New Dairy Lane Seafield Estuary Swords Seatown METROLINK ROUTE MAP Knocksedan SWORDS – SANDYFORD Swords Central Area CMalahide Fosterstown MetroLink Route Sea Mount Future Station Forrest Great Park & Ride Ward Rail Cloghran Feltrim Saint Margaret’s Luas – Red Line Dublin Airport Luas – Green Line Dublin Airport Kinsealey Portmarnock Saint Doolaghs Williamsville Dardistown Woodlands M50 Belcamp Balgriffin Clongriffin Northwood Belmayne Area B Cappoge Santry Donaghmede Abbotstown Ballymun Baldoyle Finglas Coolock Collins Avenue Kilbarrack Dunsink Beaumont Whitehall Artane Glasnevin Raheny Griffith Park Castleknock Killester Drumcondra Marino Dollymount Cabra Glasnevin Fairview Clontarf Mater Phoenix Park O’Connell Street Stoneybatter Islandbridge Area A Smithfield Chapelizod Tara Ballyfermot The Liberties Ringsend Kilmainham Inchicore St. Stephen’s Green Irishtown Rialto Bluebell Portobello Charlemont Sandymount Dolphin's Barn Rathmines Ballsbridge Drimnagh Ranelagh Harold's Cross Walkinstown Beechwood Crumlin Cowper Kimmage Rathgar Terenure Milltown Booterstown Perrystown Clonskeagh Windy Arbour Blackrock Rathfarnham Templeogue Churchtown Dundrum Mount Merrion Monkstown Dún Laoghaire Balally Stillorgan Ballyroan Knocklyon Kilmacud Firhouse Ballyboden Stillorgan Ballinteer Sandyford Deans Grange Sallynoggin Whitechurch
Drumcondra Marino Cabra Glasnevin Fairview Clontarf Mater Area A O’Connell Street Stoneybatter andbridge 6 Potential Routes Smithfield Tara 5 options to Drumcondra The Liberties Ringsend1 option to Whitworth Kilmainham St. Stephen’s Green Irishtown Rialto Portobello Charlemont Sandymount Dolphin's Barn Rathmines Ballsbridge Ranelagh Harold's Cross
Saint Margaret’s Luas – Red Line Dublin Airport Luas – Green Line Dublin Airport Kinsealey Saint Doolaghs Williamsville Dardistown Woodlands M50 Belcamp Balgriffin C Northwood Belmayne Santry Area B Donag Ballymun 9 Potential Routes Finglas Coolock Collins Avenue 3 options to ‘Griffith Park’ Beaumont Whitehall Artane Glasnevin Raheny Griffith Park Killester Drumcondra Marino Doll Cabra Glasnevin Fairview
Major Station proposed for Whitworth Interchange with Maynooth – Connolly Line Interchange with Phoenix Park Tunnel – Docklands line Proposed station offers greater interchangeability between two rail lines Previous Drumcondra option • Lines diverge at Drumcondra • Higher Cost • Drumcondra served by significantly more bus routes • Significant travel time savings from Whitworth location
Existing Boundary Potential New Boundary
Proposed Route - Impact on Na Fianna Front pitch lost to construction - Potentially All Weather pitches Period of 2 - 6 years (at least) Pitches will be returned to ‘pristine’ condition upon completion Access to clubhouse and schools to be kept throughout construction When completed, station will be partially under main pitch with access points on Mobhi Rd TII say: “we are committed to finding an alternate site in the interim”
Proposed Route - Impact on Na Fianna Assumed 24 Hours tunnelling – 5,586m Approx 80m a week Excavation works and spoil to be taken out at Mobhi Rd • 720,000 cubic metres • Each truck contains 13 cubic metres • 55,400 trucks • 145 weeks • 55 trucks a day Environmental Impact Report • Traffic • Spoil • Noise • Dust • Much more
Limmo Peninsula Tunnel Launch Site Similar Scale to Proposed site on Mobhi Rd
Summary of Key Attractions Amenities of interest were listed Interesting that Tolka Rovers were listed and not Na Fianna Why were we not listed?
Planned Timeline Public Engagement Process –6 weeks - March 22nd – May 11th TII begin detailed planning and tendering process Jun/July 2019 – Planning submission from TII Option to object/appeal decision Construction scheduled to begin late 2020 or early 2021 Project planned completion 2027
FAQ – Routes/Sites No alternate sites for Na Fianna have yet been proposed No incentives have been offered to Na Fianna We have met TII twice – March 20th and March 28th Main reason for route change – Whitworth Station Na Fianna Station – 1km distance Alternate Tunnel Launching sites – Na Fianna considered optimal Cost Disturbance Traffic disruption is a concern – independent traffic report
Timeline of Events Friday March 16th – approx. 4.30pm - First contact Tuesday March 20th - Transport Infrastructure Ireland met with club Thursday March 22nd – Public Announcement Club issued statement Wednesday March 28th – TII met with club again Thursday March 29th – Members Information Night
Working Group Cormac Ó’Donnchú – Chairman Tom Gray Stephen Behan – Vice-Chairman Kieran Rogers Cormac O’Sullivan – PRO Finbar Gaffney Donal Ring – Treasurer Anne Foley Bernie Caffrey Lesley Jamieson
Members Actions Register for Public Engagement Session – The Helix Monday 9th April Write to all public representatives Email same to consultations@metrolink.ie Do not engage with non official actions Promote all Na Fianna Social Media Club colours Club Communications All media enquiries to pro.nafianna.dublin@gaa.ie Cormac O’Sullivan - 0879250697