Installation guide Best bolting practice BOLTING PRINCIPLES • Each RotaBolt® stud or bolt is load test calibrated during manufacture to achieve the desired tension for the application in which it is to be used. Achieving and maintaining • However, it is still necessary to estimate the tightening force (torque) that needs to be used, so that the tightening tool selected has sufficient torque power capacity and for any the correct clamping force, pre-set requirement. or bolt tension, is essential • All variants of RotaBolt should be installed following best engineering practice or methodology in assuring bolted joint prescribed by the site operator to the point at which final tightening is reached. • Continuing to follow the same tightening pattern, the fasteners should now be tightened until integrity. 85% - 90% of all the RotaBolt indicator shows that the correct design tension has been reached. bolted joint failures are • Torque values are disregarded at this point as the RotaBolt indicator is the ‘control’ for caused by inaccurate bolt confirmation of the achievement of the design tension setting. tension at installation. • At the correct level of tension, the fastener has ‘stretched’ the calibrated amount and the RotaBolt indicator cap or wireless app dashboard will indicate that the fastener has been installed to within -/+5% of the design tension for the application. The method of checking the different types of RotaBolt indicator are detailed on the following pages. International standards Although requirements may vary between applications, James Walker engineers will use one of the following international bolting standards as best practice when installing RotaBolt products. • ASME PCC-1: Guideline for pressure boundary bolted flange joint assembly. • BS EN 1591-4: Competency in the assembly of the bolted connections of critical service pressurized systems. SAFETY Throughout all bolt assembly and tightening processes it is essential to follow standard safety procedures and instructions on any equipment. The relevant personal protection equipment should be worn at all times.
Installation guide Tension checking BOLTING PRINCIPLES RotaBolt RB1 Touch ® Each RotaBolt RB1 Touch is calibrated to ‘lock’ the The RotaCap on top of RotaCap at the desired preload tension value on each RotaBolt stud will installation with an accuracy of ±5%. The cap will turn freely between finger and thumb until indicate when the correct ‘locking’ when the target tension is achieved. desired tension is achieved during the tightening process. However, it is still necessary to estimate the tightening force (torque) that needs to be used, so that the RotaBolt® RB2 Touch tightening tool selected The dual load indicator has an outer cap for high has sufficient torque power tension setting and an inner cap for low tension, capacity and for any giving the choice of an operational tension range, either for overload or maintenance control. Both pre-set requirement. work in the standard RotaBolt fashion, rotating freely between finger and thumb until ‘locking’ when the target tension is achieved. RotaBolt® Vision RotaBolt Vision uses a specially developed indicator which appears as an unbroken yellow line across the head of the fastener when the target SAFETY tension is achieved. Throughout all bolt assembly Should tension be lost, the indicator instantly and tightening processes it is rotates by ninety degrees creating a distinct right angle break in the yellow line that is easily essential to follow standard identifiable even from distance. safety procedures and instructions on any equipment. The relevant personal protection equipment should be worn at all times.
Installation guide Tension checking LOAD TEST CALIBRATED RotaBolt Connect ® • O pen the App on the mobile device and login. Each RotaBolt stud or bolt is load test calibrated during • A ctivate the relevant Connect fastener by placing the magnetic activator close the cap manufacture to achieve of the fastener and then select the active bolt on the app. the desired tension for the application in which it is • P ress ‘Install’ to open the installation screen. to be used. • Y ou will now see a load reading or percentage of target load traffic light display (you can toggle between these), which will change as you tighten the fastener. • T he display will show orange whilst tightening until the target load is achieved, when it will change to green indicating that target load ±0.5% of full scale has been reached. • If the display displays red, this indicates that the bolt has been over-tightened and target load has been exceeded. • O nce the target load has been achieved SAFETY press OK to complete the install and set the Throughout all bolt assembly bolt to collect and transmit data at the predetermined levels. and tightening processes it is essential to follow standard safety procedures and instructions on any equipment. The relevant personal protection equipment should be worn at all times.
James Walker Worldwide Australia India Norway T: +61 2 9721 9500 T: +91 224 0808080 T: +47 22 75 75 00 E: sales.jwau@jameswalker.biz E: sales.in@jameswalker.biz E: sales.no@jameswalker.biz Belgium Ireland Singapore T: +32 3 820 79 00 T: +353 214 323626 T: +65 6715 6300 E: sales.be@jameswalker.biz E: sales.ie@jameswalker.biz E: sales.sg@jameswalker.biz Brazil Italy South Africa T: +55 11 4392 7360 T: +39 2 2578308 T: +27 31 304 0770 E: sales.br@jameswalker.biz E: sales.it@jameswalker.biz E: sales.za@jameswalker.biz China Middle East Spain & Portugal T: +86 21 6876 9351 T: +971 481 78888 T: +34 94 447 00 99 E: sales.cn@jameswalker.biz E: sales.jwme@jameswalker.biz E: sales.es@jameswalker.biz France Netherlands UK T: +33 437 49 74 80 T: +31 186 633111 T: +44 1270 536000 E: sales.fr@jameswalker.biz E: sales.nl@jameswalker.biz E: sales.uk@jameswalker.biz Germany New Zealand USA T: +49 4038 60810 T: +64 9 272 1599 T: +1 708 754 4020 E: sales.de@jameswalker.biz E: sales.nz@jameswalker.biz E: sales.jwna.us@jameswalker.biz Information given in this publication is given in good faith and represents the results of specific individual tests carried out by James Walker or third parties in accordance with the methodologies described in this publication, performed in a laboratory. No representation or warranty is given in relation to such information. Values and/or operating limits given in this publication are not an indication that these values and/or operating limits can be applied simultaneously. While such results may comprise useful additional information and are industry standard tests, they are no substitute for conducting (or procuring from James Walker) your own tests and engineering analysis and satisfying yourself as to the suitability of the product you select. Please also note that a product tested in accordance with the published methodology may not perform to such values in application and/or under different test conditions or methodologies for a variety of reasons, including but not limited to the environment in which it is used/tested or which passes through it or otherwise affects the product, or due to the handling, storage or installation, or due to the effect of housing or other parts. Our personnel will be happy to discuss any historical examples we have of a product having been previously used in a particular application. To ensure you are working with the very latest product specifications, please consult the relevant section of the James Walker website: www.jameswalker.biz. James Walker Sealing Products & Services Ltd Registered Office: Lion House, Oriental Road, Woking, Surrey GU22 8AP, United Kingdom. Reg no: 00264191 England Issue number 1 © James Walker 2021 JW4773 0621/PDF
You can also read