For Immediate Release Contact: Guillermo Canedo Oct. 1, 2021 (954) 777-4090 Guillermo.Canedo@dot.state.fl.us FDOT Broward County Traffic Impact Report October 1, 2021 through October 8, 2021 FORT LAUDERDALE, Fla. – Construction and maintenance-related lane closures on state highways in Broward County are expected during the week of October 1 through October 8. Weather permitting, work will be done at the following locations throughout the county. For updated lane closure information, please refer to www.d4fdot.com. Follow us on Twitter @MyFDOT_SEFL, Facebook @MyFDOTSEFL, and Instagram @myfdot_sefl. Please note, any full road, ramp or bridge closures have been highlightedbelow. CONSTRUCTION PROJECTS INTERSTATES 1. I-95 from south of Hollywood Boulevard in the City of Hollywood to south of Broward Boulevard in the City of Fort Lauderdale and I-595 from I-95 to SR-7 in the Town of Davie (95 Express Phase 3C) Description: Work on this 9-mile 95 Express project includes extending the existing Express Lanes north from just south of Hollywood Boulevard to just south of Broward Boulevard in Broward County. One lane will be added, and the High Occupancy Vehicle (HOV) lane will be converted to create two Express Lanes in each direction. The number of General Use lanes will remain the same. Other project improvements include construction of I-95/I-595 Direct Connectors between 95 Express Lanes and I-595, as well as reconstruction, milling, resurfacing and widening of I-595 from SR-7 to I-95 and along I-95 from south of Hollywood Boulevard to south of Broward Boulevard. Additional work includes bridge widening along I-95 at several locations, painting of 17 bridges within project limits, I-95/SR 84 interchange modifications, Integrated Intelligent Transportation System (ITS) Installation, including cameras, detectors and dynamic message signs to optimize traffic operations, tolling/gantry construction, ramp signalization implementation at the interchanges, lighting, signage and drainage installation and construction of shoulder–mounted sound walls and retaining walls. For more information, please contact I-95 Community Outreach Specialist Daniela Silva at (786) 441- 3088 or msilva@corradino.com. Cost/Completion: $457 million / spring 2025 I-95 Traffic Impact: I-95 northbound, from the SR-84 exit ramp to just north of SR-84, has a new traffic pattern to allow for roadway and bridge construction. This pattern is anticipated to be in place through late 2021, weather permitting. I-95 in each direction, from Pembroke Road to south of Davie Boulevard, may have up to three lanes closed, nightly as needed, Sunday through Thursday. The first lane will close at 9:30 p.m., the second lane will close at 10 p.m. and the third lane will close at 11 p.m. All lanes will be open by 5:30 a.m.
I-95 in each direction, from Griffin Road to south of Davie Boulevard, will have shoulder closures, daily and nightly, as needed, Sunday through Thursday. I-595 Traffic Impact: I-595 in each direction, from east of SR-7 (US-441) to Anglers Avenue, may have up to three lanes closed nightly as needed, Sunday through Thursday. The first lane will close at 9:30 p.m., the second lane will close at 10 p.m., the third lane will close at 11 p.m. All lanes will be open by 5:30 a.m. I-595 in each direction, from SR-7 (US-441) to I-95, will have shoulder closures, daily and nightly, Sunday through Thursday. SR-84 Traffic Impact: The SR-84 westbound bridge over I-95 is in a temporary traffic pattern through spring 2022 for bridge reconstruction. SR-84 westbound traffic is diverted to the eastbound bridge, where two lanes in each direction are maintained. Please click think link to view the activity flyer. The I-95 southbound exit ramp to SR-84 eastbound is diverted to the SR-84 westbound movement through spring 2022. Motorists are diverted via SR-84 westbound, a U-turn at SW 26th Terrace and continue eastbound on SR-84; signage is in place to advise motorists. Please click think link to view the activity flyer. The SR-84 eastbound exit ramp to I-95 northbound is diverted through spring 2022. Motorists are diverted via a U-turn at SW 15th Avenue, continue westbound on SR- 84 to access the I-95 northbound entrance ramp; signage is in place to advise motorists. Please click think link to view the activity flyer. SR-84, from SW 26th Terrace to SW 15th Street, may have one lane closed in each direction nightly, as needed, 9 p.m. until 6 a.m., Sunday through Thursday for striping operations. The SR-84 ramp from south of Marina Mile to Anglers Avenue may have one lane closed in each direction nightly as needed, 10 p.m. until 5 a.m. Sunday through Thursday. SR-84 westbound to the SR 7 and I-595 entrance ramp will be closed nightly as needed, Sunday through Thursday, through Monday night, Oct. 18 for overhead sign installation operations. Motorists will be detoured via SR 7 northbound, U-turn at SW 20 Street to SR 7 southbound and I-595. FHP will be onsite to assist motorists. Ramp Impact: The I-95 northbound exit ramp to SR-84 will be closed to traffic through spring 2022 for bridge construction operations. Motorists traveling on I-95 northbound wishing to access SR-84 east of I-95 will be detoured via I-595 eastbound to SR 5 northbound and SR-84 westbound. Motorists traveling on I-95 northbound wishing to access SR-84 west of I-95 will be detoured via I-595 westbound, SR 7 southbound and SR-84 eastbound; signage will be placed to advise motorists. Please click think link to view the activity flyer. The I-95 southbound exit ramp to Griffin Road will be closed to traffic overnight, 11 p.m. until 5 a.m., Sunday through Thursday, through Thursday night, Oct. 7 for pile driving activities. Motorists will be detoured via I-95 southbound to Stirling Road westbound, Anglers Avenue northbound. FHP will be onsite to assist motorists. The I-595 exit ramp to Griffin Road will be closed to traffic overnight, 11 p.m. until 5 a.m., Sunday through Thursday, through Thursday night, Oct. 7 for pile driving activities. Motorists will be detoured via I-95 southbound to Stirling Road westbound, Anglers Avenue northbound. FHP will be onsite to assist motorists. The I-95 southbound ramp, from south of Broward Boulevard to the I-595 entrance, will be closed nightly as needed, 11 p.m. until 5 a.m., Sunday through Thursday through Thursday night, Nov. 4 for bridgework operations. Motorists wishing to head eastbound will be detoured via the I-95 southbound exit ramp to SR-84 westbound, SR-7 (US-441) southbound and I-595 eastbound. Motorists wishing to head westbound will be detoured via the I-95 southbound exit ramp to SR-84 westbound and I-595 westbound. FHP will be onsite to assist motorists. The I-595 eastbound to I-95 northbound entrance ramp will be closed to traffic nightly as needed, 11 p.m. until 5 a.m., Sunday through Thursday, through Thursday, Oct. 28 for
bridge painting operations. Motorists will be detoured via I-595 eastbound, US-1 northbound and SR-84 westbound to the I-95 northbound entrance ramp. FHP will be onsite to assist motorists. The I-95 southbound to I-595 westbound ramp will be closed to traffic nightly as needed, 11 p.m. until 5 a.m., Monday through Thursday, through Thursday, Nov. 11 for beam setting operations. Motorists will be detoured via I-595 eastbound, US 1 northbound and SR 84 westbound to the I-95. FHP will be onsite to assist motorists. Advanced Notice: The I-95 southbound entrance ramp from Stirling Road will be closed to traffic nightly, Sunday through Thursday, beginning Sunday night, Oct. 18 for watermain relocation activities. Motorists will be detoured via Stirling Road westbound, US 441 southbound and Sheridan Street eastbound to the I-95 southbound entrance ramp. FHP will be onsite to assist motorists. Advanced Notice: The I-95 northbound exit ramp to Griffin Road will be closed to traffic nightly as needed, Sunday through Thursday, beginning Sunday night, Oct. 10 for MSE wall construction. Motorists will be detoured via I-95 northbound to I-595 eastbound, US 1 southbound and Griffin Road. FHP will be onsite to assist motorists. Advanced Notice: The I-95 northbound entrance ramp from Griffin Road will be closed to traffic nightly as needed, Sunday through Thursday, beginning Sunday night, Oct. 10 for MSE wall construction. Motorists traveling westbound will be detoured via Griffin Road, US 441 northbound, I-595 eastbound to I-95 northbound. Motorists traveling eastbound will be detoured via Griffin Road, US-1 northbound, I-595 westbound to I-95 northbound. FHP will be onsite to assist motorists. Advanced Notice: The I-95 southbound entrance ramp from Griffin Road will be closed to traffic nightly as needed, Sunday through Thursday, beginning Sunday night, Oct. 10 for MSE wall construction. Motorists traveling eastbound will be detoured via Griffin Road eastbound, US-1 southbound, Stirling Road westbound to I-95 southbound. Motorists traveling westbound will be detoured via Griffin Road westbound, Anglers Avenue southbound, Stirling Road eastbound to I-95 southbound. FHP will be onsite to assist motorists. I-595 westbound to the I-95 southbound entrance ramp has a new traffic pattern to allow for roadway and bridge construction. This pattern is anticipated to be in place through summer 2021, weather permitting. The I-595 eastbound and westbound entrance ramp from I-95 southbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-95 northbound entrance ramp from I-595 westbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-595 westbound entrance ramp from I-95 southbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-595 eastbound entrance ramp from I-95 northbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-595 westbound entrance ramp from I-95 northbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-95 southbound entrance ramp from I-595 westbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-95 southbound entrance ramp from I-595 eastbound will have one lane closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday. The I-595 eastbound exit ramp and the SR-7(US- 441) eastbound exit ramp to SR-84 will have the outside shoulder closed nightly as needed, 10 p.m. until 5:30 a.m., Sunday through Thursday. The I-95 northbound and southbound exit ramp to Griffin Road will have one lane closed intermittently, nighty as needed, 10 p.m. until 5 a.m. Sunday through Thursday, through Sunday, Oct. 31 for MSE wall construction. The I-95 northbound and southbound entrance ramp from Griffin Road will have one lane closed intermittently nighty as needed, 10 p.m. until 5 a.m. Sunday through Thursday, through Sunday, Oct. 31 for MSE wall construction. *Please note that ramp closures will be performed as needed per nighttime construction operations; consecutive ramps will not be closed at the same time. Arterial Traffic Impact:
Anglers Avenue, from SW 36th Street to south of SW 31st Street, will be closed to motorists through spring 2022 for bridge construction operations. Traffic will be detoured via SW 31st Street, SW 26th Terrace, and SW 36th Street. SW 30th Avenue, from 34th Street to Marina Mile, may have one lane closed in each direction daily, 9:30 a.m. until 4 p.m. and nightly, 10 p.m. until 5 a.m., Sunday through Thursday. SW 26th Terrace at the I-595 overpass will have one lane closed daily, 7 a.m. until 5 p.m., Sunday through Thursday for drilling operations. Flaggers will be present to assist motorists and traffic in each direction will be maintained. Southbound SR 7, from north of I-595 to SW 21st Street, will have two lanes closed nightly as needed, 10 p.m. until 5 a.m., Sunday through Thursday, for ITS board installation activities. Advanced Notice: Eastbound Stirling Road at the I-95 overpass will have the outside lane closed nightly, 9 p.m. until 6 a.m., Sunday through Thursday for watermain relocation activities. 2. I-95 from south of Broward Boulevard to north of Commercial Boulevard in Fort Lauderdale (95 Express Phase 3A-1) Description: Work on this 6.7-mile 95 Express project includes widening and converting the existing I-95 HOV Lanes to Managed Lanes which will result in two tolled Express Lanes in each direction; the number of General Use lanes will remain the same. Other work includes: widening bridges, sound wall construction, installation of Intelligent Transportation System (ITS) and tolling equipment and ramp signaling at the I-95 entrance ramps at Davie Road, Broward Boulevard, Sunrise Boulevard, Oakland Park Boulevard and Commercial Boulevard. For more information, please contact I-95 Community Outreach Specialist Andrea Pacini (954) 299-6561 or apacini@corradino.com. Cost/Completion: $153 million / fall 2022 Traffic Impacts: I-95 will have three lanes closed in each direction, 9 p.m. until 5:30 a.m., Sunday through Thursday. The first lane will close at 9 p.m., the second lane will close at 9:30 p.m. and the third lane will close at 10 p.m. I-95 southbound, from Broward Boulevard to Davie Boulevard, is shifted to the outside to allow for median construction. I-95 northbound, from south of Davie Boulevard to south of Oakland Park Boulevard, has a new traffic pattern with traffic shifted to the outside to allow for median construction. This configuration is expected to be in place through fall 2021. I-95 in both directions, from south of Davie Boulevard to north of Commercial Boulevard, will have intermittent shoulder and ramp shoulder closures, as needed, daily and nightly. I-95 southbound, between Sunrise Boulevard and Davie Road, is shifted to the inside to allow for outside widening. This pattern is anticipated to be in place through summer 2022. I-95 southbound Express Lanes at Palmetto Park Road and Sample Road will be closed nightly, 9 p.m. until 5:30 a.m., Sunday through Thursday for paving, tubular marker installation and pavement marking activities. Arterial Road Traffic Impact: Prospect Road at I-95 will have one lane closed daily, 7 a.m. until 4 p.m., Monday through Friday. Oakland Park Boulevard will undergo a full nightly closure, 10 p.m. until 6 a.m., Sunday through Thursday for new bridge construction. Traffic will be detoured via Commercial Boulevard, N. Dixie Highway and Oakland Park Boulevard. 38th Street at I-95 will undergo a full nightly closure, 10 p.m. until 6 a.m., Sunday through Thursday for bridge construction. Traffic will be detoured via NW 10th Ave and Powerline Road. FHP will be on site to assist motorists. Powerline Road at I-95 will undergo a full nightly closure, 10 p.m. until 6 a.m., Sunday through Thursday as needed for bridge construction. Traffic will be detoured via Commercial Boulevard, N. Dixie Highway and Oakland Park Boulevard. Prospect Road at I-95 will undergo a full nightly closure, 10 p.m. until 6 a.m., Sunday through Thursday as needed for bridge construction. Traffic will be detoured
via Powerline Road, Commercial Boulevard and Andrews Avenue. NW19th Street at I-95 will undergo a full nightly closure, 10 p.m. until 6 a.m., Sunday through Thursday as needed for ITS Pole installation. Traffic will be detoured via Powerline Road, Oakland Park Boulevard and NW 21st Avenue. Powerline Road at the I-95 overpass will have one lane closed daily, 9 a.m. until 3 p.m., Monday through Friday. NW 19th Street at the I-95 overpass will have one lane closed, daily, 9 a.m. until 3 p.m., Monday through Friday. NW 6th Street at the I-95 overpass will have one lane closed, daily, 9 a.m. until 4 p.m., Monday through Friday. Oakland Park Boulevard at the I-95 overpass will have one lane closed, daily, 9 a.m. until 3 p.m., Monday through Friday. Ramp Impact: The I-95 northbound entrance ramp from Oakland Park Boulevard will be closed, nightly, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via Commercial Boulevard and Powerline Road. FHP will be on site to assist motorists. The I-95 northbound exit ramps to Oakland Park Boulevard will be closed as needed 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via I-95 and Commercial Boulevard. FHP will be on site to assist motorists. The I-95 northbound exit ramp to Commercial Boulevard will be closed as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via I-95 and Cypress Creek Road. FHP will be on site to assist motorists. The I-95 northbound entrance ramp from Commercial Boulevard will be closed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via Powerline Road and Cypress Creek Road. FHP will be on site to assist motorists. The I-95 southbound exit ramp to Commercial Boulevard will be closed nightly, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via Oakland Park Boulevard and I-95. FHP will be on site to assist motorists. The I-95 southbound entrance ramps from Commercial Boulevard will be closed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via Powerline Road, Oakland Park Boulevard and I-95. FHP will be on site to assist motorists. The I-95 southbound entrance ramps from Oakland Park Boulevard will be closed, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday.Traffic will be detoured via Powerline Road and Sunrise Boulevard. FHP will be on site to assist motorists. The I-95 southbound exit ramp to Oakland Park Boulevard will be closed, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via I-95 and Sunrise Boulevard. FHP will be on site to assist motorists. The I-95 northbound exit ramp to Broward Boulevard will be closed, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via I-95 and the Broward Boulevard Park & Ride. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from Broward Boulevard will be closed, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday.Traffic will be detoured via US-441 and Davie Boulevard. FHP will be on site to assist motorists. The I-95 southbound exit ramp to Sunrise Boulevard will be closed, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via Broward Boulevard and I- 95. FHP will be on site to assist motorists. The I-95 southbound entrance ramps from Sunrise Boulevard will be closed, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via Powerline Road, Oakland Park Boulevard and I-95. FHP will be on site to assist motorists The I-95 northbound entrance ramp from Davie Boulevard will be closed nightly, 9 p.m. until 5:30 a.m., Sunday through Thursday. Traffic will be detoured via State Road 7 and Broward Boulevard. The I-95 northbound exit ramp to eastbound Oakland Park Boulevard will have one inside lane closed daily, 9 a.m. until 3 p.m., Monday through Friday. The I-95 northbound exit ramp to Commercial Boulevard will have one lane closed daily, 9 a.m. until 3 p.m., Monday through Friday. The I-95 southbound entrance ramp from Broward Boulevard to I-595 will have one outside lane closed nightly 9 p.m. until 5:30 a.m., Sunday through Thursday.
3. I-95 from south of SW 10th Street in the City of Deerfield Beach to south of Glades Road in the City of Boca Raton (95 Express Phase 3B-1) Description: Work on this 4.8-mile 95 Express project includes widening and converting the existing I-95 HOV Lanes to Managed Lanes which will result in two tolled Express Lanes in each direction; the number of General Use lanes will remain the same. Other project improvements include bridge widenings at Palmetto Park Road and Camino Real, complete bridge replacement at the Hillsboro Canal, noise wall construction, portable traffic monitoring sites, toll gantry installation, Intelligent Transportation System (ITS) installation, ramp signaling at the I-95 entrance ramps from Palmetto Park Road, Express Lane markers and landscape relocation. For more information, please contact I-95 Community Outreach Specialist Andrea Pacini at (561) 214-3358 or apacini@corradino.com. Cost/Completion: $102 million / fall 2021 Traffic Impact: I-95 will have three lanes closed in each direction nightly, as needed, Sunday through Thursday nights, with the first lane closing at 9:30 p.m., the second lane closing at 10:30 p.m., and the third lane closing at 11:30 p.m. until 5:30 a.m. I-95 northbound Express Lanes at Sample Road and SW 18th Street will be closed nightly, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. I-95 southbound Express Lanes at Palmetto Park Road will be closed nightly, as needed, 9 p.m. until 5:30 a.m., Sunday through Thursday. Arterial Road Traffic Impact: Palmetto Park Road at I-95 will have two lanes closed in each direction nightly, as needed, Sunday through Thursday. The first lane will close at 9 p.m., and the second lane will close at 10:30 p.m. All lanes will be opened by 5:30 a.m. Palmetto Park Road at I-95 will have one lane closed in each direction daily, as needed, 9:30 a.m. until 3:30 p.m., Monday through Friday. Camino Real at I-95 will have one lane closed in each direction daily, as needed, 9:30 a.m. until 4 p.m., Monday through Friday. Ramp Impact: The I-95 southbound exit ramp to Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via I-95 southbound, Hillsboro Boulevard, Military Trail and Palmetto Park Road. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from westbound Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and Hillsboro Boulevard. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from eastbound Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and Hillsboro Boulevard. FHP will be on site to assist motorists. The northbound entrance ramp from eastbound and westbound Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Traffic will be detoured via I-95 southbound to Hillsboro Boulevard to I-95 northbound. The I-95 northbound entrance ramp from westbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m. Sunday through Thursday. Motorists will be detoured via Hillsboro Boulevard, Military Trail and Palmetto Park Road. FHP will be on site to assist motorists. The I-95 northbound entrance ramp from eastbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m. Sunday through Thursday. Motorists will be detoured via Military Trail and Palmetto Park Road. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from westbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m. Sunday through Thursday. Motorists will be detoured via Hillsboro Blvd, Military Trail and SW 10thStreet. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from eastbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and SW 10th Street. FHP will be on site to assist motorists.
Please note that ramp closures will be performed as needed per nighttime construction operations; consecutive ramps will not be closed at the same time. 4. State Road 9/I-95 at Copans Road Interchange Improvement Project in Pompano Beach Description: Project improvements include constructing a dedicated merge lane for northbound I-95 traffic from Copans Road and a collector distributor road for southbound I-95 traffic entering and exiting Copans Road. Improvements also will include sound walls, lighting, intelligent transportation system upgrades, drainage and landscaping. There will also be roadway widening, milling, resurfacing, signage, pavement markings, sidewalk and curb and gutter. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $26.4 million / summer 2022 Traffic Impact: The I-95 northbound express lanes will be closed from Atlantic Boulevard to north of Sample Road nightly, from 10:30 p.m. to 5:30 a.m., Sunday, October 3, to Wednesday, October 6, for dynamic messaging sign repairs and directional boring. The I-95 southbound express lanes will be closed from Glades Road to Atlantic Boulevard nightly, from 10:30 p.m. to 5:30 a.m., Sunday, October 3 to Wednesday, October 6, for dynamic messaging sign repairs and directional boring. 5. I-95 Landscape Improvements Project in Pompano Beach Description: Project improvements include installing plants throughout the project limits, including several species of palms and shade trees, and installing a temporary irrigation system. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 orrguerrero@corradino.com. Cost/Completion: $1,322,302 / spring 2022 Traffic Impact: All lanes are open. 6. Eastbound SR 84 Connector Ramp to Southbound SR 93/ I-75 Project in Sunrise and Weston Description: Project improvements will include constructing a new entrance ramp from eastbound SR 84 to southbound SR 93/ I-75 and installing sound walls and overhead sign structures. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $7,135,978 / spring 2022 Traffic Impact: One lane along eastbound SR 84 at I-595 will be closed nightly, Sunday through Thursday, between 9 p.m. and 5:30 a.m. for striping operations. One lane along westbound I-595 to southbound I-75 may be closed nightly, Sunday through Thursday, between 9 p.m. and 6 a.m. for striping operations. Up to five lanes along southbound I-75 at westbound I-595 may be closed nightly Sunday through Thursday, between 9 p.m. and 5:30 a.m. for striping operations. 7. SR 93/I-75 from Sheridan Street to South of I-595 Resurfacing Project in Davie, Southwest Ranches, and Sunrise Description: Project improvements include milling and resurfacing along SR 93/I-75 between Sheridan Street and south of I-595, installing guardrail and double-face guardrail throughout the project limits, and installing signs and flashing beacons to alert wrong way drivers at the SR 93/I- 75 southbound exit ramp to Griffin Road. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $ $7,949,000 / summer 2022 Traffic Impact:
I-75 will have up to four lanes closed in each direction nightly, as needed, Sunday through Thursday nights, with the first lane closing at 7:30 p.m., the second, third, and fourth lanes closing at 9 p.m. until 6 a.m. Ramp Impacts: The northbound I-75 Express lane exit north of Sheridan Street and the entrance south of Griffin Road will be closed overnight, Sunday through Thursday, between 9 p.m. and 6 a.m. for paving operations. The northbound I-75 exit ramps to Griffin Road may be closed nightly, Sunday through Thursday, between 9 p.m. and 6 a.m. for milling and resurfacing. The northbound I-75 exit ramps to Royal Palm Boulevard may be closed nightly, Sunday through Thursday, between 9 p.m. and 6 a.m. for milling and resurfacing. The northbound I-75 entrance ramps from Royal Palm Boulevard may be closed nightly, Sunday through Thursday, between 9 p.m. and 6 a.m. for milling and resurfacing. 8. SR 93/ I-75 Resurfacing Project from South of I-595 to West of US 27 in Sunrise and Weston Description: Project improvements will include milling and resurfacing along SR 93/I-75 between south of I-595 and west of US 27 and installing guardrail and double-face guardrail throughout the project limits. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $8 million / spring 2023 Traffic Impact: All lanes are open. NORTHEAST BROWARD (Coral Springs, Deerfield Beach, Fort Lauderdale, Lauderhill, Lauderdale-By-The-Sea, Oakland Park, Pompano Beach, Sunrise) 9. Oakland Park Mobility Improvement Project from NW 136th Avenue to North Atlantic Boulevard in Sunrise, Lauderhill and Fort Lauderdale Description: This project will address mobility improvement on various roadways that intersect with SR 816/Oakland Park Boulevard from NW 136thAvenue to North Atlantic Boulevard in the cities of Sunrise, Lauderhill, and Fort Lauderdale. The project improvements consist of widening the roadway to accommodate bike lanes, milling and resurfacing, providing shared lanes (sharrows) and adding signage and pavement markings. Other improvements include installing traffic signal priority from NW 136th Avenue to Pine Island Road, new drainage structures, sidewalks, and ADA upgrades to curb ramps. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $3.5 million / early 2022 Traffic Impact: One lane in each direction will be closed intermittently along Inverrary Boulevard West from Oakland Park Boulevard to NW 42nd Street, 9 a.m. to 4 p.m., Monday through Friday, for sign and pavement marking installation. One lane in each direction will be closed intermittently along Environ Boulevard from Inverrary Boulevard West to La Mirage entrance, 9 a.m. to 4 p.m., Monday through Friday, for sign and pavement marking installation. The Oakland Park Boulevard Access Road from the north side of NE 32nd Avenue to the south side of NE 32nd Avenue will have intermittent closures, 9 a.m. to 4 p.m., Monday through Friday, for cleaning and litter removal. One lane in each direction along NE 32nd Street from NE 26th Avenue to NE 30th Avenue will be closed intermittently, 9 a.m. to 4 p.m., Monday through Friday, for signage installation. One lane in each direction along Middle River Drive from NE 26thAvenue to Oakland Park Boulevard will be closed intermittently, 9 a.m. to 4 p.m., Monday through Friday, for
clearing and grubbing, sidewalk installation, and roadway widening. 10. NW 31st Avenue Mobility Improvement Project in Fort Lauderdale Description: Project improvements consist of repurposing the outside travel lanes along NW 31st Street from Commercial Boulevard to NW 62nd Street to accommodate 5-foot bicycle lanes and widening the roadway and median from NW +62nd Street to West McNab Road to accommodate 4-foot bicycle lanes. Other improvements include traffic signal mast arms and pedestrian signalization at West Prospect Road, NW 65th Drive and West McNab Road, milling, resurfacing and adding pavement markings. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $3.5 million / summer 2022 Traffic Impact: The outside lane in each direction will be closed along NW 31st Avenue from Prospect Road and NW 65th Drive, 9 a.m. to 3:30 p.m., Monday through Saturday, for installation of curb pads and drilled shaft foundations. The inside lane in each direction will be closed along NW 31st Avenue from McNab Road to Commercial Boulevard, 9 a.m. to 3:30 p.m., Monday through Saturday, for curb and gutter installation in the median. 11. Coral Ridge Drive Mobility Improvement Project in Coral Springs Description: Project improvements consist of widening the roadway along Coral Ridge Drive from Southgate Boulevard to Wyndam Circle to accommodate 6-foot buffered bicycle lanes in each direction. Improvements also include upgrading vehicle and pedestrian signalization at West Atlantic Boulevard, Royal Palm Boulevard and Wiles Road. Other improvements include repairing the bridge deck joints on the bridge over the C-14 Canal (Bridge No. 864098) along Coral Ridge Drive, reconstructing sidewalk ramps, modifying and relocating drainage structures, milling, resurfacing and adding pavement markings. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $7.6 million / late 2022 Traffic Impact: One lane in each direction will be closed intermittently along Coral Ridge Drive from Southgate Boulevard to Wyndham Circle, 6 a.m. to 4 p.m., Monday through Saturday, for concrete demolition, drainage installation, signalization and curb and gutter operations and roadway widening operations. One lane in each direction will be closed intermittently along Coral Ridge Drive from Southgate Boulevard to Wyndham Circle, 6 p.m. to 6 a.m., Sunday through Thursday, for curb and gutter installation and roadway widening. 12. State Road (SR) A1A Resurfacing Project in Lauderdale-By-The-Sea Description: This project consists of resurfacing, restoration, and rehabilitation of the roadway along SR A1A from Pine Avenue to Sunset Lane. Work also includes installing and upgrading decorative pedestrian lighting and crosswalks at Bougainvilla Drive and Gatehouse Road. The midblock pedestrian crosswalks at the Assumption Catholic Church, north of Coral Reef Drive, and south of the Gardens by the Sea South Condominiums will be upgraded. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com Cost/Completion: $1.2 million/Early 2022 Traffic Impact: One lane in each direction may be closed intermittently along State Road A1A/Ocean Boulevard from Pine Avenue to Sunset Lane, 9 a.m. to 5 p.m., Monday through Friday, for sidewalk demolition and lighting installation. One lane along State Road A1A/Ocean Boulevard will be closed at Pine Avenue, 9 a.m. to 5 p.m., Monday through Friday, for curb and sidewalk concrete removal and restoration. One lane along State Road A1A/Ocean Boulevard will be closed at Bougainvilla Drive, 9 a.m. to 5 p.m., Monday through Friday, for lighting installation.
13. State Road 845/Powerline Road Mobility Improvement Project in Oakland Park Description: Project improvements consist of repurposing the outside lanes along SR 845/Powerline Road from SR 870/Commercial Boulevard to NW 29thStreet to accommodate 7- foot bicycle buffered bikes lanes and 4-foot raised landscaped islands in each direction. Improvements also include repurposing the outside lanes along SR 845/Powerline Road from SR 816/West Oakland Park Boulevard to NW 29th Street to accommodate 4-foot bicycle lanes. Other improvements include landscaping, irrigation, milling and resurfacing. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $3.1 million / spring 2022 Traffic Impact: The inside lane in each direction along Powerline Road will be closed from Commercial Boulevard to Prospect Road, 9 a.m. to 3:30 p.m., Monday through Saturday, for median operations and installation of sod. One lane may be closed in each direction along Powerline Road from Oakland Park Boulevard to Commercial Boulevard, 8 p.m. to 5 a.m., Sunday through Thursday, for striping operations. Powerline Road’s northbound outside lane from Oakland Park Boulevard to NW 38th Street is in its final configuration. It is now closed to vehicle traffic with the lane repurposed for a buffered bicycle lane and landscape bulb-outs. 14. Riverland Road Mobility Improvement Project in Fort Lauderdale Description: This project consists of widening Riverland Road from US 441/SR 7 to SR 736/Davie Boulevard to accommodate buffered bicycle lanes, repurposing the roadway from SR 736/Davie Boulevard to SR 842/Broward Boulevard to accommodate buffered bicycle lanes. Work also includes driveway tie-in reconstruction as needed, installing traffic signal mast arms and pedestrian signalization at SW 34th Terrace and the mid-block crossing just north of SW 11th Court. Improvements also include adding illuminated raised pavement markings to delineate the bike and travel lanes, installing sidewalks, signage, curb and gutter, milling and resurfacing and adding pavement markings. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $5.8 million / summer 2022 Traffic Impact: The outside lane in each direction will be closed with a flagging operation along Riverland Road from State Road 7/US 441 to Elizabeth Mays Civic Park, 9 a.m. to 3:30 p.m., Monday through Saturday, for drainage operations. The southbound lane along Riverland Road will be closed from SW 10thStreet to SW 11th Court, 9 a.m. to 3:30 p.m., Monday through Saturday, for controller cabinet signal work. 15. Powerline Road Lighting Improvement Project in Deerfield Beach Description: Project improvements consist of installing 27 new LED light poles and retrofitting seven existing light poles along Powerline Road to provide efficient light distribution, save energy and reduce maintenance cost. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $441,981 / fall 2021 Traffic Impact: All lanes are open. 16. Hammondville Road Mobility Improvement Project in Pompano Beach Description: Project improvements consist of widening the lanes and reducing the median to accommodate 7-foot buffered bicycle lanes in each direction, upgrading pedestrian signalization at the mid-block crossing east of NW 18thDrive with pedestrian detectors. Other improvements include installing and upgrading pedestrian lighting in each direction, installing landscaping and
irrigation in the median, upgrading signage, installing pavement markings, milling and resurfacing the roadway. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com. Cost/Completion: $3 million / summer 2022 Traffic Impact: The inside lane in each direction along Hammondville Road/Martin Luther King Jr. Boulevard will be closed from Powerline Road to NW 15thAvenue, 9 a.m. to 3:30 p.m., Monday through Saturday, for roadway widening and paving. The outside lane in each direction along Hammondville Road/Martin Luther King Jr. Boulevard will be closed from NW 15th Avenue to NW 13th Avenue, 9 a.m. to 3:30 p.m., Monday through Saturday, for roadway widening and paving operations. 17. Sample Road Resurfacing and Lighting Project in Deerfield Beach and Pompano Beach Description: Project improvements consist of resurfacing, restoration and rehabilitation of the roadway along Sample from Military Trail to US 1/Federal Highway. Work also includes the installation of nine new light poles, retrofitting of 21 existing light poles and upgrades to the pedestrian signalization at NW 5th Terrace and Dixie Highway, NE 12th Avenue, NE 15th Avenue and US 1/Federal Highway. Other improvements are installing high emphasis pavement markings and signing at the Florida East Coast Railroad (FEC) crossing, minor drainage, improving signing and pavement markings. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com Cost/Completion: $2.7 million / late 2021 Traffic Impact: One lane in each direction may be closed along Sample Road from Military Trail to I-95, 7 a.m. to 3:30 p.m., Monday through Saturday, for concrete installation, drainage operations, roadway widening, signalization, lighting, clearing, and grubbing. One lane in each direction will closed along Sample Road from Military Trail to I-95, 9 p.m. to 5:30 a.m., Sunday through Thursday, for manhole adjustments. One lane in each direction may be closed intermittently along Sample Road from NE 3rd Avenue to US1/North Federal Highway, 9:30 a.m. to 3:30 p.m., Monday through Saturday, for clearing and grubbing, manhole adjustments, signalization, and concrete installation. One lane in each direction will be closed intermittently along Sample Road from NW 3rd Avenue to US1/North Federal Highway, 9 p.m. to 5:30 a.m., Sunday through Thursday, for manhole adjustments and directional boring operations. 18. Henry E. Kinney Tunnel Improvements and Pedestrian Plaza Project in Fort Lauderdale Description: Project improvements include rehabilitating the structural, mechanical, electrical, architectural, and life safety components of the Henry E. Kinney Tunnel; milling and resurfacing SR 5/ US-1 from Rio Vista Boulevard to south of the Tunnel; installing Intelligent Transportation Systems (ITS) along SR 5/ US-1; extending the tunnel top to accommodate a pedestrian plaza which will include new fountains, seating facilities, re-designed brick pavers, artificial turf and landscape installation, and reconstructing the intersection of Las Olas Boulevard at SE 6th Avenue. For more information, contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Anticipated Construction Start: Sept. 7, 2021 Cost/Completion: $ 24.8 Million / late 2023 Traffic Impacts: SE 6th Avenue in each direction, from Las Olas Blvd to SE 2nd Street, will be closed to traffic through 7 a.m., Monday, Nov. 8 for wall demolition activities and construction of end bents for the proposed tunnel extension. Motorists traveling westbound or eastbound on Las Olas Boulevard wishing to access Federal Highway (US-1) via SE 6th Avenue will be detoured to SE 8th Avenue.
Motorists traveling southbound on Federal Highway (US-1) wishing to access Las Olas Boulevard via SE 6th Avenue will be detoured to SE 5th Avenue. Signage will be in place to direct motorists. US-1 in each direction through the tunnel, from SE 5th Court to SE 2nd Street, will have the outside lanes closed through 7 a.m., Monday, Nov. 8 for wall demolition activities and construction of end bents for the proposed tunnel extension. Westbound Las Olas Boulevard, from just west of 8th Avenue to just west of southbound 6th Avenue, will have the outside lane closed to traffic through 7 a.m., Monday, Nov. 8 for demolition operations of the north tunnel exit. Pedestrian Impacts: The pedestrian sidewalk along US-1 in each direction, from SE 6th Street to Las Olas Boulevard, will be closed through 7 a.m., Monday, Nov. 8 for end bent and tunnel top operations. Pedestrians will be detoured via SE 3rd Avenue. The Pedestrian sidewalk on southbound SE 6th Avenue, from Las Olas Boulevard to SE 2nd Street, will be closed through 7 a.m., Monday, Nov. 8 for end bent and tunnel top operations. Pedestrians will be detoured via SE 3rd Avenue. The pedestrian crosswalk on Las Olas Boulevard in front of the Henry E. Kinney Tunnel, from southbound SE 6th Avenue to northbound SE 6th Avenue, will be closed through 7 a.m., Monday, Nov. 8 for demolition operations. Pedestrians will be detoured via the south sidewalk on Las Olas Boulevard. 19. State Road (SR) 844/14th Street Causeway Bridge Painting Project in Pompano Beach Description: This 351-foot project in the city of Pompano Beach will begin October 7. It consists of painting the steel and concrete portions of the SR 844 / 14th Street Causeway bascule bridge (Bridge No. 860060) over the Intracoastal Waterway and refurbishing the span locks and other mechanical components of the bridge. For more information, please contact Community Outreach Specialist Angel Streeter Gardner at 561-886-8773 or angel@valerin-group.com. Cost/Completion: $1.07 million/Spring 2022 Traffic Impact: All lanes are open. NORTHWEST BROWARD (Coconut Creek, Coral Springs, Deerfield Beach, Fort Lauderdale, Lauderhill, Lauderdale- By-The-Sea, Lauderdale Lakes, Margate, Oakland Park, Plantation, Pompano Beach Sunrise, Wilton Manors) 20. Lighting Improvements Project in Coral Springs, Margate, Pompano Beach, Deerfield Beach and Fort Lauderdale Description: This project will take place along four major state roads: SR 817/University Drive, SR 834/Sample Road, SR 845/Powerline Road and SR 814/Atlantic Boulevard. The improvements will upgrade the illumination at signalized intersections with new light poles, new light fixtures and retrofit existing lighting fixtures with LED lights. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin- Group.com. Cost/Completion: $1.4 million / spring 2021 Traffic Impact: All lanes are open. 21. Lighting Improvements in Tamarac, Lauderhill, Fort Lauderdale, Oakland Park, Lauderdale-by-the-Sea, Lauderdale Lakes, Sunrise and Wilton Manors Description: This project will take place along two major state roads: SR 870/Commercial Boulevard and SR 816/Oakland Park Boulevard. The improvements will upgrade the illumination
at signalized intersections with new light poles, new light fixtures and retrofit existing lighting fixtures with LED lights. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com Cost/Completion: $1.8 million / early 2021 Traffic Impact: All lanes are open. 22. Lyons Road Mobility Improvement Project from the C-14 Canal to the Sawgrass Expressway in the city of Coconut Creek Description: This project consists of widening the roadway to accommodate new bike lanes. Improvements will also include signalization upgrades, sidewalks, miscellaneous signage, paving, restriping, drainage, lighting, bus shelters, curb and gutter, and driveways to meet Americans with Disabilities Act (ADA) standards. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin-Group.com Cost/Completion: $11,069,050 / fall 2021 Traffic Impact: One to two lanes in each direction will be closed intermittently along Lyons Road from Atlantic Boulevard to Sawgrass Expressway, 8:30 a.m. to 4:30 p.m., Monday through Friday, for signalization, irrigation work, sidewalk installation, milling and resurfacing. 23. Lighting Improvements in Fort Lauderdale, Lauderdale-by-the-Sea, Plantation, Sunrise and Lauderhill Description: This project will take place along two major state roads: State Road A1A and Sunrise Boulevard. The improvements will upgrade illuminations at signalized intersections with new light poles and new light fixtures and retrofit existing lighting. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin- Group.com. Cost/Completion: $1,550,074 / spring 2021 Traffic Impact: All lanes are open. 24. State Road (SR)/Oakland Park Boulevard Bridge Project Description: Project consist of installing gabion mattress for scour prevention along the canal bottom and side slopes to protect the bridge foundation. For more information, contact Community Outreach Specialist Justina I. Hicklyn at (954) 482-4190 or justina@Valerin- Group.com. Cost/Completion: $1.4 million/Spring 2022 Traffic Impact: All lanes are open. Marine Traffic Impact: Half-channel closures can be expected for sediment containment, during construction operations. Access will be always maintained. SOUTHWEST BROWARD (Dania Beach, Hollywood, Miramar, Pembroke Pines, Sunrise, Weston) 25. Miramar Park and Ride Lot Project in Miramar Description: Project Improvements include constructing a new park and ride lot with 488 parking spaces, including handicap and bus spaces, bus shelters, sidewalks and bicycle racks, installing landscaping and lighting within the parking lot, adding school zone signage and a right
turn lane on Pembroke Road. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $6,650,357 / spring 2022 Traffic Impact: All lanes are open. 26. Southwest Broward Mobility Improvements Project in Hollywood and Miramar Description: Project improvements include widening the roadway to accommodate 7-foot buffered bicycle lanes and adding sidewalks to create a continuous facility in each direction of SW 56th Avenue; adding shared lane pavement markings in each direction along SW 62nd Avenue and North 64thAvenue to enhance the safe travel of bicycles and motor vehicles in the same traffic lane; and adding sidewalks to create a continuous facility in each direction of SW 62nd Avenue. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $4,993,116 / early 2022 Traffic Impact: One lane in each direction of SW 62nd Avenue from Pembroke Road to County Line Road will be closed Monday through Friday, between 9 a.m. and 4 p.m., to address punch list items. Detours might be implemented through adjacent roads if necessary, to improve safety. Flaggers will be present and detour signs will be in place to direct motorists around the work zone. One lane in each direction of S 56th Avenue/N 56th Ave from Pembroke Road to Stirling Road will be closed 9 a.m. to 4 p.m., Monday through Friday, for sidewalk construction, swale improvements, and asphalt placement. Detours might be implemented through adjacent roads if necessary, to improve safety. Flaggers will be present and detour signs will be in place to direct motorists around the work zone. Pedestrian signal improvements will take place at the intersections of S 56th Avenue/N 56th Avenue with Pembroke Road, Washington Street, Hollywood Boulevard, Johnson Street, Taft Street, Sheridan Street, and Stirling Road from 9 a.m. to 4 p.m., Monday through Friday. Workers will be present and lane closures will be place in the vicinity to direct motorists around the work zone. Northbound traffic on N 56th Ave from Oak Lake Park to N Hills Drive has been shifted towards the west for road widening, swale improvements, and sidewalk construction. Motorists must follow the new traffic pattern when traversing the work zone area. 27. SR 823/Flamingo Road and SR 820/Pines Boulevard Intersection Improvement Project in Pembroke Pines Description: Project Improvements consist of upgrading existing traffic signal, lighting and pedestrian features, installing new light poles and curb ramps to meet Americans with Disabilities Act (ADA) requirements. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $737,736 / fall 2021 Traffic Impact: The right-turn lane and sidewalk on northbound Flamingo Road to eastbound Pines Boulevard may be closed Monday through Friday, between 9 a.m. and 3:30 p.m., only one corner at a time. The right-turn lane and sidewalk on southbound Flamingo Road to westbound Pines Boulevard may be closed Monday through Friday, between 9 a.m. and 3:30 p.m., only one corner at a time. The right-turn lane and sidewalk on westbound Pines Boulevard to northbound Flamingo Road may be closed Monday through Friday, between 9 a.m. and 3:30 p.m., only one corner at a time. The right-turn lane and sidewalk on eastbound Pines Boulevard to southbound Flamingo Road may be closed Monday through Friday, between 9 a.m. and 3:30 p.m., only one corner at a time.
28. SR-84 Resurfacing Improvements Project in Sunrise and Weston Description: Project Improvements consist of milling and resurfacing the roadway and replacing pavement markings, widening the shoulder along SR-84, installing bicycle lanes at Indian Trace and Glades Parkway, and repairing guardrail as needed, along westbound SR-84. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $4.4 million / early 2023 Traffic Impacts: One lane along Glades Parkway, Indian Trace Road, Bonaventure Boulevard, and Weston Road at SR-84 will be closed as needed, Monday through Friday, between 7 a.m. and 4 p.m. for the demolition of existing curb, excavation, and installation of new concrete curbs. The right lane on eastbound SR-84 between Glades Parkway and Weston Road will be closed as needed, Monday through Friday, between 7 a.m. and 4 p.m. for the demolition of existing curb, excavation, widening and installation of new concrete curbs. 29. SW 40 Avenue Mobility Improvements Project in Dania Beach and Hollywood Description: Project Improvements include widening the roadway to accommodate 5-foot bicycle lanes in each direction, providing continuous sidewalks on both sides of the road, installing a bulkhead wall with a traffic railing at Lake George, upgrading vehicle and pedestrian signalization at Griffin Road, milling, resurfacing, and replacing pavement markings. For more information, contact Community Outreach Specialist Rebecca Guerrero at (954) 218-2304 or rguerrero@corradino.com. Cost/Completion: $ 3,377,160 / spring 2023 Traffic Impact: Southbound SW 40th Avenue from Griffin Road to SW 49th Court will be closed Monday through Friday, as needed, between 7 a.m. and 5 p.m. for the installation of sheet pile walls at Lake George. Traffic will be detoured via SW 43rd Court and SW 49th Court. One eastbound lane along Griffin Road will be closed Monday through Friday, between 7:30 a.m. and 3:30 p.m., for the installation of sheet pile walls at Lake George. One southbound lane along SW 40 Avenue between Stirling Road and Griffin Road will be closed Monday through Friday, between 7:30 a.m. and 3:30 p.m., for the installation of drainage structures. Flaggers will be on site assisting drivers traveling southbound. Pedestrian detours will also be in place directing pedestrians around the work zone. MAINTENANCE, UTILITY, PERMIT & ADDITIONAL AGENCY PROJECTS INTERSTATE: Southbound I95 to Andrews Avenue exit ramp, in Fort Lauderdale, 9:30 p.m. until 3:30 a.m., Monday through Friday, Monday, Sept. 27 through Friday, Oct. 22, 1 of 1 lanes closed, for soil boring. For more information, please contact Michelle Rossi 954-928-1828. Southbound I95 1,500’ ft South of North Andrews Avenue overpass, in Fort Lauderdale, 9:30 p.m. until 4:30 a.m., Monday through Friday, Monday, Sept. 27 through Friday, Oct. 22, 1 of 1 lanes closed, for soil boring. For more information, please contact Michelle Rossi 954-928- 1828. Southbound I95 to North Andrews Avenue on-ramp, in Fort Lauderdale, 9:30 p.m. until 4:30 a.m., Monday through Friday, Monday, Sept. 27 through Friday, Oct. 22, 1 of 1 lanes closed, for soil boring. For more information, please contact Michelle Rossi 954-928-1828. Southbound I95 to Andrews Avenue exit ramp, in Fort Lauderdale, 9:30 p.m. until 4:30 a.m., Monday through Friday, Monday, Sept. 27 through Friday, Oct. 22, 1 of 1 lanes closed, for soil boring. For more information, please contact Michelle Rossi 954-928-1828.
Northbound I-95 just 300’ ft South of Hallandale Beach Boulevard, in Hallandale Beach, 10 p.m. until 5 a.m., Monday through Friday, through Thursday, Oct. 25, 1 of 1 lanes closed as needed, for light pole installation. For more information, please contact Ernesto Gutierrez (561) 352-1379. Westbound Royal Palm Boulevard 0.2 mile South of I595 and I75 interchange bridge 860341, in Weston, 9 pm - 4 am, One night only, Monday, Oct. 04 through Tuesday, Oct. 05, 1 of 4 lanes closed, for joint repair. For more information, please contact Miguel Sosa 954-295-0125. Northbound I75 under bridge 860346, in Davie, 9 pm - 4 am, One night only, Wednesday, Oct. 06 through Thursday, Oct. 07, 1 of 2 lanes closed, for bridge repair. For more information, please contact Miguel Sosa 954-295-0125. Southbound Sawgrass Expressway 0.1 mile of I75 interchange SS 86S975, in Weston, 9 pm - 4 am, One night only, Thursday, Oct. 07 through Friday, Oct. 08, 2 of 5 lanes closed, for signage repair. For more information, please contact Miguel Sosa 954-295-0125. Northbound I75 at mile marker 12, in Davie, 9 pm - 4 am, One night only, Tuesday, Oct. 05 through Wednesday, Oct. 06, 2 of 4 lanes closed, for DMS Sign repair. For more information, please contact Mark Chambers 954-328-8053. Northbound I95 between milepost 0.000 Miami/Dade County line to milepost 3.095 Broward County line up to Johnson Street, in Miami/Dade and Broward County lines, 8 pm -1 am, One night only, 1 of 6 lanes closed as needed, for FWD deflection testing. For more information, please contact Miguel Sosa 954-295-0125. FLORIDA’S TURNPIKE: Northbound and southbound Florida’s Turnpike/SR 821 between I-75 and University Drive/ NW 27 Avenue/SR 817, Overnight single lane closures, 8 p.m. to 6 a.m., Sunday, October 3, and nightly through Thursday, October 7. For more information, please contact Fiorella Teodista at Fiorella.Teodista@dot.state.fl.us. Northbound and southbound Florida’s Turnpike/SR 821 between the Snake Creek Canal Bridge and Red Road/NW 57 Avenue, Daytime single lane closures, 9 a.m. to 3:30 p.m., Monday, October 4, and daily through Friday, October 8. For more information, please contact Fiorella Teodista at Fiorella.Teodista@dot.state.fl.us. Southbound Flamingo Road/NW 67 Avenue under Florida’s Turnpike/SR 821 Long-term single lane closure through October 2021. One lane will remain open. For more information, please contact Fiorella Teodista at Fiorella.Teodista@dot.state.fl.us. Northbound and southbound Flamingo Road/NW 67 Avenue under Florida’s Turnpike/SR 821, Overnight full road closures, 11 p.m. to 5 a.m., Sunday, October 3, and nightly through Thursday, October 7. Detour information: Northbound Flamingo Road/NW 67 Avenue traffic wishing to continue north will be directed to NW 202 Street, travel east on NW 202 Street to Red Road/NW 57 Avenue/SR 823, travel north on Red Road to Miramar Parkway/SR 858 and travel west on Miramar Parkway to access Flamingo Road. Southbound Flamingo Road/NW 67 Avenue traffic wishing to continue south will be directed to Miramar Parkway/SR 858, travel east on Miramar Parkway to Red Road/NW 57 Avenue/SR 823, travel south on Red Road to NW 202 Street and travel west on NW 202 Street to access Flamingo Road. For more information, please contact Fiorella Teodista at Fiorella.Teodista@dot.state.fl.us. Northbound Red Road/NW 57 Avenue under Florida’s Turnpike/SR 821 Overnight single lane closures, 8 p.m. to 5 a.m., Sunday, October 3, and nightly through Thursday, October 7. A second lane will close at 10 p.m. Both lanes will open by 5 a.m. For more information, please contact Fiorella Teodista at Fiorella.Teodista@dot.state.fl.us. Northbound and southbound Palm Avenue/NW 47 Avenue under Florida’s Turnpike/SR 821, Daytime single lane closures, 9 a.m. to 4 p.m., Monday, October 4, and daily through Friday,