Separation of Continental Europe Synchronous Area on 8 January 2021 - Janusz Bialek Professor of Power and Energy Systems Newcastle University and ...
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Separation of Continental Europe Synchronous Area on 8 January 2021 Janusz Bialek Professor of Power and Energy Systems Newcastle University and Skoltech
Outline • Description of the event • A trip of the busbar coupler in SS Ernestinovo (Croatia) triggered a cascade of line trips ending with a network split • Unanswered questions • Comparison with 2006 system separation ENTSOE: “Continental Europe Synchronous Area Separation on 8 January 2021. Interim Report” 26 Feb 2021
System conditions on 8 January 2021 • Slightly unusual loading situation: • low demand in the South due to warm weather and Orthodox holidays • higher demand in Central/Western Europe due to cold weather • Strong South->North power flows: 6.3 GW • But not big differences (apart from ES–PT and CZ–PL) between day- ahead and realised market schedules (top) • There were differences between scheduled and measured power flows (bottom) – but they were not abnormal and to be expected • No unplanned unavailability of production units • No planned maintenance works or unplanned outages in the network • grid topology was mapped correctly in the network models used • In summary: nothing highly unusual
Croatian network • The cascade was initiated by a busbar coupler trip in SS Ernestinovo • (N-1) security analysis every minute using SCADA • Good match between forecasted Intra-Day Congestion Forecast (ICDF) values and actual power flows in SS Ernestinovo • A mismatch of only 100 MW (150 A) on the flow of the busbar coupler (vs the limit of 2080 A) • The tripping of the busbar coupler was not included as a possible event in the n-1 contingency simulations • Guideline on electricity transmission system operation (called ‘SOGL’) stipulates that it is up to individual System Operators to consider a trip of a busbar coupler in (N-1) security analysis
Busbar coupler trip in SS Ernestinovo • The current was near the limit of 2080 A • So the system was only marginally (N-0) secure! • Not clear why it was allowed if the flows were close to the predicted ones • Busbar coupler trips at 14:04 on overcurrent protection • Tripping of two 400/110 kV transformers and a separation of the two busbars in SS Ernestinovo
• A shift in power flows in neighbouring transmission lines. • Cascaded trips of transmission lines on distance, out-of-step and power swing protection • The CE power system splits up into two areas over approximately 20 seconds.
Trip of the Busbar Subotica-Novi Sad coupler trip PMU recordings transmission line • The system was already operating close to angular instability with voltage phase angle differences of close to 90 degrees between Western Europe (Switzerland) and Eastern Europe. • Not clear why was it allowed to happen • Event #1 already had a visible impact on the overall system stability. The small oscillations stabilised before the overload of the second element • After event#2, the entire system reached the “point of no return” and the two areas started to separate from each other due to angular instability. • Power deficit in the North-West (frequency drop) and power surplus in the South-East (frequency rise)
Frequency response: activation of frequency containment reserves (FCR) • All generation units which participated in the primary control either decreased (South-East) or increased (North- West) their power generation • By exceeding the 200 mHz limit, a high number of generation units changed their control mode to emergency control • activating additional reserves in the North-West area • decreasing their generation in the South-East area. • Example of a provider in Austria – a nearly perfect droop
Activation of interruptible loads in North-West • Power deficit of 6.3 GW • Shedding of 1.7 GW of automatic interruptible load in France and Italy
Disconnection of generation units or loads close to the separation line • Due to the high transients of voltage and frequency, a significant number of generation units and industrial or domestic loads were disconnected in both areas • South-East: • approximately 1 GW of generation connected to the transmission system and 60 MW connected to the distribution system • 233 MW of the load tripped - mainly close to the separation line • North-West: • 348 MW of generation tripped. • The total load disconnected was 70 MW: • 36 MW was located close to the separation line and disconnected due to extreme transients. • 34 MW tripped due to incorrect protection device settings
Disconnection of non-conforming generation units or transmission elements • South-East: • Because of the over-frequency (in excess of 300 mHz), tripping of about 833 MW of non-conforming dispersed generation connected to the transmission system and 687 MW embedded in the distribution system • North-West: • several automatic disconnections took place, even very far from the system separation line, due to frequency deviations outside the normal operation range of +/- 200 mHz. • Due to incorrect protection settings, another 296 MW of generation tripped far from the separation line and only based on the resulting 250 mHz frequency drop. • Distributed generation with non-conforming disconnection settings (49.8 Hz) with a total of 295 MW • The loss of the HVDC link between Santa Llogaia (Spain) and Baixas (France) occurred due to an erroneous protection parametrisation of the auxiliary sources for a frequency threshold of 49.75 Hz.
Support from other synchronous areas over HVDC links • The North-West area received 535 MW from the Nordic synchronous area and 60 MW from Great Britain.
Resynchronisation
Unanswered questions • Large-scale involuntary load shedding was avoided due to interruptible loads, but why did a split happen in the first place? • The loading situation was unusual but the predicted and realised market schedules were close • Why was the system close to angular instability even before the coupler trip? • Why was the system only marginally (N-0) secure as the busbar coupler current was close to the limit? • Why wasn’t a trip of the busbar coupler deemed not dangerous so it was not included in (N-1) security analysis?
Comparison with 2006 system separation in Europe • 15M households affected, 17.7 GW load shed • Why did a disturbance in Northern Germany black out customers in Portugal, Spain and Italy?
Timeline • EON agrees to disconnect a 380 kV line in North Germany to let a ship pass – a routine request • The day before the event, the shipyard requests to bring forward disconnection by 3 hours • EON agrees but does not modify Day Ahead Congestion Forecast (DACF) distributed to all TSOs • Stronger than forecasted wind on the day, big differences between predicted and actual power flows
Timeline • EON concludes empirically, without doing (N-1) analysis, that the outage would be still (N-1) secure (it wasn’t!) • Disconnecting the line results in high power flows • EON assess the situation empirically, without simulations (again!), and decides to couple a busbar in Landesbergen substation to reduce a line current by 80 A • Result: the current increases by 67 A and the line trips • Cascading line tripping resulting in separation into 3 regions with different frequencies
10 GW surplus 51.4 Hz • Western zone: 8.9 GW deficit • Drop of frequency caused tripping of 10.7 GW of generation • 60% of wind plants tripped (due to f < 49 Hz) • 30% of CHP tripped 8.9 GW deficit • 16.7 GW load shed 49 Hz • North-Eastern zone: 10 GW surplus 0.8 GW deficit 49.7 Hz • Initial rise of frequency halted by automatic frequency control and tripping of frequency-sensitive generation (mainly wind – 6.2 GW tripped) • As frequency started to drop, windmills started to reconnect automatically worsening the situation • South East: 0.8 GW deficit • No load shedding activated • Subsystem (N-1) secure
Comparison between the 2006 and 2021 incidents • Root causes of 2006 outage • Operational mistakes by EON • Lack of coordination between TSOs • Lack of operational awareness of the external situation • Significant changes have been implemented since 2006 to improve coordination and operational awareness: ENTSO-E Awareness System (EAS) • Similarities between the incidents: • It was the busbar coupler that initiated the cascades: manual merging in 2006, automatic splitting in 2021 • North-South system separation along similar lines • Differences • Poor match in 2006, and a reasonably good match in 2021, between the predicted and actual power flows • Smaller deficit (6.7 GW) of the West in 2021 than in 2006 (8.9 GW) • Far less shedding of DG • No large-scale involuntary load shedding in 2021 due to a lower deficit and automatic disconnection of interruptible loads
Summary • A busbar coupler trip caused a system separation • It was (N-1) event but it had not been included in (N-1) security analysis • Involuntary load shedding was avoided due to activation of 1.7 GW of interruptible load shedding • Unanswered questions • Some similarity to a 2006 event - busbar coupler did it!
You can also read