STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION - IURC ...

Page created by Ronnie Lynch
 
CONTINUE READING
STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION - IURC ...
STATE OF INDIANA

               INDIANA UTILITY REGULATORY COMMISSION

VERIFIED JOINT PETITION OF NORTHERN INDIANA         )
PUBLIC SERVICE COMPANY LLC AND ELLIOTT SOLAR        )             FILED
GENERATION LLC (THE “JOINT VENTURE”) FOR (1)        )          May 24, 2021
ISSUANCE TO NIPSCO OF A CERTIFICATE OF PUBLIC       )       INDIANA UTILITY
CONVENIENCE AND NECESSITY FOR THE PURCHASE          )   REGULATORY COMMISSION
AND ACQUISITION OF A 200 MW SOLAR PROJECT (THE      )
“ELLIOTT PROJECT”); (2) APPROVAL OF THE ELLIOTT     )
PROJECT AS A CLEAN ENERGY PROJECT UNDER IND.        )
CODE § 8‐1‐8.8‐11; (3) APPROVAL OF RATEMAKING AND   )
ACCOUNTING TREATMENT ASSOCIATED WITH THE            )
ELLIOTT PROJECT; (4) AUTHORITY TO ESTABLISH         )
AMORTIZATION RATES FOR NIPSCO’S INVESTMENT IN       )
THE JOINT VENTURE; (5) APPROVAL PURSUANT TO IND.    )
CODE § 8‐1‐2.5‐6 OF AN ALTERNATIVE REGULATORY       )
PLAN INCLUDING ESTABLISHMENT OF JOINT VENTURE       )
THROUGH WHICH THE ELLIOTT PROJECT WILL              )
SUPPORT NIPSCO’S GENERATION FLEET AND THE           )   CAUSE NO. 45529
REFLECTION IN NIPSCO’S NET ORIGINAL COST RATE       )
BASE OF ITS INVESTMENT IN JOINT VENTURE; (6)        )
APPROVAL OF PURCHASED POWER AGREEMENTS AND          )
CONTRACT FOR DIFFERENCES THROUGH WHICH              )
NIPSCO WILL PAY FOR THE ENERGY GENERATED BY         )
THE ELLIOTT PROJECT, INCLUDING TIMELY COST          )
RECOVERY PURSUANT TO IND. CODE § 8‐1‐8.8‐11         )
THROUGH NIPSCO’S FUEL ADJUSTMENT CLAUSE; (7)        )
AUTHORITY TO DEFER AMORTIZATION AND TO              )
ACCRUE POST‐IN SERVICE CARRYING CHARGES ON          )
NIPSCO’S INVESTMENT IN JOINT VENTURE; (8) TO THE    )
EXTENT GENERALLY ACCEPTED ACCOUNTING                )
PRINCIPLES WOULD TREAT ANY ASPECT OF JOINT          )
VENTURE AS DEBT ON NIPSCO’S FINANCIAL               )
STATEMENTS, APPROVAL OF FINANCING; (9)              )
APPROVAL OF AN ALTERNATIVE REGULATORY PLAN          )
FOR NIPSCO IN ORDER TO FACILITATE THE               )
IMPLEMENTATION OF THE ELLIOTT PROJECT; AND (10)     )
TO THE EXTENT NECESSARY, ISSUANCE OF AN ORDER       )
PURSUANT TO IND. CODE § 8‐1‐2.5‐5 DECLINING TO      )
EXERCISE JURISDICTION OVER THE JOINT VENTURE        )
AS A PUBLIC UTILITY.                                )
STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION - IURC ...
INDIANA OFFICE OF UTILITY CONSUMER COUNSELOR
             PUBLIC’S EXHIBIT NO. 1
     REDACTED TESTIMONY OF OUCC WITNESS
            CYNTHIA M. ARMSTRONG

              MAY 24, 2021
STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION - IURC ...
Public’s Exhibit No. 1
                                                                                   Cause No. 45529
                                                                                        Page 1 of 17
                                                    highlight indicates CONFIDENTIAL information

             TESTIMONY OF OUCC WITNESS CYNTHIA M. ARMSTRONG
                               CAUSE NO. 45529
         NORTHERN INDIANA PUBLIC SERVICE COMPANY LLC (“NIPSCO”) AND
                       ELLIOTT SOLAR GENERATION LLC
                    (COLLECTIVELY “JOINT PETITIONERS”)

                                               I.    INTRODUCTION

 1   Q:        Please state your name and business address.
 2   A:        My name is Cynthia M. Armstrong, and my business address is 115 W. Washington

 3             St., Suite 1500 South, Indianapolis, IN, 46204.

 4   Q:        By whom are you employed and in what capacity?
 5   A:        I am employed as a Senior Utility Analyst in the Electric Division for the Indiana

 6             Office of Utility Consumer Counselor (“OUCC”). A summary of my qualifications

 7             can be found in Appendix A.

 8   Q:        Briefly summarize Joint Petitioner’s request in this proceeding.
 9   A:        NIPSCO’s request is essentially the same as its previous joint venture solar

10             requests. 1 Elliott Solar CEI, LLC, through Elliott Solar, LLC, a special purpose

11             entity, will build a 200 MW solar system in Gibson County, Indiana. NIPSCO, with

12             a tax equity partner(s) (“TEP”), will form a limited liability company to own the

13             Solar Project in an arrangement known as a joint venture. The TEP will invest in a

14             percentage of the Solar Project in return for 99% of the Investment Tax Credits

15             (“ITC”) and the tax losses and profits the Solar Project generates. The TEP will

16             also receive cash distributions the Solar Project generates equal to its investment

17             percentage share. NIPSCO will invest in the remaining Solar Project portion and

     1
         Cause Nos. 45194, 45310, and 45462.
Public’s Exhibit No. 1
                                                                                 Cause No. 45529
                                                                                      Page 2 of 17
                                                  highlight indicates CONFIDENTIAL information

 1              operate the Solar Project once it achieves mechanical completion. The TEP

 2              arrangement will continue until the TEP reaches the specified internal rate of return

 3              (“IRR”). At this point, NIPSCO will have the option to acquire the TEP interest for

 4              fair market value. 2

 5                       To facilitate NIPSCO’s ability to procure the Solar Project and enter into

 6              the joint venture with a TEP (“Joint Venture”), Joint Petitioners request the

 7              Commission issue NIPSCO a certificate of public convenience and necessity

 8              (“CPCN”) and authorize NIPSCO to purchase and indirectly own, through the Joint

 9              Venture, the Elliott Solar Generation project (“Solar Project”). Joint Petitioners

10              request approval for a build transfer agreement (“BTA”), a BTA purchase power

11              agreement (“PPA”), and a contract for differences (“CFD”) should certain tax

12              implications require the usage of a CFD instead of the BTA PPA. Joint Petitioners

13              also request alternative regulatory plan relief in relation to the Joint Venture. In the

14              event the Commission does not approve the Solar Project’s sale through a joint

15              venture structure, Joint Petitioners request approval to use a Back-Stop PPA for the

16              Solar Project. Joint Petitioners further request associated ratemaking treatment be

17              collected through NIPSCO’s Fuel Adjustment Clause (“FAC”).

18   Q:         What is the purpose of your testimony in this proceeding?
19   A:         I provide the OUCC’s recommendations for Commission treatment of (1) project

20              risk management and (2) the CFD. Specifically, I recommend the Commission

21              modify the cap on additional project costs, with ratepayers and NIPSCO sharing

     2
         Joint Petitioner’s Confidential Exhibit No. 2, Direct Testimony of Andrew S. Campbell, pp. 24-27.
Public’s Exhibit No. 1
                                                                                 Cause No. 45529
                                                                                      Page 3 of 17
                                                  highlight indicates CONFIDENTIAL information

 1            cost overruns fifty/fifty (“50/50”) up to the cap. If NIPSCO takes the CFD option,

 2            I further recommend NIPSCO commit to ensuring it does not result in higher costs

 3            than ratepayers would experience under a BTA PPA.

 4   Q:       How did you evaluate issues presented in this Cause?
 5   A:       I reviewed materials presented in this docket pertinent to the topics addressed in

 6            my testimony, including the petition initiating this proceeding, Joint Petitioners’

 7            pre-filed verified direct testimony and exhibits, and Joint Petitioners’ responses to

 8            OUCC discovery requests. I reviewed the relevant portions of Ind. Code3

 9            compliance statutes for new generation projects. Finally, I reviewed the

10            Commission’s recent orders in Cause Nos. 45462 and 45472 issued May 5, 2021. I

11            also reviewed previous CPCN cases where cost overruns became an issue. 4

12   Q:       To the extent you do not address a specific item in your testimony, should it be
13            construed to mean you agree with Joint Petitioners’ proposals?
14   A:       No. Exclusions of any topics, issues, or items Joint Petitioners propose does not

15            indicate my approval of these topics, issues, or items. Rather, the scope of my

16            testimony is limited to the specific topics discussed herein.

                                           II.    RATEPAYER RISK

17   Q:       Why is it important to identify and manage risk?
18   A:       Risks, both known and unknown, may translate into additional ratepayer costs. The

19            OUCC has been concerned about ratepayer risk in every joint venture request. As

     3
      Including but not limited to, Ind. Code ch. 8‐1‐8.8, et seq. Ind. Code ch. 8‐1‐2.5, et seq., Ind. Code § 8‐1‐
     2.5‐5, and Ind. Code ch. 8‐1‐8.5, et seq.
     4 For example, Cause Nos. 43114, 43314 – IGCC, 1 and 4S1, 42700, 43403, 42170 ECRs 5, 7, 8, 14, 16S1,

     and 19, 43913, and 44012 Phase 1.
Public’s Exhibit No. 1
                                                                       Cause No. 45529
                                                                            Page 4 of 17
                                        highlight indicates CONFIDENTIAL information

 1        the OUCC continues to review these extremely complex arrangements, these

 2        concerns remain.

 3   Q:   Please explain some known risks associated with joint venture arrangements.
 4   A:   There are several risks associated with pursuing a joint venture arrangement instead

 5        of a traditional PPA, e.g., NIPSCO’s Back-Stop PPA. First, if NIPSCO used a

 6        traditional PPA, it would pay for the power produced at the agreed price with the

 7        developer. It would not be exposed to the financial risk if project construction,

 8        interconnection, and operation and maintenance costs are more than expected. Nor

 9        would NIPSCO be responsible if the equipment failures result in greater than

10        expected capital maintenance or frequent equipment replacements. However, under

11        a joint venture arrangement, these additional costs are typically the joint venture’s

12        responsibility. Ratepayers would eventually bear the burden of increased project

13        costs when the utility seeks to recover its portion of project investment through

14        rates.

15                 Second, when a traditional PPA term ends, the off-taker, NIPSCO, has the

16        option to pursue a variety of replacement options or to do nothing. At that time,

17        NIPSCO can make an informed decision based on its current needs and alternate

18        resource options. NIPSCO would also have the advantage to consider technology

19        progressions that make renewables or other generation types more efficient.

20        NIPSCO could then consider purchasing the Solar Project at a fair market price, if

21        that is the best option. On the other hand, in a joint venture arrangement, the TEP
Public’s Exhibit No. 1
                                                                             Cause No. 45529
                                                                                  Page 5 of 17
                                              highlight indicates CONFIDENTIAL information

 1           has the option to sell its share of the joint venture when it meets its IRR. 5 This is

 2           expected to occur in 2030 for this Joint Venture. 6 At that point, the utility is faced

 3           with limited options: purchase the TEP’s interest at the flip point or do not purchase

 4           the TEP’s interest.

 5   Q:      Are there additional risks specifically related to NIPSCO’s request?
 6   A:      Yes. While Joint Petitioners attached drafts of contracts associated with the Joint

 7           Venture, the CFD and BTA PPA remain unexecuted. 7 Until the final contracts are

 8           executed, there is a risk its terms could change, which could negatively impact

 9           ratepayers depending on the contract’s changes.

10   Q:      Please explain “unknown risk.”
11   A:      Joint venture arrangements in Indiana are still new. While the Commission

12           approved three NIPSCO requests representing five projects, 8 these projects have

13           not been implemented and thus have not yet proven beneficial to ratepayers. It is

14           uncertain if the Joint Ventures will actually result in the ratepayer savings NIPSCO

15           represents. This unknown risk is also compounded by the volume of joint venture

16           arrangements NIPSCO is pursuing. Given the lack of real-world implementation

17           examples in this jurisdiction, the OUCC wants to ensure NIPSCO’s ratepayers are

18           protected as much as practicable from these risks leading to ratepayer burden. One

19           reason utilities are proposing these types of arrangements is cost savings. If

     5
       Campbell Direct, p. 26, line 11 – p. 27, line 2.
     6
       Campbell Direct, p. 26, line 15 – p. 27, line 2 (inclusive of footnote 24).
     7
       Campbell Direct, p. 37, lines 1-2.
     8
       NIPSCO has received three (3) approvals, IURC Cause Nos. 45194, 45310, and 45462, these approvals
     represent five (5) projects. NIPSCO currently has three (3) projects pending approval, IURC Cause Nos.
     45511, 45524, and 45529.
Public’s Exhibit No. 1
                                                                       Cause No. 45529
                                                                            Page 6 of 17
                                        highlight indicates CONFIDENTIAL information

 1        NIPSCO expects the Commission to approve untraditional arrangements for

 2        acquiring generation, ratepayers deserve to receive the bargain the utility is

 3        promising.

                                 III.    MANAGING RISKS

 4   Q:   When does the OUCC recommend risks associated with the Solar Project be
 5        managed?
 6   A:   The OUCC recommends risks be managed before the Solar Project is approved.

 7   Q:   Why is it important to manage the risks associated with the Solar Project prior
 8        to approval?
 9   A:   Cost deviations from the final project amount could change the reasonableness of

10        selecting that resource option to meet customers’ needs. If the true project costs are

11        not known upfront, NIPSCO may have foregone another resource option or project

12        that would have provided greater customer benefits. However, once a project is

13        approved, it is difficult to change course and select a better resource option.

14               Additionally, changes from the final project amount may change the

15        OUCC’s conclusions and recommendations; however, the OUCC will not have the

16        ability to provide a different recommendation after the Solar Project is approved.

17        Generally, when a utility seeks subsequent approval regarding additional

18        investment associated with a project, the issue becomes the additional investment’s

19        reasonableness instead of the entire project’s reasonableness. As project

20        development proceeds, rejecting cost increases becomes increasingly difficult.

21               Within the past 15 years, the OUCC and the Commission has dealt with

22        several utility projects greatly exceeding their original estimates. During this time,
Public’s Exhibit No. 1
                                                                               Cause No. 45529
                                                                                    Page 7 of 17
                                                highlight indicates CONFIDENTIAL information

1            it was common for a utility to present a project cost estimate in a new CPCN case

2            where the final project cost would balloon to 25% or more over the original cost

3            estimate during project construction. 9 Utilities were able to shift the risk of these

4            cost overruns to customers, as they were recovered on an expedited basis through

5            trackers. While NIPSCO’s current request differs in its set-up and recovery

6            mechanism, the issue remains the same. The OUCC wants to ensure that costs

7            associated with utility investment (or, as in this case, regulatory assets associated

    9
       See e.g.: Duke Energy Indiana (DEI)’s examples of cost overruns: In Cause No. 43114, the Commission
    approved DEI’s Integrated Gasification Combined Cycle (“IGCC”) plant costs for $1.985 billion. In IGCC-
    1, this cost was revised to $2.350 billion. In Cause No. 43114 IGCC-4S1 (Phase 1), DEI requested another
    increase of the IGCC project to total $2.88 billion, but the OUCC and other intervenors settled with DEI for
    a $2.595 billion cost cap for the plant.

    Indianapolis Power and Light (IPL)’s examples: In Cause No. 42700, the Commission approved $182 million
    for the construction of the Harding Street Unit 7 Flue Gas Desulfurization (FGD) unit and the Peterburg Unit
    3 FGD upgrade. In Cause No. 42170 ECR-5, IPL sought, and the Commission approved, a modification to
    the CPCN to increase the Unit 3 FGD Enhancement cost estimate by $3 million. In 42170 ECR-7, the Unit
    3 FGD enhancement increase was re-affirmed to a total project cost of $27.5 million, compared to the original
    estimate of $24.954 million. In Cause No. 42170 ECR- 8, IPL sought, and the Commission approved another
    increase for the Unit 3 FGD Enhancement to total $29.5 million and a $60 million increase for the Harding
    Street Unit 7 FGD to total $220 million. In Cause No. 43403, the Commission approved $90 million to
    construct the Petersburg Unit 4 FGD upgrade. In Cause No. 42170 ECR-14, IPL modified the CPCN for the
    Unit 4 FGD upgrade to increase the cost estimate to $119.9 million, and the Commission approved IPL’s
    request. In Cause No. 42170 16 and 16S1, IPL increased its cost estimate for the Unit 4 FGD Upgrade again
    to reflect the total project cost at $128 million, and the Commission approved this increase. In Cause No.
    42170 ECR-19, IPL once again sought a modification to its CPCN to increase the Petersburg Unit 4 FGD
    Enhancement to $129.6 million, which the OUCC challenged. IPL and the OUCC settled and agreed the
    project amount recovered through the ECR would not exceed $129.6 million, but IPL would have to seek
    additional costs beyond that cap in a future rate case. The OUCC reserved the right to challenge any such
    additional costs in the future rate case. The Commission approved the settlement and IPL’s requested
    modification.

    NIPSCO’s examples: In Cause No. 43913, NIPSCO requested a CPCN to install a FGD system on Schahfer
    Unit 14 for $153,560,417, and the Commission approved this request. In Cause No. 44012 Phase 1, NIPSCO
    sought a CPCN for multiple environmental controls, which included an increase in the cost estimate for the
    Schahfer Unit 14 FGD to $203 million. The Commission approved NIPSCO’s CPCN, including the Unit 14
    FGD revised estimates.
Public’s Exhibit No. 1
                                                                              Cause No. 45529
                                                                                   Page 8 of 17
                                               highlight indicates CONFIDENTIAL information

 1           with investments) are managed appropriately, whether it be a coal, gas, or

 2           renewable generating facility.

 3   Q:      Has NIPSCO worked with the OUCC in previous cases to manage some
 4           ratepayer risk?
 5   A:      Yes. NIPSCO worked with the OUCC in the first tax equity partnership request to

 6           design some customer protections to manage some ratepayer risks. 10 NIPSCO

 7           committed to implement these management strategies in subsequent joint venture

 8           arrangements, including the Elliott Solar Joint Venture presented in this case. 11

 9   Q:      Please explain how the OUCC addressed risk management in previous cases.
10   A:      In the Rosewater proceeding, Cause No. 45194, the OUCC was concerned with

11           NIPSCO ratepayers’ total investment in the project and subsequent projects tied to

12           NIPSCO’s Short Term Action Plan from its 2018 Integrated Resource Plan

13           (“IRP”). 12 As this was the first joint venture arrangement the OUCC encountered,

14           the OUCC was under the impression the only risk of additional ratepayer costs was

15           tied to the additional investments NIPSCO described. Therefore, capping additional

16           costs would protect ratepayers from increases in the overall cost of the project.

17   Q:      Is NIPSCO committing to cap costs on additional investments in this
18           proceeding as it has done in previous joint venture proceedings?
19   A:      Yes, as explained in Mr. Campbell’s testimony, “NIPSCO commits that there will

20           be a cap of cost recovery related to any additional investments . . . NIPSCO may

21           make into the Joint Ventures. The amount recoverable from ratepayers shall be

     10
         Campbell Direct (Confidential), p. 44, line 3 – p. 46, line 10.
     11
        Id.
     12
         See IURC Cause No. 45194, Public’s Exhibit No. 3, Direct Testimony of John Haselden.
Public’s Exhibit No. 1
                                                                                  Cause No. 45529
                                                                                       Page 9 of 17
                                                   highlight indicates CONFIDENTIAL information

 1            capped at

 2                                             .” 13

 3   Q:       Does this commitment manage all risks?
 4   A:       No. This commitment does not manage all risks. NIPSCO’s management strategy

 5            only applies to a limited category of additional investment. 14 As discussed below,

 6            NIPSCO’s classification of additional investment can circumvent the agreed upon

 7            management strategy of a cap on ratepayers’ share. Additionally, NIPSCO and the

 8            OUCC have not worked together to review the efficacy of the management strategy

 9            since its first joint venture request. As the OUCC continues reviewing this new

10            acquisition structure it is apparent there are additional risks to consider that do not

11            fall under the current management strategy, and NIPSCO has discretion regarding

12            how to categorize a cost.

13   Q:       In the IURC’s Cause No. 45462 Order, the Commission discussed cost
14            estimates in relation to OUCC Witness Lauren Aguilar’s testimony. Please
15            explain the context.
16   A:       In IURC Cause No. 45462, the OUCC took issue with specific confidential terms

17            in the BTA NIPSCO negotiated with NextEra. The Commission accepted

18            NIPSCO’s best estimate, as it originated through the request for proposals (“RFP”)

19            and rejected the OUCC’s concern with the specific BTA terms. 15

20   Q:       Are your concerns here in a different context?
21   A:       Yes. In addition to the unknown risk I discussed above, I am concerned with the

22            discretion afforded to NIPSCO in determining what falls under the Joint Venture’s

     13
        Campbell Direct, p. 44, lines 15-17, to 45, line 3.
     14
        Campbell Direct, p. 27, line 7 – p. 28, line 2.
     15
        Cause No. 45462, Final Order, pp. 48 and 60-61.
Public’s Exhibit No. 1
                                                                              Cause No. 45529
                                                                                  Page 11 of 17
                                               highlight indicates CONFIDENTIAL information

 1   A:         The OUCC proposes eliminating specific cost categories and imposing a cap on all

 2              potential additional ratepayer costs associated with the Joint Venture. In line with

 3              previous ratepayer protection iterations, to incentivize NIPSCO to keep costs low,

 4              the OUCC proposes 50/50 cost sharing between ratepayers and shareholders.

 5

 6

 7                                    . 18

 8                        In any subsequent filing where NIPSCO recovers costs associated with the

 9              Solar Project, I recommend NIPSCO refile the Confidential documents Mr.

10              Campbell presents in this Cause with his testimony in order to enforce such a cap.

11              Currently, the Solar Facility’s cost is redacted from public documents. It is

12              unconventional to redact the total project cost the Commission approves in CPCN

13              proceedings. However, the OUCC understands the Solar Project developer does not

14              want this information made public, as it could inhibit its negotiation ability for other

15              projects it develops. Because the OUCC must destroy Confidential documents after

16              a case has reached its final ruling it cannot keep a record of the original costs

17              proposed in this proceeding. Therefore, refiling these documents in any future

18              proceeding where NIPSCO recovers the Solar Project costs will assist in the

19              Commission’s and OUCC’s review.

     18
          Campbell Direct, p. 45, lines 2-3.
Public’s Exhibit No. 1
                                                                              Cause No. 45529
                                                                                  Page 12 of 17
                                               highlight indicates CONFIDENTIAL information

 1   Q:      Please further explain why the terms of the OUCC’s recommended cap are
 2           reasonable.
 3   A:      This approach acknowledges that NIPSCO provided its Project’s best estimate

 4           based on what it knows at this time. However, NIPSCO represented that this

 5           project, along with the other projects which are part of the 2018 IRP Short-Term

 6           Action Plan, provide economic benefits to ratepayers, in addition to societal

 7           environmental benefits. NIPSCO estimates its generation transition will generate

 8           more than $4 billion in cost savings over the next 30 years, and NIPSCO’s

 9           customers are expected to see these savings as early as 2023. 19 Additional costs

10           associated with the Solar Project or the Joint Venture could potentially evaporate

11           the savings NIPSCO represents. The OUCC’s recommended 50/50 sharing with a

12           ratepayer cost cap balances the risk between NIPSCO ratepayers and shareholders

13           and further incentivizes NIPSCO to minimize the Solar Project’s cost overruns.

14                    Further, imposing caps on utility projects as ratepayer protection is not a

15           new concept. In past CPCN cases, the OUCC recommended, and the Commission

16           approved, imposing construction cost caps on pollution control projects and

17           generating plants. 20 While the joint venture presents a different method of

18           constructing and acquiring generation to serve customers, the concept of imposing

19           a cap as an incentive to NIPSCO and the Joint Venture to control project overruns

20           and protect ratepayers is still applicable.

     19
       Id. p. 9, line 13 – p. 10, line 2.
     20
       These cost caps were usually the result of settlements, and the Commission approved these settlements.
     See Cause Nos. 43114 IGCC-4S1, 42170-ECR-19, and 44794.
Public’s Exhibit No. 1
                                                                               Cause No. 45529
                                                                                   Page 13 of 17
                                                highlight indicates CONFIDENTIAL information

 1   Q:         Does imposing a ratepayer cap completely alleviate the OUCC’s concerns?
 2   A:         No. OUCC witness Caleb Loveman discusses other concerns with Joint Petitioner’s

 3              accounting and ratemaking treatment proposal. This proposed ratepayer cap does

 4              not negate other OUCC witnesses’ recommendations.

 5   Q:         Are there any other issues regarding project risk you would like to address?
 6   A:         Yes, but it appears NIPSCO already addressed the risk issue

 7                        . NIPSCO investigated the possibility of procuring insurance that would

 8              protect it if project delays impact the ITC amount for which the Elliott Project

9               qualifies. NIPSCO’s search revealed such insurance products are available (“ITC

10              insurance”). 21 In Cause No. 45524 (Crossroads Solar Joint Venture), the OUCC

11              questioned the reasonableness of acquiring ITC insurance. However, in this case,

12

13                                                    . 22 Therefore, the OUCC’s concern about the

14              ITC insurance OUCC witness Lauren Aguilar notes in Cause No. 45524 do not

15              appear to apply in this case. However,

16

17                                                  the OUCC asserts the same position it takes in

18              Cause No. 45524, that the ITC insurance costs should be subject to a prudency

19              review in the rate case following when such costs are incurred.

     21
          Campbell Direct, p. 28, lines 5-15.
     22
          Campbell Direct, p. 29, lines 7-10.
Public’s Exhibit No. 1
                                                                            Cause No. 45529
                                                                                Page 14 of 17
                                             highlight indicates CONFIDENTIAL information

                             IV.     CONTRACT FOR DIFFERENCES

 1   Q:      Has the OUCC previously raised concerns about the contract NIPSCO refers
 2           to as a CFD?
 3   A:      Yes. These concerns were previously raised in two cases. 23 Joint Petitioners

 4           represent the CFD will produce the same result for ratepayers as the BTA PPA.

 5           However, the OUCC will be unable to verify this until the Solar Project becomes

 6           commercially operational and costs begin to flow through the FAC.

 7   Q:      Has the Commission ruled on these concerns?
 8   A:      Yes. In its Cause No. 45463 Order regarding NIPSCO’s and Indiana Crossroads

 9           Wind Generation LLC’s request for modification of the Commission’s Cause No.

10           45310 Order authorizing a CFD as a third option for the purchase of the electrical

11           energy output of the Crossroads Project, the Commission stated:

12                   While we recognize NIPSCO’s assertion that the CFD should
13                   produce no difference in recovery from the BTA PPA, we agree with
14                   the OUCC’s concerns that ratepayers should not be harmed if the
15                   CFD does, for whatever reason, produce a different result. 24

16           The Commission subsequently ordered:

17                   Should NIPSCO utilize the Contract for Differences instead of the
18                   BTA PPA, NIPSCO shall submit a work paper in each quarterly
19                   FAC filing comparing recovery amounts under the Contract for
20                   Differences and the BTA PPA to show that NIPSCO’s customers
21                   are not negatively impacted by using the Contract for Differences.
22                   NIPSCO shall work with interested FAC stakeholders in the
23                   development of the work paper. 25

     23
        IURC Cause Nos. 45462 (Order May 5, 2021) and 45463 (Order March 29, 2021).
     24
        IURC Cause No. 45463 (Order March 29, 2021) p. 8.
     25
        Id. p. 9, ordering paragraph 4.
Public’s Exhibit No. 1
                                                                               Cause No. 45529
                                                                                   Page 15 of 17
                                                highlight indicates CONFIDENTIAL information

 1              The Commission required the same in Cause No. 45462 to ensure ratepayers

 2              were not negatively affected by using a CFD in lieu of the BTA PPA. 26

 3   Q:         Is the OUCC recommending the same requirements for this Solar Project?
 4   A:         Yes.

                                       V.     RECOMMENDATIONS

 5   Q:         Please list the OUCC’s recommendations.
 6   A:         In order to minimize risk, the OUCC recommends:

 7                  1) Any additional costs associated with the Joint Venture or Solar Project

 8                      should be subject to 50/50 cost sharing and included in the aforementioned

 9                      future investment cap to shield ratepayers from increased cost risk.

10                      Additionally, NIPSCO should refile Mr. Campbell’s attachments with any

11                      future rate proceeding where the costs associated with the Joint Venture are

12                      recovered.

13                  2) Any unintended negative consequences resulting from using a CFD rather

14                      than a BTA PPA be unrecoverable from ratepayers through the FAC (or any

15                      other recovery means). Also, NIPSCO should work with the OUCC to

16                      develop a workpaper for use in the FAC to show the flow of dollars under

17                      the CFD and the BTA PPA, if the CFD is utilized.

18   Q:         Does this conclude your testimony?
19   A:         Yes.

     26
          IURC Cause No. 45462 (Order May 5, 2021) p. 70.
Public’s Exhibit No. 1
                                                                      Cause No. 45529
                                                                          Page 16 of 17
                                       highlight indicates CONFIDENTIAL information

                                       APPENDIX A

 1   Q:   Summarize your professional background and experience.
 2   A:   I graduated from the University of Evansville in 2004 with a Bachelor of Science

 3        degree in Environmental Administration. I graduated from Indiana University,

 4        Bloomington in May 2007 with a Master of Public Affairs degree and a Master of

 5        Science degree in Environmental Science. I have also completed internships with

 6        the Environmental Affairs Department at Vectren in the spring of 2004, with the

 7        U.S. Environmental Protection Agency in the summer of 2005, and with the U.S.

 8        Department of the Interior in the summer of 2006. During my final year at Indiana

 9        University, I served as a research and teaching assistant for a Capstone course

10        offered at the School of Public and Environmental Affairs. I also have obtained my

11        OSHA Hazardous Operations and Emergency Response (“HAZWOPER”)

12        Certification. I have been employed by the OUCC since May 2007. As part of my

13        continuing education at the OUCC, I have attended both weeks of the National

14        Association of Regulatory Utility Commissioners’ (“NARUC”) seminar in East

15        Lansing, Michigan, completed three 8-hour OSHA HAZWOPER refresher courses

16        to maintain my certification, and attended the Indiana Chamber of Commerce’s

17        Environmental Permitting Conference.

18   Q:   Describe some of your duties at the OUCC.
19   A:   I review and analyze utilities’ requests and file recommendations on behalf of

20        consumers in utility proceedings. Depending on the case at hand, my duties may

21        also include analyzing state and federal regulations, evaluating rate design and
Public’s Exhibit No. 1
                                                                     Cause No. 45529
                                                                         Page 17 of 17
                                      highlight indicates CONFIDENTIAL information

1        tariffs, examining books and records, inspecting facilities, and preparing various

2        studies. Since my expertise lies in environmental science and policy, I assist in

3        many cases where environmental compliance is an issue.

4   Q:   Have you previously provided testimony to the Indiana Utility Regulatory
5        Commission (“Commission”)?
6   A:   Yes.
AFFIRMATION

I affirm, under the penalties for perjury, that the foregoing representations are true.

                                          Cause No. 45529
                                          NIPSCO, LLC/Elliott Solar Generation, LLC
                                          The “Joint Venture”

                                          Date: May 24, 2021
CERTIFICATE OF SERVICE

       This is to certify that a copy of the foregoing Indiana Office of Utility Consumer Counselor

Public’s Exhibit No. 1 Redacted Testimony of OUCC Witness Cynthia M. Armstrong has been

served upon the following counsel of record in the captioned proceeding by electronic service on

May 24, 2021.

Petitioner                                        Intervenor-CAC
Bryan M. Likins                                   Jennifer A. Washburn
Alison M. Becker                                  Reagan Kurtz
NISOURCE CORPORATE SERVICES – LEGAL               CITIZENS ACTION COALITION
blikins@nisource.com                              jwashburn@citact.org
abecker@nisource.com                              rkurtz@citact.org

INDIANA OFFICE OF UTILITY CONSUMER COUNSELOR
115 West Washington Street
Suite 1500 South
Indianapolis, IN 46204
infomgt@oucc.in.gov
317/232-2494 – Phone
317/232-5923 – Facsimile
You can also read