Tender number: 59 CON 1881 Title: The provision of meter move, upgrade and Meter LPU & SPU audits for various zones within the Limpopo Operating Unit on an “as and when” required basis for the period of 36 months 19 September 2018
Tender Information • Project title: The provision of meter move, upgrade and Meter LPU & SPU audits for various zones within the Limpopo Operating Unit on an “as and when” required basis for the period of 36 months • C3.1 Works information” • Type of contract: NEC 3 - ECSC • Buyer: Shele Mogale • Clarification date: 19 Sept • Closing date: 16 Oct 2018 • Quality Requirements: check Pages 26-28 of the Tender Enquiry – category 3 requirements – Category 3 criteria; Form A ;QM 58 document; CQP and QCP • Quality evaluation to be done after Technical/ Price & BBBEE - only on successful supplier shortlisted for award. 2018/10/02 2
Quality Requirements Returnable 1. QM 58 for reference only- NB: do not print and submit; 2. Category 3 Quality requirements - submit listed items; 3. Category 3 Form A- complete Section A & D ; sign and return 4. Templates provided - • Category 3 - CQP; QCP/ITP to be completed and returned based on the NEC Scope of Work 2018/10/02 3
Quality requirements for the tender (based on new QM 58- Category 3) Unique Identifier QM-5 Revision 8.00 Supplier Quality Management: Effective Date 18/07/2013 List of Tender Returnables Documents Specifi cation QM 58 Category 3: Quality Requirements Deliverables to be evaluated indicator = 1 Weights SECTION A : Quality Management System Requirements ISO 9001:2008 Objective evidence of documented QMS that is not certified but complies with ISO9001 Apply (Yes=1) A.1 Quality Management System (QMS) Manual - based on ISO 9001:2008 framework 1 A.2 Copy of Quality Policy signed by top management. 1 A.3 Procedure for Control of Documents 1 25% A.4 Procedure for Control of Records 1 A.5 Internal Audits Procedure – Not audit checklist or Audit report 1 A.6 Procedures for Control of Nonconforming Product 1 A.7 Corrective Action Procedure 1 A.8 Preventive Action Procedure. 1 Sub-Section A Score Option 2 8 SECTION B : Evidence of QMS in operation (Tender Quality Requirements -Ref QM-58 or 240-51544462) Apply (Yes=1) B.1 Copy of appointment letter & CV/ resume of a Quality Representative for the project ( Quality training recommended) 1 B.2 Signed project Organogram with names and or functions / responsibilities 1 B.3 Copy of procedure for control of suppliers & subcontractors 1 25% B.4 Copy of Customer satisfaction surveys- 2 clients minimum( Reference letter from previous clients) 1 B.5 Historical Information (list) of similar work performed < 2yrs- (sow /date/reference); detailed reference letter from previous employers 1 Section B Score 5 2018/10/02 4
Quality requirements Cont’d SECTION C : Contract Quality Plan Requirements (Ref QM-58 and 240-109253698) Contract Quality Plan as per Scope of Works (Ref ISO 10005) 20% NB!!!! draft Contract/Project Quality Plan has important QA deliverables Apply Section C Score 0 SECTION D : Quality Control Plan Requirements (Ref QM-58 Annexure I or 240-51544462) QCP /Checklist/ ITP (Quality Control Plans) as per Scope of Works (Ref ISO 10005 / 35-59 / 39-71) NB!!!! draft QCP/ITP (jobcards) haves important QC deliverables Apply Simulated QCP required for tender evaluation 1 20% Section D Score 1 SECTION E : User defined additional Requirements & miscellaneous (Ref QM-58) Customer specific requirements & other standards and required can be listed and evaluated Apply E.1 Form A is completed and signed. 1 10% Section E Score 1 2018/10/02 5
NEC3- ECSC - C3.1 Description of Works (for completing the CQP template) 1 Open this document for Works Information 2018/10/02 6
Detailed SCOPE of Work- keywords • Scope 1 Meter Audits • Audit and Capture Field Data, Perform meter accuracy test, Observe and Capture Remarks using own Handheld Unit (Rural) • Auditing of the rural installation (exclude testing) Digital meter • Replacement of the 5Amp meters • Auditing and testing SPU meters • Change-out of Single phase meter due to Faulty / Tampered. (Rural); Change-out of 2 x Single Phase meter due to Faulty / Tampered. (Rural); Change-out of 3 x Single Phase meter due to Faulty / Tampered. (Rural); Change-out of 3 x 5 AMP meters due to Faulty / Tampered and convert to single Polyphase meter (160A). (Rural); Take a photo on an SPU meter when required by PM; Change-out up to 50kva - Polyphase meter 125amp due to Faulty / Tampered. (Rural); Change-out of Single Polyphase meter 160 amp due to Faulty / Tampered. (Rural); Change-out of 3 x Single Phase meters and convert to Polyphase meter due to Faulty / Tampered. (Rural); Audit and Capture Field Data, Perform meter accuracy test per meter, Observe and Capture Remarks using own Handheld Unit (Urban Rate) 2018/10/02 7
SOW Continued • Change-out of 3 x Single Phase meters and convert to Polyphase meter due to Faulty / Tampered. (Rural) • Audit and Capture Field Data, Perform meter accuracy test per meter, Observe and Capture Remarks using own Handheld Unit (Urban Rate) • Change-out/ of Single phase meter due to Faulty / Tampered. (Urban) • Collect & Submit MV Pole numbers with photos If instructed by PM • Auditing, testing of meter and Capturing Field Data Using Own Handheld Units (PPU single and three phase) • Disconnect All Bypassed/Tampered/Illegal connection and Issue Tamper Fine (PPU) • Seal Meters under the Following conditions: All unsealed meters ; All replaced Faulty meters • Reconnecting If Instructed by Project Manager (PPU Rural/ Urban); Collect & Submit MV Pole numbers with photos; Lock the pole top Boxes with an Eskom lock when requested by PM; Punch in the key change token on a PPU meter on request by PM 2018/10/02 8
Scope 2 Meter Moves , Change Outs and Upgrades • HOUSE CONNECTION • Overhead Connection • Underground Connection • SHACK POLES (Incl. Excavation) • 4&5m Wood Shack Pole • 7m Wood Shack Pole; 9m shack pole (including excavation); Extra over for hard holes 4 & 5m; Extra over for hard holes 7m; Extra over for hard holes 9m • SUNDRY ITEMS- Trenching for cable: Soft; Trenching for cable: Rock; Pole top box installation; Store and site office (fixit) 0-200; 63A Morsdorf Breaker; Change Faulty meter; Installation of external ECU Box 2018/10/02 9
SPU & LPU CONNECTIONS • Meter box single phase installation including cable above ground level • Meter box three phase 25 to 100kVA installation including cable above ground level • Poly phase meter box 200kVA installation including cable above ground level . • Lay cables including terminations; Cables laid in ground 16 x 2; Cables laid in ground 25 x 4; Cables laid in ground 35 x 4; Cables laid in ground 70 x 4; Cables laid in ground 120 x 4; Cables laid in ground 240 x 4; Excavate in soft material for trench (600mm) incl. backfilling • HOUSE CONNECTION- Overhead Connection; Underground Connection • SHACK POLES- 4&5m Wood Shack Pole; 7m Wood Shack Pole • SUNDRY ITEMS- Pole top box; 63A Morsdorf Breaker; Faulty meter 2018/10/02 10
Common mistakes made by tenderers on Quality submissions 1. Section A 1. Quality manual structure layout not aligned to latest Standard (2008 or 2015); 2. QMS Procedures incomplete and do no comply with particular ISO clause elements; Do not copy and paste the ISO standard- inteprete and customise to your business; address all elements of the procedure as per clause requirements 3. Quality policy not signed or not submitted; or does not comply with clause ISO 9001:2008 -5.3 ( it’s a controlled document must have ref number; revision; authorization date); 4. For Option1- ISO certification scope must be relevant; valid by tender closing date; 2018/10/02 11
Common errors when evaluating- cont’d Section B 1. QMR appointment letter or and CV not submitted; QMR to attend training on QM in the first 12 months after contract award (contract condition) 2. Organogram has no names and signed nor on letterhead- must be a controlled document; 3. Supplier Management procedure not aligned to Clause 8.4 of ISO 9001:2015 4. Satisfaction surveys not completed by clients; Name of clients- name of project/service- stamp/signature missing; Submit CS survey templates- rather submit reference letter ( name of client- project/service-date); Reference letter from previous clients; 5. History of similar work not detailed- does not indicate client- client contact details- SOW provided; ( Project Completion letters; Reference letters fro previous employer accepted) 2018/10/02 12
Common errors when evaluating- cont’d Section C 1. CQP sow not described as in the NEC; project organogram does not include roles and responsibilities of organogram functions in respect of SOW; 2. Does not add the out-sourced SOW functions/activities; and other CQP ;elements; Section D 1. ITP/QCP template not used; 2. If used, sow specific task order is not used (eg; design instead of installation; construction instead of design – Use a previousTender SOW Task order); 3. Quality inspection checksheet is accepted for a while but get used to completing an ITP; Implement ITPs and ask for signatures as they are a requirement for Category 2 Contracts; Section E 1. Incorrect Form A- old Forms; 2. Form A neither completed not signed and incorrectly marked Form submitted. 2018/10/02 13
2018/10/02 14
2018/10/02 15
When completing CQP & ITP/QCP • Complete the scope of work as described on the NEC- ECSC Works Information ; • complete other information as indicated in the Index, some requirements are not applicable. If any section on CQP not applicable indicate so and reason why. 2018/10/02 16