South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...

Page created by Jose Ford
 
CONTINUE READING
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
South Canal Bank Road and South Canal
                       Reconstruction at Highway 400

                    Presentation for MTO Executive Review
                               January 30, 2018

                              2014                          2017

K. Smart Associates Limited
By Kenn Smart P. Eng.
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
Background
   South Canal of the Holland Marsh system in the vicinity of Hwy 400 remains to be
    relocated/improved as per the requirements of the 2009 Engineering report, prepared by K. Smart,
    pursuant to the Drainage Act and passed into Bylaw in 2010.
   This is one of only three remaining items of work to complete the requirements of the 2009 Report.
   This work was originally included as part of Contract 2015-2004 (Hwy 400/9 Interchange
    Reconstruction and South Canal Bridge Replacement) but was later removed to reduce the risk to
    the MTO contract.
   At MTO’s request, the Holland Marsh Drainage System Joint Municipal Services Board (the
    “Board”) agreed to tender the work as a separate contract for construction in 2018 once MTO has
    sufficiently completed the South Canal bridge replacement.
   The work will be paid 100% by MTO to fulfill their obligation under the Drainage Act.
   Road design and preliminary drainage design was originally prepared by MTO’s design consultant
    (URS/AECOM/Golder) and then finalized by the Board’s consultant, K. Smart.
   Canal realignment design is as required by 2009 Drainage Act Report (Peto Geotech).

                                                                                                         2
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
Background - Continued
   Design and construction of Work will undertaken by the Board in accordance with the following
    legal agreements between the Ministry and the Board:
     ▪   April 2015 MOU which outlined the general principles of the agreement, including the fact that the
         Board would complete the design and tender the work as an independent contract, subject to approval
         by MTO, and at the cost of MTO.
     ▪   January 2017 MOU which covered the Design component of the work.
     ▪   One final Legal Agreement is currently being finalized to cover Construction and Contract
         Administration Services which requires Minister’s approval.
   The 90% Review Meeting with MTO was held on January 15, 2018.
   The canal and road realignment (to base course asphalt) must occur within a very limited time
    period from June to Nov 2018. If necessary, surface course asphalt may be placed in 2019.
   Wist Road and Davis Road must be opened prior to fall harvest and South Canal Bank Road
    must be opened by late 2018 to allow work to proceed on MTO North Canal Bridge replacement
    contract in 2019.

                                                                                                               3
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
2009 Aerial
       Of
  Highway 400
  Crossing Over
South Canal Bank
 Road and South
  Canal Prior to
    Canal and
  Highway Work

                   4
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
2017 Aerial to
show:

a) Canal
   reconstruction
   completed in
   2010/2011

b) Highway 400
   construction
   and South
   Canal Bridge
   replacement
   in progress

                    5
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
South Canal Bank Road Looking West
  Below Highway 400 (Sept. 2014)

                                     6
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
South Canal Bank Road Looking West
  Below Highway 400 (June 2017)

                                     7
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
Scope of Work
   Realignment of South Canal (270 m) to match realigned canal sections east and west of
    Highway 400 in 2010/2011
   Realignment of South Canal Bank Road (370 m) to allow road to be lowered 1.7m± to give
    5.15m± clearance below new Highway 400 deck girders
   Reconstruction of Davis Road (160 m) and Wist Road (60 m) to match lowered South Canal
    Bank Road
   All roads to have 2 – 3.5m lanes of asphalt with 50mm surface and 70mm base asphalt,
    450mm granular and SSM subgrade
   Drainage to be a combination of standard road side ditches and culverts except where sections
    of subdrain, swales and manholes are required due to utilities and/or constrained space
   Construction of new pumping station (two 3-HP pumps), including oil grit separator and two
    overflow culverts, to minimize occasions of road flooding
   Construction of new generator station, including one 600 volt 3-phase natural gas generator for
    backup power
   Installation of flood warning system with water level sensors and wireless feed to King
    Township and Board
                                                                                                      8
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
Existing
   Section
  extracted
 from 2009
Engineering
   Report

 Proposed
   Section
 Extracted
 from 90%
Submission

              9
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 - K. Smart Associates ...
Overview of
 Proposed
   Canal
Construction

               10
Overview of
   Proposed
 South Canal
  Bank Road
Reconstruction

                 11
Final Canal
  and Road
Construction
as Proposed

               12
Details of Construction Work and Timing
Work has been subdivided into 8 Stages:
Stage    Estimated Timing    Description              Activities
1        Late May/Early      Canal dewatering         - Install two transverse cofferdams 270m apart to
         June± 2018                                     isolate canal & four turbidity curtains to control
                                                        sediment
                                                      - Fish collection and relocation
                                                      - Canal dewatering
                                                      - Road closures and detours remain as currently
                                                        signed (right through to Stage 4)

2        June±               Remaining bridge &       - Remove balance of 1 pier, 1 pile cap in full, 1
                             canal removals and         pile cap partially, sheet wall bracing, sheet
                             longitudinal cofferdam     walls, canal sediments
                             construction (start of   - Construct new canal banks where in route of
                             new canal north bank       old canal (also called “longitudinal cofferdams”)
                             work)                    - Start foundation for pumping and generator
                                                        stations
                                                                                                             13
Details of Construction Work and Timing-Cont’d
Stage Estimated Timing   Description              Activities
3     June and July±     Canal excavation         - Excavate new canal
                                                  - Complete north bank including flood
                                                    berm
                                                  - Complete all in-ground pumphouse and
                                                    generator station work
                                                  - Introduce flows into new canal
                                                  - Remove transverse cofferdams

4     August±            SCBR (East) and Wist     - Excavate for roads
                         Road reconstruction to   - Construct roads (to top of granular) and
                         granular                   drainage
                                                  - Complete pumphouse
                                                  - Change road closures and detour
                                                    signage (Wist intersection is closed but
                                                    Davis intersection remains open)
                                                                                               14
Details of Construction Work and Timing-Cont’d
Stage   Estimated Timing Description              Activities
5       September±       SCBR (West) and Davis    - Excavate for and construct roads (to top of
                         Road reconstruction to     granular) and drainage
                         granular                 - Complete generator station
                                                  - Change road closures and detours (Wist
                                                    Road intersection is reopened)
6       October±         SCBR Central (below      - Excavate for and construct road (to top of
                         Hwy 400)                   granular) and drainage
                                                  - Change closures and signage back to
                                                    current configuration
                                                  - Connect pumping station and generator
                                                    station (both Wist and Davis intersections
                                                    are open)
7       November±        Base course asphalt,     - Complete all remaining work to allow
                         topsoil and seeding        substantial completion and removal of detour
                                                    and road closure signage

8       May/June 2019    Surface course asphalt   - Complete surface course paving and all         15
                                                    remaining activities to finalize work
Details
   of
Pumping
 Station

           16
Details
   of
Pumping
Station-
 Cont’d

           17
Details of Pumping Station – Cont’d
   Capacity of pumping station and culverts:
     ▪   Even for a 100mm one-hour rainfall, if canal levels are normal – no road flooding
     ▪   With same 100mm rain localized event and both overflow culverts already closed off due to high canal
         level, maximum road flooding is expected to be 150mm
     ▪   Worst case scenario of canals already at highest recently recorded level and a 100 year storm event
         over full marsh watershed, max. flooding on road is expected to be 670mm.

   Two stage flood warning system to be constructed, both triggered by sonar sensors within
    pumphouse.
     ▪   First level is a “caution” which will be activated when water levels are 300 to 400 mm below lowest
         part of South Canal Bank Road.
     ▪   King Township will be notified electronically.
     ▪   If King deems it necessary, sawhorse barricades (stored in generator station building) will be placed
         before the red second level “Road Closed” beacons are activated.
     ▪   Second level will be activated when water levels are within 50mm of the lowest point of the road.

                                                                                                                 18
Details of
Generator
Station

             19
Details of Generator Station-Cont’d

                                      20
Environmental Approvals
DCR by MTO          - All work is pursuant to the November 2014 DCR
DFO Authorization   - $125,000 Letter of Credit filed by the Board
                    - Authorization expected January/February 2018
                    - Will allow pre June 15 in-canal work
MOECC re PTTW and   - PTTW and EASR not expected to be required
EASR
LSRCA Permits       - Blanket permit already obtained for all canal work
MNRF Permits        - Only permit necessary is that for fish relocation (Scientific Collector’s
                      Permit) – to be obtained by Contractor
Migratory Birds     - Season is set at April 15 to August 15
                    - No clearing required except of brush
                    - Nesting surveys to be undertaken prior to any clearing
Species at Risk     - Mitigation for Barn Swallows (May 31-Aug 31) has already been installed
                      under MTO contract (bird kiosk)
                    - Ongoing monitoring will occur during construction, as needed, to avoid
                      harassment of birds at South Canal structure
                                                                                                  21
Estimate of Costs

   General (Mob., Insurance, Traffic, Layout, etc.)    $ 173,000
   Canal work                                            668,475
   Road and drainage work                                872,800
   Pumping station                                       178,175
   Generator station                                      94,900
   Flood warning system                                   75,000
   Construction contingencies                            120,000
   Contract Administration (10%)                         218,235
                  TOTAL ESTIMATED COSTS:               $ 2,400,585

                                                                     22
Target Dates
February 2018           -   Complete tender package
                        -   Obtain Encroachment permit from MTO
                        -   Applications for Hydro and Gas services by Board
                        -   Receipt of DFO approval

March 2018              - Tendering (invitational)

April 2018              - Review of tenders by Board and MTO
                        - Contract Award

May 2018                - Start up of construction (cofferdams and dewatering)
                          provided no constructor issues with Contract 2015-2004

June to November 2018   - Construction to substantial completion Stage 7

May/June 2019           - Stage 8 and final completion                             23
You can also read