Washington State Department of Labor and Industries Conveyance Management System (CMS) Project Quality Assurance Services Monthly Assessment Report March 2021 April 23, 2021
ISG Quality Assurance Team Name Title Phone E-mail Gena Cruciani Engagement Manager 253.376.0439 gena.cruciani@isg-nw.com Jeff Closson Quality Assurance Lead 816.598.3345 jeff.closson@isg-nw.com Revision History Revision Revision Date Name Notes 0.1 04/16/2021 ISG Draft for Review 0.2 04/21/2021 ISG & Project Team Incorporated PM Feedback 1.0 04/23/2021 ISG & Steering Committee Finalized Assessment with SC Feedback i Conveyance Monthly Assessment Report - March 2021
Table of Contents Executive Summary ...................................................................................................................... 1 Assessment Period .................................................................................................................... 1 Executive Summary Dashboard .............................................................................................. 2 Historical View of Risk Ratings .................................................................................................. 3 Reporting Period Accomplishments ........................................................................................ 4 QA Recommendation Summary ............................................................................................. 4 High Priority Recommendations .............................................................................................. 4 Detailed Assessment Findings and Recommendations ............................................................ 6 1.0 Integration Management.............................................................................................. 6 2.0 Scope Management ..................................................................................................... 7 3.0 Schedule Management ................................................................................................ 8 4.0 Cost Management ........................................................................................................ 9 5.0 Quality Management .................................................................................................. 10 6.0 Human Resource Management ................................................................................. 12 7.0 Communications Management ................................................................................. 13 8.0 Risk Management ........................................................................................................ 14 9.0 Procurement Management ........................................................................................ 15 10.0 Stakeholder Management .......................................................................................... 16 Appendix A. ISG Discovery Interviews and Meetings.............................................................. 18 Appendix B. ISG Discovery Documentation ............................................................................ 19 Appendix C. ISG Framework Categories and Legend ........................................................... 20 ii Conveyance Monthly Assessment Report - March 2021
April 23, 2021 Ms. Annette Taylor, Executive Sponsor Deputy Assistant Director, Field Services & Public Safety Washington State Department of Labor and Industries RE: Conveyance Project - Project Quality Assurance Contract No. K4443, SOW #3 Follow-on QA Assessment Report – March 2021 Dear Ms. Taylor, Integrated Solutions Group LLC (ISG) is pleased to provide this Initial Readiness Assessment Report, per our agreed upon Statement of Work (SOW) to provide Quality Assurance (QA) services. The QA Assessment Report that follows contains ISG's finding and recommendations for the Conveyance Project. It is based on project team and stakeholder activities relative to the baseline QA recommendations as well as assessment of new project activities and deliverables. The QA Assessment Report identifies findings, and recommendations that are based on the professional experience and judgment of ISG's consulting team. The report was prepared in an independent manner. Project participants and stakeholders were consulted only for discovery interviews, informational inquiries, and validation of fact and assumptions. Thank you for the opportunity to provide QA services to the Conveyance Project. Please let me know if you have any questions or comments. Regards, Gena Cruciani Principal Integrated Solutions Group, LLC Cc: Robyn Garcia, Project Manager iii Conveyance Monthly Assessment Report - March 2021
Executive Summary The objective of the Conveyance Project is to replace the Department of Labor and Industries (L&I) Elevator Program's computer system (Conveyance Management System), used for managing customer accounts, issuing invoices and permits, storing inspection, and violation records, scheduling inspections, etc. The existing system is aging and failing. Further, it cannot be modified cost-effectively to support program improvements recommended by an independent audit requested by legislators. The replacement system is intended to serve the Elevator Program with the potential to be expanded to serve other licensing and permit programs, such as the Electrical Program and Factory Assembled Structures. Integrated Solutions Group (ISG) was retained in October of 2020 to provide Quality Assurance assessment and reporting services to the L&I Executive Sponsor and the Office of the Chief Information Officer (OCIO). Assessment Period The QA Assessment Report outlines ISG's findings from interviews, documents reviewed, and observations from March 26th through April 22nd. ISG continues to observe a steady velocity as the project finishes up the Discovery Phase and prepares to begin the Procurement Phase. The project displays a high level of collaboration and a positive morale both internally and with external stakeholders. The team and sponsors continue to be proactive and exemplify a commitment to the objectives of the project. ISG closed no recommendations and opened one (1) new recommendation during this reporting period. High-level themes described in the detailed section of this report include: 1. Deloitte Consulting working to finish the Discovery Phase Deloitte Consulting has now completed all the deliverables as part of the Discovery Phase including the Fit Gap Assessment, the Market Assessment, and the Overall Assessment. The first two deliverables have been presented to the Steering Committee, and the third will be presented in the April meeting. All three of these deliverables will be used to inform the procurement of a solution and should be incorporated into the Procurement Plan (see New Recommendation 9.2). 2. Project controls being completed in preparation for the Procurement Phase The team continues to work on the Project Management Plan (PMP) (Recommendation 1.2) and several other critical project controls. Based on the delay in approving several of these documents, the priority of several recommendations has been increased to High including Recommendations 1.2 (PMP), 2.1 (Scope), 3.1 (Schedule) and 4.1 (Cost). ISG has also increased the risk ratings of these categories to highlight the crucial nature of completing, 1 Conveyance Monthly Assessment Report - March 2021
approving, and socializing these critical project controls. Completion of these foundational project management controls is important prior to start of the procurement phase so the team can focus on the next set of critical activities. Executive Summary Dashboard ISG assessed the Conveyance project using each of the ten (10) categories in the QA Framework that align with the Project Management Institute (PMI) Project Management Body of Knowledge (PMBOK) guidelines and OCIO policy 132. ISG's rating methodology is described in further detail in Appendix C. ISG Framework Categories and Legend. Figure 1: QA Assessment Dashboard 2 Conveyance Monthly Assessment Report - March 2021
Historical View of Risk Ratings ISG utilizes visual cues to indicate trending in each area's risk impact assessment, where a down arrow reflects a lowering risk. Trending will be added to future monthly reports for comparison purposes. Impact Assessment Impact Assessment Impact Assessment rating has decreased rating has not changed rating has increased from previous from previous reporting from previous reporting period period reporting period Table 1: Risk Assessment Rating Trends Management Impact Initial Jan Feb Mar Category Trending Assessment Assessment Assessment Assessment Overall Program Rating 1.0 Integration 2.0 Scope 3.0 Schedule 4.0 Cost 5.0 Quality 6.0 Human Resources 7.0 Communications 8.0 Risk 9.0 Vendor 10.0 Stakeholder 3 Conveyance Monthly Assessment Report - March 2021
Reporting Period Accomplishments ✓ Submitted an updated Technology Budget and Gate 2 application for OCIO/OFM approval ✓ Continued work on the Investment Plan ✓ Completed Discovery Phase Part 2: Market Analysis and presented to the Steering Committee ✓ Completed Discovery Phase Part 3: Overall Analysis ✓ Continued developing the Project Management Plan (PMP) and associated subplans ✓ Completed process flows for current state Payments and Collections process ✓ Continued work on converting requirements to User Stories and reviewing with business customers QA Recommendation Summary ISG opened one (1) new recommendation in this period and closed one (1) recommendation leaving eleven (11) open QA recommendations as shown below. Total QA Recommendations to Date 15 Total QA Recommendations Remaining Open 11 High Priority Recommendations Five (5) high-priority recommendations are open, as shown in the detailed section of this report and as summarized below. Table 2: High Priority Recommendations High Priority Recommendation Opened 1.2 Develop and socialize a high-level Project Management Plan (PMP) that Oct-2020 outlines all project controls at a high level and points to the detailed plans as they are developed. Status Update: The Project Management Plan (PMP) has been drafted. However, the approval of this critical project control has now been delayed for several months. It is critical that this plan, and associated sub-plans, are completed, approved, and socialized to ensure the successful management of the project. 2.1 Develop and socialize a Scope Management Plan that outlines the change Oct-2020 control processes for the project and prescribes the use of a Requirements Traceability Matrix (RTM) to manage requirements. 4 Conveyance Monthly Assessment Report - March 2021
Status Update: As the project moves from the Discovery Phase to the Procurement Phase, it is crucial that the Scope Management Plan, which has been drafted by the project team, is approved by sponsors, socialized to the team, and put into action. 3.1 Develop, as part of the Project Management Plan (PMP), a Schedule Management Plan Status Update: While this critical plan has been drafted, the approval has been delayed for several months. Once approved and socialized, ISG will close this recommendation. 4.1 Develop a Cost Management Plan which outlines the process for managing Oct-2020 the project’s budget and expenditures. Status Update: The project plans on completing the Cost Management Plan by the end of April 2021. Once approved and socialized, ISG will close this recommendation. 9.2 NEW Develop a Procurement Plan outlining the approach to the solicitation, Mar-2021 evaluation, selection, and contracting of a Conveyance Management System solution. Status Update: This plan should include the strategy, processes, timelines, resources, and expected outcomes of the Procurement Phase. The defined tasks, activities, dependencies, and milestones should be included in the Integrated Project Schedule (IPS) and socialized with the project team and sponsors. 5 Conveyance Monthly Assessment Report - March 2021
Detailed Assessment Findings and Recommendations 1.0 Integration Management Jan Feb Mar Category Summary Assessment Assessment Assessment The project team continues to display a high level of collaboration. The team and sponsors are committed to the goals of the project. Velocity remains high as the project approaches the end of the Discovery Phase, planned for completion at the end of April, and begins the Procurement Phase to select a vendor. 4 4 5 The focus of the project continues to be the Discovery Phase being conducted by Deloitte Consulting. Deloitte has completed the first two deliverables of this phase, a Fit Gap Analysis and a Market Research analysis which have been shared with the Steering Committee. The final deliverable of this phase, an Overall Assessment Document, has been delivered to the project and will be shared with the Steering Committee at the April meeting. The Project Management Plan (PMP) has been drafted but not yet approved or socialized. While work continues on the refinement and approval of the PMP and other major project controls, ISG continues to stress the need to complete these plans, outlined in Recommendation 1.2 and other recommendations within this report, to ensure the proper management of the project. Based on the critical nature of this work, ISG has raised the risk rating of this category. Recommendations Status Priority Current Assessment 1.2 Develop and socialize a high-level The Project Management Plan (PMP) has been drafted. However, the Open High Project Management Plan (PMP) approval of this critical project control has now been delayed for several that outlines all project controls at months. It is critical that this plan and associated sub-plans are a high level and points to the detailed plans as they are completed, approved, and socialized to ensure the project's successful 6 Conveyance Monthly Assessment Report - March 2021
Recommendations Status Priority Current Assessment developed. management. 2.0 Scope Management Jan Feb Mar Category Summary Assessment Assessment Assessment Deloitte Consulting has now completed all the deliverables as part of the Discovery Phase. These deliverables include the following: 1. Fit Gap Assessment 3 3 4 2. Market Assessment 3. Overall Assessment Deliverables 1 and 2 have been presented to the Steering Committee, and the third will be presented in the April meeting which includes the following: • An overall summary of findings for the discovery phase • An assessment of the feasibility of an Enterprise solution for the programs in scope • Documentation of alternate or hybrid approaches for business processes or programs that may not be covered by an Enterprise solution; and • A roadmap for modernization of programs that may be covered by an Enterprise solution. All three of these deliverables will be used to inform the procurement of a solution and should be incorporated into the Procurement Plan (see New Recommendation 9.2). The project has drafted a Scope Management Plan and had intended to have it reviewed and approved by the Steering Committee in February; however, this has not yet occurred. ISG continues to stress the importance of clearly defining this plan and, once it is approved and socialized, will close Recommendation 2.1. ISG has raised the 7 Conveyance Monthly Assessment Report - March 2021
priority of this recommendation. Based on the increasing risk of not having a clear plan for managing scope, ISG has raised the risk rating of this category. Recommendations Status Priority Current Assessment 2.1 Develop and socialize a Scope As the project moves from the Discovery Phase to the Procurement Phase, Open High Management Plan that outlines it is crucial that the Scope Management Plan, which the project team has the change control processes for drafted, is approved by sponsors, socialized to the team, and put into the project and prescribes the use action. of a Requirements Traceability Matrix (RTM) to manage requirements. 3.0 Schedule Management Jan Feb Mar Category Summary Assessment Assessment Assessment The project has a schedule, developed in Microsoft Project, that is used to manage the activities, tasks, and timelines of the project. The project is currently finishing up the Discovery Phase and moving into the Procurement Phase. The current schedule for these phases is as follows: 3 3 4 • Discovery Phase Oct 2020 – Apr 2021 • Procurement Phase Mar 2021 – Feb 2022 • Development Phase Mar 2022 – Mar 2023 • User Readiness Phase Jun 2022 – Jun 2023 While the project is on schedule with these phases, several of the project controls have yet to be completed, approved, and socialized. This includes the Schedule Management Plan. This plan has been drafted and was intended to be reviewed and 8 Conveyance Monthly Assessment Report - March 2021
approved by the Steering Committee in February. However, to date, it has not been approved. ISG has raised the priority of Recommendation 3.2 to High and the risk rating of this category to stress the need to approve and socialize the Schedule Management Plan to ensure this critical project control is properly managed. Recommendations Status Priority Current Assessment 3.2 Develop, as part of the Project While this critical plan has been drafted, the approval has been delayed Open High Management Plan (PMP), a for several months. Once approved and socialized, ISG will close this Schedule Management Plan recommendation. 4.0 Cost Management Jan Feb Mar Category Summary Assessment Assessment Assessment The project has submitted an updated Technology Budget and the Gate 2 application for approval by the Office of the Chief Information Officer (OCIO) and the Office of Financial Management (OFM). The project has amended the Investment Plan based on the Discovery Phase findings and is currently conducting internal reviews before 4 4 5 being submitted for approval. The project has now built in the OCIO and OFM review cycles into the project schedule. ISG continues to stress the need to develop and socialize a Cost Management Plan as outlined in Recommendation 4.1 and begin formally tracking expenditures using the Budget Worksheet or equivalent mechanism. To this end, ISG has raised the priority of this recommendation to High. ISG has increased the risk rating of this category to stress the importance of completing a Cost Management Plan outlining how the budget will be managed. 9 Conveyance Monthly Assessment Report - March 2021
Recommendations Status Priority Current Assessment 4.1 Develop a Cost Management The project plans on completing the Cost Management Plan by the end of Open High Plan which outlines the process for April 2021. Once approved and socialized, ISG will close this recommendation. managing the project's budget and expenditures. 5.0 Quality Management Jan Feb Mar Category Summary Assessment Assessment Assessment As the project completes the Discovery Phase, conducted by Deloitte Consulting, it plans to update the Test Plan draft based on the information received from this process. It will be updated again as a vendor is selected and onboarded, and the details of the Implementation Phase are outlined. 3 3 3 The project is currently drafting the Quality Management Plan (Recommendation 5.1) and intends to complete it by the end of April. ISG continues to suggest that this plan outline how the project plans to align with L&I goals, as outlined in the Project Charter and listed here: • L&I Goal 1: Keep workers and the public safe: o By ensuring elevator inspectors have a reliable system to record elevator inspection details and upload the results faster so corrections can be made quicker. o By ensuring Elevator Program staff have a reliable system to approve elevator installation plans, issue permits and certificates of safety. • Goal 3: Make it easier to do business and engage with L&I: o By providing one tool for customers to view conveyance status, schedule inspections, pay for permits and report on conveyances. • Goal 5: Ensure L&I is the employer of choice: 10 Conveyance Monthly Assessment Report - March 2021
o By resolving the “pain points” identified in the 2016 Stellar Study, Elevator Program staff will process inspection data, issue permits, and collect fees more efficiently. As stated in the previous report, the Quality Management Plan (QMP) or Quality management section of the PMP should be updated using “progressive elaboration” techniques to address quality strategies over time to ensure the project meets its business goals and objectives. The QMP should address the following: • Project Objectives: The Project Charter includes a description of the project goals and objectives. The QMP should identify the business/process improvement measures and how they will be tracked/reported. • Deliverable Acceptance: What is the process and roles/responsibilities for ensuring quality deliverables. Who are the reviewers and approvers, for example? • Continuous Process Improvements: How will the project incorporate retrospectives and lessons learned to ensure improvement to project processes (after the pilot, for example)? • Product Quality: What are the high-level strategies for testing configuration prior to deployment, including roles/responsibilities for the project team, vendor, and stakeholders? Once this plan is approved and socialized, ISG will close Recommendation 5.1. Recommendations Status Priority Current Assessment 5.1 Develop a Quality Management Once the Quality Management Plan, currently in draft, is approved and Open Med Plan (QMP) to ensure that quality socialized, ISG will close this recommendation. objectives are achieved for technical and application performance. 11 Conveyance Monthly Assessment Report - March 2021
6.0 Human Resource Management Jan Feb Mar Category Summary Assessment Assessment Assessment The team continues to work with resource managers within the agency to determine what resources will be needed and how to source them. The project reports that they currently have the necessary resources and plan to onboard an additional Business Analyst prior to the Implementation Phase. They are also planning on onboarding 3 3 3 Organizational Change Management (OCM) at that time. The project is currently drafting its Human Resource Management Plan and intends to complete it by the end of April 2021. ISG continues to stress the importance of approving and socializing the Human Resource Management Plan, and once this is done, will close Recommendation 6.1. Recommendations Status Priority Current Assessment 6.1 Develop a Human Resource The project is currently drafting its Human Resource Management Plan Open Med Management Plan with a focus and intends to complete it by the end of April 2021. ISG continues to stress on activity estimating and the importance of approving and socializing the Human Resource managing resource needs for the Management Plan, and once this is done, will close this recommendation. project. 12 Conveyance Monthly Assessment Report - March 2021
7.0 Communications Management Jan Feb Mar Category Summary Assessment Assessment Assessment The Communication Plan has been drafted; however, the formal review and approval have been delayed for several months. ISG continues to stress the need to complete this essential project control to outline the project’s communication processes, as outlined in Recommendation 7.1. 4 4 4 The project provides status and other information through a series of regular meetings, including the following: • CMS Business Managers meetings (bi-weekly) • CMS Project Team meetings (bi-weekly) • CMS Steering Committee meetings (monthly) • Elevator Safety Advisory Committee (ESAC) meetings (as scheduled) Monthly status reports are developed and distributed to project stakeholders. These reports, as well as responses to the Independent QA recommendations and major project deliverables are posted to the OCIO Dashboard in a timely manner. Based on this progress, ISG has closed Recommendation 7.2. Recommendations Status Priority Current Assessment 7.1 Develop and socialize a The Communication Plan has been drafted; however, the formal review Open Med Communication Plan that and approval have been delayed for several months. ISG continues to incorporates a strategy for stress the need to complete this essential project control to outline the integrating communications project’s communication processes. across the workstreams. 13 Conveyance Monthly Assessment Report - March 2021
Recommendations Status Priority Current Assessment 7.2 Ensure that all relevant project Monthly status reports are developed and distributed to project Closed Med information, including monthly stakeholders. These reports, as well as major deliverables, are being project status, is uploaded to the posted to the OCIO Dashboard in a timely manner. Based on this OCIO dashboard in a timely progress, ISG has closed this recommendation. manner. 8.0 Risk Management Jan Feb Mar Category Summary Assessment Assessment Assessment The project is actively managing risks and issues in the respective logs on the project’s SharePoint site. The team mitigates these issues where possible and escalates to the Steering Committee for resolution where necessary. ISG continues to stress the importance of approving and socializing the Risk Management Plan draft, which 3 3 3 outlines these processes (see Recommendation 8.1 below). Recommendations Status Priority Current Assessment 8.1 Develop a Risk Management Plan The Risk Management Plan has been drafted. Once approved and Open Med which outlines the processes and socialized, ISG will close this recommendation. tools for the identification, assignment, mitigation, tracking and communication of project risks and issues. 14 Conveyance Monthly Assessment Report - March 2021
9.0 Vendor Management Jan Feb Mar Category Summary Assessment Assessment Assessment It is also critical that the approach and processes necessary for the proper management of the selected vendor or vendors is clearly outlined and agreed upon in a Vendor Management Plan (see Recommendation 9.1). The project intends to have this plan developed by the end of May, 2021. 4 4 5 As Deloitte completes the deliverables agreed upon, the Discovery Phase is coming to an end. The project is now entering the Procurement Phase of the project. The goal of this phase is to select a product, and a vendor to implement the solution necessary to address the Conveyance Management needs of the agency. To properly prepare for this next phase, the project should develop a Procurement Plan which outlines the approach to selecting a solution. This plan will be informed by the outcomes of the Discovery Phase. To this end, ISG has opened Recommendation 9.2. Based on the importance of both of these plans, and the impending start of the Procurement Phase, ISG has raised the risk rating of this category, and will continue to monitor progress in this area. Recommendations Status Priority Current Assessment 9.1 Develop a Vendor Management As the project moves into this next phase, it is critical that the approach Open Med Plan outlining the approach and and processes necessary for the proper management of vendors is clearly roles & responsibilities necessary outlined and agreed upon in a Vendor Management Plan. ISG has to successfully manage vendors increased the priority of this recommendation to High meaning it should to ensure the state continues to be addressed as soon as possible. receive the best value from project-related contracts. 15 Conveyance Monthly Assessment Report - March 2021
Recommendations Status Priority Current Assessment 9.2 Develop a Procurement Plan This plan should include the strategy, processes, timelines, resources, and New High outlining the approach to the expected outcomes of the Procurement Phase. The defined tasks, solicitation, evaluation, selection, activities, dependencies, and milestones should be included in the and contracting of a Integrated Project Schedule (IPS) and socialized with the project team and Conveyance Management sponsors. System solution. 10.0 Stakeholder Management Jan Feb Mar Category Summary Assessment Assessment Assessment The intention of the project is to select and implement a Commercial Off-the-Shelf (COTS) or Software as a Service (SaaS) product to provide a Conveyance Management System (CMS) solution to the Elevator Program. However, the agency is hoping to select a product that can also address the needs of nine (9) other related 3 3 3 programs in separate initiatives. As the project moves forward with the Procurement Phase, and eventual selection of a solution, it is critical that the needs of these other areas remain in focus. Based on the funding, the project’s scope is limited to the needs of the Elevator Program and can only provide a Conveyance Management System (CMS). Therefore, choices will have to be made regarding competing priorities of these other program areas versus the Elevator Program as this solution is selected. To address these other program areas, the project has included representatives from each program area in the Discovery sessions and has determined the processes that are similar across these areas. The project also continues to engage these other program areas in quarterly Stakeholder meetings. ISG commends the approach to selecting a more holistic solution that can, in the future, address other program areas, and suggests that this approach be incorporated in the Stakeholder Management Plan 16 Conveyance Monthly Assessment Report - March 2021
(see Recommendation 10.1). The Procurement Plan (See Recommendation 9.2) could also identify whether other program representatives will participate in vendor selection, even as observers of demonstrations for example. Recommendations Status Priority Current Assessment 10.1 Develop a Stakeholder The OCM staff, once onboarded, will be responsible for developing the Open Med Management Plan outlining how Stakeholder Management Plan. ISG suggests the incorporation of an stakeholders will be identified, approach for including the nine (9) related program areas in their assessed, and communicated with to ensure a successful stakeholder management activities, as outlined in the Stakeholder adaptation of the solution. Management section of this report. 17 Conveyance Monthly Assessment Report - March 2021
Appendix A. ISG Discovery Interviews and Meetings ISG conducted interviews as an information gathering and validation process of the discovery and assessment phase. Interview sessions were designed to gather information in relationship to the ISG QA Framework. Interviewee questions were prepared in advance by the ISG team assigning specific QA Framework questions to the roles of individuals being interviewed. Interviews • Annette Taylor • Gerald Brown • Robyn Garcia • Tamra Shaefer Meetings Observed • Monthly Steering Committee meetings • Monthly Executive Sponsor Check-Ins • Bi-weekly PM Check-In meetings • Bi-weekly Business Managers meetings • Bi-weekly Project Team meetings 18 Conveyance Monthly Assessment Report - March 2021
Appendix B. ISG Discovery Documentation ISG reviewed the following program documents during this assessment period. ISG's assessment and findings are based in part on review of the documents reviewed. 1. Steering Committee presentations 2. Monthly Status Reports 3. CMS February 2020 Response to QA Recommendations 4. CMS Schedule (Approved/Baselined) 5. Risk & Issues Log 6. Fated Funding Application Form – LI – Gate 2 040521 7. IT Pool Technology Budget 19-21 – CMS 040121 8. CMS Discovery Phase Deliverables: • Deliverable 1 - Fit Gap Assessment with Workbook • Deliverable 2 - Market Assessment • Deliverable 3 – Overall Assessment 19 Conveyance Monthly Assessment Report - March 2021
Appendix C. ISG Framework Categories and Legend ISG utilizes the following ten (10) areas within its assessment framework. Each of these areas are assessed, and qualitatively and quantitatively described in the detailed assessment report. ISG utilizes the following quantitative system in our assessment process: ISG QA Process Background and Approach ISG's process in developing the initial assessment report includes discovery interviews, project artifact reviews, and meeting attendance. Meeting attendance includes project team meeting observations. Artifact review includes project plans, status reports, deliverable documentation, and project management methodology, please refer to (Appendix A & B) for full list of interviewees and deliverables reviewed. Assessment/Findings: Describes ISG assessment findings in narrative and qualitative form. This information is gathered from key staff interviews and documentation review and is specific to the ISG QA framework area being assessed. Impact Rating: ISG assigns an impact rating that is based on our assessment findings being compared to industry best practices, similar project benchmarking where appropriate and our consultant's experience. The rating system is a high, medium, and low impact rating. 20 Conveyance Monthly Assessment Report - March 2021
Recommendations: Identifies ISG's recommendations for moving the program closer to industry best practices and reducing risks. Implementation of the recommendation is delignated by a high, mid, and low priority implementation designation. This designation is intended to assist the project team in determining ISG's position on which recommendations to address in what general order. 21 Conveyance Monthly Assessment Report - March 2021