Quality Control and Assurance - for Gas Pipeline Construction Carly Voigt - Quality Manager
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Discussion Topics • Why is it important to focus on Quality now? • What exactly is Quality Control and Assurance? • How can I implement it? 2
Why Focus on Quality Now? • When: September, 2010 • What: A pipeline explosion killed 8 people, injured dozens more, and destroyed 38 homes. The blast left a crater in the ground measuring 167’ long, 26’ wide, and 40’ deep. • Why: Long seam failure of a 30” transmission pipeline • Probable Cause: “…inadequate QA/QC in 1956, which allowed the installation of a substandard and poorly welded pipe section with a visible seam weld flaw that, over time grew to a critical size, causing the pipe to rupture…” 6
Why Focus on Quality Now? Other Causes Other Outside Force Damage Material/Weld/ 8% Equipment Natural Force 8% Failure Damage 4% 35% Incorrect Operation 1% 18% Excavation Damage 26% Corrosion 2013 Gas Transmission Significant Incidents (By Cause ) 9
Why Focus on Quality Now? Topic Frequency Coating 117 Welding 87 Excavation 20 Nondestructive Testing 20 Pipe material 12 Bending 9 Lowering In 7 Hydrotesting 4 Design 3 Other 8 10
Why Focus on Quality Now? • Reduce re-work • Minimize delays • Increase productivity • Increase customer satisfaction Quality Work --> Increased Profit 12
What exactly is Quality Control and Assurance? 13
What is QC/QA? • Not this…. – “We have a great Quality Control program. We have Craft Inspectors onsite every day during construction.” – “Wow, I heard about all those construction Quality issues discovered by PHMSA inspectors, but luckily that kind of stuff never happens on our jobs…Our guys know better than that.” – “We’ve been doing it this way for generations, so it must be right.” 14
What is Quality Control? A set of processes designed to confirm that a product meets all requirements Define the acceptance criteria to meet/exceed those requirements Measure to determine whether it meets/exceeds the requirements 15
What is Quality Assurance? A review and modification of QC processes to ensure their effectiveness Confirming QC results on a sampling basis Performing Root Cause Analysis Best Practice identification & sharing (copy exact) Implementing process changes if needed 16
Case Study – Field Applied Epoxy Coatings 17
How can I implement QC/QA? 18
How Can I Implement QC/QA? Step 1: Determine your most critical work activities 19
List of Key Quality Issues 3 1. Material Defects 6 High 2. Lowering-In 3. Welding 5 7 4. Surface Prep 11 10 FREQUENCY 5. Pipeline coating 6. Strength Testing 2 9 7. Underground separation 4 8. Compaction 12 9. As-built Documentation Low 13 10. Non Non-Destructive 1 Testing (NDT) 8 11. Excavation 12. Shipping Damage 13. Pipe Drying Low CONSEQUENCE High 20
How Can I Implement QC/QA? Step 2: Define and document the process to determine acceptance for each of those activities 21
Step 2: Quality Control Plan 1.1.2: Quality Control Process for Welding References: PG&E construction drawings; PG&E Gas Standards: D-22, "Arc Welding Procedure Requirements for All Stress Levels"; D-30.2, "Arc Welder Qualification for Working on Pipelines that Operate at Over 20% of SMYS"; D-30, "Welder Qualification for Under 20% of SMYS"; and D-40, "Weld Inspection"; and the approved Weld Procedures Item Documentation Acceptance No: Quality Control Activity: Frequency: (As Required): Qualifications: Criteria: Tools Required: D.) Visual Inspection of Welds: All transmission Complete 1.2.1 Completed Weld meets Flashlight, Perform a visual inspection of welds pipeline welds (100%) "Quality Control - Daily visual inspection requirements GAL V-Wac as defined by PG&E Gas Standard D-40. are to be visually Field Weld Summary training (OQ 10- in API 1104 for undercut gage, inspected by qualified Report" for each weld. 02). cap height, GAL Cambridge individuals. misalignment, gage, root gap, and GAL Fillet weld undercut. gages, Flexible rule E.) Radiographic Inspection of Welds: Per PG&E Standard D-40 All Radiographic ACCP Level II Contract NDT Per PG&E Confirm Radiographic Inspection of or construction Inspection Reports and Certification or Inspector Specification welds is being performed in drawings, whichever is the original films are to better 4793 accordance with PG&E Gas standard D- more stringent. be provided to the 40, or per construction drawings, Foreman or Weld whichever is more stringent. Inspector. F.) Magnetic Particle Inspection of Welds: Per PG&E Standard D-40 All Magnetic Particle ACCP Level II Contract NDT Per PG&E Confirm Magnetic Particle Inspection or construction Inspection Reports to Certification or Inspector Specification of welds is being performed in drawings, whichever is be provided to the better 4793 accordance with PG&E Gas Standard D- more stringent. Also as Foreman or Weld 40, or per construction drawings, requested by the Inspector. whichever is more stringent. Pipeline Engineer. 22
How Can I Implement QC/QA? Step 3: Measure and provide feedback to correct non- conformances (Perform QC) 23
Step 3: Perform QC 24
How Can I Implement QC/QA? Step 4: Sample the results from step 3 (Perform QA) 25
Step 4: Perform QA 26
How Can I Implement QC/QA? Step 5: Determine root causes of quality issues, implement corrective actions, and share solutions across the organization 27
Step 5: Root Cause Analysis Methods Manpower Environment Welding Long Shifts/ Procedure worker fatigue Wind/Rain Heat Inputs Unqualified Personnel Ambient Temps High Travel Speed Adequate Lighting frequency of Lack of QC rejected girth weld x-rays Wall thickness Lincoln vs. Miller Xray Technique Rod ovens Source Selection Improper bevel Interpretation of Out-of-roundness Use of Clamps Code Req’mts Materials Machines Measurement 28
How Can I Implement QC/QA? Key Elements of a Quality Management System (QMS) High Quality Assurance Process Maturity Quality Control Craft Inspection Leadership Communication & Support Qualification & Training Low Policies & Standards Low Confidence of Quality High 29
Summary • The pipeline industry needs to continue to improve construction quality - we can’t keep doing the same thing and expect different results • With more pipelines being constructed than ever before, implementing a comprehensive quality program can mitigate risks, increase profits, and help ensure the integrity of our nation’s pipelines for many years to come “I know it’s a hell of a challenge, but ask yourselves, if not us, who, if not now, when?” -- President Ronald Reagan (1981) 30
Thank You Any Questions? Contact Info: Carly Voigt carlyvoigt@gtsinc.us (925) 478-8530 ext. 115 31
You can also read