Quarterly System Status Briefing: Summer Status - Brian Molefe Group Chief Executive - Eskom
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Overview • Eskom continues to supply 100% electricity for the most part, while performing maintenance • To date, we have had 99 days with only 2 hours and and 20 minutes of load-shedding. • The recent introduction of a new maintenance methodology called Tetris enables effective management of maintenance with no load shedding • The performance of our generation fleet has stabilised with unplanned outages (UCLF) below target of 7 000MW • The New Build programme delivered 720MW to the grid with the commercial operation of Medupi Unit 6 on 23 August 2015 • Our focus is on fast tracking the capacity build programme • Summer projections is that no load shedding is expected. 3
Since Winter 2015 was warmer than last year, more maintenance was performed while still supplying 96% electricity • Eskom performed three times more maintenance this past winter • Renewable energy contributed up than ever before to 1 300MW during the day, of which 800MW was from solar and 500MW from wind, including • Typically the winter demand for Eskom’s Sere wind farm electricity increases along with localised power outages and illegal connections putting • All available levers were used to additional strain on the power contain the level of load shedding: system - Independent Power Producers - Open Cycle Gas Turbines • While load shedding was - Demand Market Participation implemented this winter, Eskom continued to supply up to 96% of electricity during this period • Coal stock levels were at healthy levels throughout the winter with an average of 51 days 5
In summer, the system is tight all day up to 10pm, showing a flat “Table Mountain” profile “Table mountain” profile Typical Winter Day Typical Summer Day Summer and winter typical daily load profiles MW 36 000 34 000 32 000 30 000 28 000 26 000 24 000 22 000 20 000 23:00 02:00 05:00 08:00 11:00 14:00 17:00 20:00 23:00 02:00 7
Eskom will continue to execute maintenance without load shedding throughout the summer period (1/2) • While the system remains tight, Eskom will continue with maintenance with no or limited load shedding • Summer is likely to be hotter than last year, with a higher expected demand in electricity throughout the day as consumers switch on air conditioners and pool pumps • We plan to meet demand for electricity 100% of the time and implement stage 1 load shedding only when demand increases beyond available capacity • The 2hr 20min of stage 1 load shedding that took place on 14 September was an extreme incident as there was a loss of a number of generating units in quick succession • Key industrial customers experienced stage 2 load curtailment only once in the last 99 days on 9 October 2015 for 5 hr 30 min 8
Eskom will continue to execute maintenance without load shedding throughout the summer period (2/2) • The development of a new methodology, called Tetris has resulted in better predictability e.g. Medupi unit 6 remained on planned outage from 21 October until 9 November with no load shedding • Tetris enables us to perform maintenance within our maintenance budget of 4 500 MW • During the severe heat wave experienced in early October, Eskom was able to perform maintenance without load shedding • Eskom has connected an additional 43 Independent Power Producers (IPP) projects with a total capacity of 2 147 MW of which 2 021 MW is in commercial operation • An additional 334MW from the Department of Energy’s Dedisa IPP project • Coal stock is sustained at healthy levels of 58.2 days on average • Dam levels are currently at 58% 9
Capacity outlook until August 2016 Available Capacity Operating Reserves PCLF UCLF Peak Demand Installed Capacity Capacity outlook from November 2015 to August 2016 MW 45000 1 Winter UCLF Summer UCLF UCLF 6000 MW 40000 7000 MW 35000 PCLF Operating Reserves 30000 25000 Available Capacity 20000 Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2015 2016 Source: Tetris V4.03 1 Additional capacity from IPPs (500MW) 10
Tetris: Overview of planned maintenance from November 1 to December 2015 Capacity outlook from November to December 2015 Available Capacity = Installed Capacity - Peak Demand - UCLF MW 11 Source: Tetris V4.03
2 Tetris: Overview of planned maintenance from January to April 2016 Capacity outlook from January to April 2016 Available Capacity = Installed Capacity - Peak Demand - UCLF MW Source: Tetris V4.03 12
Tetris: Overview of planned maintenance from May to 3 August 2016 Capacity outlook from May to August 2016 Available Capacity = Installed Capacity - Peak Demand - UCLF MW Source: Tetris V4.03 13
On average the demand has been the same between August and October when compared to 2013, 2014 and 2015 Weekly Energy Sent out –YOY comparison 2013 - 2015 Insights • Despite recent statements in the Incl IPPs 2015 Incl IPPs 2014 Incl IPPs 2013 media, electricity demand profile 5 300 has remained relatively similar over the Aug – Oct over the last 3 Thousands years 5 100 • Stable electricity supply has also led to the increase in 4 900 manufacturing output: ‒ Output rose 0.9% year on year 4 700 compared to a revised -0.3% in August 4 500 ‒ Factory production jumped Energy (GWh) 2.2% and was up 1.4% in the 4 300 three months to Sep 2015 4 100 “Not a bad manufacturing print at all. It may be that both the more competitive rand and stabilisation of power, 3 900 helped” – Razia Khan (head of Africa 38 39 40 41 42 43 44 45 46 Weeks research at Standard Chartered” Source: Eskom Transmission, Reuters, The Witness 14
Introduction Winter performance Summer outlook Recovery and build programme Conclusion 15
Progress at Majuba Power Station (1/2) • Majuba Power Station experienced a • An interim solution is currently in coal storage silo collapse on 1 place and has been in operation November 2014 from 1 October 2015 • A short term solution was • This includes a newly constructed implemented with coal being fed temporary conveyer belt to ferry through an elevated mobile boom the coal feeder • The power station has been able to • The use of trucks to transport coal has been curtailed from an average run at full load from February of 1060 trucks before the 2015 implementation of the interim solution to an average of 90 trucks 16
Progress at Majuba Power Station (2/2) Permanent solution • Designs for the permanent solution have been completed • This includes re-instatement of the damaged silo and the associated coal conveyor system • Two other coal silos will also be reinforced • A tender enquiry was issued to the market and closed on 03 November 2015 • Evaluation in progress and anticipated contract award date is 01 December 2015 • Construction will be complete by 31 December 2017 17
Progress at Duvha Power Station Progress update • Duvha Power Station experienced an over- pressurisation incident in March 2014 • The collaborative process undertaken in conjunction with the Loss Adjuster is nearing completion • An indicative settlement offer has been made by the insurers and the Loss Adjuster • The boiler needs to be replaced, however, issues of technology assessment and cost uncertainty have delayed progress on this project • A proposed investment and commercial process will be submitted to the Eskom governance committees for a decision on the way forward 18
Build Programme - current scheduled dates The Intention is to fast track the build programme Medupi Commercial operation dates Unit 6 (794MW) 23 August 2015 Unit 5 (794MW) March 2018 Unit 4 (794MW) July 2018 Unit 3 (794MW) June 2019 Unit 2 (794MW) December 2019 Unit 1 (794MW) May 2020 Kusile Commercial operation dates Unit 1 (800MW) July 2018 Unit 2 (800MW) July 2019 Unit 3 (800MW) August 2020 Unit 4 (800MW) March 2021 Unit 5 (800MW) November 2021 Unit 6 (800MW) September 2022 Ingula Commercial operation dates Unit 3 (333MW) January 2017 Unit 4 (333MW) March 2017 Unit 2 (333MW) May 2017 Unit 1 (333MW) July 2017 19
The New Build Programme and Recovery Projects will contribute 5 620 MW to the network over the MYPD3 window xx MW added to the network Post MYPD3 • First sync Mar 2015 • Full stable power by • Commissioned in Jun 2015 early Mar 2015 • Commissioned Aug • Additional 100MW 2015 • Ingula Unit 4 first • Ingula Unit 1 first • Kusile Unit 1 First sync added to the • Additional 794 MW sync in Jan 2017 sync in May 2017 in Nov 2017 network added to the network • CO by Mar 2017 • CO in Jul 2017 • CO in Jul 2018 100 794 333 333 800 Mar 2015 Jun 2015 Mar 2017 Jul 2017 Jul 2018 5 620 Sere Wind Farm Medupi Unit 6 Ingula Unit 4 Ingula Unit 1 Kusile 1 Mar 2015 Jan 2017 May 2017 Mar 2018 Majuba Recovery Ingula Unit 3 Ingula Unit 2 Medupi 5 1200 333 333 794 600 • 600MW from unit 3 gap • Ingula Unit 3 first • Ingula Unit 2 first • Medupi Unit 5 first • Duvha 3 will be fully solution in Feb & sync in Oct 2016 sync in Mar 2017 sync in Sep 2017 recovered in 600MW from Unit 4 in • CO by Jan 2017 • CO by May 2017 • CO in Mar 2018 2019/2020 Mar 2015 • This project falls out of MYPD3 window SOURCE: Team analysis 20 1 Dates based on P80 Schedule
We will collaborate with our customers to reduce demand- “Less is more − Live Lightly!” Saving electricity reduces pressure on the grid, cuts your electricity bill and reduces South Africa’s carbon emissions The power system remains vulnerable all day during summer 1. Use air conditioning efficiently “Know your o Set air conditioning to 23ºC number” o Close windows and doors to optimise air conditioning o Switch off 30 minutes before leaving the office 2. Switch off all geysers and pool pumps (all day until 9pm), and invest in a timer 3. If you use the pool frequently, limit pool filtering cycles to two cycles daily, and not between 5pm & 9pm 4. Switch off all non-essential lighting “Live 5. Respond to Power Alert messages by switching off all Lightly” appliances that are not being used 21
Conclusion We endeavour to perform maintenance with no load shedding this summer To date we have had 99 days with only 2 hours and 20 minutes of load- shedding. Key industrial customers experienced stage 2 load curtailment only once in the last 99 days Eskom will fast track its build programme to ensure supply in winter We appreciate the support of all our customers and encourage that we maintain 10% electricity savings Eskom will continue to provide regular updates on the state of the power system through various media platforms Please also follow us on twitter @Eskom_SA and @Eskom_MediaDesk for updates 22
Thank you
You can also read