Network Innovation Annual Summary 2017/2018 - Electricity Transmission

Page created by Craig Flores
 
CONTINUE READING
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Network Innovation
               Annual Summary
               2017/2018

Electricity
Transmission
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Contents
3 Introduction      15–16 Project
                    portfolio
4–5 Altering our
DNA and investing   17–19 Our Network
in the future       Innovation
6 Working with      Competition Project
partners            – Deeside

7 Out and about     20–21 Project
                    updates
8–13 Updates on
key projects        22–23 Reference
                    tables
14 Shaping up to
meet the future     24 Appendix
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Welcome to the
                                   innovation annual
                                   summary for 2017/18
                                   As an engineer, I have grown up                 Looking towards the immediate future, at
                                   understanding the true value of innovation      Deeside we are converting an existing
                                   to society, and have seen how major             400kV substation into a facility for testing
                                   innovations change the way we live and          and evaluating solutions without putting
                                   do business. Whether it’s been the              the customer supply at risk. The site gives
                                   creation of the iPad in 2010, or SpaceX         us and other organisations a place to trial
                                   landing a first-stage rocket on an ocean-       technologies and new practices. And it
                                   going drone ship in 2016, innovation done       means we can support the start-up
                                   properly transforms people’s lives. My          community and help small to medium
                                   vision for our customers is not to drive        enterprises succeed in an increasingly
                                   incremental change through our                  competitive market. Deeside, the first of its
                                   innovation programme, but to change             kind in Europe, saw us securing £12m in
                                   electrical transmission networks for the        funding from Ofgem in 2015 and putting
                                   good of society. Our research is driven by      £14m of our own money in. Projects we
                                   the belief that one day we will change the      have started at the facility this year
“Innovation is                     very idea of how we interact with a             include trialing a retrofit for cable sealing
                                   transmission network and what it can do         ends, non-invasive tower foundation
one of the pillars                 for our world.                                  inspections and zip-up scaffolding
raising National                                                                   solutions that offer time-efficiency savings
Grid’s performance,                How do we make that new vision of the
                                                                                   and improved safety for access to
                                                                                   high-level asset components. You can
helping us shape the               future network a reality? We begin by           read more about these projects and their
energy markets for                 solving the engineering problems of today.
                                   For example, we have delivered the
                                                                                   status from page 20.
the future.”                       world’s first 400kV gas insulated electricity
                                   substation that uses an alternative gas to      With the rise of autonomous, electric
David Wright
Director
                                   SF6. We are also looking at materials that      vehicles and distributed battery storage
Electricity Transmission           extend the lifetime of our assets (see page     technologies we need to take a flexible,
Group Chief Electricity Engineer   eight), investigating methods to reduce the     evolutionary approach to delivering the
                                   amount of work we carry out on sites and        electricity transmission network in the
                                   investigating technologies to deliver cost      coming decades. Flexibility and evolution
                                   efficiencies. Then there are research           can only come from working with the
                                   projects that continue to increase safety       broader engineering community and
                                   for both workers and the public, and            understanding the whole picture. So, we
                                   reduce the outage time of networks, like        not only look to our own people to embed
                                   the portable earthing vehicles that can be      innovation into our everyday practices; we
                                   quickly deployed to our sites.                  engage with external experts who can
                                                                                   help us make a difference for customers
                                                                                   and end-consumers. On page six you can
                                   During the 2017/18 period, we’ve invested       read about our partners and the research
                                   over £4.6m into projects through the            we are doing with business and academia.
                                   Network Innovation Allowance (NIA)
                                   funding mechanism. Our innovation
                                   projects involved more than 85 people           Innovation has always been in the DNA of
                                   working on NIA, NIC and Totex projects.         National Grid and over the next few pages
                                   That’s over 14,000 hours on NIA and NIC         I’m proud to share the work that we have
                                   projects and a total of more than 15,660        been doing to continue that tradition. The
                                   hours on Totex projects from world-class        future starts here.
                                   researchers and engineers. These hours
                                   have contributed towards making sure we
                                   have the right people working on the 49         David Wright
                                   projects that were underway at the end of       Director
                                   April 2018. We can also ensure we               Electricity Transmission
                                   successfully and effectively implement the      Group Chief Electricity Engineer
                                   output of those projects we have closed
                                   off. During that 2017/18 period, these
                                   totalled 34.

03   ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Innovation

                                 Altering our DNA and investing in the future

“Gas Insulated Lines             Innovation is in our DNA and as such, we are
(GIL) provide greater            continuously reshaping ourselves for the rapidly
flexibility to meet              changing energy landscape.
demands, such as
the increasing desire
for underground                  This landscape is seeing an increasing          our industry thinks about decarbonisation
                                 amount of renewable energy sources              and sustainability.
power transmission               come online and transformational changes
lines, especially in             to the transport and energy infrastructure.
                                 This is also reflected in an increased
                                                                                 This year we have also increased our
                                                                                 engagement with our stakeholders and
areas of outstanding             demand from household and commercial            suppliers, at both national and international
natural beauty                   consumers to match the fast-paced digital       level, because the future energy network
                                 world they live in and the drive for reduced    will also be impacted by what happens
like national parks              carbon emissions. It has become obvious         outside our area of influence. This has led
or highly densely                that the transmission network needs to          us to develop a new strategy where we
                                 reflect that demand.                            focus our research efforts within value
populated areas                                                                  themes, so we ensure our spending creates
like cities. The                 Our approach has been to broaden our            value for customers.
                                 portfolio of innovative projects and reshape
potential deployment             our business and innovation processes
of enhanced GIL                  to be agile enough to explore a wide
                                 range of solutions to drive costs down. All
solutions is viewed              while continuing to identify new ways and
by both National                 technologies to improve the environmental
                                 and safety benefits of our work.
Grid and Siemens
as a potential game              Over the past year, we’ve invested £4.6m into
                                 49 NIA projects. But growing our business
changer in the global            means we must look beyond the NIA and
transmission sector.”            NIC funding frameworks and invest our own
                                 money to develop long-term solutions.
Matthias Müller
Director                         One example has been our investment
Power Transmission Lines
Siemens                          of £20m into a £40m initiative to research      Official signing of the GIL Innovation
                                 and develop the use of Gas Insulated            Partnership January 2018. Clockwise from top
                                 Lines (GIL), as well as new gases with          left: Carl Ennis, Managing Director, Energy
                                 global warming potential of less than ten,      Management Division, Siemens; Simon Harnett,
                                 for transmission purposes as part of the        Head of UK Procurement, National Grid; David
                                 first European Innovation Partnership with      Wright, Director ETO, National Grid; and Miko
                                 Siemens. It is also an example of how we        Düsel, Chief Executive Officer of Business Unit
                                 are playing our part in transforming the way    Transmission Solutions, Siemens.

04   ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Innovation

                                 Innovation consumer value themes

                                 The best way of ensuring we have an aligned
                                 and broad portfolio of research is to channel it
                                 through four customer value themes. These are:
                                 managing assets, efficient build, service delivery
                                 and corporate responsibility.

                                 Managing assets                      Efficient build
                                 £3.44m                               £1.34m
                                 spend in 2017/18                     spend in 2017/18
                                 We’re constantly looking for ways    We’re continuing to reduce the
                                 to increase the lifespan of our      cost of building new infrastructure.
                                 assets. During the 2017/18 period,   Examples of where we’ve invested
                                 we spent £3.44m understanding        the £1.34m during the 2017/18
                                 what can be done to increase         period include trialling new
                                 their lifespan and performance.      materials and products, finding
                                 The more we know, the better we      equipment that can be used more
                                 can maintain assets at the lowest    flexibly, and improving the design
                                 cost and with the least amount of    of the network.
                                 disruption to our customers.

                                                                      Corporate
                                 Service delivery                     responsibility
                                 £0.24m                               £0.84m
                                 spend in 2017/18                     spend in 2017/18
                                 As the transmission network
                                                                      Researching and developing safer
                                 changes, we find new ways to
                                                                      working practices is a critical
                                 provide value to our customers
                                                                      element of delivering network
                                 and consumers. The 2017/18
                                                                      reliability. Our investment of £0.84m
                                 investment of £0.24m has helped
                                                                      in corporate responsibility projects
                                 our understanding of present
                                                                      in 2017/18 included looking at
                                 and future expectations, so we
                                                                      the entire build and maintenance
                                 can develop the right products
                                                                      process. This helped to find safe,
                                 and services.
                                                                      efficient scaffolding-erection
                                                                      techniques, and reduce noise
                                                                      pollution on urban substations.

05   ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Partnerships

                                 Working with partners
“Working with the                Any modern business that wants to deliver the
academic partners                best value to its customers must put collaboration
allows National Grid             at the front of its strategy. This is why we, at
to leverage their
innovation funds,                National Grid Electricity Transmission (NGET)
providing additional             have been building partnerships with the best
benefit to the                   people in the engineering community.
industry and
our consumers.”
                                 Collaboration widens our perspective of the       We believe that a proactively managed
Ian Cotton                       industry, increases our knowledge and at the      portfolio of projects at different technology
Professor of High                same time means we can share our                  readiness levels is key to deliver sustainable
Voltage Technology               experiences and insights with the rest of the     innovation. We want to keep the work flow full
The University of Manchester     engineering community. It also guarantees         of new ideas; they are the basis for
                                 we are aligned to deliver the best value for      innovation. Universities are key in this area,
                                 consumers and stakeholders.                       both from the point of developing new ideas
“Our long-standing                                                                 and providing state-of-the-art facilities. We
partnership has                  Recent examples of collaborations include         currently have three strategic academic
                                 the development of an alternative to SF6,         partners: The University of Manchester,
meant technical                  known as Green Gas for Grid (g3) with GE          Cardiff University and the University of
and skill sharing                Grid Solutions. This led to the delivery of the
                                 first 400kV electricity system with an SF6
                                                                                   Southampton. We also have projects running
                                                                                   with 17 other academic institutions across
with National Grid;              alternative. From the success of the work, we     the UK. In the coming year, we are looking at
including highly                 came to realise there are several other
                                 potential alternatives to SF6 and have been
                                                                                   increasing our strategic relationships both
                                                                                   nationally and internationally.
trained students                 collaborating with 3M, Siemens and both
and staff, mitigation            Cardiff University and The University of          The £40m Innovation Partnership with
                                 Manchester. You can find out more about           Siemens to research and use Gas Insulated
of safety voltages,              our research and testing of alternative           Lines (GIL) on the electricity transmission
and trials of                    insulating gases on page 10.                      network has, to date, allowed us to develop a
                                                                                   new way of collaboratively working with our
alternative gases                                                                  international partners to drive the industry
to replace SF6.”                     We want to develop an
                                                                                   forward. We will be looking at rolling out this
                                                                                   co-creation initiative further with both
Manu Haddad                          alternative to SF6 with a Global              suppliers and customers in the near future.
Director                             Warming Potential (GWP) of less
Advanced High Voltage                than ten. The GWP scale, or ratio,            Our collaboration extends to our involvement
Engineering Research Centre                                                        with initiatives across the UK. One of these is
Cardiff University                   was developed for comparing
                                     the global warming impacts of                 FLEXIS, a £24.5m Welsh university (Cardiff,
                                                                                   Swansea and USW), industry and local
                                     different gases, where Carbon                 government partnership researching the
                                     dioxide (CO2) is used as the                  decarbonisation of energy systems. Hywel
                                     reference gas with a GWP set                  Thomas, FLEXIS Lead Principal Investigator,
                                     equal to one. GWP values allow                said: “Given the importance of National Grid
                                     us to compare the impact of                   in the electrical energy sector, we highly
                                     emissions and reductions of                   value our partnership in the areas of
                                                                                   environmentally-friendly electrical power
                                     different gases.
                                                                                   plants and insulation, liquid soil and smart
                                                                                   geogrids. We’re very grateful to have Dr Iliana
                                                                                   Portugues, Head of Innovation, on our
                                                                                   Advisory Board. Her influence is important in
                                                                                   directing our future demonstrator work.”

06   ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
Strategic

     Conferences                    Out and about
     Euro TechCon 2017
     (November):                    As you read in the previous section, we           Our colleagues regularly attend and take
     We attended the 2017           place collaboration and partnerships at           part in conferences, events, and high-profile
     Euro TechCon in Glasgow        the centre of our approach to innovation.         industry meetings across the country and
     during November 2017.          This means we can be open to learning             abroad. While it isn’t always possible to
     We gave a presentation         different ways of thinking and discovering        capture the many informal conversations
     on how the Deeside facility    new points of view. It also allows us to share    and breakout sessions where knowledge
     will accelerate the roll-out   what we learn from our innovation work with       sharing takes place, a review of some of the
     of new technologies            industry and academia and help the                conferences and meetings we have
     and services.                  shaping of our industry.                          attended this year gives an understanding of
                                                                                      where we have been sharing our insights.
     LCNI 2017
     (December):
     The LCNI (Low Carbon
     Networks and Innovation)       Call for proposals
     conference in December
     2017 was, once again,
     a great opportunity to         Gas Insulated Lines                               invite engineers from industry and
     talk to our stakeholders,      innovation partnership                            academia to submit their ideas to be
     explore new opportunities      In early 2017 we launched a procurement           considered for research funding.
     and gain valuable              event in relation to the development,
     feedback on the projects       production and installation of Gas                There were three categories for
     we showcased on our            Insulated Lines, tunnelled, direct or             the submissions:
     stand. The conference          non-direct buried installation and
     was a chance to meet           Replacement Gas using innovative                  • C
                                                                                         hallenge one: cable asset
     and discuss potential          technologies. This bespoke contract                 health indicators.
     collaborations with            combines three elements within one
     network operators,             contract, which helps both us and                 •	Challenge two: transforming civil
     academic institutions,         suppliers to co-invest in high-risk                 infrastructure for all transmission assets.
     suppliers, generators and      innovations with an incentive around their
     manufacturers on future        success. This novel contractual                   • C
                                                                                         hallenge three: solutions to increasing
     innovation projects.           arrangement addresses one of the main               transmission boundary power flows.
                                    concerns we have heard from many of
     Future Networks                our innovation stakeholders who feel the          The judging team received 25
     Conference (April):            barrier for adoption of innovation is high        submissions that went through a review
     In April 2018 we               and difficult to overcome.                        and presentation process and 11 projects
     presented a talk on                                                              were chosen. These have now been
     driving value through          Masters of innovation competition                 funded through the Network Innovation
     innovation at the Future       We launched the Masters of Innovation             Allowance (NIA) scheme and will go
     Networks Conference            competition in 2017 as an open call to            through to the formal sanction process.
     in London.

     Future of Utilities (July):
     In July 2018 we talked
     about the digitalisation           Dissemination events
     of our industry and how
     innovation is shaping the          Novel acoustic attenuation:                   MIDEL 7131:
     future at the Future of            We shared the outcomes of our research        In July 2017 we invited representatives
     Utilities Conference               into reducing noise pollution with internal   from SSE, Energy Networks, WSP, PB
     in London.                         and external stakeholders at Walton Hall      World, M&I Materials, The Environment
                                        in May 2018. Invited guests included          Agency and Siemens to National Grid
                                        Sonobex, SP Energy Networks, WSP,             House. We shared updates and outcomes
                                        Merford and Northern Power Grid.              of our research on the uses of MIDEL 7131
                                                                                      (find out more on page 13).

07    ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
NIA projects

                                   Updates on key projects
                                   In the previous section, we covered the          projects and where our collaborations and
                                   events and conferences where we shared           research have led us. As you will see, the
                                   updates on our projects and invited              research has uncovered a wide range of
                                   engineers to take part in the Masters of         solutions to engineering and environmental
                                   Innovation contest. Over the next few pages      issues that are going to extend the efficient
                                   you can read more about some of those            lifespan and cost-effectiveness of our assets.

     Title:
                                   How advanced materials are improving the
     Feasibility study on the      future of our network
     application of advanced
     materials
     Project reference number:     Faults on our equipment can often result         infrastructure. Potential solutions included
     NIA_NGET0176                  in system downtime while repairs are             using graphene and materials that respond
     Consumer value theme :        carried out. If we want to maximise the life     to their environment or self-heal.
     Efficient Build               and performance of the network, using
                                   advanced materials could significantly           The biggest impact is likely to be seen in
                                   improve reliability and reduce the               the ratings of overhead lines and buried
                                   environmental impact of our assets.              cables, where advanced materials and
                                                                                    processes could increase performance
                                   The first step has been to work with The         by around 40 per cent and 330 per cent
     Innovation                    University of Manchester to review the           respectively. This could meet the increased
     in numbers:                   current research literature. We identified
                                   over 50 potential solutions for improved
                                                                                    demand for electricity as the UK plans to
                                                                                    phase out diesel and petrol vehicles in

     480km
                                   sustainability and network resilience. These     favour of electric vehicles by 2040.
                                   ranged from the need to increase the
                                   ratings of conductors, to new materials for      Over the next 12 months we will be
     of line analysed              monitoring the performance of assets and         selecting the most promising projects to
                                   improved materials for the network’s civil       develop further.

     Title:
                                  Increasing the lifespan for overhead lines
     Novel methodology for
     assessing environmental      This year we completed a research               rate of conductors and fittings. We can
     exposure of OHL routes       programme to extend the life of our             now fine-tune our asset replacement
     Project reference number:    overhead line fittings. We now have             plans and target spending on the assets
     NIA_NGET0206                 a greater understanding of how the              with the highest risk of developing defects
     Consumer value theme :       environment affects our overhead line           and failures. So far, we have analysed
     Managing Assets              spans and how the energy input from             480km of line, reducing our RIIO-T1
                                  wind-induced motion and corrosive               spending by £72m from last year.
                                  compounds increases the deterioration

08    ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
NIA projects

                                                                                     Using bamboo to reduce noise involves
                                                                                     drilling holes in the bamboo. By altering
                                                                                     the radius and length of the hole, the
                                                                                     resonant frequency can be changed.
                                                                                     This allows you to ‘tune’ the bamboo and
                                                                                     reduce the frequency of noise you’re
                                                                                     trying to control.

     Title:
                                      Keeping the noise down for the neighbours
     Novel acoustic attenuation
     feasibility study                Many of our substations are built near         associated with substations, an active noise
     Project reference number:        or right in the heart of communities. To       control system that works on the principle of
     NIA_NGET0203                     understand how we can reduce the impact        phase cancellation and a noise enclosure
     Consumer value theme:
                                      of transformer noise on those communities,     with potential to deploy quickly that uses
     Efficient Build                  we commissioned a report on novel,             fewer resources than current options.
                                      cost-effective and practical solutions. We
                                      selected three options from the report to      We are now working with the researchers
                                      install and test. These were a bamboo noise    and suppliers to develop these for trials at
                                      barrier, tuned to reduce low frequency tones   our substations.

     Title:
                                      First test area complete at Deeside
     Offline Substation Environment
     for the Acceleration of
     Innovative Technologies
                                      Preparation of the Deeside project has         awarded in May 2018. Construction is
     (OSEAIT)
                                      progressed significantly over the past year.   due to finish in April 2019. This important
                                      Design, development and tendering for the      milestone will bring the first operational area
     Project reference number:        overhead line (OHL) test area has been         into service so that project trials can begin.
     NGETEN02
                                      completed with the construction contract       You can read the full report on page 17.

09    ET Annual Summary 2017/18
Network Innovation Annual Summary 2017/2018 - Electricity Transmission
NIA projects

                                   Building our understanding of EMFs
     Title:
     Identify opportunities and
     developments in EMF           As substations continue to become part               polls. The other initiative is membership
     research                      of the built environment, public concerns            of the Electric Power Research Institute’s
     Project reference number:     over the effects of Electrical Magnetic Fields       (EPRI) EMF programme, where our
     NIA_NGET0184                  (EMFs) on health have risen.                         subscription (and that of other companies)
     Consumer value theme:                                                              supports a broad and balanced programme
     Corporate Responsibility      We have been carrying out research to                of research.
                                   address these concerns through two
                                   NIA-funded initiatives. The first was to             We have been investigating and sharing our
                                   increase our knowledge and understanding             unique insights into assessing occupational
                                   of public concerns through a review of               exposure to EMFs with the international
                                   current research literature, engage with             scientific community.
     Innovation                    researchers and carry out public opinion
     in numbers:
     900
     calls to our EMF
     Helpline per year

     20,000
     unique visitors to our
     EMF website
     www.emfs.info
     per month

                                   Replacing SF6 to reduce global impact
     Title:
     SF6 management and
     alternative gases             The unique characteristics of Sulphur               and CO2 could withstand the equivalent
     Project reference number:     hexafluoride (SF6) make it an ideal                 electrical performance that using SF6 in
     NIA_NGET0163                  insulator for use in high-voltage electrical        this configuration would have given.
     Consumer value theme:         applications. This is why it has proven
     Corporate Responsibility      difficult to find a substitute in the 40 years it   We have also been working closely with
                                   has been used in substation equipment.              Cardiff University to investigate the use
                                                                                       of other alternatives to SF6, in switchgear,
                                   The downside is that SF6 is a potent                such as Trifluoroiodomethane. This will
                                   greenhouse gas with a global warming                also further our understanding of the
“In addition to the                impact 23,900 times higher than carbon              long-term behaviour of a variety of new
                                   dioxide. Emissions of SF6 currently make up         gas mixtures that might replace SF6 in
local benefits, the                a large percentage of our carbon footprint.         the switchgear market. To this end, we
SF6 alternatives                                                                       recently started a project for small-scale
project is an                      In the search for a substitute, we have             stability tests of these gases under different
                                   been running a pilot installation of an             operating conditions and in the presence
important step in                  SF6-free, 420kV busbar at Sellindge for             of various materials. Measurement of
finding alternative                the past year. Because of this pilot, our
                                   confidence in this new gas technology has
                                                                                       chemical by-products resulting from, for
                                                                                       example, exposure to electrical arcing
gases which are                    increased. Monitoring and assessment will           will enhance our knowledge of how to
both safer and more                continue, ensuring there are no signs of
                                   long-term deterioration.
                                                                                       manage these solutions in the long-term.
environmentally                                                                        This is a valuable first step towards
friendly.”                         A test rig, consisting of a sample of               replacing SF6 across the network, but
                                   modern 420kV gas insulated busbar,                  considerable effort and investment is
Mark Waldron                       designed for use with pure SF6, was                 still needed to achieve a fully proven,
Switchgear Technical Leader        commissioned at the University of                   retro-fitted solution that suits the unique
                                   Manchester. A programme of tests                    design of many substations.
                                   demonstrated that a mixture of Novec 4710

                                   The trend towards SF6 alternatives looks set to continue in the future, judging by the
                                   increased interest in research from international parties over the past few years. This
                                   has been partly stimulated and accelerated by the commercial availability of Green
                                   Gas for Grid (g3) solutions and pilot projects such as Sellindge.

10     ET Annual Summary 2017/18
NIA projects

     Title:
                                  Portable earthing devices are improving site
     Portable earthing device     efficiency and safety
     Project reference number:
     NIA_NGET0201
     Consumer value theme:        Replacing, repairing or maintaining            merits of several concept designs before
     Managing Assets              electricity substation assets is a complex     the detailed design stage. Following the
                                  process. A key activity is earthing and        manufacture and commissioning (including
                                  de-earthing the high-level busbars. The        stability and full functionality tests) of a
                                  development of the portable earthing           prototype in September 2017, the device
                                  device means our staff can now work            was European Conformity (CE) marked as
                                  more efficiently and safely, which reduces     safe to use.
                                  outage time and delivers much needed
                                  cost-savings to customers.                     Since December 2017 the prototype has
                                                                                 been put through tests at Walpole 400kV
                                  The motorised device will allow engineers      substation and used during many outage
                                  to apply flexible earths to busbars (for all   occasions. This has given us feedback on
                                  voltages) from ground level, reducing the      its performance, strengths and limitations.
                                  amount of manual handling needed, and
                                  providing greater control. This reduces        The next step is to deploy the prototype unit
                                  the risk to workers by removing the need       at more sites for trials and further feedback
                                  to work at height, which comes with other      to improve the design. These improvements
                                  earthing methods.                              will lead to better units being used by us,
                                                                                 bringing the benefits to everyday site work.
                                  At each stage of the project we consulted
                                  with stakeholders, exploring the relative

11    ET Annual Summary 2017/18
NIA projects

                                    Raising the heights of British industry
     Title:
     Cost effective removal of
     conductor crossing clearance   We believe innovation should not only          Traditional solutions to this sort of problem
     constraints                    benefit our own business, but all British      are often expensive and inconvenient. We
     Project reference number:      industry. When we extended the height of       designed a novel, cost-effective solution to
     NIA_NGET0198                   our Tyne river overhead lines we put that      increase the height of the conductors by
     Consumer value theme :
                                    belief into action.                            five metres. This method has been used
     Managing Assets                                                               before on the network but never on two
                                    In 2016, the Newcastle yard of the             adjacent towers and never on a 130m river
                                    Offshore Group, on the banks of the            crossing tower. Our design solution gave
                                    Tyne, was commissioned to build wind           Offshore Group the confidence that they
                                    turbine foundation structures. However,        could deliver the structures and they won
                                    the existing 130m overhead lines across        the contract.
     Innovation                     the Tyne presented a problem. Offshore
     in numbers:                    Group’s yard is upriver of the crossing and
                                    the commissioned structures were taller
                                                                                   Outages and land access were secured at
                                                                                   short notice and we developed new working

     100m
                                    than the height of the line (almost 85m tall   methods. The project was completed in June
                                    in some cases). Before Offshore Group          2017 against a challenging timeline, while still
                                    could guarantee the yard would deliver the     ensuring the safety of everyone involved.
     high                           order, they approached us to find a way to
                                    increase the height of the line.

12    ET Annual Summary 2017/18
NIA projects

                                         VSATT and process bus technology
     Title:
     Digital Substation – virtual site
     acceptance testing & training       As monitoring systems become capable              showed that the performance, stability and
     Project reference number:           of processing and capturing more data,            engineering process met our requirements.
     NIA_NGET0162                        the need to replace traditional copper
     Consumer value theme:
                                         connections with digital ones is becoming         To further test vendor-interoperability of
     Efficient Build                     critical to the future resilience of the          AS3, a follow-up project known as Virtual
                                         transmission network. A digital system            Site Acceptance Testing and Training
                                         with standardised architecture could also         (VSATT) was launched. To test AS3-
                                         improve modelling of supply needs and             based substation systems in an off-grid
                                         asset health, along with improved security.       environment a laboratory was built at The
                                                                                           University of Manchester.
                                         Cost-savings could also be made because
                                         of reduced construction time, integration         The VSATT project started in September
                                         with digital networks and the ability to mix      2015 and ran for two years. We found that
                                         and match the most cost-effective products        integrating solutions from multiple vendors
                                         from a range of vendors.                          is possible, but it requires further work to
                                                                                           ensure the process is seamless. Our results
                                         However, digital connections require              have been shared with suppliers and other
                                         standardised communication architecture.          stakeholders to guide specifications and
                                         So, in 2008 we began developing a                 configuration design.
                                         standardised architecture known as
                                         Architecture of Substation Secondary              Routine use of digital substations is now
                                         Systems (AS3). Working with four different        one step closer, with the first rollout of
                                         suppliers, we installed four digital protection   process bus solutions expected in 2019.
                                         bays in parallel to conventional bays on the
                                         transmission network. These trial installations

          Title:
          Environment Containment
          Solution of MIDEL 7131
          Project reference number:
          NIA_NGET0178
          Consumer value theme:
          Efficient Build

     “In Manchester,
     we are particularly
     proud of the
     Transformer
     Research
     Consortium that
     sees National Grid
     work with a range                   MIDEL transformers
     of partners, and
     has resulted in the
                                         The likely increases in the demand for            design footprint of the substation.
     delivery of three                   electricity from the decarbonisation of
     transformers filled                 transport and heat are bringing their             The result of our research has been the
                                         own unique challenges to modern urban             installation of three MIDEL 7131 (a synthetic
     with a fluid that                   substations. Among them, increasing safety        ester) filled transformers at our Highbury
     is safer and more                   and making the most of the limited space          substation and the sanctioning of two more
                                         available in inner cities.                        at our Willesden site.
     environmentally
     friendly than                       One approach has been our research into           This brings the installation of new and
                                         the use of low fire-hazard, biodegradable         replacement, compact, low fire-hazard
     other oils.”                        and cost-effective liquids (such as synthetic     transformers on tight urban sites a
     Ian Cotton                          esters) in our super grid transformers            step closer to being business as usual.
     Professor of High                   (SGTs). These alternatives to commonly            Meanwhile, we are working with suppliers to
     Voltage Technology                  used mineral oils remove the need to install      ensure that the price difference from using
     The University of Manchester        and maintain extensive fire protection            synthetic ester-filled transformers is low
                                         systems, and consequently reduce the              enough to deliver value for consumers.

13     ET Annual Summary 2017/18
Strategy

                                  Shaping up to meet the future
                                  We are continuously exploring new ways of
                                  working and shaping our business to meet the
                                  challenges of the evolving energy landscape.
                                  This year we developed the Electricity            •	A new Network Innovation Competition
                                  Transmission Innovation Strategy to                 proposal focused on the future energy
                                  enhance this activity by investigating              network.
                                  contemporary ideas to help define and
                                  shape the future of our industry, to anticipate   •	2018’s Masters of Innovation competition.
                                  our customer needs and give them what
                                  they will want. We are introducing new            •	An increased number of stakeholder
                                  programmes in materials research, digital           innovation events to help us further
                                  solutions and electrification of transport at       develop our programme of work.
“Innovation is a                  the forefront of our innovation, and helping
paradox. On the                   organisations who, historically, have not         •	A new programme of work around
                                  been involved with our industry, understand         electrification of transport.
one hand, it can’t be             the commercial opportunities from their
forced or managed                 involvement. Our new strategy looks at how        •	A new programme of work around
                                  to innovate for the near and distant future,        the effective and efficient integration of
in the usual sense,               for the customer and society of today and           energy vectors.
on the other hand,                that of 2060. Alongside our research into
                                  the needs of the present and future markets,      •	Create a programme of work for digital
we have to stimulate              our strategy aims to drive increased and            transformation, focused on setting up
it and create the                 more meaningful partnerships to develop a
                                  clear view of the cutting-edge technologies
                                                                                      the foundation and platforms necessary
                                                                                      that will allow us and our innovation
preconditions for it.”            for the years ahead, working collaboratively        partners to develop novel artificial
                                  to drive them forwards at pace.                     intelligence solutions to improve the way
Iliana Portugues
Head of Innovation                                                                    we do things.
Electricity Transmission          As such, our plan, while looking to lead
                                  new technologies into the marketplace, is         •	Continue to drive innovations in the areas
                                  underpinned by actively managing and                of transmission, both under and above
                                  prioritising customer and stakeholder               ground, developing a strong portfolio of
                                  relationships. The adjacent list, while not         work to drive down costs.
                                  comprehensive, gives a broad flavour of
                                  the work we will be doing to achieve this in      •	Begin a new programme of work to
                                  the coming financial year. If you want to be        deliver targets innovation in conjunction
                                  involved, please drop us an email at box.           with our customers and stakeholders.
                                  ETO.InnovationTeam@nationalgrid.com

                                  The innovation team

                                  This year, our innovation strategy and plan       Institute (EPRI) for her PhD on developing
                                  have evolved to reflect the challenges of         a system for using antennae. Iliana then
                                  the contemporary environment. Equally, we         moved to the University of Strathclyde
                                  have developed and added new people to            as a research fellow, where in 2007 she
                                  the innovation team in the past 12 months         spun out the technology into Elimpus
                                  to meet these challenges.                         Ltd. In 2010, Iliana went to work as a
                                                                                    Sensor Laboratory Manager and Senior
                                  Iliana Portugues heads up Electricity             Project Manager for EPRI, before moving
                                  Transmission Innovation at National Grid,         back to the University of Strathclyde in
                                  and joined the team in 2014.                      2012 as Director of the Power Networks
                                                                                    Demonstration Centre.
                                  Iliana graduated from the University
                                  of Bath with a MEng in Electronic and             If you would like to get in touch to discuss
                                  Communications Engineering, where she             developing an idea for the transmission
                                  also obtained sponsorship from National           network, email box.ETO.InnovationTeam@
                                  Grid and the Electric Power Research              nationalgrid.com

14    ET Annual Summary 2017/18
Project portfolio

Project portfolio
To learn more about the projects, click the title to be taken to the ENA smarter
networks portal or visit: www.smarternetworks.org
Project         Project name                                                                           Partners
reference

NIA_NGET0013    Tablet interface for a SF6 mass flow top-up device                                     DILO Armaturen and Anlagen GmbH

NIA_NGET0015    Dinorwig Thermal Cycling and Cable Rating                                              The University of Southampton, Doble PowerTest

NIA_NGET0102    13kV Shunt Reactor Refurbishment                                                       ABB

NIA_NGET0104    Proof of Concept for IEC61850 Process Bus Technology                                   ABB

NIA_NGET0018    Potentials and profiles around earth electrodes and opposite-side injection for        Cardiff University
                large-area earthing

NIA_NGET0025    Feasibility Study for Sustainable Substation Design                                    Ove Arup and Partners

NIA_NGET0040    Magnetic Models for Transformers                                                       Cardiff University, The University of Manchester

NIA_NGET0043    Live Line Working Equipment                                                            Ashbrook Engineering Ltd, Bond Aviation Group, Bond
                                                                                                       Helicopters Europe, Eurocopter UK, New and Renewable Energy
                                                                                                       Centre, Northern Connectors, Oxford Computer Consultants, P&B
                                                                                                       Weir Electrical, RS Components, The University of Manchester,
                                                                                                       The University of Southampton, Clydesdale Bank, TTI Testing,
                                                                                                       Cunningham Design, T.M. Utley Offshore PLC, Du Monte UK,
                                                                                                       Bridge Engineering UK, Rotary Wing Ltd, Broadcast Media
                                                                                                       Services, Hiatco, John Werrell & Son Ltd, Airbus Helicopters
NIA_NGET0048    Cables with Long Electrical Sections                                                   The University of Southampton, The University of Manchester

NIA_NGET0056    Humber Smartzone Pilot Project                                                         EPRI, Ampacimon, Invisible Systems Ltd, Global
                                                                                                       Substation Solutions, The University of Manchester

NIA_NGET0060    Application of DC circuit-breakers in DC Grids                                         Cardiff University

NIA_NGET0073    Partial discharge monitoring of DC cable (DCPD)                                        The University of Southampton

NIA_NGET0079    Rapid Deployment Ballistic Screens                                                     Access Design & Engineering, RS Components, Photron
                                                                                                       (Europe), Doble PowerTest, C3global, Radnor Range

NIA_NGET0083    Cable Oil Regeneration                                                                 Enervac Corporation, JSM Group, Midlands Truck & Van, Utilise

NIA_NGET0088    Transformer Research Consortium                                                        The University of Manchester

NIA_NGET0089    Impact of HVDC Cable Operation on Telecommunication Lines                              PowerSure Technology

NIA_NGET0090    Cable Extraction                                                                       JSM

NIA_NGET0092    Partial Discharge on Existing HV Cable                                                 Elimpus, Doble PowerTest, Prysmian Group, NDB Technologies

NIA_NGET0093    Online Gas in Oil Analysis on Existing HV Cables                                       Invisible Systems, Doble PowerTest

NIA_NGET0103    Modelling the tape corrosion process for oil-filled underground cables                 The University of Leicester

NIA_NGET0107    Stakeholder attitudes to electricity infrastructure                                    The University of Exeter

NIA_NGET0109    Bushing and Instrument Transformer Test Tap Connection Condition Assessment            Elisys Engineering, Process Parameters, Elimpus, Invisible
                Tool                                                                                   Systems, GE Grid Solutions (UK), Macintosh Consultancy

NIA_NGET0112    Enhanced AC and DC safety voltage limits assessment                                    Cardiff University

NIA_NGET0117    Bulk Oil Circuit Breaker Bushing In Situ Refurbishment                                 NAREC Electrical Networks

NIA_NGET0130    Determining a threshold for magnetophosphenes perception at 50Hz                       Lawson Health Research Institute

NIA_NGET0132    UltraWire                                                                              University of Cambridge, Outotec, National Grid, Aurubis, Aalto
                                                                                                       University, CNT ltd, Nexans, AGH, KME, IOM, PSA Peugeot
                                                                                                       Citroen, Wieland

NIA_NGET0135    Enhanced Sensor Development (iCASE Award)                                              The University of Manchester

NIA_NGET0136    Impact of Seabed Properties on Ampacity and Reliability of Cables (iCASE Award)        The University of Southampton

NIA_NGET0140    OHL Condition Assessment                                                               Brunel University London, Amey

NIA_NGET0141    T-pylon Structure and Composite Insulator Testing                                      Europea De Construcciones Metalicas SA, Russell Ductile Castings
                                                                                                       Ltd, STRI, Valmont SM A/S, EPL Composite Solutions, Allied
                                                                                                       Insulators, Eaves Machining, Lapp Insulators, SPIE SAG Group.

NIA_NGET0143    Transient and Clearances in the Future Electrical Transmission Systems (iCASE Award)   The University of Manchester

NIA_NGET0147    Condition Monitoring of Power Assets (COMPASS)                                         The Watt, PSC Group

NIA_NGET0148    Network Reliability Asset Replacement Decision Support Tool                            The University of Manchester

NIA_NGET0153    Life Cycle Costing and Value Optimisation (iCASE Award)                                The University of Bath

NIA_NGET0160    Feasibility of Risk based Network Planning                                             The University of Manchester

15   ET Annual Summary 2017/18
Project portfolio

Project portfolio – continued
Project         Project name                                                                           Partners
reference

NIA_NGET0162    Digital Substation – Virtual Site Acceptance Testing & Training                        The University of Manchester

NIA_NGET0163    SF6 Management and Alternative Gases                                                   Cardiff University, The University of Manchester, GE Grid Solutions

NIA_NGET0164    Evaluation of a Novel Variant of ACCC HTLS Conductor                                   Lapp Insulators, Nexans Benelux, Central Engineering &
                                                                                                       Hydraulic Services, CBS Products

NIA_NGET0165    Transformer Rating Modelling Tool Enhancement                                          Oxford Computer Consultants, Southampton Dielectric Consultants
                                                                                                       Ltd, The University of Southampton

NIA_NGET0166    VSC-HVDC Model Validation and Improvement (iCASE)                                      The University of Manchester

NIA_NGET0168    A New Independent Methodology For P&C Coordination Studies Using Real Time             The University of Birmingham
                Digital Simulation

NIA_NGET0176    Feasibility study on the application of advanced materials                             The University of Manchester

NIA_NGET0178    Environmental Containment solutions for MIDEL 7131                                     Adler and Allan, Parsons Brinckerhoff

NIA_NGET0179    Travelling Wave Fault Locator Trial

NIA_NGET0180    EPRI Research Collaboration on Electric & Magnetic Fields Health & Safety (P60) 2016   EPRI

NIA_NGET0181    Classification of Wind Exposed Overhead line Spans                                     Digital Engineering

NIA_NGET0182    Feasibility study on suitability of protection policy for future energy scenarios      The University of Manchester

NIA_NGET0184    Identify opportunities and developments in EMF Research (2016-2018)                    Torrance

NIA_NGET0185    Investigation of transient and safety issues in gas insulated systems                  Cardiff University

NIA_NGET0186    Condition Monitoring of Circuit Breakers - (iCASE)                                     The University of Liverpool

NIA_NGET0189    Security Assessment of Industrial Control Systems (ICS)                                EPRI

NIA_NGET0190    EPRI Research Collaboration on Cyber Security 2016 (P183)                              EPRI

NIA_NGET0191    EPRI Research Collaboration on Grid Planning (P40)                                     EPRI

NIA_NGET0194    Detailed design of 400kV 240MVA Mobile Substation Bay                                  ABB

NIA_NGET0195    EPRI Research Collaboration on Substations 2016 (P37)                                  EPRI

NIA_NGET0196    EPRI Research Collaboration on Overhead Lines 2016 (P35)                               EPRI

NIA_NGET0197    Development of fittings analysis model                                                 Amey

NIA_NGET0198    Cost effective removal of conductor crossing clearance constraints

NIA_NGET0199    Alternatives to SF6 for retro-filling existing equipment                               The University of Manchester

NIA_NGET0200    Study into the Concept of High Impact, Low Probability Events

NIA_NGET0201    Portable Earthing Device                                                               Aldercote Ltd

NIA_NGET0202    Development of a Universal Bushing                                                     Abb Group, BTRAC Ltd, John Graham

NIA_NGET0203    Novel acoustic attenuation feasibility study                                           WSP Environmental Ltd

NIA_NGET0204    Frequency Response Analysis for Transformer Characterisation and Objective             The University Of Manchester
                Interpretation of Results

NIA_NGET0206    Novel methodology for assessing environmental exposure of OHL routes                   Digital Engineering

NIA_NGET0207    Development of Tools for the Assessment and Control of Impressed Voltage               P&B Weir Electrical

NIA_NGET0208    EPRI Research Collaboration on Electric & Magnetic Fields Health & Safety (P60)        EPRI
                2017-2021

NIA_NGET0209    EPRI Research Collaboration on Overhead Lines (P35) 2017                               EPRI

NIA_NGET0210    EPRI Research Collaboration on Substations (P37) 2017-2020                             EPRI

NIA_NGET0211    Controllable Series Impedance at 275 and 400kV (CSI)                                   Manitoba HVDC Research Centre, Smart Wire Grid Inc

NIA_NGET0213    Condition and Climatic Environment for Power Transformers (ConCEPT)                    The Watt Ltd

NIA_NGET0214    Transformer and Transformer Oil Life Optimisation and Management Through               The University of Manchester, M&I Materials Limited, SP Power
                Analysis and Modelling                                                                 Systems Limited, SHELL Research Limited, TJ/H2b Technology
                                                                                                       Services LLC, UK Power Networks (Operations) Ltd, WEIDMANN
                                                                                                       Electrical Technology AG, SGB-SMIT Management GmbH,
                                                                                                       The Electric Power Research Institute, Inc., Cargill Incorporated
                                                                                                       Materials Limited

NIA_NGTO005     EPRI Research Collaboration on Information and Communication Technology (P161)         EPRI

NIA_NGTO007     EPRI Research Collaboration on Electric Transportation (P18)                           EPRI

NIA_NGTO006     Automated identification of failures in HV assets                                      The University of Manchester

16   ET Annual Summary 2017/18
Our Network Innovation
     Competition Project
     Deeside

17
Deeside

                                 Overview
                                 The past 12 months have seen significant          use of the capabilities that are available.
                                 work taking place on the Deeside facility in      We are also fully developing the designs
                                 preparation for the start of construction work    and making certain the contractual
                                 on the site. The design, development and          arrangements are in place so we can start
                                 tender work for the overhead line (OHL) test      work as soon as possible. The next year will
                                 area was completed, with the construction         see the design, development and tender
                                 contract being awarded in June 2018.              activity completed for the substation section
                                 Construction will be completed by April           of the facility, along with the procurement
                                 2019 and will be an important milestone           of long lead time test equipment. This
                                 for the facility, bringing the first energised,   delay will therefore not impact the overall
                                 operational area into service so that             completion date of the project.
                                 innovation project trials can begin.
                                                                                   We have continued to review the costs and
                                 The handover of the rest of the substation,       benefits. The existing control building will
                                 due to operational reasons, might be              be refurbished to reduce expenditure. The
                                 delayed until 2019 as opposed to 2018 as          construction of the new storage building has
                                 was initially projected. The impact of this       been put on hold until we have completed
                                 risk is being managed through progress            the tender process for the substation area
                                 on the OHL area and considered selection          (expected in the last quarter of this new
                                 of the project trials to ensure we make full      financial year).

18   ET Annual Summary 2017/18
Collaboration
                                                                                                          Deeside

                                                Business case update
                                                 The project is on track to deliver the benefits      SDRC 9.7 Completion of stage two
                                                 we outlined in the original bid. Presently,          construction works (May 2018)
                                                 only our cashable benefits of innovation             The construction of the internal access
                                                 projects have been quantified and                    road is also delayed. This work will be
                                                 forecasted. Over the next reporting period           undertaken as part of the construction of
                                                 we will work with other LNOs to forecast             the OHL area, expected to complete in April
                                                 the benefits to the whole industry from the          2019. As per SDRC 9.5 (see previous), this
                                                 project trials.                                      does not impact the innovation programme
                                                                                                      or project benefits.
                                                 Progress against plan
                                                 The project is on track for completion in            SDRC 9.6 Approval of phase two
                                                 October 2020. Some of the works and                  innovation programme
                                                 key milestones have been re-sequenced                This has been delayed by two months
                                                 to manage uncertainties and changes in               because of lack of availability of technical
                                                 the plan.                                            advisory board members and rescheduling
                                                                                                      of the meeting from March to April 2018.
                                                 SDRC 9.5 Completion of stage one                     Projects are now approved.
                                                 construction works (June 2017)
                                                 The construction of the control building             Progress against budget
                                                 refurbishment has been delayed and is                The project is on track to deliver within
                                                 expected to be completed in April 2019 – a           budget. Until construction works are
                                                 change request has been submitted for this           complete there will be delivery risks that
                                                 work. This does not impact the innovation            may require use of the contingency budget.
                                                 programme or potential benefits of the               Designs for all areas of the facility have
                                                 facility, as the OHL area and other parallel         been reviewed to ensure they are efficient
                                                 project trials can be delivered independently        and to maintain the overall project forecast
                                                 of this construction work. The delay will            within budget.
                                                 only influence the facility if it impacts the
                                                 commissioning of the substation (currently
                                                 expected in 2020).

Further information about the SDRC
codes and status can be seen in
Table 1. SDRC reference table.

                         2017                            2018                                 2019                                2020

                                                                                        Phase 3                                        Confirm Future
                                                                                     Commencement                                      Arrangements

 SDRC
                    Stage 1                  Phase 2  Stage 2                     Phase 3     Stage 3                                    Consolidate &
                   Completion                 Scope Completion                     Scope     Completion                                   Disseminate
                                             Approval                             Approval                                                 Learning

                                               Design/Tender             Construction                          Refurbished Office Facilities Available

 Construction                        FEED/Tender     Detailed Design/Construction                                       CHL Area (Fully) Operational

                                                       FEED/Tender                       Detailed Design/Construction     Substation Area Operational

                                       132kV Cable Sealing End Testing
                                                                                                                         Textured Insulators

                                         Live Line Trial of Line Scout

 Innovation                                        Tower Foundation Inspections
 Programme                                                      Zip-up Scaffold

                                                                                                                   Conductor Coating Systems (NIA)

                                                                                                                               Approved
                                                                                                                               Awaiting Approval

19   ET Annual Summary 2017/18
Project updates

                                 Project updates
                                 Cable sealing end

                                 The cable sealing end project trialled         of silicone oil, leading to further research
                                 a retrofit cable sealing end, developing       projects that will develop the industry’s
                                 new condition monitoring techniques for        knowledge. Further testing of condition
                                 cable sealing ends, and investigating the      monitoring systems will begin later in 2018.
                                 underlying reasons behind recent failures
                                 of 132kV cable sealing ends.                   Investigations into failures of the cable
                                                                                sealing ends revealed several areas that
                                 The retrofit cable sealing end has gone        the failure could be coming from. Further
                                 through several design iterations to meet      investigations using advanced analytics
                                 our challenging specifications and is now in   techniques looked at the information from
                                 its final design iteration.                    dissolved gas analysis. This helped identify
                                                                                different behaviours across the types of
                                 Research into condition monitoring of cable    cable sealing ends not previously known.
                                 sealing ends assured us that they are not
                                 near to failure. This meant people could       Working with our domestic and global
                                 work safely near our assets. As a result       partners, we are gaining a better
                                 of this research, we now have a greater        understanding of the behaviour of
                                 understanding of the electrical performance    silicone-oil-filled cable sealing ends.

20   ET Annual Summary 2017/18
Project updates

                                 Textured insulators

                                 The textured insulator project developed           processes have been developed so
                                 a novel insulator not used on the network          the insulators can be made to a higher
                                 before. These new insulators are the result        standard than previous prototypes.
                                 of a collaboration between Cardiff University,
                                 the manufacturer and us. The insulators            Test circuits, for comparing the performance
                                 are created by impressing a textured               of textured insulators to previous designs,
                                 surface into their material. The result brings     are presently under construction, along
                                 improvements in the performance of the             with the condition monitoring systems, to
                                 underlying composite technology.                   measure the insulator’s performance.

                                 The textured surface makes the                     The first prototypes will handle 11kV and
                                 manufacturing difficult because of the             be available from October 2018. The first
                                 increased complexity of the material and           transmission system level insulators will be
                                 surface compared to previous designs. To           available in the middle of 2019.
                                 overcome this alternative manufacturing

                                     Zip-up scaffold

                                     National Grid is currently undertaking a        repeated redesign would help reduce
                                     bulk replacement of several 132kV cable         outage times and reduce costs.
                                     sealing ends. A key factor when carrying
                                     out this type of replacement work is to         This project is currently in the
                                     have safe work areas and access to              procurement phase. We have several
                                     assets at an elevated height. Initial cost      potential suppliers who could provide a
                                     estimates show that scaffolding would be        bespoke scaffold design to support the
                                     a major part of the replacement costs.          bulk replacement of cable sealing ends.
                                                                                     Once we have chosen a supplier, we
                                     One way to make cost savings for                will begin designing a new scaffold and
                                     this type of work is to pre-fabricate           carry out trials at the Deeside facility.
                                     scaffolding. Removing the need for

                                 Non-invasive tower foundation inspections

                                 Overhead line tower foundations form a             foundations, avoiding the need for digging,
                                 critical part of the transmission infrastructure   which would provide significant savings.
                                 across the UK. Ensuring foundations are in
                                 good condition is essential to keeping the         The information collected from
                                 public safe and our infrastructure resilient.      non-invasive inspections can also be
                                                                                    combined with other asset data, providing
                                 At the moment, we inspect tower                    a better understanding of all of our tower
                                 foundations by exposing a significant              foundations. Combining all sample data
                                 proportion of the foundation and carrying          could result in a reduction in the number
                                 out a visual inspection and concrete               of invasive inspections by improving
                                 core testing. Non-invasive inspection              confidence in the non-invasive techniques.
                                 technologies already on the market                 This would provide savings to consumers,
                                 may provide a clean and simple way                 while ensuring that the network is still safe
                                 to understand the condition of tower               and secure.

21   ET Annual Summary 2017/18
Reference tables

Table 1. SDRC reference table
Ref       Criteria                      Description                                                                    Status

9.1       Formal agreement on Terms     To achieve the efficiency required to meet the project’s objectives,           Complete
          of Reference with Technical   it is essential that the other Transmission Licensees fully engage in
          Advisory Board members.       the Technical Advisory Board. An early indication that this project will
                                        succeed will be in this Board agreeing the Terms of Reference.

9.2       Detailed design of            The completion of both the infrastructure and technical layout designs         Complete
          the facility completed        are an important milestone on the way to delivery of the overall project
          and approved.                 as they will determine the level of testing/evaluation that can be carried
                                        out, and at which stage.

9.3       Design, develop and           One of the fundamental knowledge and dissemination channels for                Complete
          publish internet site.        the project is the utilisation of the facility website, which will provide a
                                        secure area to share the outputs with the other Transmission Licensees.

9.4       Scope of work for the         With there being a phased handover of assets, it is essential to the           Complete
          phase one innovation          project’s success that a detailed plan be put in place, based on the
          programme approved.           assets available during this phase. This plan will also include any
                                        relevant Network Innovation Allowance (NIA) projects that can be
                                        undertaken at this time.

9.5       Completion of stage one       The completion of the construction of the buildings and the transfer of        Due: June 2017
          construction works.           the protection and control panels to the new control room are a key            Forecast: April 2019
                                        milestone to the effective functioning and monitoring of the facility, as is   Delayed due to change in
                                        securing the perimeter of the overhead line enclosure.                         control building option.
                                                                                                                       Change request submitted.
                                                                                                                       No impact on completion date
                                                                                                                       or project benefits.

9.6       Scope of work for the         The continuation of the phased handover of assets is essential to the          Due: March 2018
          phase two innovation          project’s success and a detailed plan is to be put in place, based on          Completed: May 2018
          programme approved.           the assets available during this phase. This plan will also include any        Delayed due to TAB member
                                        relevant NIA projects that can be undertaken at this time.                     availability, mitigated by early
                                                                                                                       presentation of two projects in
                                                                                                                       Nov 2017.
9.7       Completion of stage two       The completion of the construction of the internal access road is a key        Due: May 2018
          construction works.           milestone to the effective functioning of the facility, as this will enable    Forecast: April 2019
                                        the necessary vehicles to access all areas of the facility.                    To be delivered as part of
                                                                                                                       OHL area.
9.8       Scope of work for the         The continuation of the phased handover of assets is essential to the          March 2019
          phase three innovation        project’s success and that a detailed plan is put in place, based on           On track
          programme approved.           the assets available during this phase. This plan will also include any
                                        relevant NIA projects that can be undertaken at this time.

9.9       Commencement of               The delivery of the innovation programme testing/evaluation is a key           April 2019
          phase three innovation        milestone in the project and the ability to start operations at the facility   On track
          programme.                    is fundamental to the measurement of its success.
9.10      Completion of stage three     The completion of the construction of the Gas Insulated Switchgear            May 2019
          construction works.           enclosure is a key milestone to the effective functioning of the facility, as Forecast: April 2020
                                        this will enable the delivery of GIS and SF6 testing/evaluation projects.     Delayed by decommissioning
                                                                                                                      and handover of Deeside
                                                                                                                      substation.
9.11      Approval of model for         The Technical Advisory Board will determine, based on the flow of              October 2020
          enduring facility.            projects, the future of the facility.
9.12      Project close down.           All project learning will be consolidated and disseminated appropriately.      October 2020

22     ET Annual Summary 2017/18
You can also read