LS2 a great success in spite the COVID LS2 Master Schedule Version 3.1 End-of-year online meeting Frédérick Bordry 2 15th December 2020
Today Linac 4 Progressive restart of LS2 activities Linac4 beam setup completed, ready to inject beam into the PSB Excellent source stability Low-energy part of the linac re-optimized for better matching to the accelerating structures and improved transmission Different transfer line optics prepared and applied to adapt to different Accelerating structures in Linac4 beam production schemes in the PSB Source Availability Improved machine safety > 99% over the last 3 months Increase of Linac4 availability (up to 99%) (1/9/2020 – 30/11/2020) All cycles required during the first weeks of PSB beam commissioning have been prepared Linac 4 Availability exceeds frequently 95% since beginning of End-of-year online meeting October 2020 Frédérick Bordry 3 15th December 2020
Today Booster - PSB Progressive restart of LS2 activities Completed period of hardware commissioning which lasted 3.5 months PSB machine was almost rebuilt during LS2 Profound changes to equipment and operational controls Intense period with hardware tests as well as installation activities to be finished, e.g. magnet cover consolidation New PSB magnet covers installation All new critical injection equipment currently receiving beam from Linac4 PSB ready to operate with new equipment and controls Beam Commissioning 7th December: start of 2.5 months of beam commissioning PS Booster key on 3 July 2020 End-of-year online meeting Frédérick Bordry 4 15th December 2020
Booster – PSB: beam commissioning started the 7th December Pre-LS2 Example • At 13h00 first beam crossing LTB.BHZ40 and threading to the first BTV, BI.BTV10 Beam Head Ring3 Ring3 End-of-year online meeting Frédérick Bordry 5 15th December 2020
Booster – PSB: Circulating Low Intensity Beam • Insert the stripping foil in PSB ring 3 • Inject H- beam, strip electrons → proton beam circulating for 1 turn, until the BTV in sector 15L1! • After optimizing injection parameters, managed to circulate a few E10 protons in the PSB for several 100s of ms, i.e. almost the entire length of the magnetic cycle. BCT in the PSB ring 3 End-of-year online meeting Frédérick Bordry 6 15th December 2020 Courtesy of Bettina and Gian Piero
PS: Hardware tests PS installation, alignment and Individual System Tests Phase successfully completed on 23 October Machine officially handed over from shutdown coordination team to operation team Hardware commissioning Main power supply and magnet tests successfully completed Handover of the PS key to the Checklist items rapidly ticked according to schedule operation crew on 23 October Upcoming February 2021: Final hardware tests linking different systems March 2021: First beam injection from PSB Pulsing of the PS main power supply End-of-year online meeting Frédérick Bordry 7 15th December 2020
East Area Renovation Project The facility is old thus causing reliability issues and operational restrictions. The primary beam line is generating high radiations, due to the nature of its usage and the lack of ventilation. The buildings achieved in the 60’s are not insulated and contain hazardous material. Power is currently supplied to the magnets on a continuous basis, with only 7% of it actually being used during beam time. Power converters to the new magnets will be on a cyclical basis, with an energy recovery stage between each cycle. The energy returned by the magnets during their de-magnetisation will be stored in capacitor banks connected to the new power converters and immediately reused during the next cycle to re-magnetise the magnets. From 11 GWh/year to 10 MJ of energy storage factory tested and received at CERN Goal: around 0.6 GWh/year (> 90% reduction) End-of-year online meeting Frédérick Bordry 9 15th December 2020
East area renovation F61 Mixed area • Dismantling finished • Beamline re-installation started (F61 finished) • Building 251 installation completed • Electrical non-conformities fully addressed • Individual System Tests started • On schedule for beam late summer 2021 Power Converter Farm End-of-year online meeting Frédérick Bordry 10 15th December 2020
East Area Renovation Project: energy saving Validated with the first 15 converters Confirmed Projected 15 converters 61 converters Average power: 31.2kW 128.6kWh Operation time: 4300h/year 4300h/year Annual 136 MWh 553 MWh consumption: Instead of: 2230 MWh 9128 MWh TOTAL SAVING: 8575 MWh/year End-of-year online meeting Frédérick Bordry 11 15th December 2020 Courtesy of Konstantinos Papastergiou
AD/ELENA – Ready for Post-LS2 Beam profiles in TL’s August 2020 November 2018 ELENA ring 2020 highlights 25 AD ring magnets refurbished PUMA new exp area LNE51 TL BHW09 End-of-year online meeting Frédérick Bordry 12 15th December 2020
Today SPS Progressive restart of LS2 activities SPS installation and testing activities (I) All installations in Long Straight Section with radiofrequency (RF) equipment completed All six reconfigured RF cavities successfully connected to their amplifiers and currently being processed Two RF cavities fed by brand new power system One RF cavity ready to test controls 32 new amplifier towers to feed two RF cavities All RF cavities successfully powered up to target peak power Cavity being processed in the tunnel End-of-year online meeting Frédérick Bordry 13 15th December 2020
Today SPS Progressive restart of LS2 activities SPS installation and testing activities (II) Installation of full new beam dump system in the machine successfully executed in November ahead of schedule Now commissioning the beam dump’s cooling system Happening and upcoming 4 December: Machine handover from shutdown coordination to operation team and start of hardware commissioning April 2021: End of 4 months of hardware commissioning and beginning of Insertion of beam dump block in external shielding beam commissioning Handover of the SPS key to the operation crew on 4th December Installation of new beam dump End-of-year online meeting Frédérick Bordry 14 15th December 2020
SPS-FIRE Safety Project: the new automatic fire SPS-ACCESS Project: the new access system to detection & fire protection systems are fully operational the SPS ring and transfer tunnels is fully operational End-of-year online meeting Frédérick Bordry 15 15th December 2020
AWAKE has been very active in 2020 ! End-of-year online meeting Frédérick Bordry 16 15th December 2020
RS November 23, 2020 Injector Accelerator Schedule 2021 Version 1.0 2021 Injectors Schedule Start L4 with beam Resume L3 beam test Start PSB with beam Approved by Reasearch Board on 02.12.2020 LHCINDIV Low int. TOF to PS Low int. R3 MTE to PS Low int. MTE to PS LHC25-R3 to PS End L3 beam test Jan Feb Mar Wk 53 1 2 3 4 5 6 7 8 9 10 11 12 Mo 28 4 11 18 25 1 8 15 22 1 8 15 22 Sys. Admin. days SPS Cold Check-out Tu SPS Cold Check-out SPS Cold Check-out SPS Cold Check-out PS Cold Check-out PS Cold Check-out PS Cold Check-out Approved by We Closure Annual Th Fr Sa Research Board on Su LHC25 MTE-core LHCIndiv to to SPS Start L3 MTE 5E12 to SPS LHCPilot to SPS MTE-nom. to PS MTE-nom. to SPS LHC25 to SPS FT Beam to Beam to SPS LHCPilot Ready Start L3 with beam AD Beam Start ISOLDE Beam to 2nd December 2020 Apr to PS SPS source May TT20 TED ISOLDE June to PS physics AD target Wk 13 14 15 16 17 18 19 20 21 22 23 24 25 SPS Cold Check-out Mo 29 Easter Mon 5 12 19 26 3 10 17 Whit 24 31 7 14 21 Tu We Technical Stop SPS Scrubbing SPS Scrubbing SPS Scrubbing SPS Scrubbing ITS (48 hrs) L4 Source Th exchange Ascension SPS Scrubbing Restart Fr G. Friday May Day Sa Su Start SPS-NA FT beam to Ions to EARLY East Area NOMINAL FT physics Beam to TDC2/TCC2 LEIR Beam to Ions to Beam to PS Pbars to Ions to Start ELENA Pbars to East Area July AD nTOF target PS Aug ELENA PS physics Sep Wk 26 27 28 29 30 31 32 33 34 35 36 37 38 SPS Parallel LIU MD 08:00 - 18:00 Mo 28 5 12 19 26 2 9 16 23 30 6 13 20 AWAKE Par. SPS MD Tu 8:00 - 18:00 Cool-down Low int. test Ded. Inj. MD Ded. Inj. MD SPS-NA Setting-up Ded. Inj. MD Ded. Inj. MD Ded. Inj. MD Ded. Inj. MD Ded. Inj. MD SPS-NA Setting-up Ded. Inj. MD We 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 Technical Stop HiRadMat 2 HiRadMat 1 ITS (30 hrs) AWAKE AWAKE AWAKE AWAKE Par. SPS MD Par. SPS MD Par. SPS MD Par. SPS MD Par. SPS MD Par. SPS MD Restart Th 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 Jeune G Coldex Run 24 hrs Fr AWAKE Sa Su Ions to End p+ beams Start nTOF Start East Start LINAC4 Start PSB SPS End Pb beams physics HWC (2021) HWC (2021) Oct Area physics Nov 06:00 Dec Wk 39 40 41 42 43 44 45 46 47 48 49 50 51 SPS Parallel LIU MD 08:00 - 18:00 Mo SPS Parallel ions commissioning 07:00 - 20:00 SPS Parallel ions commissioning 07:00 - 20:00 SPS Parallel ions commissioning 07:00 - 20:00 27 4 11 18 25 1 8 15 22 29 6 13 20 Sys. Admin. days Tu Rad. Survey Ded. Inj. MD Ded. Inj. MD Ded. Inj. MD Ded. Pb Comm.. We 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 8:00 - 18:00 HiRadMat 3 YETS Closure Annual AWAKE AWAKE Par. SPS MD Ded. Pb Comm.. Th 8:00 - 18:00 8:00 - 18:00 Fr LHC beam Sa test Run Xmas AWAKE Su Injector Complex MD Block (dedicated) HiRadMat Run Special interventions/stops Injectors Technical Stop AWAKE Run xxxxx CERN Official Holidays End-of-year online meeting Protons physics LIU parallel MD Controls system interventions Frédérick Bordry LHC beam test period Special Run Pb ion commissioning SPS MD block (parallel) YETS & HWC 2021 17 15th December 2020
LHC schedule End-of-year online meeting Frédérick Bordry 18 15th December 2020
DISMAC project status: diode consolidation Diodes Insulation and Super-conducting MAgnets Consolidation 3rd August 2020: Last Interconnection Closure QBBI.8L8 sector 78 Pakistan Atomic Energy Commission End-of-year online meeting Frédérick Bordry 19 15th December 2020 Courtesy of Jean-Philippe Tock
Energy recovery CERN-P8 heat recovery injected into a local energy network 10MW exchangers on cooling towers (ZAC Ferney-Voltaire innovation) End-of-year online meeting Frédérick Bordry 20 15th December 2020
Cryogenic challenges in 2020 Sector 8-1 Sector 1-2 Sector 7-8 Sector 3-4 Sector 4-5 Sector 5-6 New helium liquefier in SM18 End-of-year online meeting Frédérick Bordry 21 15th December 2020 Courtesy of Dimitri Delikaris
LIU: Budget situation and EVM status (Nov. 2020) In kCHF In kCHF Material 158,131 952,394 LIU Cost to completion M to P 23,072 181,203 HL-LHC Cost to completion Material 989,109 M to P 36,715 (Personnel +Material) Personnel 153,220 (Personnel +Material) Personnel 448,019 334,423 1,437,128 EV 176 MCHF EV 382 MCHF 96% 37% Cost variance Schedule variance Cost Variance Schedule Variance in kCHF in kCHF in month in kCHF in kCHF in Months 2,211 Active baseline -2,184 -2.9 20,402 Active Baseline -27,961 -3.1 2019 CSR baseline -4,594 -4.6 CSR 2019 Baseline -61,753 -6.2 CSR 2018 baseline -79,516 -8.4 End-of-year online meeting Frédérick Bordry 22 15th December 2020
HL-LHC: Power Transmission Line for HL-LHC Triplets MgB2 cable: 90 mm Itot > 100 kA @ 25 K A total current of up to 120 kA Industrialization on-going MgB2 L= 60 m System demonstrator in SM 18 End-of-year online meeting Frédérick Bordry 15th December 2020 Courtesy of Amalia Ballarino 23
HL-LHC: 2nd Long Prototype quadrupole (MQXFBP2) ready for cryostating MQXFBP2 magnet (7.2 m) assembly completed in September 2020. Assembly went smoothly, implementing lessons learnt from MQXFBP1 and MQXFBMT2. Testing in February 2021 End-of-year online meeting Frédérick Bordry 24 15th December 2020
End-of-year online meeting Frédérick Bordry 25 15th December 2020
Consolidation and upgrade of LHC experiments’ vacuum LHCb beampipe LHCb beampipe CMS beampipe ALICE: X-rays inspection of VMDBB module ALICE: A-side after TPC movement ATLAS beampipe dismounting End-of-year online meeting Frédérick Bordry 26 15th December 2020
LHC : cool down and hardware commissioning LHC-LS2 schedule V 3.1 under study following the short to ground End of Magnet Trainings Low intensity beam test (1 week) End-of-year online meeting Frédérick Bordry 27 15th December 2020
FCC footprint exploration (for 12 suitable surface sites) Since CDR, much detailed input was gathered on „territorial constraints“ CDR placement to be disregarded. Enormous amount of requirements to be respected simultaneously (machine design, geology, urbanistic, environmental, ...). Efficient tool needed to - vary machine and geographical ring parameters and update the resulting positions of 12 access points in real time; - use various base maps and superimpose additional layers (e.g. constraints maps/“sensibility grids”). While using it, underground and transfer line criteria are borne in mind. Following that first step, results are output for further processing (ArcGIS DB, site description/analysis, “micro-optimisation”, …). select bas map and overlays WebApp „FCC Footprint Explorer“ (1500 lines of JavaScript) vary machine and geographical parameters for chosen parameters, the new trace and all point positions are updated in real time traces only for illustration „Assisted pre-search“ (additional SW module varies machine parameters automatically within chosen limits Many scenarios were looked at individually and candidates and outputs candidate scenarios retained for further evaluation and optimisation (collaboration with enough hits in „target zones“ of J. Gutleber, V. Mertens, A.-L. Verdier, Host State bodies). 28 for manual post-optimisation). End-of-year online meeting Frédérick Bordry 15th December 2020 ERC: Eviter Réduire Compenser 28
FLASH radiotherapy: CDR in 2020 An intense beam of electrons is produced in a photoinjector, accelerated to around 100 MeV and then is expanded, shaped and guided to the patient. The design of this facility is the result of an intense dialogue between groups at CHUV and CERN. Jean Bourhis from CHUV: “The clinical need that we have really converges with the technological answer that CERN has.” End-of-year online meeting Frédérick Bordry 29 15th December 2020
NIMMS: Next Ion Medical Machine Study End-of-year online meeting Frédérick Bordry 15th December 2020 https://indico.cern.ch/event/956260/ 30
- LS2 is over in the injectors: hardware and beam https://indico.cern.ch/event/980341/ commissioning under progress. - 2021 Injector schedule approved by Research Board - LHC: Sector cool down under progress Powering tests and magnet training in 2021 Low intensity beam test by September 2021 Beam operation in February 2022 Many thanks to the coordination of LS2, the project managements and all the teams (CERN, collaborators from Institutes and Universities, Industrial Support Teams) for their work and commitment in this difficult period. The hardware and beam commissioning are and will be an absorbing and captivating period
End-of-year online meeting Frédérick Bordry 32 15th December 2020
My heartfelt thanks End-of-year online meeting Frédérick Bordry 33 15th December 2020
Joyeuses Fêtes et bonne année 2021 Happy Holidays and Happy New Year 2021 STAY SAFE (Safety First) and HEALTHY End-of-year online meeting Frédérick Bordry 34 15th December 2020
Booster – PSB: new main power converter (POPS B) Milestone activity of the PSB HW commissioning carried out : About 6000 A peak current, 3000 V peak voltage and 18 MW peak power. About 7000 kJ stored in capacitors ≈ 2 kg of TNT! Reliability run ongoing: POPS-B and main magnets pulsed more than 270000 times since the beginning of the commissioning. Pulsing at both 1.4 GeV (pre-LS2) and 2.0 GeV (post-LIU) kinetic energies. As a side note, the previous Main Power Supply (MPS) was also resurrected and tested at 1.4 GeV and will serve as emergency backup. Example of different PSB magnetic cycles alternating 1.4 GeV and 2.0 GeV extraction POPS-B installation in the new Building 245 End-of-year online meeting Frédérick Bordry 35 15th December 2020
Upgraded beam collimation for Run 3 Coated secondary collimators: 6/8 installed IR7 The first phase of HL-LHC collimation upgrade — Dispersion suppressor cleaning for ALICE — Low-impedance primary and secondary (coated) collimators in IR7 — Passive absorbers for IR7 22 collimators built! TCSPM #4 Impedance reduction: low- impedance, high robustness secondary collimators: coated MoGr Un-coated MoGr primary collimators. Dispersion suppressor collimation: Secondary Primary MoGr collimators: beams from ion physics 4/4 installed IR7 DS collimators ALICE: 2/2 installed IR2 Very successful collaboration End-of-year online meeting Frédérick Bordry across several groups in the 36 15th December 2020 ATS sector!
New Injection / Extraction systems in accelerators New LIU-PSB 160 MeV H- injection system with 16 New LIU-PS 2 GeV injection pulsed New MKDV kicker magnets for LIU- chicane magnets and 4 stripping foil assemblies eddy-current septum SPS beam dump system in LSS5 160 MeV H- Linac4 beam at PSB, ELENA beamline fast deflectors Upgraded SPS ZS electrostatic septa kicked by new LIU distributer installed and commissioned for LIU, with partial recabling of gorder End-of-year online meeting Frédérick Bordry 37 15th December 2020
Fire brigade - Robots Collaboration First test of for FB-CERNbot collaboration for search and rescue in disaster zones End-of-year online meeting Frédérick Bordry 38 15th December 2020