Eskom Presentation Standing Committee on Appropriations - 12 June 2015

Page created by Eddie Rose
 
CONTINUE READING
Eskom Presentation Standing Committee on Appropriations - 12 June 2015
Eskom Presentation
Standing Committee on
Appropriations

12 June 2015
Eskom Presentation Standing Committee on Appropriations - 12 June 2015
Contents

 Content

  1. Introduction

  2. Financial situation

  3. Eliminating Load shedding

                                 2
Executive summary (1 of 2)

• Eskom is a fully integrated power utility (generation, transmission,
  distribution and wholesale/retail) that supplies 95% of SA’s electricity and
  fourth largest in the world in terms of installed capacity
• We are well-governed with a Shareholder, functioning Board and EXCO
  and more than 46 000 employees
• Eskom’s Labour Relations has matured over time and since 1998,
  Eskom has never had a strike except for isolated localized incidents of
  work-stoppages (in 2010 and in 2013 both in support of the wage
  demands).
• We are currently undertaking a R280 bn capex programme over 5
  years and building two of the biggest coal fired power plants in Africa
• Since 2001 we added 32 generating units increasing a number of
  current units to 121
• Medupi Unit 6 has been synchronised and Sere Wind farm (100 MW)
  is completed.
• Delays in new build has primarily been caused by our contractors
  through strikes or technical non-performance
Executive summary (2 of 2)

• We have a maintenance backlog and this has led to deteriorating power station
  availability and subsequent load shedding.
• We need a minimum of 3000 MW and maximum of 5000 MW capacity either
  through supply-side or demand-side options within 18 to 24 months and avoid
  load-shedding
• At Stage 1 load-shedding we still supply 96% of the required demand. At stage
  2 it is 94% of required demand
• We have added about 160, 000 new electrification customers in the last
  financial year
• In Distribution side we have sustainably reduced the duration of customer
  interruptions over the last three years by close to 10 hours per annum
• Eskom is finalising a turnaround strategy addressing its financial strength,
  operational excellence and new build delivery
• A strong and sustainable Eskom is required to ensure a sustainable
  economy
The Capital Portfolio is made up of almost
8000 projects costing R280bn over 5 years...

 The main drivers of the CAPEX requirements are:

  • New build / new capacity (R159bn)
  • Major overhauls that are capitalized (R29bn)
  • Refurbishment and replacements (R63bn)
  • Customer connections (R10bn)
  • Compliance (legal, regulatory, safety, environmental) R19bn
Contents

 Content

  1. Introduction

  2. Financial situation

  3. Eliminating Load shedding

                                 6
Finance situation

• Eskom is going through an intensive capital investment phase

• Eskom will remain liquid in the Financial year

• At minimum, Eskom must break-even in the current financial year
  which will require a close monitoring of expenditure as well as
  improved sales and collections from customers to minimise
  impairment of revenue

• We are pursuing a maintenance strategy without load shedding

• The New Build Programme is expected to deliver 3 units in the
  current financial year from Medupi (one unit) and Ingula (two
  units)

                                                                    7
Eskom is funded through various sources

•   Equity: Funding injected by the Shareholder

•   Revenue: Funds received through sale of electricity per Tariffs
    determined by the NERSA
•
•   Debt: Raised through Local & international markets from a
    variety of lenders

Debt and equity financing is mainly utilised to close the gap
where there is a short-fall from revenue funding

                                                              8
Eskom is in a capex intensive phase – this is cyclical

                                                                                          ILLUSTRATIVE

 Eskom's
 net cash
 balance

Eskom Early Years       1990ies - 2005            2006 - 2018                Beyond 2018
And Early 1980          •   Cash-out phase        •   Investment phase       •   Cash Positive
• Investment phase      •   Almost no new build   •   Tight supply           •   Repayment of debt
• Significant           •   Oversupply and        •   Increasing tariff to   •   Planning for the next
  investment into new       cheap electricity         fund new build             phase
  power plants

                                           CONFIDENTIAL                                                  9
Cash flows for FY2016 indicate a closing balance
of R15.7 bn
Cash flows for FY2016                              Key insights
R’ Million

                                                    • The R23 bn equity
                                                      injection will be
                                                      used to fund
                                                      CAPEX
                                                    • Gearing will
                                                      improve from 75%
                                                      to 67% with the
                                                      conversion of the
                                                      subordinated loan
                                                      and the R23bn
                                                      equity injection

                                                                          10
Eskom plans to raise a total of R55 bn of debt
securities for FY2016

  Debt securities
  R’ Million
      Eskom bonds                                8 000

      DFI and other loans                        7 244

      Export credit facilities               10 576

      International bonds                    16 500

      Commercial paper                       10 000

      DBSA                                       3 000

      Total debt securities raised           55 320

                                                         11
The total Capital Expenditure for the year is R60bn
 with new builds contributing over 40 % of the
 expenditure
Capital expenditure                                    Insights
R Million

  Capital expansion                  R Million
   - Medupi                                  10 926    • It is critical that
                                                         each division
   - Kusile                                  12 800      keeps within the
                                                         Capital allocations
   - Ingula                                   1 474
  Transmission                                3 427    • Deviations from the
                                                         allocated capital
  Other                                       4 737      expenditure will
  Total capital expansion                    33 364      have an impact on
                                                         Eskom’s financial
  Generation                                  9 760      health and
  Transmission                                  959      sustainability

  Distribution                                6 027
  Future fuel (coal)                          1 142
  Other project related expenses              8 929
  Asset purchases                             1 471
  Total                                      61 652

                                                                        12
Capital projects are on track with Medupi unit 6
commercial operation expected in Q3 of 2015
Project                 Description
                        •   Continue to ramp up to full commercial operation. Full Load planned for the 2nd quarter of 2015,
                            and CO (Hand-over to Generation) during the 3rd quarter of 2015.
   Medupi unit 6:

                        •   Unit 1 Boiler Re-heater hydrostatic test was successfully executed per the acceptance criteria on
                            12 April 2015. Balance of Plant items is progressing
   Kusile Project:

                        •   our first utility-scale renewable energy project, was put into commercial operation on 31 March
   The 100MW Sere           2015
   Wind Farm

                        •   We have 48 active schemes contributing to 14,415 MVA of transformer capacity and 4,397km to
   Transmission             the network at completion. Financial year 2014-2015 we achieved 318.6 kms of line built and
   Projects                 2,090 MVA transformation capacity built.

                        •   1st commercial train expected in the 2nd quarter of 2017.
   Majuba Rail

                        •   Progress is being made on PV rollout at power stations and administration buildings for self-
                            consumption, with a Solar PV plant
   Other Projects:

                        • Future build falls under the Minister of Energy.
   Future Build Plans   • The Cabinet approved IRP 2010 however provides for 9,600 Megawatts of electricity to be
   including Nuclear:       generated through nuclear power, with the first unit commissioned by 2023.

Source: Team analysis                                      13
Eskom needs to ensure capital is available to ensure
delivery of one Medupi and two Ingula units for FY16                                                                                xx      MW added to
                                                                                                                                            the network

                                                                                                                                            Post MYPD3

  • Commissioned in           • First sync Mar         • Unit 4 to be           • Unit 1 to be                • Kusile 1 will be
    early Feb 2015              2015                     commissioned Apr         commissioned                  commercially
  • Additional 100MW          • Full stable power        2016                     Aug 2016                      operating Aug
    added to the                by Jun 2015                                                                     2017                         2015/16
    network                                                                                                                                 1466 MW

                                                                                                                                         Medupi x1 unit
     100                             800                     333                      333                            800
                                                                                                                                         Ingula x2 units
  Feb 2015                        Aug 2015                Mar 2016                Jul 2016                        Aug 2017
  Sere Wind Farm                  Medupi Unit 6           Ingula Unit 4           Ingula Unit 1                   Kusile 1                  Total MW
                                                                                                                                              5532

              Mar 2015                     Jan 2016                  May 2016               Sep 2017                                       2019/2020
              Majuba                       Ingula                    Ingula                 Medupi 5                                       Duvha 3
              Recovery                     Unit 3                    Unit 2                                                                Recovery

                1200                         333                          333                     800                                          500

           • 600MW from unit          • Unit 3 to be           • Unit 2 to be           • Medupi 5                                 • Duvha 3 will be
             3 gap solution in          commissioned             commissioned             commercial                                 fully recovered in
             Feb & 600MW                Jan 2016                 May 2016                 operation date is                          2019/2020
             from Unit 4 in Mar                                                           Sep 2017                                 • This project falls
             2015                                                                                                                    out of MYPD3
                                                                                                                                     window

Source: GCD, Team analysis                                                                                                                                 14
Principles of electricity prepayment

                        There are key benefits that can be derived from maximizing
                      prepayment across all the customer groupings, these include:

                  •     Improved cash flows as a once-off benefit

                  •     Improve most balance sheet ratios

                  •     Interest free borrowing mechanism

                  •     Reduces long term debt

                                        Increases short term debt

SOURCE: Team analysis
                                                                                     14
Contents

 Content

  1. Introduction

  2. Financial situation

  3. Eliminating Load shedding

                                 16
5 May 2015 Stage 1 load shedding was implemented
  during evening peak due to a 2180MW shortfall

 Available capacity vs peak demand for 5 May 2015    Key Insights

 MW                                                      Type      Number Number       Nominal    %
                                                                      of    of units   capacity
45,000                 43,500
                                                                   stations             (MW)
40,000                                                Coal-fired     14       87       35 721     82

                                                      Hydro           2        6         600      1.4
35,000
                                          32,180      electric
30,000                                                Pumped          2        6        1 400     3.2
                                                      storage
25,000                                                Nuclear         1        2        1 860     4.3

20,000                                                Gas             4       20        2 409     5.5

15,000                                                Imports         1        1        1500      3.4

10,000                                                Total          24       124      43 4901
                                                      nominal
 5,000                                                capacity

      0
                 Available Capacity    Peak demand

SOURCE: National Control
                                               17
5 May 2015 Stage 1 load shedding was implemented
during evening peak due to a 2180MW shortfall

 Available capacity vs peak demand for 5 May 2015                       Key Insights
                                                                        •   Installed capacity is 43500MW
 MW                                              Planned
                                                 Available              •   Peak demand for Tuesday 5
                                       Available maintenance
                                                  This resulted
                                                 capacity      isin a
                                                          during
 45,000                    43,500                Unplanned                  May 2015 was 32180MW
                                       capacity during
                                                  shortfall
                                                 currently
                                                 peak is at of
                                                 maintenance
                                       peak is 6500MW          is       •   Planned maintenance is
 40,000                                           2180MW
                                                 30200MW
                                       ~30200MW  currently at               currently at 6500MW
                                                 7000MW                 •   Unplanned maintenance is
 35,000                                             32,180                  currently at 7000MW
                                                                        •   To complete sufficient
 30,000
                                                                            maintenance, deficit between
                                       We have                              demand and capacity should
 25,000                                6000MW at
                                                                            not exceed 4500MW
                                       Risk of
 20,000                                Breaking
                                                                        •   Available capacity during peak
                                       down                                 is ~30200MW
 15,000                                                                 •   This resulted in a shortfall of
                                                                            2180MW
 10,000                                                                 •   The shortfall was reduced
                                                                            through the use of Pot lines
   5,000                                                                    (680MW)
                                                                        •   The remaining shortfall of
        0
                                                                            1500MW resulted in stage 1
                  Available Capacity               Peak demand
                                                                            load shedding
SOURCE: National Control
                                                         18
5 May 2015 Stage 1 load shedding was implemented
during evening peak due to a 2180MW shortfall

 Available capacity vs peak demand for 5 May 2015                                  Key Insights

            Planned maintenance is                                                 •   Installed capacity is
 MW         currently at 6500MW                                                        43500MW
                                                                                   •   Peak demand for Tuesday 5
                                       Unplanned maintenance is
                                                                                       May 2015 was 32180MW
 45,000                    43,500      currently at 7000MW
                                                                                   •   Planned maintenance is
                                                                                       currently at 6500MW
 40,000                                         Available capacity during peak     •   Unplanned maintenance is
                                                is ~30200MW                            currently at 7000MW
 35,000                                                 32,180                     •   To complete sufficient
                                                                                       maintenance, deficit between
 30,000                                                                                demand and capacity should
                                                                                       not exceed 4500MW
 25,000                                 We have                        This
                                                                                   •   Available capacity during
                                        6000MW                         resulted
                                                                                       peak is ~30200MW
 20,000                                 at Risk of                     in a
                                                                       shortfall   •   This resulted in a shortfall of
                                        Breaking
                                                                       of              2180MW
 15,000                                 down
                                                                       2180MW      •   The shortfall was reduced
 10,000                                                                                through the use of Pot lines
                                                                                       (680MW)
   5,000                                                                           •   The remaining shortfall of
                                                                                       1500MW resulted in stage 1
        0                                                                              load shedding
                  Available Capacity                 Peak demand

SOURCE: National Control                                                                                             19
The strategy is to do maintenance without load
  shedding

 Available capacity vs peak demand

 MW
45,000                 43,500

40,000
                                      Maintenance Budget < = 9,500
                                                                             Key Insights
35,000
                                                                     1,000
                                                 33,000                         Maintenance Budget < =
30,000                                                                       Available capacity – Daily Peak
                                                                             Demand + Operating Reserves
25,000

20,000

15,000

10,000

 5,000

      0
                 Available Capacity           Peak demand

SOURCE: National Control
                                                       20                                                      20
Eskom needs to prioritise risk maintenance to ensure
sufficient capacity is available for philosophy
maintenance

                        Planned          • Philosophy maintenance
                        maintenance      • Safety maintenance
                                         • Statutory maintenance

     Maintenance
                                         • Risk maintenance
                        Unplanned        • Breakdowns (Total and
                        maintenance       partial load losses)

           Maintenance = Philosophy + safety + statutory + risk + breakdowns

           In the short term, Eskom will prioritise RISK MAINTENANCE in order
                     to reduce the amount of unplanned maintenance

              On average Eskom has a maintenance budget of 9500MW, this is
                           dependent on demand requirements
SOURCE: Generation                                                              11
Contents

 Content

  1. Introduction

  2. Corporate governance

  3. Financial situation

  4. Eliminating Load shedding

                                 22
Thank you

            23
You can also read