LIVERPOOL RESIDENTIAL DEVELOPMENT UPDATE - October 2018 - Regenerating Liverpool
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Foreword 2018 has been a significant year and turning point for Liverpool’s housing market. Named as one of the friendliest cities in which to live, it seems that more and more people want to live here and the city’s population is now rising. A recent report by the Centre for Cities stated that Liverpool City Centre’s population grew by over 180% between 2002 and 2015, the highest percentage in the UK. We have a clear need to build new homes for that growing population. Based on our current estimates, we need to develop 30,000 new homes by 2030. Since I became Mayor in April 2012, over 9,500 homes have been built by both the public and private sectors, with more than 5,000 of these being homes I promised under the Housing Delivery Plan. I am also happy to report that all of our targets for bringing empty homes back into use have seen almost double the target actually being achieved. Over 8,000 new homes are currently being built on schemes that have commenced, and a further 25,000 either have or are seeking planning approval. On top of these, several thousand more (such as at Liverpool Waters) will be coming forward for planning approval in the next few years. Whilst the Strategic Housing Delivery Plan is already past halfway to delivering 1,500 homes, we have now set ourselves a new target of building a further 10,000 homes as part of our own new ethical housing company “Foundations”. Foundations will provide homes to satisfy demand and to support in particular first time buyers, foster carers, large families, the elderly and people with a disability and to improve the availability of good quality, affordable homes in the city. We have already hit the ground running, and the first two schemes under the programme have already commenced, with the first tranche of schemes being announced further on in this document. I am also delighted to report that Peel’s long-awaited Liverpool Waters project is now well underway, with no fewer than five residential towers and blocks now on site on four separate schemes that will deliver a combined 922 private rented sector apartments over the coming years. I hope that the data included in the following schedules will be useful to individuals and organisations involved in regeneration. Joe Anderson, OBE COVER PHOTOS CLOCKWISE FROM TOP LEFT: ON Mayor of Liverpool SITE - “THE APPROACH”, EDGE LANE (LMH); ON SITE – THE WELSH STREETS (PLUS DANE); ON SITE – FORMER MOREDALE HALL, LIVINGSTON DRIVE (SOUTH LIVERPOOL HOMES AND PRAYA HOMES)
Contents Executive Summary 1 City Centre: Residential Accommodation 3 City Centre: Student Accommodation 15 Neighbourhoods: Housing Delivery Plan 21 Neighbourhoods: Strategic Housing 29 Development Partnership Neighbourhoods: Refurbishments & Empty Homes 33 Liverpool Foundation Homes Limited 35 Neighbourhoods: Private Sector 39 Neighbourhoods: Student Accommodation 51 Affordability: Helping residents to buy their 56 first home, and giving tenants more choice DISCLAIMER: All information provided in this document is correct as known at the time of publication based on information provided by 3 developers, architects and agents. Liverpool City Council cannot be held responsible for alterations to completion due dates, values or other RESIDENTIAL DEVELOPMENT UPDATE // where such occur for reasons beyond our control.
2018 has seen levels of home building sustained, whilst the number of new residential applications coming forward for planning has been increasing. Between January and September 2018 some 1,244 new homes have been completed, with the number of homes to be built on schemes currently on site is now 8,100. As in 2017, a significantly greater proportion of the homes completed this year have been by the private sector which increasingly sees Liverpool as a profitable location in which to invest. The City Centre is on course to have around 845 new homes completed – similar to the number seen built during 2016 and 2017. However, the number of homes either with permission or coming forward for planning has seen a significant jump this year, with over 11,000 homes being suggested for the City Centre alone. The City Centre population, as low as 2,500 in the early 1990s, has now risen to around 43,000 – half of which are students, mostly living in purpose built accommodation. With a further 4,670 student bedrooms and over 4,500 non-student apartments currently on site, this means that over the next three years the City Centre population could grow to at least 50,000. Meanwhile, in the Neighbourhoods, the Council is stepping up its game and rising to the challenge of providing housing for people at most in need. Not only has the city built more than the 5,000 homes promised under the Mayor’s Housing Delivery Plan, and the number of empty homes brought back into use soared beyond original targets, our latest venture – an ethical housing company named “Liverpool Foundation Homes Ltd” is now on site with its first schemes. STUDENT ROOMS/BEDSPACES 1,634 COMPLETED since January EXECUTIVE 2018 (City-wide) Estimated total development £90m SUMMARY value of the above STUDENT ROOMS/BEDSPACES 5,890 CURRENTLY ON SITE (City-wide) Estimated total development £227m value of the above schemes NEW HOMES (Non-student) 1,244 COMPLETED since January 2018 (City-wide) Estimated total development £100m value of the above schemes NEW HOMES CURRENTLY ON 8,100 ACTIVE DEVELOPMENTS (City- wide) ABOVE: “QUAY CENTRAL” AND “PARK CENTRAL” ON CENTRAL DOCKS ARE THE Estimated total development £783m FIRST MAJOR SCHEMES TO BE ON SITE IN LIVERPOOL WATERS OUTSIDE OF THE value of the above schemes CITY CENTRE. THE £40 MILLION SCHEME WILL DELIVER 237 PRIVATE RENTED SECTOR APARTMENTS. RESIDENTIAL DEVELOPMENT UPDATE // 1
THE MAYOR’S HOUSING PRIORITIES HOUSING DELIVERY PLAN: TARGET FOR EMPTY HOMES NEW STRATEGIC HOUSING EXCEEDING THE MAYOR’S TO BE BROUGHT BACK INTO DELIVERY PARTNERSHIP TARGET FOR 5,000 NEW USE EXTENDED GETS UNDERWAY HOMES In 2012, Liverpool’s Mayor made a An additional target of the Mayor set In addition to the above 5,000 target to build 5,000 new homes in 2012 was to see 1,000 empty homes to be delivered under the across the city, and with the promise homes brought back into use. Housing Delivery Plan, in June 2014 that many of these will be Exceptional progress was made, and the Mayor announced new £200m “affordable” homes. The Council’s as a result of direct action taken by plans to build an extra 1,500 houses. Housing Delivery Plan is now the City Council and its partners, that Under the “Building Our Futures” exceeding this original target, and original target was exceeded with programme, a mixture of executive continues to build new homes in over 2,000 homes occupied again by properties and affordable family conjunction with Registered Providers March 2015. homes will be built across the city of Social Housing, or by private over the next five years. The developers with input/assistance from Determined to maintain this Council has teamed up with Liverpool City Council, including the momentum, in April 2015 the Mayor Redrow Homes and Liverpool use of City Council land or assets. committed to bringing a further 2,000 Mutual Homes (LMH) to deliver the homes back into use. In order to As we now approach the end of 2018, plans. achieve this, a Ten Point Plan was the programme has already delivered approved to tackle the blight of 5,698 new homes, with 1,048 currently Ten schemes have completed so empty properties across the city. A under construction or about to far, bringing 325 new homes, whilst a number of well received new commence. Combined, these take further 60 homes are currently under initiatives undertaken including the total that will have been initiated construction across 3 schemes, with ‘Homes for a Pound Plus’, empty under the scheme to 6,746 – and a further 362 either with or seeking homes loans and the acquisition of there are a further 678 homes still permission. long term empty properties have proposed, either with or seeking been implemented. Yet again, that planning permission or in the early target has been exceeded with stages of pre-application that have almost 5,500 empty homes brought the potential to take the overall total back into use since 2012. to 7,424, some 48% higher than the original target. 3,500 3,427 Empty homes TARGET: 7000 brought back New homes in into use 1,500 1,048 active 3,000 6000 11 developments (either on site or awaiting start in future phases of 5,698 commenced schemes) 2,500 TARGET: 5000 Actual new home completions TARGET: (includes homes on Active 1,000 Developments where 2,000 4000 individual properties have 362 New homes been signed off by NHBC or other certification). seeking or with approval 3000 1,500 500 205 New homes 2000 1,000 on site 325 Homes 1000 500 completed 0 0 0 HOUSING DELIVERY PLAN EMPTY HOMES – PHASE 2 STRATEGIC HOUSING (from April 2012) (from April 2015) DEVELOPMENT PARTNERSHIP (from August 2016) RESIDENTIAL DEVELOPMENT UPDATE // 2
SECTION 1 CITY CENTRE RESIDENTIAL SECTOR ACTIVITY BOOM RETURNS Residential development activity in the City Centre CITY CENTRE has returned to the high levels seen in the mid 2000s. In the early 1990s the City Centre’s population was just below 2,500 – but today has risen to over 43,000. RESIDENTIAL Just over 4,500 new homes are currently under construction within the City Centre boundary, with ACCOMMODATION several large volume schemes not expected to complete until 2019 or into 2020; as has been reported previously and elsewhere, an increasing percentage of these are destined for the Private Rented Sector as opposed to be offered for outright sale to individual home buyers. Schemes which have commenced since the start of this year include the first 708 of 945 units that will form part of Liverpool Waters. “Hive City” (278 apartments), Number of new City Centre homes “The Lexington” (304 units), and “Plaza 1821” (105 290 completed since January 2018 * does not include homes or phases completed on units). All 708 apartments are destined for the Private Rented Sector. The other 237 PRS apartments are unfinished schemes that are still on site outside of the City Centre at Quay Central on the part of Liverpool Waters known as Central Docks. Number of non-student residential 1,840 Number of City Centre homes on units completed or on site in Liverpool City Centre since 2012 4,525 active developments to be completed 1600 Residential units completed Residential units on site 1,566 1400 Number of potential new City 1200 Centre homes either announced, 11,280 seeking or with planning 1000 555 permission, but not yet started on 845 800 844 site 600 600 400 290 200 262 24 2014 114 19 0 2017 2018 2012 2016 2013 2020 2019 2015 2021 1101 Year The volume and scale of proposed schemes are growing significantly. The Elliot Group’s “Infinity Waters” is on site to deliver over 1,000 apartments over the next three years, whilst Strand House on Strand Street has commenced to bring 395 PRS apartments. New schemes that have come forward for planning include Maro’s £100 million 552 apartments at Brunswick Dock, and Legacie Developments’ £90 million “Parliament Square” development at Greenland Street/ Parliament Street bringing 505 apartments. Bevington Developments Ltd have gained consent for a 614 apartment scheme at PROPOSED: MARO DEVELOPMENTS’ 552 APARTMENT SCHEME FOR BRUNSWICK DOCK Bevington Bush/Aldersey Street. Plans have also been submitted for a scheme with 427 apartments on land to the west of St Bartholomew Road, south of Paul Street and north of Naylor Street. RESIDENTIAL DEVELOPMENT UPDATE // 3
C74 LIVERPOOL PUMPFIELDS C71 C75 C70 C72 WATERS C68 C69 C73 (Waterloo- B23 Princes) B22 C25 MARYBONE C67 C49 C42 B15 COMMERCIALC22 C43 B19 C45 C44 KNOWLEDGE QUARTER: C50 B20 DISTRICT C66 C46 KNOWLEDGE B8 ST GEORGE’S FABRIC DISTRICT C51 B21 C23 C27 C26 C47 QUARTER: C28 B9 QUARTER C94 C41 HEALTH CAMPUS A2 A3 C95 C24 HISTORIC DOWNTOWN C29 B11 C31 B10 B12 C32 C30 C76 KNOWLEDGE C33 C78 A9 KNOWLEDGE QUARTER KNOWLEDGE C34 C35 C77 C79 C36 C37 A4 C81 QUARTER: C48 QUARTER: B13 C38 C80 GATEWAY PADDINGTON C39 A10 VILLAGE C82 C40 B14 MAIN RETAIL C83 AREA C84 C86 C91 C93 B24 C85 B16 A5 KNOWLEDGE B25 ROPEWALKS A12 C52 C53 QUARTER: C92 C90 B27 B28 C87 C55 C54 A6 HOPE STREET B17 C56 B26 C89 C1 A11 B18 C57 C88 A7 C2 A8 C58 C63 CANNING C59 B6 C60 C64 GEORGIAN C4 C61 C65 A1 C3 B1 C20 B7 C62 C19 QUARTER CHINATOWN C6 C7 C21 C98 C5 B2 C8 C18 C9 C17 STRAND C10 BALTIC C11 C12 WATERFRONT CREATIVE C13 Residential scheme completed since November 2017 C97 B4 B5 C14 B3 Residential scheme under construction C16 C15 Residential scheme proposed City Centre Residential Schemes C96 Crown copyright and database rights 2018 Ordnance Survey 100018351 RESIDENTIAL DEVELOPMENT UPDATE // 4
CITY CENTRE: RESIDENTIAL ACCOMMODATION SCHEME: 87-95 Dale Street SCHEME: “Castle Hey”, Harrington Street DEVELOPER: Legacie Developments DEVELOPER: Derwent Lodge Properties COST: £4 million COST: £3 million UNITS: 18 apartments above 6 ground floor retail units UNITS: 33 apartments STATUS: Completed November 2017 STATUS: Completed November 2017 SCHEME: “Philharmonic Rise”, Catherine Street SCHEME: ”Produce Exchange”, 8 Victoria Street DEVELOPER: Hollinwood Homes Ltd DEVELOPER: Treasure View Ltd COST: £7 million COST: £8 million UNITS: 23 town houses UNITS: 54 luxury apartments STATUS: Completed Spring 2018 STATUS: Completed February 2018 SCHEME: “Kings Dock Mill – Phase 2”, Hurst Street SCHEME: “Eight by Illiad”, Grenville Street/Upper Pitt Street DEVELOPER: YPG Developments Ltd DEVELOPER: Illiad Cosgrove Ltd COST: £15 million COST: £12 million UNITS: 204 apartments UNITS: 120 apartments STATUS: On site for completion Spring 2019 STATUS: On site for completion Summer 2019 RESIDENTIAL DEVELOPMENT UPDATE // 5
CITY CENTRE: RESIDENTIAL ACCOMMODATION Schemes Completed since November 2017 (Total: 354 units) Key Address Developer Description No of Date of units Completion Zone: CANNING GEORGIAN QUARTER A1 144 Bedford Street Liver Property Ltd Conversion of basement into 2 x 2 bed flats, and 4 January 2018 South loft into 2 x 1 bed flats Zone: COMMERCIAL DISTRICT A2 Silkhouse Court, Fortis Conversion from office tower to create 193 self- 193 September 2018 Tithebarn Street contained apartments. Zone: HISTORIC DOWNTOWN A3 87-95 Dale Street/2-6 Legacie New four storey building with 6 ground floor 18 November 2017 Cheapside commercial units and 18 flats above A4 “Castle Hey”, Harrington Derwent Lodge Conversion/extension of upper floors to 33 flats. 33 November 2017 Street Estates Refurbishment of ground floor nightclubs/shopfronts. Zone: KNOWLEDGE QUARTER: HOPE STREET A5 24 Rodney Street M&N Property Conversion from surgery to 5 self-contained flats 5 August 2018 Limited A6 50 Rodney Street Mr Cowley Conversion to 3 self-contained apartments 3 April 2018 A7 51 Rodney Street Rodney Street To extend coach house at rear to create first floor 1 April 2018 Limited studio apartment. A8 “Philharmonic Rise”, 35- Hollinwood Homes Deconversion of existing student accommodation 23 Spring 2018 39 Falkner Street, 4-22 Limited back to original 23 individual private town houses Catherine Street Zone: MAIN RETAIL AREA A9 Produce Exchange, 8 Treasure View Refurbishment and conversion to 54 x 1, 2 and 3 54 February 2018 Victoria Street Limited bedroom luxury apartments A10 21-23 Ranelagh Street Rathbone Trust Conversion of ground and lower ground floor into 9 November 2017 Company Ltd restaurant, with 9 apartments above Zone: ROPEWALKS A11 Circle 109, Henry Street Circle Property To convert two existing ground floor commercial 4 November 2017 Limited units into 4 residential flats A12 Havelock Building 2-6 Blue Horizon To change use of 2nd and 3rd floors to 7 residential 7 April 2018 Berry Street, 130-132 (Liverpool) Limited apartments. Bold Street Schemes On Site (Total: 4,525 units) Key Address Developer Description No of Estimated units Completion Zone: BALTIC CREATIVE B1 “Kings Dock Mill: Phase 2”, YPG Develop- To erect 11/12 storey block containing 204 204 Spring 2019 land at Hurst Street ments Limited apartments B2 “The Baldocks”, HUP (BALTIC) To convert vacant warehouse into 5 town houses, 9 March 2019 Bridgewater Street/ erect 4 x 4 storey town houses with basement car Watkinson Street parking and commercial unit. B3 “The Tower” at X1 The X1 Developments To erect 25 storey building containing 196 residential 196 December 2018 Quarter, Sefton Street/ Ltd apartments Parliament Street B4 “Parliament Residence – Asset Corp To redevelop site to provide 56 residential apartments 56 Winter 2018 Phase 1”, 32-34 Parliament Street B5 “Parliament Residence – Asset Corp To erect a part 8/part 11 storey building with 145 145 December 2019 Phase 2”, 12-30 Parliament apartments and ground floor commercial unit Street Zone: CHINATOWN B6 “Eight by Illiad”, Grenville Iliad Cosgrove Ltd To replace former community building with , 2 blocks 120 Summer 2019 Street/Upper Pitt Street (max 7 storey) of 120 apartments, ground floor commercial and community uses. B7 New Chinatown Phase 1 Great George To erect a 6 storey mixed use building comprising 6 115 (not Scheme had Street townhouses, 115 apartments, public events space included started but Developments commercial space and underground car parking in total) stalled. Now in the hands of a new developer who is re- evaluating the scheme. RESIDENTIAL DEVELOPMENT UPDATE // 6
CITY CENTRE: RESIDENTIAL ACCOMMODATION Schemes on site continued Key Address Developer Description No of Estimated units Completion Zone: COMMERCIAL DISTRICT B8 60 Old Hall Street Signature Living Conversion to 115 apartments for private sale 115 June 2019 Zone: HISTORIC DOWNTOWN B9 81 Princes Building, Dale LAAB Properties Conversion to 41 apartments 41 Autumn 2018 Street & 11-13 Cheapside B10 North House, North John Park House Conversion from office to 43 apartments. 43 December 2018 Street Developments (NW) Limited B11 Reliance House, 20 Water Legacie Conversion from offices to 139 apartments 139 September 2018 Street B12 “The Residence”, 8 Water Prospect Capital Conversion from offices to 123 apartments including 123 April 2019 Street Limited rooftop extension B13 “Strand Plaza”, The Strand Primesite Conversion of offices to 138 apartments 138 Spring 2019 Developments B14 Strand House, 21 Strand Patten Properties Replacement 16/19 storey mixed use development 395 for August 2020 Street and Panacea comprising 395 apartments with residents gym, PRS rent Property cinema, roof terrace), and two ground floor Development commercial units Zone: KNOWLEDGE QUARTER: HEALTH CAMPUS B15 "Aura 2", Erskine Street The Elliot Group Two buildings up to 14 storeys with 142 x 1 and 2 142 August 2020 bedroom apartments for rent to key workers Zone: KNOWLEDGE QUARTER: HOPE STREET B16 “Ropemaker Place”, 89-99 Citylife To erect 8 storey building with 77 residential units and 77 April 2019 Renshaw Street Developments Ltd ground floor retail/office uses B17 70 Rodney Street Not disclosed Conversion from office to dwelling house 1 September 2018 B18 72 Rodney Street Rodney Street Ltd Conversion of existing outbuilding to house 1 September 2018 Zone: LIVERPOOL WATERS: WATERLOO-PRINCES B19 “The Hive”, William Jessop Your Housing To erect 30 storey tower with 276 PRS (private rented 276 September 2020 Way, Princes Dock Group sector) apartments and “premium restaurant and (Liverpool Waters) bistro facilities”, with 24-hour concierge B20 “Plaza 1821”, William Peel/The Regenda New tower with 105 one and two-bedroom PRS 105 September 2019 Jessop Way Group apartments and ground floor commercial B21 “The Lexington”, William Moda Living 34 storey residential block with 304 PRS apartments 304 Summer 2020 Jessop Way Zone: PUMPFIELDS B22 “Infinity Waters”, Leeds The Elliot Group Three towers of 39, 33 and 27 floors to include 1,002 1,002 Summer 2021 Street/Pall Mall apartments B23 “The Metalworks”, Azure Horizons Ltd To erect 2 linked blocks (13 and 15 storeys) comprising 323 Autumn 2020 Vauxhall Road, 323 apartments, 475 sqm of commercial floorspace Freemason's Row, and 66 car parking spaces Zone: ROPEWALKS B24 “One Wolstenholme Wolstenholme Mixed use development of four blocks between 3 447 April 2019 Square ”, 5 Parr Street & Square and 10 storeys, with commercial units and 333 studio Wolstenholme Square Developments apartments on upper floors; and conversion of Limited existing warehouse to commercial uses and 114 studio apartments above. B25 65 Duke Street/14 Lady Mia Ltd To replace existing buildings with a 3 to 7 storey 69 December 2018 Wolstenholme Square building with 69 apartments with retail at ground floor. B26 “Chavasse Building”, Living Brick To erect 7 storey block with 47 apartments, ground 47 February 2019 Former Council Depot Projects floor retail and parking Site, Lydia Ann Street B27 84-86 Seel Street Mr Gleeson To demolish existing garage and erect new 4 Autumn 2018 bar/restaurant with 4 studio apartments above B28 14 Colquitt Street Postvine Limited Conversion of upper floors to 5 flats 5 November 2018 RESIDENTIAL DEVELOPMENT UPDATE // 7
CITY CENTRE: RESIDENTIAL ACCOMMODATION SCHEME: “Parliament Residence – Phases 1 & 2”, Parliament Street SCHEME: Strand House, 21 Strand Street DEVELOPER: Asset Corp DEVELOPER: Patten Properties and Panacea Property Development COST: £38 million COST: £86 million UNITS: 201 apartments over 2 phases UNITS: 395 PRS apartments STATUS: On site for completion December 2019 STATUS: On site for completion August 2020 SCHEME: ”Strand Plaza”, The Strand SCHEME: “Infinity Waters”, Leeds Street/Pall Mall DEVELOPER: Jupiter Investments Ltd DEVELOPER: The Elliot Group COST: £6 million COST: £250 million UNITS: 122 apartments (10 x 3 beds, 56 x 2 beds, 56 x 1 bed) UNITS: 1,002 apartments (63 x 3 bed apartments, 457 x 2 beds, 163 x 1 STATUS: On site for completion April 2019. beds and 232 studios) STATUS: On site for completion 2021 SCHEME: “Plaza 1821”, William Jessop way, Princes Dock/Liverpool SCHEME: “One Wolstenholme Square”, Ropewalks Waters DEVELOPER: Wolstenholme Square Developments Limited DEVELOPERS: Peel/The Regenda Group COST: £40 million COST: £21 million UNITS: 447 apartments UNITS: 105 PRS apartments STATUS: On site for completion April 2019 STATUS: On site for completion September 2019 RESIDENTIAL DEVELOPMENT UPDATE // 8
CITY CENTRE: RESIDENTIAL ACCOMMODATION Anticipated Schemes (Total: 11,280 units) Note: The granting of planning permission does not guarantee that a particular scheme will actually be built Key Address Developer Description No of Comments (status) units Zone: BALTIC CREATIVE C1 “One Park Lane”, Land One Park Lane To construct two buildings from 10 to 16 storeys, 264 Permission granted bounded by Park Lane, Limited comprising 264 apartments, four commercial units, August 2015 Pownall Street, Liver Street gymnasium, pavement cafes/terraces with 47 and Beckwith Street basement parking spaces C2 “Baltic Square”, Park Lane, Inhabit Conversion of existing Mill into 138 residential 138 Permission granted Beckwith Street, apartments; and to redevelop land around it with private December 2017 Carpenters Row and three blocks, 10, 11 and 14 storeys, to provide 194 and 194 Cornhill (former Heap's residential apartments, 200 serviced apartments) for PRS Rice Mill) and, ground floor commercial rent C3 King’s Dock Mill – Phases 2 Fountain Mixed use development with 180 bedroom hotel, 100 Permission regranted & 3, land at Hurst Street, Trustees & Hurst 100 apartments, 220 bed YHA building, ground floor March 2015 Sparling Street, Tabley Street Ltd retail, car parking; and outline application for 95 Street, Wapping bedroom care home. C4 “Art Apartments”, Vacant Baltic Cool To erect 10/11 storey residential apartment block to 55 Permission granted land at Tabley Street Limited provide 55 apartments. April 2017 C5 66-68 Kitchen Street Waterfront Conversion/extension of fourth floor to create new 30 Application 15F/0827 Holdings restaurant/cafe; and outline application to erect 8 submitted April 2015 storeys of 30 flats above warehouse. C6 Land bounded by Blundell Ingenious Tribe To erect 2 blocks of 7-9 storeys creating 200 200 Application 17F/2656 Street, Kitchen Street and (Blundell Street) apartments, ground floor commercial floorspace submitted November Simpson Street Development and basement car parking. 2017 Ltd C7 35 Bridgewater Street Eloquent Conversion of ground floor to leisure/ commercial 43 Application 17F/2758 Yinyang Building uses, and three upper floors to 19 apartments. 4 awaiting signing of Limited storey rooftop extension to form 16 additional legal agreement since apartments. June 2018 C8 “Berry House”, Land Baltic House To redevelop with 9 storey building comprising 147 147 Application 16F/0825 between Norfolk Street Developments apartments, 11 ground floor commercial units, first submitted April 2016 and Brick Street Limited floor restaurant and car parking. C9 Jamaica Street and land Baltic House To replace existing structures with 9 storey building 89 Application 16F/0809 between Norfolk Street Developments containing 89 studio apartments, 8 ground floor submitted April 2016 and Brick Street Limited commercial units; and conversion of 43 Jamaica Street to self-contained offices. C10 “Baltic Tower”, Land The Elliot Group To erect 15 storey mixed used development 50 Permission granted between Norfolk Street, comprising 306 bed hotel, 50 residential apartments May 2018 Watkinson Street with gym, spa, restaurant, conferencing/ banqueting facilities, entrepreneurial hub, sky lounge, basement parking. C11 Former Bogans Carpets, Miami Ltd To erect 10 storey block creating 202 apartments 202 Application 16F/2922 New Bird Street ground floor commercial space and parking resubmitted May 2018 C12 “St James Court”, Site Hillmore To erect part 11/part 12 storey block containing 217 217 Application 17F/3527 bounded by Greenland Developments apartments with two ground floor commercial units submitted December Street/New Bird Street and Limited (alternative scheme to 15F/2835). 2017 St James Court C13 “Parliament Square”, Legacie To erect mixed use development over four buildings 505 Application 18F/1649 Greenland Street, Developments (8 to 18 storeys) comprising 505 apartments, spa submitted June 2018 Parliament Street, Great and facilities, 12 commercial units and car parking George Street, Newhall Street and St James Street C14 Cains Brewery Village, Cains Brewery New tourism, leisure and retail destination including 450 Permission granted Stanhope Street four screen cinema, food store, food market, hotel, March 2014. Food restaurants, spa, gym, function rooms, 400 space market completed car park and 450 flats. Summer 2017. C15 Grafton Street, Hill Street & Mr S Woods To erect between 4 and 9 storeys containing 301 301 Permission granted Brassey Street apartments with ground floor commercial units December 2016 C16 Land east of Brassey Street Eloquent Global To erect a part 8/part 9 storey building comprising 174 Permission granted Limited 174 apartments, with 96 parking spaces June 2018 Zone: CANNING GEORGIAN QUARTER C17 40-50 Percy Street The Elliott Group Conversion of existing flats to 6 townhouses and 18 Permission granted 12 x 1 bedroom apartments. November 2017 C18 109-109A Upper Liverpool Conversion to 9 self-contained apartments 9 Permission granted Parliament Street Housing Trust February 2017 C19 73 Canning Street Robert & To sub divide vacant town house to form two self- 2 Permission granted Patricia Wilson contained dwellings August 2015 RESIDENTIAL DEVELOPMENT UPDATE // 9
CITY CENTRE: RESIDENTIAL ACCOMMODATION Anticipated Schemes continued Key Address Developer Description No of Comments (status) units Zone: CHINATOWN C20 “The Address”, 8 Upper Pitt HDCO EPL1 To erect 7 storey building containing 52 studio 52 Permission granted Street Limited apartments with residents’ gym March 2018 C21 New Chinatown Phases 2 Great George Redevelopment with 800 new homes, ground 800 Outline permission and 3, Great George Street floor commercial space, 140 bedroom hotel, granted February 2016 Street Developments restaurants, gymnasium, Chinese market, food court, hospitality facilities, landscaped gardens and underground parking. Zone: COMMERCIAL DISTRICT C22 30-36 Pall Mall Anwyl Part 10/part 22 storey tower with 336 apartments 336 for Permission granted July Construction and ground floor commercial units PRS rent 2017 C23 Honeycomb, Edmund Paladium Conversion from offices to 35 residential 35 Application 17PO/2509 Street Group apartments submitted September 2017 C24 5 Fazakerley Street AR2 Conversion of semi-basement to office space, 9 Application 18F/1223 Developments and erect a three storey roof top extension to submitted June 2018 Limited provide 9 apartments C25 Ovatus 1, 122 Old Hall 122 Old Hall To erect 27 storey residential development with 168 for Permission granted Street Street Limited 168 PRS apartments PRS rent December 2017 Zone: HISTORIC DOWNTOWN C26 Kingsway House, Hatton Signature Living Conversion from offices to 76 x 1 and 3 bedroom 76 Permission granted Garden apartments August 2017 C27 Cablehouse, 49 Landinvest To erect an additional storey to provide 4 4 Permission granted Cheapside Limited additional flats with designated parking area. March 2016 C28 33-35 Cheapside Mr Ali Conversion of office building to create 2 x 5 2 Permission granted July bedroom HMO's over three floors and two storey (HMOs) 2018 extension to the rear. C29 Colonial Chambers, 1-3 Ultimate UK To convert ground floors and floors 1-5 to 94 x 1 94 Permission granted June Temple Square Homes Td bed studio apartments. 2016 C30 Union House, 19-21 Victoria Pure Manage- To convert office to residential with two storey 9 Permission granted April Street ment Inc rooftop and central circulation core extension. 2018 C31 19 Castle Street Machett Ltd Conversion from retail/offices to cafeteria with 9 9 Permission granted April self-contained flats on the upper floors. 2017 C32 New Zealand House, 18 The Flanagan Conversion from office to 16 x 1 bed apartments 16 Permission granted Water Street Group December 2015 C33 7 Water Street Aqua Conversion of upper floors to 10 apartments 10 Permission granted Commercial Ltd October 2017 C34 Existing car park, Drury CRC To erect building 8-11 storeys to provide 125 'co- 125 Application 18F/1074 Lane and Brunswick Street living' residential units with associated communal submitted April 2018 facilities (kitchen/dining/lounge/laundry/gym/ cinema) together with associated cycle storage and ground floor commercial unit C35 44 Castle Street JSM Company Conversion of upper floors to 8 apartments 8 Permission granted Group January 2018 C36 42 Castle Street Forgate Conversion of upper floors to 19 apartments 19 Application 18L/0232 Developments submitted January 2018 Limited C37 Crown House, 10-12 James District & Urban Conversion of office building to 23 x 1 bedroom 23 Permission granted Street apartments October 2017 C38 National Bank Building, 24 Adderstone Conversion of 8th floor of former office/staff 1 Permission granted Fenwick Street Developments accommodation to two bed penthouse January 2017 (103) Ltd C39 Victoria House, 7-11 James Downing Conversion of office building to 71 x 1 bedroom 71 Permission granted Street Developments studio apartments December 2017 Zone: KNOWLEDGE QUARTER C40 Land on the corner of JD Estates To erect 9 storey building with 60 residential 60 Application 17F/2249 Pomona Street and Limited apartments above café and auditorium submitted August 2017 Cathedral Walk C41 110 London Road BPL Conversion of first and second floors from 10 Permission granted offices to 10 x 2 bed apartments November 2016 RESIDENTIAL DEVELOPMENT UPDATE //10
CITY CENTRE: RESIDENTIAL ACCOMMODATION SCHEME: ”Fabric Village”, Gildart Street/Devon Street SCHEME: West of St Bartholomew Road, south of Paul Street and North of DEVELOPER: YPG Developments Limited Naylor Street COST: £53 million DEVELOPER: Smith Young Architecture Limited UNITS: 449 COST: £50 million STATUS: Application 18F/0347 submitted February 2018 UNITS: 427 apartments STATUS: Application 18F/1035 submitted April 2018 SCHEME: 2 Blackburne Place SCHEME: “Bevington Bush”, Bevington Bush/Aldersey Street DEVELOPER: Hope Street Commercial Limited DEVELOPER: Bevington Developments Limited COST: Not stated COST: £65 million UNITS: 9 apartments UNITS: 614 apartments STATUS: Application 17F/3453 submitted December 2017 STATUS: Permission granted October 2017 SCHEME: 9-27 Freemasons Row SCHEME: “Parliament Square”, Greenland Street/Parliament Street DEVELOPER: Vinco Group Limited with John and Elaine Sutch DEVELOPER: Legacie Developments COST: £80 million COST: £90 million UNITS: 656 apartments UNITS: 505 apartments STATUS: Permission granted September 2017 STATUS: Application 18F/1649 submitted June 2018 RESIDENTIAL DEVELOPMENT UPDATE //11
CITY CENTRE: RESIDENTIAL ACCOMMODATION Anticipated Schemes continued Key Address Developer Description No of Comments (status) units Zone: KNOWLEDGE QUARTER: FABRIC DISTRICT C42 “Fabric Village”, Gildart YPG To erect three residential blocks between 7 449 Application 18F/0347 Street/ Devon Street Developments and 10 storeys high comprising 449 residential submitted February 2018 Limited apartments with ground floor retail. C43 43-47 Stafford Street Mr Joseph Aiello Conversion from shop to community centre 1 Permission granted with 1 x 3 bedroom flat on first floor. December 2015 C44 Bianca House, 80 JD Estates Limited Extension and conversion from 19 bed HMO to 11 Permission granted Devon Street/54-56 11 self-contained flats March 2018 Stafford Street C45 48-50 Stafford Street Mr Chu To erect four storey extension to the rear, 9 Application 18F/1047 change use of ground floor to restaurant/bar submitted April 2018 and separate shop and 9 residential units to first, second and third floors. C46 23 Stafford Street Mr Singh Conversion of ground floor and basement to HMO Permission granted May extend existing HMO with 3 additional rooms (3 2017 beds) C47 Hughes House, 101-113 Town Square To erect part 6/part 8 storey building for student 82 Application 17F/2414 London Road Developments accommodation (100 bedrooms) from ground submitted September Limited to 4th floor, 82 residential apartments from 5th 2017 to 7th floors, retail units on ground floor, car parking to the basement and roof gardens. Zone: KNOWLEDGE QUARTER: GATEWAY C48 66 Lime Street Golding Conversion of 1st-3rd floors from office space to 3 Permission granted July 3 apartments with roof top extension. 2018 Zone: KNOWLEDGE QUARTER: HEALTH CAMPUS C49 12-14 Moss Street Everbright To erect eight storey building for 42 studio 42 Application 18F/1989 Developments apartments and ground floor commercial submitted July 2018 Limited business use C50 19-21 Prescot Street Mr Norman Cowley To erect 4 storey apartment block, consisting of 6 Permission granted April 6 apartments. 2018 C51 194 London Road BPL Conversion of first and second floors from 6 Permission granted offices to 6 x 2 bed apartments November 2017 Zone: KNOWLEDGE QUARTER: HOPE STREET C52 1-3 Leece Street Mr Haralambus To erect 3 storey extension to the front and 2 Application 16F/2357 Michael change single dwelling to 2 x 2 bedroom flats. submitted Sept 2016 C53 35-37 Leece Street Elite Properties Conversion of upper floors of building to 6 6 Permission granted Liverpool Limited residential apartments. 2018 C54 10 Hardman Street Internorth Conversion of 3 upper storeys from vacant 3 Permission granted Development Ltd restaurant to 3 self-contained flats November 2014 C55 63 Roscoe Street Mr Tim Cowley To demolish existing vacant garage and 2 Application 18F/1946 construction of a new build garage with 2 no. submitted August 2018 apartments with dormer to rear above C56 39 Rodney Street Solidum Limited To create 3 bed apartment at basement level 1 Permission granted April 2017 C57 45 Rodney Street The Bear's Den To demolish existing garages fronting Pilgrim 2 Permission granted Street and erect two dwelling houses. October 2016 C58 66 Rodney Street BGH Properties To convert property to 8 residential units (4 x 1 8 Application 18F/0070 Limited and 2 bedroom flats and 4 studios). submitted January 2018 C59 57 Rodney Street RWMC Property Conversion of medical consulting rooms to 2 2 Application 15F/3170 Management dwellings submitted Dec 2015 C60 91 Roscoe Street The Global Property Conversion of outbuilding to dwellinghouse 1 Permission granted June Agency Limited 2017 C61 99 Roscoe Street Mr & Mrs Harrys Demolition of former coach house and rebuild 1 Permission granted with a new 2 bedroom coach house January 2015 C62 80 Rodney Street Mr Michael Murphy To convert property and outbuilding to create 13 Permission granted 13 studios/apartments December 2017 C63 2 Blackburne Place Hope Street Conversion of townhouse into 5 apartments, 9 Application 17F/3453 Commercial Limited and new building to rear with 4 apartments submitted December and restaurant at basement and ground floor 2017 levels C64 37 Hope Street Signature Living To convert to 5 self contained apartments. 5 Permission granted September 2018 C65 10 Back Canning Street Mr Miles Falkingham To convert existing coach house into annexe 1 Permission granted accommodation with external alterations. January 2018 RESIDENTIAL DEVELOPMENT UPDATE //12
CITY CENTRE: RESIDENTIAL ACCOMMODATION Anticipated Schemes continued Key Address Developer Description No of Comments (status) units Zone: MARYBONE C66 Trueman Court, 21 Alexander Property Conversion from offices to 4 residential 4 Permission granted May Trueman Street Group apartments 2017 C67 55 - 63 Great Crosshall Bridgewater To convert former church school building into 9 124 Application 18F/1874 Street Services Limited apartments and construction of 6-10 storey submitted July 2018 building accommodating 115 apartments Zone: PUMPFIELDS C68 “North Point”, 70-90 Pall Replacement Redevelopment with 3 to 18 storey mixed use 507 Scheme stalled. Mall, L3 developer being buildings comprising 507 live/work units studios, Completion unknown. sought 1, 2 & 3 bedroom apartments and duplexes, multi-storey car park, ground floor retail, café/bar, restaurants, spa & commercial offices and first floor gym. C69 “The Northern Quarter”, Eldonian Projects Redevelopment with 5 blocks from 4 to 12 914 Application 15F/3121 Leeds Street/Vauxhall Limited storeys containing 914 x 1 and 2 bed apart- submitted March 2016 Road/ Pumpfields Road ments, retail/commercial/employment space on ground floors plus 364 car parking spaces. C70 9-27 Freemasons Row Vinco Group To erect 11 to 15 storey interconnected blocks 656 Permission granted Limited with John with commercial space at ground floor and 656 September 2017 and Elaine Sutch PRS apartments above. C71 Paul Street/Oriel Street Vauxhall To redevelop part of site (Phase 1) by the 69 Application 18F/0585 between Vauxhall Road Developments Ltd erection of part 7/part 8 storey block consisting submitted March 2018 and St Bartholomew of 69 residential apartments, together with Road commercial uses on the ground floor and 16 space car park. C72 4 Paul Street Vauxhall To erect 20 x 3/4 storey town houses following 20 Application 16F/1088 Developments Ltd demolition of existing buildings submitted July 2016 C73 Land to the west of St Smith Young To erect 8 combined buildings ranging from 5 427 Application 18F/1035 Bartholomew Road, Architecture Limited to 12 storeys with 427 apartments, basement submitted April 2018 south of Paul Street and parking and ground floor leisure/commercial North of Naylor Street units C74 “Bevington Bush”, Bevington To demolish existing buildings and erect three 9- 614 Permission granted Bevington Bush/Aldersey Developments 17 storey blocks of residential accommodation October 2017 Street Limited containing 614 apartments with ground floor communal space, gym, commercial unit C75 “The Tannery”, Bevington Jamworks To demolish existing buildings and erect 3 new 381 Permission granted Bush/ Gardners Row/ buildings (7, 9 & 15 storey) for 381 residential June 2016 Edgar Street apartments Zone: MAIN RETAIL AREA C76 Fruit Exchange Building, JSM Limited To convert building into 74 apartments, 74 Application 18F/0083 10-18 Victoria Street including four storey roof top extension to submitted January 2018 Mathew Street frontage. C77 1-3 Temple Court Highneal Limited Conversion of first to fourth floors of existing 18 Permission granted office premises into 18 residential apartments. August 2016 C78 42-44 Stanley Street The Flanagan Conversion of first to fourth floors from offices to 20 Permission granted Group 20 x 1 bed apartments. August 2016 C79 9-13 Temple Court JSM Limited To erect 3 floors above existing building to 9 Application 17F/3297 create 9 x 1 bed apartments submitted November 2017 C80 2-8 Church Street NFU Mutual Conversion of upper floors to 18 apartments 18 Permission granted Insurance Society May 2018 Limited C81 13-17 Tarleton Street Miller Brook Conversion of upper storeys from offices to 6 6 Permission granted Properties Limited studio duplex apartments at first floor level November 2015 Zone: ROPEWALKS C82 9-19 Bold Street AEW UK To change use of part of ground, second and 10 Permission granted May third floor from offices to create 10 apartments. 2017 C83 21-25 Bold Street AEW UK Conversion of upper floors to 10 flats 10 Permission granted June 2016 C84 84 Bold Street Zoe Antonis Conversion of first and second floors 6 self- 6 Permission granted Limited contained apartments May 2015 C85 101-103 Bold Street Dr A Sahab Conversion of basement and ground floor from 6 Permission granted offices to café/restaurant, and extension to rear January 2018 to provide 2 x 2 and 4 x 1 bed apartments on upper floors. RESIDENTIAL DEVELOPMENT UPDATE //13
CITY CENTRE: RESIDENTIAL ACCOMMODATION SCHEME: ”Brunswick Quay”, Atlantic Way SCHEME: 118-124 Duke Street DEVELOPER: Maro Developments Ltd DEVELOPER: Henry Space Development Limited COST: £100 million COST: £12 million UNITS: 552 apartments UNITS: 151 apartments STATUS: Application 18F/1932 submitted July 2018 STATUS: Permission granted June 2016 Anticipated Schemes continued Key Address Developer Description No of Comments (status) units Zone: ROPEWALKS continued C86 108 Bold Street Glennonston To erect 4 storey building consisting of 3 Application 17F/1382 Properties Limited commercial unit on ground floor and 3 x 3 submitted May 2017 bedroom apartments on upper three floors. C87 108 Wood Street Mr Tareq Alblooshi To erect 4 storey building, comprising 3 Permission granted commercial unit to ground floor and 3 self- September 2017 contained apartments above C88 181-185 Duke Street Ropeworks Ltd To erect 3 storey building with 3 apartments 3 Permission granted above ground floor retail October 2017 C89 118-124 Duke Street Henry Space Conversion of existing building and erection of 151 Permission granted Development 4-8 storey new building to create 151 residential June 2016 Limited units with ground floor communal use C90 3-5 York Street York Street Limited Conversion into 18 apartments 18 Permission granted November 2017 C91 “The Address at One Wolstenholme 11 storey block with 200 luxury apartments, 200 Application 18F/0301 Wolstenholme Square”, Square spa, pool and ground floor commercial space submitted February 18-24 Seel Street Developments Ltd 2018 C92 Land adjacent to Hodge Hill To erect a 4 storey building consisting of 6 x 1 6 Application 18F/0014 Argyle Court, Argyle Securities bedroom apartments submitted January 2018 Street C93 Gostins Building, 32-36 Hanover Holding Conversion of ground to 6th floor to 154 47 Application 18F/1162 Hanover Street Limited bedroom hotel, 7th floor and rooftop extension submitted May 2018 to create 47 apartments Zone: ST GEORGES QUARTER C94 50-58 London Road Jay Development Conversion of vacant first and second floor of 6 Permission granted premises to 6 self-contained flats August 2017 C95 St Vincent Street (35-44 Silver Fern Design Conversion of vacant ground floor commercial 1 Application 16F/1460 Bridport Street Limited to one 3 bed residential apartment. submitted June 2016 Zone: STRAND WATERFRONT C96 Brunswick Quay, Maro To erect 4 blocks with 552 apartments with 552 Application 18F/1932 Atlantic Way Developments Ltd ground floor commercial space submitted July 2018 C97 “The Keel” – phase 2 Barings Real Estate To erect 2 x 8 storey buildings of 257 PRS 257 for Permission granted apartments PRS rent March 2017 C98 The Block, 19 Keel Wharf Artisan H (Kings Conversion from storage areas to 8 8 Permission granted Waterfront) Ltd apartments January 2017 RESIDENTIAL DEVELOPMENT UPDATE //14
SECTION 2 INCREASING STANDARD OF CITY CENTRE STUDENT ACCOMMODATION REPLACES OLDER STOCK CITY CENTRE STUDENT Twenty-first century students expect far more than previous generations. Their accommodation is now expected to feature en-suite facilities, their own ACCOMMODATION kitchen facilities, wi-fi access, large screen televisions, and high quality social gathering spaces including gyms, laundry and other facilities. Some of (Schemes of 5 units or more) the 1980s and 1990s student schemes completed in the city are themselves falling out of favour, requiring significant refurbishment. The pace of development in the student sector is now rising again, with some 4,666 student bedspaces currently under construction at a combined cost of £190 million. This is mostly down to some large volume schemes which have been in the pipeline for a while coming forward. For example, there are currently two schemes on site with over 1,000 units each: The Unite Group’s “Horizon Heights” at Number of student bedrooms 830 completed since January 2018 Skelhorne Street, and the Elliot Group’s “Aura” at Low Hill/Erskine Street. These join “The Weavers” off Norton Street (738 bedspaces) which will complete in September 2019. Number of student bedrooms completed or on site in Liverpool City Centre since 2012 3,113 Number of student bedrooms 4,670 currently under construction 2,800 2,400 2,583 2,318 2,000 1,600 Number of potential student 1,535 1,896 bedrooms either with or seeking 1,200 1,244 52 1,259 1,102 1,007 planning approval 800 830 400 0 2019 2020 2012 2017 2018 2013 2014 2015 2016 Year Student bedrooms Student bedrooms completed on site The focus of attention for emerging new develop- ments continues to be the Knowledge Quarter’s Fabric District on the north-eastern edge of the City Centre where there are currently 1,307 bedspaces on site on four schemes worth £93 million; and a further five large volume schemes totalling 1,268 at a combined cost of £135 million either with or seeking planning approval. Amongst the schemes most recently submitted this year are 109-113 Mulberry Street (366 student studios & ground floor retail unit) and “Fabric Village” at Gildart Street/Devon Street (449 residential apartments with ground floor retail). Following these, however, the number of larger schemes coming forward are believed to be slowing down as the market reaches saturation point. There are increasing incidences of developers coming forward to discuss student scheme proposals, but switching them to residential by the time of actual ON SITE: “BALTIC 56” IS THE LATEST STUDENT RESIDENTIAL SCHEME TO GET UNDERWAY IN THE BALTIC CREATIVE AREA OF THE CITY registration. RESIDENTIAL DEVELOPMENT UPDATE //15
CITY CENTRE: STUDENT ACCOMMODATION PUMPFIELDS LIVERPOOL WATERS: WATERLOO PRINCES MARYBONE E6 E7 F7 E8 D3 COMMERCIAL D8 E5 KNOWLEDGE QUARTER: KNOWLEDGE F9 DISTRICT F6 FABRIC DISTRICT QUARTER: E4 F5 ST GEORGE’S F8 HEALTH QUARTER E13 CAMPUS D2 F4 HISTORIC E3 KNOWLEDGE D7 E2 QUARTER: DOWNTOWN KNOWLEDGE D1 D5 KNOWLEDGE QUARTER PADDINGTON E11 QUARTER: VILLAGE MAIN RETAIL F12 E10 AREA GATEWAY D6 D4 E12 F11 F10 ROPEWALKS F14 E9 F13 KNOWLEDGE F3 QUARTER: F2 HOPE STREET CANNING GEORGIAN CHINATOWN QUARTER E1 F1 STRAND BALTIC Student accommodation scheme WATERFRONT CREATIVE completed since November 2017 Student scheme under construction Student scheme proposed City Centre Student Accommodation Schemes since November 2017 Crown copyright and database rights 2018 Ordnance Survey 100018351 RESIDENTIAL DEVELOPMENT UPDATE //16
CITY CENTRE: STUDENT ACCOMMODATION Schemes Completed since November 2017 (Total: 1,070 bedrooms/bedspaces) Key Address Developer/ Description Bedrooms/ Completed Owner bedspaces Zone: HISTORIC DOWNTOWN D1 “Gravity”, Drury House, Signature Black Conversion from office to student accomm- 104 September 2018 19 Water Street Limited odation with 92 studios and 12 flats Zone: KNOWLEDGE QUARTER D2 41-43 Seymour Terrace Mr Steve Murray Conversion to 8 student apartments 8 August 2018 Zone: KNOWLEDGE QUARTER: FABRIC DISTRICT D3 71-73 Kempston Street Skyline Conversion to 42 student bedrooms, gym, 42 September 2018 Developments Ltd laundry and ground floor retail unit. Zone: KNOWLEDGE QUARTER: GATEWAY D4 “The Ascent in Liverpool”, IconInk New 13 storey building with 196 student 196 November 2017 Renshaw Street apartments D5 Lime Street Gateway, Regeneration 412 student bedrooms over 9 storeys above 412 September 2018 Lime Street/Bolton Street Liverpool and Ion ground floor commercial units. Zone: KNOWLEDGE QUARTER: PADDINGTON VILLAGE D6 “Smithdown Court”, 65- G.C. Capital Ltd To erect part 3, part 5 storey block of student 64 September 2018 73 Smithdown Lane accommodation comprising 64 bedrooms Zone: MAIN RETAIL AREA D7 Sir Thomas House, Sir Urban Point Ltd Conversion to 44 luxury student studios with gym 44 November 2017 Thomas Street and cinema room Zone: MARYBONE D8 “Collegiate Apartments”, Key Design LLP To erect nine storey building with 200 student 200 September 2018 11 Fontenoy Street bedrooms Schemes On Site (Total: 4,670 bedrooms/bedspaces) Key Address Developer/ Description Bedrooms/ Completion Owner bedspaces Expected Zone: BALTIC CREATIVE E1 “Baltic 56”, 56 Norfolk Borden Properties To erect 10 storey block creating 126 student 126 September 2019 Street/ Jamaica Street Ltd apartments, 2 units of commercial space Zone: HISTORIC DOWNTOWN E2 8-10 Stanley Street Necarcu Limited Conversion from offices to 39 student flats 39 September 2019 Zone: KNOWLEDGE QUARTER: GATEWAY E3 “Horizon Heights”, Unite Mixed use development comprising two blocks 1,027 September 2019 Skelhorne Street, Bolton up to 20 storeys high providing ground floor Street, Hilbre Street commercial uses with student accommodation. Zone: KNOWLEDGE QUARTER: FABRIC DISTRICT E4 9-11 Camden Street Mr Tony Shirley To erect 5 storey student block with 5 cluster units 44 September 2019 (44 bedrooms). E5 “The Weavers”, Site at Islington 3 blocks of 8, 11 and 15 storeys providing 738 738 September 2019 the corner of Islington Regeneration student bedrooms with ground floor communal and Norton Street Company welfare, leisure and management facilities. E6 Devon House, 33 Devon YPG Devon House New part 6/part 8 storey building with ground 208 September 2019 Street Ltd floor retail and 208 student studio bedrooms E7 "One Islington Plaza", 1- Islington Regen- To erect 8/10 storey block with 317 student 317 September 2019 10 Devon Street, eration Company bedrooms and ground floor commercial space Zone: KNOWLEDGE QUARTER: HEALTH CAMPUS E8 "Aura", Erskine Street Elliot Property Two buildings up to 14 storeys with 1,007 student 1,007 September 2020 Construction Ltd & bedrooms Equity Group Ltd Zone: KNOWLEDGE QUARTER: HOPE STREET E9 Hardman House & Haigh Liverpool Edge To erect 2 interlinked blocks between 5-8 storeys, 355 September 2019 Building, Hardman (Hardman Street) containing 51 student accommodation cluster Street/Maryland Street Ltd apartments (355 bedspaces). Zone: KNOWLEDGE QUARTER: PADDINGTON VILLAGE E10 Liverpool International Kaplan Liverpool New live/learn facility including 259 student 259 September 2019 College Limited bedspaces in 30 studios and 46 clusters. Zone: MAIN RETAIL AREA E11 31-33 Tarleton Street Peelclose Conversion of two upper floors into 2 x 5 10 Spring 2019 Properties Limited bedroom (student) apartments. RESIDENTIAL DEVELOPMENT UPDATE //17
CITY CENTRE: STUDENT ACCOMMODATION SCHEME: 41-43 Seymour terrace, Seymour Street SCHEME: “Smithdown Court”, Smithdown Lane DEVELOPER: Steve Murray DEVELOPER: G.C Capital COST: £0.5 million COST: £2 million BEDROOMS: 8 BEDROOMS: 64 STATUS: Completed May 2018 STATUS: Completed September 2018 SCHEME: “Collegiate Fontenoy Apartments”, Fontenoy Street SCHEME: “Aura”, Erskine Street DEVELOPER: Collegiate/Key Design LLP DEVELOPER: Elliot Property Construction Ltd & Equity Group Ltd COST: £16 million COST: £100 million BEDROOMS: 200 BEDROOMS: 1,002 STATUS: Completed September 2018 STATUS: On site for completion September 2020 SCHEME: Hardman House & Haigh Building, Hardman/Maryland Street SCHEME: 9-11 Camden Street DEVELOPER: Liverpool Edge (Hardman Street) Ltd DEVELOPER: Tony Shirley COST: £20 million COST: £2.5 million BEDROOMS: 355 BEDROOMS: 44 STATUS: On site for completion September 2019 STATUS: On site for completion September 2019 RESIDENTIAL DEVELOPMENT UPDATE //18
CITY CENTRE: STUDENT ACCOMMODATION Schemes On Site continued Key Address Developer/ Description Bedrooms/ Completion Owner bedspaces Expected Zone: ROPEWALKS E12 L1 Studios, 16 Fleet Fleet Street To erect seven storey block of 52 student 52 December 2018 Street Liverpool Ltd bedrooms with ground floor commercial space Zone: ST GEORGES QUARTER E13 “The Paramount”, 28 Pinnacle Student To erect new student accommodation building 488* Stalled - not London Road Developments Ltd known * an undisclosed number of these are currently occupied even though the building is far from complete Anticipated Schemes (Total: 1,896 bedrooms/bedspaces) Note: The granting of planning permission does not guarantee that a particular scheme will actually be built Key Address Developer/ Description Bedrooms/ Status Owner bedspaces Zone: BALTIC CEATIVE F1 “Baltic House – Replacement New part 11 part 9 storey building with 150 150 Permission granted Phase 1”, Land developer sought student bedrooms, communal facilities and February 2015. between Norfolk office/creative workshop space Scheme commenced Street and Brick but stalled at 40% Street completed. Zone: CANNING GEORGIAN QUARTER F2 Myrtle Court, 200 Unite Group PLC To erect 3 storey extension within existing car 51 Permission granted Crown Street park to provide additional 51 student bedrooms January 2017 F3 109-113 Mulberry Property Capital Plc To replace existing building with new student Not known Revised application to Street accommodation & ground floor retail unit. be submitted Zone: KNOWLEDGE QUARTER F4 Copperas Hill Study Inn Limited To demolish former police station and erect six 220 Revised application Police Station, storey student accommodation block. 17F/1029 submitted Copperas Hill November 2017 Zone: KNOWLEDGE QUARTER: FABRIC DISTRICT F5 20-28 Oakes Mr Harry Manning To erect 6 storey building containing 30 flats with 30 Application 14F/1576 Street courtyard to rear. awaiting signing of legal agreement since December 2014 F6 4 Gildart Street Mr Jayson Van Flute To erect 6 storey building comprising 116 116 Permission granted bedrooms in 44 clusters with ground floor retail February 2016 F7 “The Drapery”, Devon Street To redevelop vacant car park into seven storey 124 Permission granted April land at Devon Limited block, consisting of 2 commercial units on the 2018 Street ground floor and 44 studio apartments and 10 student clusters (80 bedrooms) on upper floors. F8 Hughes House, Town Square To erect part 6/part 8 storey building for student 100 Application 17F/2414 101-113 London Developments accommodation (100 bedrooms) from ground to awaiting signing of legal Road Limited 4th floor, 82 residential apartments from 5th to 7th agreement since floors, retail units on ground floor, car parking to December 2017 the basement and roof gardens. F9 “Natex”, Land at Anwyl Construction To erect two blocks of 10 and 16 storeys with 566 566 Permission granted Norton Street/ Limited student bedrooms above commercial units. August 2018 Islington Zone: KNOWLEDGE QUARTER: HOPE STREET F10 3 Oldham Place Menworth To erect 8 storey building comprising 210 210 Application 17F/0174 Liverpool student bedrooms and 1 retail unit submitted November Investment Limited 2017 E11 Renshaw Hall, NR Capricornus Redevelopment with 292 student bedrooms 292 Permission granted Benson Street (and 56 bedroom apart-hotel) October 2016 Zone: MAIN RETAIL AREA F12 15-17 Ranelagh Poseidon Conversion of 1st and 3rd floors into 7 bed HMO 7 Permission granted Street Investments September 2015 Zone: ROPEWALKS F13 56 Parr Street G & W Stamper To demolish garage and redevelop with a four 7 Permission regranted storey, 7 bedroom student town house September 2017 F14 32 Slater Street G Stamper To erect 4 storey building comprising student 13 Permission granted accommodation (13 bedrooms) with ground November 2017 floor management office RESIDENTIAL DEVELOPMENT UPDATE //19
You can also read