Implementation of Production System Design in House Building Projects: a Lean Journey in Chile Karina Barth - Ph.D. Candidate Marcus Sterzi - MSc Carlos Formoso - PhD Juan Ignácio Alliende - Eng Daniela Bertín - Eng Jorge Del Rio - Eng
Agents involved • Largest real estate group in Chile. • Both development and construction. • High degree of repetitiveness in its residential building projects. • More than a 100 projects in progress and sells more than 3,000 units per year. • The company is promoting a major Lean • Research center in transformation process. the University. • Co-Responsible • Lean consultancy company for the Lean • Responsible for the Lean Implementation Implementation Program Program. 2
Production System Design (PSD) in Construction • PSD translates the production strategy into a set of decisions, which establishes a structure to manage different activities, and creates conditions for control and improvement (Ballard et al. 2001a; Schramm et al. 2006). • PSD consists of developing operation and process design in alignment with (Ballard et al. 2007): • product design, • the allocation of resources, and • the structure of supply chains, • design-for-assembly efforts. • PSD involves a set of interconnected decisions, considering the need to improve the production system as a whole (Schramm et al. 2004). • PSD can potentialize the benefits of the LPS, allowing the early identification of a larger range of problems (Frandson et al. 2015). 3
Aim of the study • This paper reports the experience of a construction company that has implemented PSD and the LPS over 3 years, as part of an ongoing Lean implementation program. • Contributions of this paper: • the definition of the scope and potential benefits of PSD • the proposition of a set of practices that can be used along the PSD stages, with emphasis on location-based planning and control 4
Implementation Process and Results PHASE 01 PHASE 02 PHASE 03 Assessment of existing situation Development and initial testing Implementation of PSD and – 2017 of the Production Management LPS – 2018/19 System – 2017/18 2 PROJECTS 3 PILOT PROJECTS 5 IMPLEMENTATION PROJECTS - Construction sites visits for assessing - Training course on Lean Construction - Implementation of LPS planning and control system: Evaluation protocol - Implementation of PSD (emphasis on - Implementation of PSD model - Participation in planning sessions, location-based planning and control) - Evaluation of results, refinement interviews and analysis of the - Implementation of LPS and standardization company’s Lean Supporting Group: consultants and Company did system not haveforaplanning andand systematic - Evaluation of the benefits of the - Evaluation of the benefits of PSD control company members. Workshop organized by the LSGroup to explicit PSD. implementation and proposition of through indicators: LPS metrics, New decision category included to identify and disseminate batch adherence control,the benefits rhythm Lack of understanding of Lean concepts. PSD model emphasize layout and logistics planning. of implementing deviation, and cycle timePSD. variance Large amount of WIP (based on Batch Standardized control tools: cycle time, Proposition of a PSD Guidebook. Completeness Index and Heatmaps). takt time, WIP and synchronization. 5
PSD Company Model 4. Definition of 5. Layout and 1. Analysis and 2. Definition of the execution logistics 3. Definition 7. Identification definition of resources and strategy planning of workflows and design of construction estimation of critical sequence production capacity 6. Definition of processes workflows (whole project) Base-unit 8. PSD review 6
PSD Company Model: Decision Categories 1. Analysis and definition of construction sequence (base-unit) 2. Definition of resources and estimation of production capacity (base-unit) 03. Masonry 01. Foundations 02. Structure 04. Roof Structure 05. Roof 06. Facade Cladding and Plumbing 07. Drywall / Electric 12. Bath and 08. Windows 09. Doors 10. Flooring 11. Painting Systems Kitchen Artefacts 7
PSD Company Model 4. Definition of 5. Layout and 1. Analysis and 2. Definition of the execution logistics 3. Definition 7. Identification definition of resources and strategy planning of workflows and design of construction estimation of critical sequence production capacity 6. Definition of processes workflows (whole project) Base-unit 8. PSD review 8
PSD Company Model 4. Definition of 5. Layout and 1. Analysis and 2. Definition of the execution logistics 3. Definition 7. Identification definition of resources and strategy planning of workflows and design of construction estimation of critical sequence production capacity 6. Definition of processes workflows (whole project) Base-unit 8. PSD review 9
PSD Company Model: Decision Categories 4. Definition of the execution strategy 3rd stage 2nd stage 1st stage 4th stage Execution path of critical processes not Work areas ("small projects”) and included in BU: Facades 10 execution path of BU processes
PSD Company Model: Decision Categories 5. Layout and logistics planning 11
PSD Company Model: Decision Categories 6. Definition of workflows (whole project) LOB PATAGUAS V PRELIMINAR 17.06.2020 ago-2020 set-2020 out-2020 nov-2020 dez-2020 jan-2021 fev-2021 mar-2021 abr-2021 mai-2021 jun-2021 jul-2021 ago-2021 set-2021 out-2021 PISO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Line of Balance SEMAN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 LEYENDA 3/8 10/8 17/8 24/8 31/8 7/9 14/9 21/9 28/9 5/10 12/10 19/10 26/10 2/11 9/11 16/11 23/11 30/11 7/12 14/12 21/12 28/12 4/1 11/1 18/1 25/1 1/2 8/2 15/2 22/2 1/3 8/3 15/3 22/3 29/3 5/4 12/4 19/4 26/4 3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7 2/8 9/8 16/8 23/8 30/8 6/9 13/9 20/9 CADA UNA DE LAS ACTIVIDADES DE 2I 1° 2° LOS LOCALES COMERCIALES INICIA RADIER with Wagon TERMINANDO LOS PAREOS CORRESPONDIENTES 2H 1° 2° MACHONES System 2G 1° 2° CORONACIÓN ESTRUCTURA TECHUMBRE 2F 1° 2° CUBIERTA ESTUCO EXTERIOR 2E 1° 2° ALERO Y FRONTON YESO 1° Y 2° PISO 2D 1° 2° INST. ESCALA CIELO FALSO 2C 1° 2° TABIQUE IMPERMEABILIZACIÓN/TINA 2B 1° 2° VENTANAS INSTALACION PUERTAS 2A 1° 2° CERAMICA CARPITERÍA DE TERMINACIÓN 1I 1° 2° REMATE DE YESO APAREJO 1H 1° 2° Post delivery PINTURA 1 MANO MUEBLES COCINA Y CLOSET 1G 1° 2° activities ARTEFACTO SANITARIO QUINCALLERIA 1F 1° 2° GRANO EXTERIOR ALFOMBRA 1 1E 1° 2° REJA METALICA Y BAJADAS DE ALL EMPAREJAMENTO PATIO FINO/ PASTELONES 1D 1° 2° ENTREGA INTERNA ENTREGA INMOBILIARIA (2° MANO PINTURA EXTERIOR - 2° MANO PINTURA INTERIOR - ACCESORIOS - GRIFERIA) 1C 1° 2° 1B 1° 2° ENTREGA ENTREGA CARPETA CARPETA BLOQUE N° 1 BLOQUE N° 2 1A 1° 2° 1st delivery 2nd delivery 12 SEMANA 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 DIA INICIO MES 3/8 10/8 Buffer = 1 week ago-2020 1 17/8 24/8 31/8 7/9 2 set-2020 14/9 21/9 28/9 5/10 out-2020 3 12/10 19/10 26/10 2/11 nov-2020 4 9/11 16/11 Buffer = 1 week 23/11 30/11 5 dez-2020 7/12 14/12 21/12 28/12 jan-2021 6 4/1 11/1 18/1 7 fev-2021 25/1 31/1 7/2 14/2 8 mar-2021 21/2 28/2 7/3 14/3 abr-2021 9 21/3 28/3 4/4 11/4 10 mai-2021 18/4 25/4 2/5 9/5 16/5 11 jun-2021 23/5 30/5 6/6 13/6 12 jul-2021 20/6 27/6 5/7 12/7 13 ago-2021 19/7 26/7 2/8 9/8 14 set-2021 16/8 23/8 30/8 6/9 15 out-2021 13/9 20/9 Total dias de actividades 199,0 193,0 273,0 345,0 446,0 418,0 474,0 855,0 stage 705,0 659,0 stage 732,0 495,0 399,0 406,0 117,0
PSD Company Model 4. Definition of 5. Layout and 1. Analysis and 2. Definition of the execution logistics 3. Definition 7. Identification definition of resources and strategy planning of workflows and design of construction estimation of critical sequence production capacity 6. Definition of processes workflows (whole project) Base-unit 8. PSD review 13
PSD Company Model 4. Definition of 5. Layout and 1. Analysis and 2. Definition of the execution logistics 3. Definition 7. Identification definition of resources and strategy planning of workflows and design of construction estimation of critical sequence production capacity 6. Definition of processes workflows (whole project) Base-unit 8. PSD review 14
Benefits of Implementing PSD • Formalizing and making explicit planning decisions: Key decisions on the design of the production system were made with the participation of main stakeholders • Reduction in uncertainty: PSD helps identifying production system limitations and critical processes. Examples of PSD meetings 15
Benefits of Implementing PSD • Improving planning accuracy: considering multiple alternatives of construction systems and subsystems • Facilitating the adoption of cycle time and takt time control: provides information in a systematic way Planed Executed Planed Executed
Benefits of Implementing PSD • Increasing engagement of stakeholders • Improving production stability Evolution of PPC Sequence and WIP control
Conclusions Proposed PSD model X Previous studies: • It was tested and implemented on several residential projects in a systematic way • Provides more emphasis on location-based planning and control, layout and logistics studies during pre-construction stages • Advances in terms of cycle time, takt time, WIP and synchronization analysis before construction • Generates information concerning the production system as a whole • Produces a set of standardized tools to be used to monitor the implementation of PSD Data have been collected by the research team and, in the near future, the main results achieved will be systematically reported. 18
THANK YOU! Karina Barth – karina@ldconsulting.com.br Marcus Sterzi - marcus@ldconsulting.com.br