Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS

Page created by Patrick Griffith
 
CONTINUE READING
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
Presentation to Portfolio
Committee on Energy
15 March 2011

Eskom Holdings Ltd
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
Update of Eskom’s
Capital Expansion
Programme
Paul O’Flaherty
Finance Director

                    2
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
1. Business overview

2. South Africa requirements and the capital expansion programme

3. Alignment with SA macro-economic principles

4. Costs and funding

5. Conclusion

                                                                   3
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
Eskom at a glance

 •     Strategic 100% state-owned electricity utility, strongly                                                               Eskom power grid(1)
       supported by the government

 •     Vertically integrated across generation, transmission and
       distribution

 •     Supplies approximately 95% of South Africa’s electricity
       (45% of the total electricity consumed in Africa)

 •     40 887 employees as at 31 December 2010

 •     Serves 3 000 industrial, 1 000 mining, 48 000 commercial,
       84 000 agricultural and more than 4 million residential
       customers

 •     27 (including 1 nuclear) operational power stations with a                                            Existing grid system                   Thermal power station
                                                                                                             Possible future grid system            Future interconnection substation
       net maximum capacity of 40.87GW as at 31 March 2010                                                   Future hydroelectric power station     Nuclear power station
                                                                                                             Future thermal power station           Future gas station
                                                                                                             Hydroelectric power station            Gas power station
 •     Total electricity sales of 218 591GWh and total revenues of                                           Interconnection substation             Town
       R71.21bn for the year ended 31 March 2010 (R71,6bn for 9
       months ended 31 December 2010)                                                                      Eskom’s net capacity mix – 31 March 2010
                                                                                                                                        Total: 40.87GW
 •     Infrastructure includes 390,338km of power lines and
       cables (all voltages) as at 31 March 2010

 •     Committed to build 17GW new generation capacity
       expected by 31 March 2018. This includes 5,032MW
       already commissioned as at 31 December 2010

(1)   The map indicates the South African power network and interconnections with neighbouring countries

                                                                                                                                                                                        4
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
Generation

•   Operates Eskom’s generation plants                                                               Key figures
•   27 power stations: 13 coal, 4 gas / liquid fuel turbines,
                                                                                                          Financial Year 2009   Financial Year 2010
    6 hydro electric, 2 pump storage, 1 nuclear and 1
    wind
                                                                Net Capacity (MW)                                  40,506                40,870
•   Total net capacity of 40,870MW as at 31 March 2010          Capacity from Coal (MW)                            34,294                34,658
                                                                   Coal Share in Total Capacity                     84.7%                 84.8%
    •   Approximately 85% of net capacity is coal-fired
                                                                Capacity from Nuclear (MW)                          1,800                 1,800

•   Koeberg nuclear power plant                                    Nuclear Share in Total Capacity                   4.4%                  4.4%
                                                                Total Output (TWh)                                    229                   233
    •   1 800MW net capacity                                    Production from Coal (TWh)                            212                   216
                                                                   Coal Share in Total Output                       92.6%                 92.8%
    •   12 806GWh electricity produced from nuclear in          Production from Nuclear (TWh)                         13.0                  12.8
        year ended 31 March 2010                                   Nuclear Share in Total Output                     5.7%                  5.5%
•   17 000MW of new capacity plans committed
    expected by 31 March 2018 (including already
    commissioned since 2005)                                                                      Reserve margins
•   10 896MW of new capacity to come from three
    projects
    •   Medupi: 4 764MW coal-fired; first unit expected                    15% international norm
                                                                             and Eskom target
        to be commissioned in 2012
    •   Kusile: 4 800MW coal-fired; first unit expected to
        be commissioned in 2014
    •   Ingula: 1 332MW pumped storage; expected to
        be commissioned in 2014
•   Reserve margin of 15,1% for the nine months to31
    December 2010, up from 5,6% as at 31 March 2008
    and above international norms and Eskom’s target of
    15%
•   No load shedding since April 2008                                                                                                                 5
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
Transmission and Distribution

•   Total electricity sales of 218,591GWh and more
                                                                                  Key Figures – 31 March 2010
    than 4,46 million customers (including transmission
                                                                                        2010 Gross Electricity
    customers) as at 31 March 2010                               2010 Sales Split           Revenue Split                   Customers
                                                                Total: 218,591GWh          Total: R69,942m               Total: 4.46 million
•   Directly provides electricity to 45% of all end users
    in South Africa

•   Country split into six regional distribution areas

•   Two main types of customers:

    •   Redistributors: Mainly municipalities that sell
        electricity to residential customers. Eskom bills
        the municipality; the municipalities are
        responsible for billing and collecting their own
        tariffs

    •   Direct customers: Industrial, commercial,
        mining, agricultural and residential consumers
                                                                                        Energy Losses

•   Key Sales and Customer Service unit (‘KSACS’)                                                                                 NERSA 2010
    deals with customers using more than 100GWh of                                                2008           2009    2010       Target

    energy per year
                                                            Distribution losses                    5.47%         5.46%    5.87%
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
1. Business overview

2. South Africa requirements and the capital expansion programme

3. Alignment with SA macro-economic principles

4. Costs and Funding

5. Conclusion

                                                                   7
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
IRP 2010 – balanced scenario

                               8
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
The future

 • South Africa needs to create ~40 800MW of new electricity capacity by
   2030 – more than doubling the current requirements

    • This assumes decommissioning of 10 000MW of existing capacity

 • There will be two periods in the next 20 years when the risk of supply
   interruptions significantly increases in South Africa

    • from 2011-2013, and then again …

    • from 2018-2024

 • South Africa needs to take urgent action in 2010 in order to ensure
   security of supply for the country for the next 20 years

                                                                      9
Presentation to Portfolio Committee on Energy - Eskom Holdings Ltd 15 March 2011 - Amazon AWS
Eskom Capital Expansion Programme – began in
2005
                                                                                      Mpumalanga
 Return-to-service (RTS)            New Baseload            Peaking & Renewables     Refurbishment             Transmission

     „ Komati                       „ Medupi                   „ Ankerlig            „ Arnot                   „ 765 KV projects

     „ Camden                       „ Kusile                   „ Gourikwa                                      „ Central projects

     „ Grootvlei                                               „ Ingula                                        „ Northern projects

                                                               „ Sere                                          „ Cape projects

         3,720MW                        9,564MW                   3,516MW               300MW                     4,000km

            Commissions of new stations

                           First Unit              Last Unit                              „    17,000MW of new capacity
                                                                                               (5,032MW commissioned )
Medupi                       2012                    2016
Kusile                       2014                    2018                                 „    4,000km of required transmission
Ingula                       2014                    2014                                      network (3,103km commissioned)

                Medupi is the first coal-generating plant in Africa to use supercritical power generation technology

                                                                                                                                    10
Progress to date (as at 31 December 2010)

    •   To date, a large amount of construction work has been completed, adding ~5,031.8 MW,
                  ~3,103.40 km of transmission network, and ~15,670 sub-stations . . .
Megawatts
                 MW of capacity                                                          125
                                                                                452.5
                                                                   1,769.9
                                                       1,042.6                                    5,031.8
                                           1,351.8
                           0       290

Transmission
                                                                                        278.80
                 Km line                                                     600.30
                                                                 418.30
                                                      480
                                           430                                                    3,103.40
                                 237
                    659

Substations
                                                                                         3,940
                                                                               1,630
                 MVAs                                              1,375
                                                       1,355
                                           1,000
                    5,280        1,090
                                                                                                  15,670

                  FY           FY        FY          FY          FY          FY         FY        Total
                  2004/5       2005/6    2006/7      2007/8      2008/9      2009/10    2010/11
                                                                                                             11
Of the new capacity being installed, baseload coal-fired power stations
account for 73%, while the peaking portfolio (OCGT, pumped storage,
wind) will contribute the remaining 27%

    Of the coal-fired power stations, all but
           Medupi are located in the
     Mpumalanga province. Medupi is in
        Lephalale (Limpopo province).                                       Medupi

                                                                                      Kusile

                                                                                       Arnot
                  Peaking                                                 Komati

                                                                          Grootvlei         Camden

                                                                                   Ingula
                  New coal

                  Return To Service             Sere

                                                Ankerlig
                                                           Gourikwa

                  Capacity upgrade

                                                                                               12
Key Transmission projects

                                Medupi
                                integration

                                                            East Grid
                                                            765kV

                                              Ingula
                                              integration

                     Cape
                     corridor

                                 Southern
                                 Grid
                                 765kV

     13                                                                 13
While there is quite some progress already, there is a lot
more construction work to be done in this programme

                The main technical KPIs are on track. . .
                                                            Installed to date
                                                            Not yet installed

                                              29%                         MW

                             MW installed     ~5,031.8     ~12,188.5

                                                         ~17 220.3

                                              78%                         Km

                            Transmission
                                                    ~3,103.4         ~896.6
                            lines installed

                                                          ~4 000
                                              76%                      MVAs

                             Substation          ~15,670           ~4,930
                             projects

                                                          ~20 600
                                                                                14
Focus is now on Medupi, Kusile, and Ingula - the first units
will come on line between 2012 and 2014

        Construction activities                                 1st unit commissioned                              Fully commissioned
        started                                                 December 2012                                      Mid 2016

2006      2007            2008         2009      2010   2011             2012           2013          2014           2015           2016             2017          2018

                                                                                                 Fully
  Construction              Construction                                 1st Unit commissioned   commissioned                                                Fully commissioned
                                                                                                                                             Fully commissioned
                                                                                                                 1st unit commissioned
                                                                         January 2014
  activities started        activities started                                                   September 2014
                                                                                                             October 207
                                                                                                                 December    2014            October 2017 December     2018
                                                                                                                                                             October 207

       •Medupi Power Station                                   Kusile Power Station                                         Ingula Power Station

       •Execution partner:                                      Execution partner:                                          Road works

       •Coal supply                                             Coal supply                                                 Civil works

       •Boiler                                                  Boiler

       •Turbine                                                 Main Civils

       •Enabling Civils                                                                                                     Infrastructure
                                                                Turbine                                                                            B&E Quanza

       •Main Civils                                             Enabling Civils

                                                                                                                            Dam construction       Concor
                                                                                                                                                   -Silver -WBHO
                                                                                                                                                           Rock
       •Generator transformers                                  Generator transformers                                                             Edwin

                                                                                                                                                                           15
Build programme overview
            Medupi                                    Kusile                                   Ingula
Project Summary                          Project Summary                          Project Summary
► Greenfields Project – Lephalale        ► Greenfields Project – Delmas           ► Greenfields Project – Ladysmith
  (Limpopo Province)                       (Mpumalanga Province)                    (KwaZulu Natal Province)
► 6 Unit Coal Fired Power Station        ► 6 Unit Coal Fired Power Station        ► 4 Unit pumped storage power
                                                                                    station
► Planned capacity 4,764MW               ► Planned capacity 4,800MW
                                                                                  ► Planned capacity 1,352MW

Financial & Economic Impact              Financial & Economic Impact              Financial & Economic Impact

► Projected   project cost  to           ► Projected project cost to completion   ► Projected   project cost  to
  completion ~R98.900 bn (excl.            ~R121,000 bn (excl. IDC)                 completion ~R21.377 bn (excl.
  IDC)                                                                              IDC)
                                         ► Estimated 25% impact on Delmas
► Estimated    95%   impact         on     town GDP                               ► Estimated    7%   impact      on
  Lephalale town GDP                                                                Ladysmith town GDP
Project Schedule                            Project Schedule                      Project Schedule
► Construction commenced March           ► Construction commenced Mid 2008
  2007                                                                            ► Construction   commenced      Mid
                                         ► First Unit    planned   to        be     2006
► First Unit   planned   to  be            commissioned December 2014
  commissioned December 2012                                                      ► First Unit   planned    to        be
                                         ► Subsequent Units 2 & 3 at 12 month       commissioned January 2014
► Subsequent Units at 6 to 9 month         intervals and Units 4, 5 & 6 at 8
  intervals thereafter                                                            ► Subsequent Units at 3 month
                                           months thereafter
                                                                                    intervals thereafter
► Last    Unit       planned     for     ► Last     Unit       planned    for
  commissioning    late 2015,   mid                                               ► Last    Unit    planned     for
                                           commissioning     during December
  2016                                                                              commissioning during September
                                           2018
                                                                                    2014

                                                                                                                 16
Build programme overview

        Return to Service                              Transmission                          Mpumalanga & Other

   Projects Summary                          Project Summary                               Projects Summary - Mpumalanga
► Refurbishment and return to service of     ► Transformers – 20 600 MVAs:               ► Major refurbishments of existing and
  previously moth-balled coal fired               •765kv (Planned: 12,000 MVAs)            operational power stations, i.e.
  power stations in Mpumalanga.                                                            Duvha, Matla & Kriel.
                                                  •Cape Grid (Planned: 1,500 MVAs)
    - Camden (8 units – total 1,600MW)                                                   ► Arnot capacity increase (300MW).
                                                  •Northern Grid (Planned: 3,500 MVAs)
    - Komati (9 units – 1,000MW)                                                         ► Majuba Rail infrastructure for coal
                                                  •Central Grid (Planned: 3,600 MVAs)      supply for the operational Majuba
    - Grootvlei (6 units – 1,200MW)
                                             ► Transmission Lines – 3,977.5 Km:            Power Station. CO planned for August
                                                                                           2014.
   Financial & Economic Impact                    •765kv (Planned:1,689.9 km)
                                                                                         ► Camden Rail infrastructure for coal
► Projected RTS cost to completion                •Northern Grid (Planned: 1,253.6 km)     supply for the operation Camden
  ~R23.477 bn (excl. IDC)                                                                  power station.
                                                  •Cape Grid (Planned: 621 km)
   Project Schedule                               •Central Grid (Planned: 413 km)        ► Tutuka Brine Project        to   reduce
► All 8 units at Camden power plant are                                                    amount of brine in water.
  now in commercial operation                Financial & Economic Impact                 ► Projected Mpumalanga Projects cost
► 3 units, each rated at 125MW, have         ► Projected Transmission cost to              to completion ~ R12.950 bn (excl.
  been commissioned at Komati power            completion ~R27.800 bn (excl. IDC)          IDC)
  station. Last unit (unit 1) planned for                                                  Other Projects (not part of original)
                                             Project Schedule
  handover May 2012.                         (Projected completion dates)                ► 100 MW Greenfields pilot Wind Farm
► 4 units, each rated at 200MW (total        ► 765kv: December 2013                        (Sere) project on the West Coast. CO
  800MW) have been commissioned at                                                         planned for October 2013.
  Grootvlei. Last unit (unit 6) planned to   ► Northern Grid: June 2015
                                                                                         ► 100 MW Concentrated Solar Power
  be completed end March 2011                ► Central Grid: Mar 2015                      (CSP) pilot plant project. CO planned
                                             ► Cape Grid: Aug 2016                         for December 2015.

                                                                                                                            17
Kusile and Medupi will be the third and fourth largest coal-
fired power plant in the world, respectively,…

 Higher than Sandton                                                           4x more investment than
 City Towers                                                                   Gautrain

                                              Coal-fired power plants (MW)
                                             1▪ Taichung (Taiwan, 7 1001)
                                             2▪ Waigaoqiao (China, 5 000)
                                             3▪ Kusile (South Africa, 4 800)
                                                                                  4x
                                             4▪ Medupi (South Africa, 4 764)
                                     ~113m

                                             5▪ Zouxian (China, 4 540)
                                             6▪ Kendal (South Africa, 4 374)
                                             7▪ …
                                             8▪ …

                                                                                             Medupi

        18existing + 1 600 planned
1 = 5 500                                                                                         18
…requiring huge amounts of materials and large
transport effort in their construction
             Characteristics of Medupi/ Kusile

             ▪ … to build 4 Greenpoint stadiums will be
Concrete…      used per plant

Parts and    ▪ …weighing the same as 14 super tankers
cement…        will be transported over land

             ▪ …to build one of the world’s tallest
Steel…         buildings (The Burj Khalifa) will be used

             ▪ …of materials to site is equivalent to at least 40
Transport…     times around the world

                                                                    19
1. Business overview

2. South Africa requirements and the capital expansion programme

3. Alignment with SA macro-economic principles

4. Costs and funding

5. Conclusion

                                                                   20
As such, the programme will have significant impact on local
     industry, skills, jobs, infrastructure and regional development

1                                  2Local skills                  3                         4                      5Regional
 Local content                       development                  Jobs                      Infrastructure          development
 >50% of local content
                                     Rapid growth in SA’s         ~40 000 jobs created,     Development of roads    Spend and invest-
 directly benefiting the             skills pool                                                                    ment in local areas
                                                                  directly and indirectly   and railways
 SA economy

1 Based on GDP in 2008

SOURCE: Eskom Enterprises division and Medupi project, STATS-SA                                                                      21
A large share of the Medupi, Kusile and Ingula spend will go
    to the local economy, thereby also benefitting local
    construction companies
%
               Composition of
               total project                       Examples from Medupi, Kusile, and Ingula
               spend
                                                   Main civils
                                                                               Main civils (MPS-JV):
Medupi                42%            58%                                       84% of contract (~2,5bn) are
                      Foreign        Local
                                                                               spent locally

                                                   Main civils
                                                                               Main civils (KCW-JV):
Kusile                            56%                                          65% of contract (~2,9bn) are
                       44%        Local
                       Foreign
                                                                               spent locally

                                                   Access roads package
                        26%
Ingula                 Foreign                                                 Main civils (Grinaker-LTA):
                                                                               100% of contract (~0,3bn)
                                 74%
                             Local                                             are spent locally

SOURCE: Medupi, Kusile, and Ingula project management                                                  22
Many skills are being developed as local content
   requirements kick-start whole new industries in SA

    New fabrication and training facilities   90% of major orders placed
    established                               on Mechanical equipment
                                                         Equipment           Local content
   ▪ Brand new fabrication facility built     Air Cooled Condenser (ACC)
      in Nigel                                                                  >90%
      – Boiler Membrane Wall Workshop         Major pumps                       >55%
      – Two new CNC Benders commissioned      Heaters                           >45%
      – New welding training centre
      – CNC header drilling machine           LP outer casing Unit 6            100%

                                              Feedwater tank                    >80%
   ▪ Training facilities in Pretoria and in
      Wadeville                               Heaters Drain recovery pumps      >20%

SOURCE: Medupi project management                                                       23
The programme will fuel demand for relevant graduates and
     artisans and will grow the wide required skill base

  Medupi would …

        … consume 43% of a year’s relevant
        university graduation (engine-
        ering, project planning, etc.)

        … deploy 48% of a year’s output
        of artisans

        … rapidly grow South Africa’s supply
        of engineers, artisans, R&D and
        project management experts

        … develop a wide range of additional
        skills through ASGI-SA commitments

SOURCE: Eskom Enterprises division and Medupi project            24
Across Medupi, Kusile, and Ingula new employment
          opportunities will touch the lives of ~160 000 people

                                                         Medupi    Kusile   Ingula
          DIRECT
           On site construction                           8 300     7 200   4 100
           Supporting project staff                       2 200     2 000     300
           Coal mine expansion                            2 100     2 000
           Transmission expansion                         2 700      200
           Crocodile River expansion                      3 000
           Ongoing operations                               700       600     100

           Subtotal                                     ~19 000   ~12 000   ~4 500

          INDIRECT
           Social services +                             1 700      1 700   1 100
           local business
           Total employed                               20 700     13 700   5 600
           x family multiplier                           x4
           (4/family)

           People directly impacted                        ~160 000                  Other projects such as 765kV and
                                                                                               RTS provide
           by Medupi, Kusile & Ingula                                                   ~ 11 000 direct employment
                                                                                     opportunities during construction
                                                                                        and a further ~1 700 during
                                                                                                 operation

SOURCE: Eskom Enterprises division and Medupi project                                                                    25
Medupi, Kusile and Ingula will support local and
     national infrastructure
                                                        Area of impact                       Example
  National infrastructure                                                                     Richards Bay to Lephalale and Lephalale bypass 22 km of new
                                                                 Roads
                                                                                              roads reinforcing of 3 bridges: >R500bn, 500 jobs

                                                                 Ongoing roads maintenance    Maintenance of local access roads: > R100m p.a.

                                                                 Freight forwarding           Richards Bay facility: R90m, 150 jobs

                                                                                              3 x 38 wagon train per day for limestone, 2 x 12 tank carriers per
                                                                 Trains
                                                                                              year of oil maintenance or rail lines: 100 jobs

  Local infrastructure                                           Catering and workforce       Food, laundry, maintenance security supplied to workforce:
                                                                 supply                       >R2bn, 1 000 jobs

                                                                 Hotels                       Hotels to expand significantly

                                                                 Local transport              Additional buses at peak, increased taxis: ~500 jobs

                                                                 Vehicle maintenance          1 000+ extra vehicles maintained locally: 50 jobs

                                                                                              3 300 houses and accommodation units to be built by Eskom and
                                                                 Housing
                                                                                              suppliers: ~R4bn

                                                                 Water                        Benefit from Crocodile River diversion pipeline from Kendal

                                                                 Sanitation                   Sewerage plant upgrade: R50m

                                                                                              7 schools impacted, increased policing, recruitment centre, fire,
                                                                 Social facilities
                                                                                              social club, ICT centre. Ongoing work with stakeholder forums

SOURCE: Eskom Enterprises division and Medupi project                                                                                                             26
5 Each project will measurably impact the local towns through
      local spend & investment

     Impact on local town’s
     GDP from each project

     Lephalale (Medupi)                  95%

     Delmas (Kusile)                     25%
                                                                                 Other businesses and
     Ladysmith (Ingula)                   1%                                     infrastructure created:
                                                                                 • Catering
                                                                                 • Laundry
                                                                                 • Building companies
     Typical local businesses and infrastructure created
                                                                                 • House maintenance
                                                                                 • Hotels
                                                                                 • Entertainment
                                                                                 • Training facilities
                                                                                 • Security
       Shops                                              Civil infrastructure   • Schools / education
                                                                                 • Policing
                                                                                 • Churches
                                                                                 • Medical care
                                                                                 • Banks & financial
                                                                                   services

       Schools                                    Transport

SOURCE: Eskom Enterprises division and Medupi project                                                      27
1. Business overview

2. South Africa requirements and the capital expansion programme

3. Alignment with SA macro-economic principles

4. Costs and funding

5. Conclusion

                                                                   28
Significant progress in build programme

                         R billion spent and to be spent
                         (excluding borrowing costs capitalised)
                         % completion as at 31 December 2010
                17.7%
                121.2
     38.6%
     98,9

                                                         52.5%
                              33.1%        88.8%
                                                         27.4
                                           23.5
                              21.4

                                                                16,3
                        5,2     6,6

                                                                23,7
                                                                       29
Strong Government support

 „ The Government, through the Department of Public Enterprises, is the sole shareholder and after consulting
   with the Board appoints the Chairman, the Chief Executive and Non-Executive Directors

 „ The Government recognizes Eskom’s critical role in the economy and remains committed to ensuring Eskom’s
   financial stability

 „ To ensure Eskom has the financial resources necessary to deliver on its R550bn(1) capital expenditure up until
   the 2017 financial year, the Government has committed R430bn financial support to Eskom:

           ƒ In 2008 Government committed a subordinated R60bn loan to Eskom. R55bn disbursed so far with the
             balance by 31 March 2011

           ƒ In 2009 Government approved R176bn of debt guarantees to be used over 5 years. R117bn utilised as at
             30 September 2010

                    ƒ Under the guarantee, the rights of Government are subordinated to all other unsecured and
                      unsubordinated creditors of Eskom, including the holders of the proposed Note issuance

           ƒ In October 2010, Government announced that it would extend its guarantees for Eskom by a further
             R174bn to a total of R350bn

           ƒ In November 2010, Government announced a proposal for an additional equity recapitalisation of R20bn
             (subject to internal Government approval) into Eskom to help it fund its capital expenditure.

(1)   In 2005 Eskom embarked on a R340bn capital expansion programme that is planned to achieve additional capacity of 17GW by 31 March 2018

                                                                                                                                               30
Funding plan
•    Eskom’s funding plan has been finalised with the Department of Public Enterprises, Department of Energy and National Treasury
•    R300bn total funding requirement over the next seven years (from 1 April 2010); including R550 billion of capital expenditure of
     which R250 billion relates to the completion of the capacity expansion programme (total cost R340billion)
•    R300bn funding secured or identified as at 30 September 2010
         •   R160bn to come from bond and commercial paper markets
         •   R95bn from development finance institutions and export credit agencies
         •   R40bn from the government (R20 billion loan and proposed R20bn equity recapitalisation)
         •   R5bn from other sources
•    Government guarantee facility increased to R350bn (R174bn increase)
•    S&P and Moody’s have reaffirmed Eskom’s investment grade ratings under this funding plan and removed the negative watch

                                   Eskom’s expected and assumed 7-year funding plan
ZAR bn

                             Eskom secured or identified R300bn of funding over the next seven years
                                                                                                                                        31
1. Business overview

2. South Africa requirements and the capital expansion programme

3. Alignment with SA macro-economic principles

4. Costs and funding

5. Conclusion

                                                                   32
Expansion programme challenges - since inception

The market

The market within which Eskom is operating is extremely tight, with significant demands
on supplier capacity and basic commodities being a feature since 2005

Contracting and risk sharing

New thinking on contracting and risk sharing has become essential based on the
following:
•Global demand for new plant is high
•The supplier market is global and limited
•Supplier market experiencing shortages of material, components and engineering
capacity
•Fixed price or construction commitments cannot be secured
•Increased demand for power plants leading to significant escalation in prices
•Seller’s market, not a buyer’s market
•Contract and risk-sharing profiles fundamentally changed

Timeline

Given the reserve margin, the Eskom programme is working with very tight timelines
                                                                                          33
Expansion programme challenges - since inception

Funding

Eskom clearly finds itself in a very challenging funding environment. Until October 2010, Eskom did
not have a full funding plan to complete the capacity expansion programme

Safety

Despite the importance of executing projects on a tight schedule and within a tight budget, it is
Eskom’s firm belief that safety is the most important objective of all. The inherent risky nature of major
construction activities requires constant management and leadership

Skills development

•The build programme is used to contribute to skills development and facilitate manufacturing
capability in South Africa
•Skills remain a significant factor for Eskom. The competition for skills is fierce, both internationally
and locally

Local communities

The new build impact on local communities is massive – housing, education, safety, health services
and social impacts

                                                                                                             34
In conclusion, since 2005 until today

  •   The new build programme is significant by any measure. Cost increases are understood and taken
      into account, lessons have been learnt and implemented for future projects and across existing
      projects.

  •   Good progress has been made, but many serious risks will need to be carefully managed in the
      future. Strong mitigating measures have been put in place to manage these risks.

  •   The global financial crisis has affected all sectors of the economy, Eskom included. This led to a
      review of the build program taking into account:

       •   Financial contractions of the markets,

       •   Resultant re-prioritisation of certain capacity projects and

       •   Delaying the execution of some of the projects at certain times since 2005; full go ahead on
           Kusile was given in October 2010

  •   Macro-economic factors have negatively impacted the build programme:

                   • CPA, and

                   • Cost of cover and other market forces

                                                                                                       35
State of the Power
System – Current
Situation and Future
Prognosis
Kannan Lakmeeharan
Divisional Director: System Operations and Planning

                                                      36
Table of contents

Introduction

Reflecting on what we said

What Eskom is doing

What SA can do to help

Conclusion

                             37
Introduction
 We have said 2011-2012 will be tight. Now 2011 is here.

                 •   The supply-demand margin will remain slim for the next 5 - 6 years and in particular the next 2 years.
 Overview        •   Peak gap in 2012 equivalent to 9TWh – supply to Cape Town for a year.
                 •   Plan in place that requires all stakeholders and citizens to work together to keep the lights on.

                 •   Support from Government will ensure Eskom’s new build programme is completed.
                 •   Procurement of 1 025MW renewable generation in the next 3 years.
Supply-side      •   Signing up co-generation and municipal generation on short to medium-term contracts (minimum of
                     600MW).
 Initiatives
                 •   Eskom will improve its plant performance over the next 3 years.
                 •   Create an enabling framework to support own generation options.

                 •   Support Government’s million solar water geyser rollout programme by 2012.
                 •   Eskom will execute its planned demand-side management programme and aim to accelerate it by 25%
Demand-side          over the next 6 years.
 Initiatives     •   Eskom will aim to contract incentivised demand response from its customer base.
                 •   Call to voluntarily save 10% across the customer base through campaigns.

                 •   Need “safety nets” as last resort to prevent disruptive load shedding.
                 •   Energy Conservation scheme enables mandatory savings from largest 500 customers.
 Safety nets     •   Demand response programmes aimed at smaller customers to respond to price and system signals.
                 •   Running Eskom’s open cycle gas turbines harder

                 •   Switch off if you are not using it.
                 •   Respond to the Power Alert messages on TV and other campaigns by Government and Eskom.
Call to action
                 •   We can meet our resolve to never load shed again if we all work together. It is good for our economy and
                     for our environment

                                                                                                                              38
Keeping the lights on: the next seven years

The system will be constrained
  Annual energy gap for 2010 to 2017 under base case outlook, TWh shortfall

                                                                             9 TWh is equivalent
                                                                             to ~1000 MW
                                                                             baseload capacity

         2010               11               12                13               14                15    16   2017

Assumptions
Eskom estimate of the IRP2010 moderate load forecast (~260 TWh in 2010);
New build (e.g., Medupi, Kusile, Ingula) and RTS at current dates; REFIT as per IRP1 (1GW by FY2018);
DSM as per base plan (3.9 GW by FY2018); Planned maintenance allocation39    increased to ±10%                      39
Ensuring security of supply in the next 3 years

• Eskom’s generation plant performance and new build programme
    • Ensure critical plant maintenance is done to ensure sustainable plant performance.
    • Target to improve generation output by between 1% and 2%.

• Energy efficiency initiatives
    • Eskom will need to execute its 4TWh demand-side management programme and do
      more with its funding and internal energy efficiency programme (target is 1 billion kWh).
    • Enabling the 1 million solar water geyser programme run by Government.

• Own and co-generation
    • Sign up about 400MW of co-generation and own generation by April 2011.
    • Procurement process for 1 025MW of renewable energy technologies, to be
      commissioned in the next 3 to 4 years, should start as soon as possible. Eskom is
      ready to connect and pay the IPPs.
    • Investigating mechanisms with NERSA and Government to ensure already
      commissioned municipality generators produce and further co-generation options are
      secured.
    • Working with industry and NERSA to finalise a grid access framework to enable
      wheeling and own generation.
                                                                                            40
Putting a safety net in place
A “safety net” is required in case further risks materialise, which would consist of:
1.Energy Conservation Scheme
    • Mandatory and aimed at the largest 500 electricity users
    • Will provide certainty of demand (for at least 7 years from those customers
       that consume between 50% and 60% of the electricity)
    • Will send strong signals to move to energy efficiency
    • Imposes mandatory savings targets rather than disruptive load shedding.
2.Demand response initiatives
    • Incentive-based demand response programme in place already for our
       largest customers; achieves about 500MW.
    • Imminent placement of contract with aggregator to obtain nearly 500MW
       from the larger commercial and smaller industrial customers. This can be
       ramped up to 2 000MW in the next 3 to 6 years.
    • Investigation into technologies for residential demand response completed.
3.Open cycle gas turbine use
    • The OCGTs in South Africa will have to be run at higher load factors
       incurring significant cost.

                                                                                        41
SA can prevent load shedding by working together

 • There are risks to the successful execution of some of the initiatives identified.
 • In the next two years, there is an energy gap and therefore an immediate focus
   is needed on implementing the identified actions and establishing a “safety net”
 • This can only be done through a national effort involving all stakeholders and
   the people of South Africa
 • Eskom will play its part in leading and partnering

                 Energy gap after all the “safety nets” and “levers”
                    10
                     5
                     0
                     ‐5
                    ‐10
                    ‐15
                    ‐20
                    ‐25
                    ‐30
                    ‐35
                    ‐40
                          2011   2012   2013         2014     2015   2016   2017

                                        Worst case      Best Case
                                                                                   42
What is Eskom doing currently?
•   Plant performance: Creating maintenance windows and targeting improved plant
    performance of 1 to 2% in the next 3 years.
•   Engaging with stakeholders: Eskom will update stakeholders and the country on a
    quarterly basis over the next two years. Management is fully focused on keeping the lights
    on and will monitor the state of the system on a daily basis and take action.
•   Tackling the coal challenges: Eskom’s coal stockpile levels are healthy (over 40
    days). The focus has shifted to improving the coal quality and coal handling at the power
    stations. Steps taken have already resulted in improvements in the last 2 months. This is
    still a significant challenge.
•   Signing up non-Eskom generation:
    •    Eskom has signed up 373MW through the medium term power purchase programme
         and aims to sign 376 MW by April 2011.
    •    Eskom is supporting certain municipalities to run their generation plant. 410 MW has
         been signed up and 260 MW have been operational in the last month.
•   Integrated Demand Management:
    •    Eskom is aggressively rolling out its demand management programme to achieve at
         least 1000MW over the next 3 years and will work on accelerating the programme to
         achieve 25% more.
    •    Eskom will aim to achieve 1billion kWh in savings through improved plant efficiency
         and energy efficiency initiatives in its operations over the next six years
                                                                                                43
What can SA do to help?

• In the next two years, there is an energy gap and therefore an immediate focus
  is needed on energy efficiency

• This can only be done through a national effort involving all stakeholders and
  the people of South Africa

• A voluntary, incentive-based demand response programme is in place for our
  largest customers

• If needed, a mandatory Energy Conservation scheme aimed at the largest 500
  customers may be implemented

• Eskom will play its part in leading and partnering

                                                                                   44
Good for the environment and good for
 the economy
• A 10% saving in consumption
  could save up to 20 million tons
  of CO2 emissions per annum.

• The demand forecast caters for
  the projected growth in GDP
  output and therefore any
  improvement in energy efficiency
  provides an increased reserve to
  support this growth.                Compared to other countries
                                      with a similar per capita GDP
• Energy efficiency enables            (15% variance), SA is more
                                     electricity intensive by a factor
  customers to save money and
                                                 of 30-85%
  assists in shifting to a more        This includes countries like
  competitive economy.               Argentina & Botswana. This is
                                        influenced by the current
                                        structure of the economy
                                                                         45
Energy intensity - based on
World Energy Outlook 2010 new policy projections
                                                                                                    Energy intensity for selected countries and regions
  toe per thousand Intl. dollars of PPP GDP (IMF 2010)

                                                         1.2

                                                                                                                                                             South Africa has a higher
                                                         1.0
                                                                                                                                                              energy intensity as well                                                               Brazil
                                                                                                                                                          compared to the BRIC countries
                                                                                                                                                          and Africa and higher the world                                                            Russia

                                                         0.8
                                                                                                                                                           average. This is influenced by
                                                                                                                                                            the current structure of the                                                             India
                                                                                                                                                                     economy.
                                                                                                                                                                                                                                                     China
                                                         0.6

                                                                                                                                                                                                                                                     South Africa

                                                         0.4
                                                                                                                                                                                                                                                     Africa

                                                         0.2                                                                                                                                                                                         World

                                                         0.0
                                                               1990

                                                                      1991

                                                                             1992

                                                                                    1993

                                                                                           1994

                                                                                                  1995

                                                                                                         1996

                                                                                                                1997

                                                                                                                       1998

                                                                                                                              1999

                                                                                                                                     2000

                                                                                                                                            2001

                                                                                                                                                   2002

                                                                                                                                                          2003

                                                                                                                                                                 2004

                                                                                                                                                                        2005

                                                                                                                                                                               2006

                                                                                                                                                                                      2007

                                                                                                                                                                                             2008

                                                                                                                                                                                                    2009

                                                                                                                                                                                                           2010

                                                                                                                                                                                                                  2011

                                                                                                                                                                                                                         2012

                                                                                                                                                                                                                                2013

                                                                                                                                                                                                                                       2014

                                                                                                                                                                                                                                              2015
                                                                 Source: 1) Calculations based on IMF World Economic Outlook, BP Energy Statistics and IEA World Energy Outlook 2010 policy projections.
                                                                         2) South Africa projection based on trend growth for period 2005 ‐ 2009 since IEA WEO 2010 does not provide policy projection.

                                                                                                                                                                                                                                                                    46
Action needed from households

•    “If you’re not using it, switch it off.”
•    Geyser: Switch off geysers between 06:00 and 22:00, reduce thermostat to 60
     degrees, insulate geyser and water pipes and replace geysers with solar water
     heaters using Eskom’s rebate programme
•    Lighting: Replace incandescent light bulbs with energy savers, and switch off lights
     in unoccupied rooms
•    Bathing: Shower rather than bath as less hot water is used, and install an energy
     efficient shower head
•    Climate control:
      •   Minimise use of air conditioners by first opening windows to allow cool air to
          circulate
      •   When using an air-conditioner keep the temperature setting between 18 – 22
          degrees C
      •   Insulate ceilings to keep home cool in summer and warm in winter
•    Pool pumps: Reduce the operating time to limit water circulation to twice a day and
     set the pool pump to operate between 24:00 and 05:00
•    Vampire appliance usage - Don’t leave appliances in standby mode. Unplug
     cellphone charger
•    Participate in the Power Alert programme on national TV (SABC and etv)
                                                                                            47
Action needed from commercial offices

•   “If you’re not using it, switch it off.”

•   Standby electricity: At the end of the day, don’t leave your computer, copier, printers and
    fax machines on standby mode

•   Lighting:
     •   Replace inefficient systems - Eskom incentives available
     •   Motion sensors for meeting rooms and security lighting,
     •   Reduce lighting levels in parking areas to the minimum legal
         requirement during the day, and turn it off at night after the building lights have been turned off

•   Climate control:
     •   Replace inefficient systems - Eskom incentives available
     •   Maintain a difference of not more than 10 degrees Celsius between inside and outside a building,
     •   Extraction fans can be turned on at around 04:00 to draw cold outside air through the building to
         cool down the structure,
     •   Close window blinds to shade your rooms from direct sunlight, allow your workers to wear light,
         comfortable clothing during hot weather.
•   Appoint an Energy Manager for each building to monitor usage and identify savings
    opportunities
                                                                                                               48
Action needed from industry

• Electricity usage optimisation needs to be driven by top management
• Participate in a voluntary 10% energy reduction programme – some SA
  companies have already reduced by 10%
• Identify opportunities for improved energy utilisation
    • Process optimisation
    • Technology improvements
    • Shift usage to off-peak periods
• Participate in Eskom’s demand saving programme
    • Incentives available for energy savings projects
    • Approval lead times improved considerably
• Participation in Demand Market Participation Programme
    • Incentives for hourly load reduction when constrained system
      conditions prevail

                                                                        49
National Power Alert Impacts – Evening Peak
Impacts

           Power Alert impact during the World Cup period (11
                         June to 11 July 2010)
                                                 Average MW saved
                                                 Worst day MW impact
         1800
         1600
         1400
         1200
         1000
    MW

          800
          600
          400
          200
            0
                                       1

   Worst day indicates the highest daily savings on a red alert. The
 energy savings during the World Cup in terms of the public reacting to
  Power Alert on national television is showing that working together,
                South Africans can make a difference
                                                                       50
Reserve Margin – based on the draft IRP2010

      35
           %
                                            Reserve Margin
      30

      25

      20

      15

      10
                                       Total Capacity
      5                                Total Reliable Capacity
      0
               0   1   2   3   4   5    6   7   8   9   0   1    2   3   4   5   6   7   8   9   0
               1   1   1   1   1   1    1   1   1   1   2   2    2   2   2   2   2   2   2   2   3
               0   0   0   0   0   0    0   0   0   0   0   0    0   0   0   0   0   0   0   0   0
               2   2   2   2   2   2    2   2   2   2   2   2    2   2   2   2   2   2   2   2   2

   The draft
         NoteIntegrated
               to Kannan:Resource
                          Does not Plan  (IRP)
                                   include     aimsand
                                            Co-gen    to Own
                                                         keepbuild
                                                                the reliable
      reserve   margin
         from 2011     closeRemember
                    – 2015.  to or above   15% Ifrom
                                        Medupi         2013
                                                  1 year lateronwards.
                                                               than
           mtrm and Kusile 2 years.

                                                                                                     51
Reserve Margin – Not further Expansion after
current commitments

    30
         %           Reserve Margin ‐ No Expansion after
                                Committed
    25
                                                               The reliable reserve margin
    20
                                                               goes below 15% after 2018
    15

    10
                                     Total Capacity
     5
                                     Total Reliable Capacity
     0
             0   1   2   3   4   5    6   7   8   9   0   1    2   3   4   5   6   7   8   9   0
             1   1   1   1   1   1    1   1   1   1   2   2    2   2   2   2   2   2   2   2   3
             0   0   0   0   0   0    0   0   0   0   0   0    0   0   0   0   0   0   0   0   0
             2   2   2   2   2   2    2   2   2   2   2   2    2   2   2   2   2   2   2   2   2

   It is important
             Note tothe decisions
                     Kannan: Same are made this
                                  as previous     yearallonnon
                                              but with      capacity to build
             after 2018 tocommitted
                            ensure security  of supply after 2018
                                     taken out

                                                                                                   52
Conclusion

• The supply/demand balance will
  be tight for the period 2011-2013
• The summer of 2011 has seen
  risks to the system increase
• Eskom is on alert and its
  leadership is taking action to
  keep the lights on
• We cannot do it alone – we seek
  to partner with stakeholders
• We will communicate with our
  stakeholders and the public
  every quarter on the state of the
  system

                                      53
49M Campaign
Chose Choeu
Divisional Executive: Corporate Affairs

                                          54
49M is an Eskom initiative,
   supported by government,
spurring an urgent need for the
  more than 49 million South
  Africans to embrace energy
 saving as a national culture,
   joining the global journey
 towards a sustainable future

                                  55
The value proposition

49M desires a better future for all South
Africans

•economically,
•socially and
•environmentally

49M asks that we look for a sustainable future
and a better tomorrow for all

Energy efficiency is not only       a   national
concern, it is a global concern.

                                               56
By saving, South Africans will be
      contributing to ensuring continued
            economic growth by taking the
     pressure off the ‘grid’, while Eskom
       builds the power stations to ensure
electricity sustainability for the future of all South
                                              Africans

                                                    57
Thank you
You can also read