies (The Law was signed by President of the Republic of Kazakhstan on July 11 2017) Step 52. IntroducGon of the new tariff policy in the power sector sGmulaGng investments in the industry. (introduced from January 1 2019). 7
STEP 50. ReorganizaGon of the power sector IntroducGon of the "Single buyer" model By Law of the RK of 12 November 2015 No 394-V "On the introducGon of changes and addenda to certain legislaGve acts in the area of electric power" the new Single Buyer model will be introduced from January 1 2019. Purchase of the capacity by the Single buyer will take place as follows: 1. 1) Purchasing the capacity from exis8ng power genera8ng organiza8ons 2. 2) Purchasing the capacity from new power genera8ng organiza8ons under direct long-term contracts based on the results of tenders 3. The law envisages an addi8onal mechanism to purchase capacity from exis8ng power genera8ng organiza8ons without tenders. This type of capacity purchase is brought about by the need to ensure long term guarantees for the return of investments made in moderniza8on, reconstruc8on, renova8on, expansion of the exis8ng power producing organiza8ons. 4. Guaranteed purchases of capacity from CHPs within technological minimums. 8
STEP 52. IntroducGon of a new tariff policy in the power sector sGmulaGng investments in the industry By Law of the RK of 12 November 2015 No 394-V "On the introducGon of changes and addenda to certain legislaGve acts in the area of electric power" a new tariff policy in the power sector sGmulaGng investments in the industry will be introduced from January 1 2019. The exis8ng power tariff will be split in two parts ELECTRIC POWER TARIFF: CAPACITY TARIFF: variable part which will the permanent part which will ensure return of ensure return of costs investments made in the construc8on of new, and for genera8ng electric power. renova8on, moderniza8on, reconstruc8on and expansion of exis8ng electrical capacity. 9
Market model according to the changes to the Law "On the electrical energy sector" within the framework of execuGon of steps from January 1 2019. Market Council POWER PLANTS New PPOs all PPOs (by Func8oning PPOs not Func8oning PPOs RE commissioned under groups requiring moderniza8on requiring moderniza8on tenders Short-term capacity Power Market Long-term capacity market market Bilateral Centralized 100% Long-term nego8a8ons procure Centralized trading for agreements trading Investment agreements based on tender results ment one year (more than 10 years) SETTLEMENT AND FINANCE CENTER Single buyer of RE and capacity Consumers 10
RESOURCE POTENTIAL OF RENEWABLE ENERGY IN THE REPUBLIC OF KAZAKHSTAN 11
920 billion 3000 kWh per year Wind energy Solar energy hours of sunshine per year 62 billion kWh per year Hydropower 12
RE SECTOR DEVELOPMENT INDICATORS 2016 2020 50 RE facilities till 2020 WPP 100 MW HPP 103 RE facilities till 2020 WPP 960 MW HPP 142 MW 290 MW 300 MW 2000 MW SPP SPP total capacity 58 MW total capacity 750 MW 13
2016 RE share in the total power generation 50 RE facilities till 2020 WPP 100 MW 50 % HPP 142 MW 300 MW total capacity SPP 58 MW 10 % 2020 3 % 103 RE facilities till 2020 WPP 960 MW HPP 290 MW 2000 MW 2020 2030 2050 SPP total capacity 750 MW 14
NUMBER OF COUNTRIES EMPLOYING THE AUCTION METHOD OF RE SUPPORT 70 60 50 40 30 20 10 0 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 At present 67 countries aroung the world use the auction method for RE support 15
SOLAR GENERATION TARIFFS, $/kWh COMMISSIONING OF NEW SOLAR CAPACITY, GW 1 100 0.95 0.9 80 0.8 80 75 0.7 55 0.6 60 0.6 40 0.5 32 0.5 40 30 0.4 0.35 18 0.3 0.15 20 0.12 0.08 0.06 5 0.2 0.03 0.025 0.0 0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2009 2010 2011 2012 2013 2014 2015 2016 2017 Over the last 10 yeas the cost of solar power declined from 1,0 to 0,025 USD This has resulted from an economy of scale, cheapening technologies and the shift towards a market mechanism – the auction.
PRICE OF WIND ENERGY, $/kW 0.5 0.40 0.39 0.4 0.30 0.3 0.17 0.2 0.10 0.06 0.05 0.04 0.034 0.0 2009 2010 2011 2012 2013 2014 2015 2016 2017 17
The price of RE may be lower that new coal and gas-fired power plants 2016 AUCTION RESULTS BY TYPES OF GENERATION 7 6 5 4.8 4.75 4.8 4.3 4.2 4 3.2 2.8 2.9 3 2.5 2 solar solar solar coal coal gas gas gas win 1 0 Mexico Mexico Mexico Chile Chile Chile UAE UAE UAE Cents/kW (in USD) 18
FURTHER DEVELOPMENT OF RE IN KAZAKHSTAN It is necessary to address two important tasks: 1 Select and implement the most effective RE projects and attract the best investors with advanced technologies 2 Reduce RE burden on the country’s economy AUCTION MECHANISM to RE support will enable us to address these two tasks 19