Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0

Page created by Veronica Ingram
 
CONTINUE READING
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Project Management
Plan Draft

Sporting Life
Collingwood

                Created by: Michael Dixon
                 Date: November 22, 2020
                              Version 1.0
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                                             Project Name: Sporting Life
                                                      Project Number: TBD
                                                                                             Collingwood

                                                      Version: 1.0                           Page 2 of 25

                                                     Table of Contents

1. General, Project Safety and Security ........................... 4Error! Bookmark not defined.
   A(1.1) Project Description ............................................................................................... 4
   B(1.2) Project Team Contact Information (Owner, Consultant, Contractor)…………………..4
   C(1.3) Construction Schedule (Milestones) ....................................................................... 7
   D(1.4) Construction Safety and Security............................................................................ 8
   E(1.5) Fire and Emergency Access .................................................................................... 9
   F(1.5) Hours of Construction ......................................................................................... 10
   G(1.5) Construction Process Outline ............................................................................... 10
          i) Excavating and Grading .................................................................................... 10
          ii) Shoring........................................................................................................... 11
          iii) Servicing ........................................................................................................ 11
          iV) Crane and Hoist Operation ........................................................................................ 12
          v) Construction of Structure ................................................................................. 12
          vi) Interior and Exterior Finishing .......................................................................... 12
          vii) Occupancy .................................................................................................... 13

2. Noise, Dust and Vibration Control ......................................................................... ….13
  A(2.1) Preconstruction Survey of Neighbouring Properties ............................................... 13
  B(2.2) Dust and Mud Control ......................................................................................... 13
  C(2.3) Road Cleaning Schedule ...................................................................................... 14
  D(2.4) Emissions and Air Quality Controls ....................................................................... 13
  E(2.5) Noise................................................................................................................. 13
  F(2.6) Key Project Milestones ........................................................................................ 14

3. Site Management ....................................................................................................... 15
   A(4.1) Site Access and Haul Route Map .......................................................................... 16
   B(4.2) Fill Source and/or Disposal Site ............................................................................ 17
   C(4.3) Vendor Management .......................................................................................... 18
   D(4.4) Traffic Management Plan………………………………………………………………………………………..…18
   E(4.5) Construction Trailer and Materials Storage Location……………………………………………….…18
   F(4.6) Off-Site Requirements ......................................................................................... 18
   G(4.7) Delivery Times and Loading Areas .................................................................................. 18
   H(4.8) Worker Access and Parking ................................................................................. 18
   I (4.9) Pedestrian Access ............................................................................................... 19
   J (5.0) Adjacent Propert Access Impacts ......................................................................... 21
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                                            Project Name: Sporting Life
                                                     Project Number: TBD
                                                                                            Collingwood

                                                     Version: 1.0                           Page 3 of 25

4. Waste Management ................................................................................................... 21
   A(4.1) General Waste Management ............................................................................... 21
   B(4.2) Site Tidiness ....................................................................................................... 21

5. Environmental Management ...................................................................................... 21
   A(5.1) Erosion and Sediment Control ............................................................................. 21
   B(5.2) Water Quality Control ......................................................................................... 21
   C(5.3) Tree Protection .......................................................................................... 22 & 23
   D(5.4) Spill Response Plan ............................................................................................. 24
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                                             Project Name: Sporting Life
                                                      Project Number: TBD
                                                                                             Collingwood

                                                      Version: 1.0                           Page 4 of 25

General, Project Safety and Security

      A (1.1) Project Description

This project is located at 222 Hurontario Street in Collingwood, Ontario. It consists of Foundation work, new steel and
decking, new masonry, new partitions including ceilings, new paint, doors and frames, mechanical and electrical.

This project is a restoration to the existing building that unfortunately was burnt down.

      B (1.2) Project Team Contact Information

 Integricon Contact List - Sporting Life Collingwood
 Name                      Position                 Phone Number             Email Address

 Darryl D'Silva            Project Manager          416-436-6744             darryl.dsilva@ipcg.ca
 Andy Iadinardi            Site Supervisor          416-970-6908             andy.iadinardi@ipcg.ca
 Michael Dixon             Estimator                647-395-4273             michael.dixon@ipcg.ca

 DELIVERABLE                  DESCRIPTION                                     COMPLETED BY                     APPROVER(S)
                               Outlines key high level objectives of the
                               project including, scope, schedule, budget,
 1.     Project Plan                                                          Integricon Project Manager
                               resources, risk and governance.

                               Detailed project schedule specific to the
 2.     Construction           physical construction aspects of the
                                                                               Integricon Project Manager
        Project Schedule       project.

 3.     Master                High level integrated schedule containing
        (Integrated)          both operational and construction                Integricon Project Manager
        Schedule              milestones.
 4.     Risk Register/Issue   Consolidated list of any potential project
                                                                              Integricon Project Manager
        Log                   risks or issues, their likelihood of
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                                             Project Name: Sporting Life
                                                     Project Number: TBD
                                                                                             Collingwood

                                                     Version: 1.0                            Page 5 of 25

DELIVERABLE                 DESCRIPTION                                        COMPLETED BY                      APPROVER(S)
                            occurrence, identification of the risk owner
                            and their mitigation strategy.
5.    Communication         Detailed communication strategies,
                                                                               Integricon Project Manager
      Matrix                schedules and owners.
                            Questionnaire for project team/external
6.    Project Close         stakeholders as required to identify project
                                                                                       Consultant
      Questionnaire         wins and challenges and provide context
                            for the Project Close Report.
                            The Project Close-Out Report is the
                            project’s epilogue. Provides detail on all
7.    Project Close         project wins and challenges and
                                                                                      Consultant
      Report                recommendations on how replicate the
                            good and mitigate the issues in like
                            projects in future.

                                                                               Manages the construction process of the
                                                                                project
                                                                               Oversees the design drawing process –
                                                                                IBPA/Tender, IFC , record drawings and
                                                                                development of trade specifications
                                                                               Establishes and develops trade tender
                                                                                process
                                                                               Initiates construction and 3rd party liability
                                                                                insurance
                                                                               Identifies construction staffing and resource
     Construction Manager
                                                                                requirements as necessary; sources staff as
                                                                                appropriate
                                                                               Plans, organizes, leads, motivates and
                                                                                monitors the activities of the construction
                                                                                staff members / general contractors
                                                                               Manages construction budget portion of
                                                                                project. Tracks, manages Construction
                                                                                Change Control process.
                                                                               Oversees and manages risks; escalates as
                                                                                necessary
                                                                               Construction administration
                                                                               Construction coordination
     Project Technician
                                                                               Create layout design printouts showing FF&E
                                                                                and technical equipment (DVR, Monitors, etc)
     Project                                                                   Assists the PM and CM in providing draft
     Coordinators/Communications                                                Agendas and Meeting Minutes, Dashboards
     Leads                                                                      for review and distribution.
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                    Project Name: Sporting Life
                                Project Number: TBD
                                                                    Collingwood

                                Version: 1.0                        Page 6 of 25

                                                      Schedules corporate and on-site resources for
                                                       cut-over initiatives.
                                                      Books meetings and travel as required.
                                                      Budget reconciliation
                                                      Function research as required, collation of
                                                       information and reporting back to the larger
                                                       team.
                                                      Purchasing assistance through generation and
                                                       follow up of PO’s and other orders.
                                                       Liquor license update / changes
Manager, Licensing &                                   Prior to conducting business or the execution
Registration                                            of a contract, notice will be given to the
                                                        Compliance Officer.
                                                       Provides financial reporting and guidance
                                                        related to project
Finance                                                Set up new accounts for new vendors
                                                       SEA submissions & management
                                                       Asset transfer management
                                                      Manages and oversees the budget and
                                                       scheduling portion of the FF&E items
                                                      Initiates FFE tender bids. Proposes FFE
                                                       alternates received from vendors
Purchasing and Fit Out                                Coordinates installation with vendors and
                                                       operations
                                                      Provides direction to operations regarding
                                                       daily operating items to be ordered outside of
                                                       the FF&E items
                                                      Manages the low tension requirements for
                                                       the project: surveillance, access controls, A/V
                                                       , IT
                                                      Manages and oversees the budget and
                                                       scheduling portion of the low tension
                                                       requirements
                                                      Responsible for technical recommendations
Manager, IT Operations
                                                      Responsible for low tension
Services
                                                       recommendations
                                                      Documents trouble shooting and reporting
                                                       procedures and policies
                                                      Trains applicable staff on the use of said
                                                       equipment
                                                      Trains applicable staff on trouble shooting
                                                       and reporting procedures and policies
                                                      Identifies surveillance equipment and
Surveillance Director /
                                                       procedural requirement to comply with
Manager
                                                       company and regulatory policies and
                                                       procedures
                                                      Identifies access controls equipment and
                                                       procedural requirement to comply with
Security Director / Manager
                                                       company and regulatory policies and
                                                       procedures
Construction Site Supervisor/                         Oversees day to day on site construction
CSO / Foreman/ Laborers                                activities
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                              Project Name: Sporting Life
                                         Project Number: TBD
                                                                              Collingwood

                                         Version: 1.0                         Page 7 of 25

                                                               Supervision and coordination of trades on
                                                                site. Determines work sequencing of trades
                                                               Develops construction schedule based on
                                                                overall project milestone
                                                               Provides site safety policies and procedures
                                                                to construction site as well as areas outside of
                                                                construction site boundaries.
                                                               Provides carpentry work, site organization
                                                                and general cleanup of work site
                                                               Provides design and specifications for each of
 Architect, Engineering and                                     their disciplines
 Design Consultants                                            Development of design concepts, Permit, IFC
                                                                and As built drawings

C (1.3) Construction Schedule

 Project Schedule:

 -   Mobilization – March 1 – March 8 (1 Weeks)
 -   Excavating – March 9 – March 16 (1 Week)
 -   Concrete Forming and Pour – March 17 – 31 (2 Weeks)
 -   Backfill and Compact – April 1 – April 7 (5 Days)
 -   Erect Structural Steel and Metal Deck - April 12 – April 30 (3 Weeks)
 -   Roofing – May 3 – May 24 (3 Weeks)
 -   Masonry for Envelope – May 25 – June 15 (3 Weeks)
 -   Mechanical – June 16 – June 30 (2 Weeks)
 -   Partition Framing – July 1 – July 22 (3 Weeks)
 -   Electrical Rough- Ins – July 23 – July 30 (1 Week)
 -   Drywall – August 1 – September 1 (1 Month)
 -   Painting – September 1 – September 10 (1.5 Weeks)
 -   Flooring – September 13 – September 20 (1 Week)
 -   Mechanical and Electrical Finishes – September 21 – September 24 (2 Days)
 -   Coordinate Owner Supplier Millwork - September 21 – September 22 (2 Days)
 -   Occupancy and Demobilization – September 23 – September 28
 -   Deficiencies (2 Weeks)
 Total Timeline – 6 Months
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                                Project Name: Sporting Life
                                             Project Number: TBD
                                                                                Collingwood

                                             Version: 1.0                       Page 8 of 25

D (1.4) Construction Safety and Security

In order to meet the overall goal of project safety and security, the Project will be organized and managed to
accomplish the following objective :

     Establish policies regarding acceptable levels of risk, to guide the review and evaluation of safety and
      security issues throughout the Project
     Provide mechanisms for the formal identification, consideration, elimination or control of hazards to and
      vulnerabilities of employees, contractors, emergency responders, and the general public
     Verify that appropriate codes, guidelines and standards have been reviewed to provide a basis for safety
      and security considerations in the design criteria and implemented to site
     Verify that contract deliverables (facilities, systems and equipment) are reviewed against the contract
      specifications and drawings (including all approved design changes) for compliance with safety and security
      requirements
     Verify the emergency preparedness and operational readiness of the Project before entering
      commencement of the project
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                     Project Name: Sporting Life
                                    Project Number: TBD
                                                                     Collingwood

                                    Version: 1.0                     Page 9 of 25

E (1.5) Fire and Emergency Access
Project Management Plan Draft Sporting Life Collingwood - Created by: Michael Dixon Date: November 22, 2020 Version 1.0
Title: Project Management Plan
                                                                                Project Name: Sporting Life
                                            Project Number: TBD
                                                                                Collingwood

                                            Version: 1.0                        Page 10 of 25

F (1.6) Hours of Construction

     Hours of construction will be Monday to Friday, 7am – 5pm. Weekends may be required.

G (1.7) Construction Process Outline

     i)       Excavating and Grading

              -   The primary step is to confirm the extent of soil and clearing of the site (unwanted bush, weeds
                  and plants)
              -   Set ground tracing – Process of laying excavation lines and centre lines before excavation
              -   Place maximum of 4, no less than 2 benchmarks are marked in the corner for the measurement
                  of level. Benchmarks are usually marked on a permanent structure.
              -   With the drawing reference and benchmarks, the excavation depth is fixed.
              -   Excavation commences with either machine or manual depending on the volume needed to be
                  removed.
              -   Excavated Material is then removed or stockpiled on site depending upon geotechnical results.
                  Contaminated soil is to be removed from site and engineered fill is to be put in place of. A
                  minimum of 1m is to be maintained between stockpile and pit to keep run off from rain entering
                  the excavated pit.
              -   If loose soil is the condition, shoring must be in place to avoid collapse.
              -   Dewatering is to be used providing the area has a high water table or after rainfall
              -   Backfill and compact with a plate tamper in lifts of 1-2” once concrete forms have been
                  removed. Water is also used in addition to accomplish a minimum of 98% proctor.

              Standard Scope of Work for Excavating

              -   Setting of corner benchmarks
              -   Survey for ground levels
              -   Survey for top levels
              -   Excavate until approved depths
              -   Dressing of loose soil
              -   Making up to cut off level
              -   Construction dewatering wells and interconnecting trenches
              -   Marking boundaries of the building
              -   Constructing trench protection

     ii)      Shoring

              -   Shoring is the process of supporting underground walls of a building, trench or floor while under
                  construction. Shores are usually either jacks, shotcrete or plywood.
              -   Depending on the soil type, shoring support is usually provided when we need to support an
                  excavation with at least 1.20-meter difference in levels from the +/- 0.00 level.
              -   The structural engineer’s drawings are reviewed by the construction team and the pile locations
                  are marked on site.
Title: Project Management Plan
                                                                             Project Name: Sporting Life
                                       Project Number: TBD
                                                                             Collingwood

                                       Version: 1.0                          Page 11 of 25

       -   Early survey information is reviewed, control points are established on-site, and the property
           line is confirmed if shoring is present along the property line (which it nearly always is). With this
           information in hand, the team can safely and legally proceed with shoring installation.
       -   The hole for each pile is augered one-by-one and the wide flanges are dropped into place. The
           wide flange section can vary depending on the project, however W12s are often used in
           residential applications; this requires the augered hole to range anywhere from 18 to 24 inches
           in diameter. In the image below, the drilling rig has just completed a 24-inch diameter hole and
           is lifting a W12x45 (that’s 12 inches deep and 45 pounds per linear foot) into place.
       -   In the event of poor soil conditions, where the soil would collapse in on the hole, an auger cast
           is used in conjunction with the drilling. A steel sleeve follows the drill to the bottom of the hole,
           as the drill retracts, the dirt is pushed upward and replaced with concrete. The wide flange is
           then inserted into the concrete filled hole. The image below shows the steel sleeves along with
           a pile of wide flanges in the background.\
       -   Where jacks are used, they are to be placed 1’ from the existing location of the column(s). Once
           installed, removal of the column can begin.

       Types of Shoring

       -   H or I-Beam Shoring
       -   Pile Shoring
       -   Shotcrete Shoring
       -   Sheet Piles
       -   Diaphragm Walls
       -   Adjustable Jacks

iii)   Servicing

       -   Preliminary steps include reviewing above ground light poles and power supply, Bell/Telephone
           cables, pedestals and transformers and landscaping.
       -   Secondary steps include review and survey of existing underground services – sanitary sewers,
           storm sewers, foundation drains, watermain and water services (domestic and fire lines),
           including all bedding, diameter, slopes, direction of flow and invert elevations.
       -   Once identified, shut off requirements from the city/town must be done.
       -   Once shut off, excavation can begin for the new lines.
       -   Upon completion of the lines, chlorination included, all services can be opened. In cases where
           the water supply line is opened, a thrust block is used in case of the pressure is too high and
           damages the flange of new to existing.
       -   Backfilling of the required bedding is installed and backfilling of either engineered fill or native
           begins.

iv)    Crane and Hoist Operations

       Prior to hoisting or rigging material, the following reviews will be done on site:

       -   Review of working load limit
       -   Review of equipment to determine and defective equipment
       -   Review of weather or wind conditions
       -   Review of any local electrical contact
Title: Project Management Plan
                                                                               Project Name: Sporting Life
                                           Project Number: TBD
                                                                               Collingwood

                                           Version: 1.0                        Page 12 of 25

         -     Review of hoist line not plumb when crane in place

Procedure

Once all items have been removed, the crane will be put in place. Outriggers will then be extended with pads.
Material must be stockpiled within a safe reach and the required slings, handlines and taglines will be used to
secure the load.
A crane safety check will be done daily by the site supervisor and crane operator. In the case of a basket, an
inspector will Sign off on the condition of the basket. A copy of all safety procedures will be on site at all
times.

v)       Construction of Structure

         Standard Construction Procedure is as follows:

         1)    Site Preparation
         2)    Implement drainage to code
         3)    Excavate Site
         4)    Lay Utilities
         5)    Arrange power, water and sanitation
         6)    Remove vegetation/grading site
         7)    Construct temporary storage facilities/mobilization
         8)    Begin inspections – structural, building code, utilities, HVAC, electrical…etc
         9)    Foundation work (forming, rebar, concrete)
         10)   Framing, either structural steel or wood framing
         11)   Roofing and siding (complete envelope)
         12)   Interior (HVAC, Electrical, Partitions, Paint, Millwork Flooring) all once envelope is water tight
         13)   Exterior Landscaping
         14)   Demobilization

vi)      Interior and Exterior Finishing

         Interior finishes will consist of framing, gypsum board, acoustic tile, paint, flooring, millwork, doors
         and frames.

         Exterior finishes will consist of roofing material, brick, siding, paving and landscaping.

vii)     Occupancy

         Occupancy will be obtained through providing the necessary requirements as per inspections
         (rough-in, finish, EAS…etc.). If occupancy is not obtained, a deficiency list will be acquired by the
         city inspector and there is a 60 day timeline for correction.
Title: Project Management Plan
                                                                                  Project Name: Sporting Life
                                                Project Number: TBD
                                                                                  Collingwood

                                                Version: 1.0                      Page 13 of 25

 2. Noise, Dust and Vibration Control

A (2.1) Preconstruction Survey of Neighbouring Properties

 None Necessary. Access remains separate for gas station.

B (2.2) Dust and Mud Control

              -    Reduce Traffic - Vehicles traveling on unpaved roads stir up dust. Reducing the number of
                   vehicles can reduce dust. Traffic can be reduced voluntarily; encouraging walking is one way.
                   Traffic can be reduced by restricting vehicle weight or type, or by limiting motor vehicle access
                   to dirt roads.
              -    Reduce Speed - Speed limit signs and enforcement can reduce speeds. Drainage channels
                   across roads and speed bumps can reduce speeds.
              -    Water on the Road - Moisture in the surface of dirt roads causes particles to stick together. The
                   moisture content of dirt roads can be increased by watering the road surface. Depending on
                   weather conditions, a single watering may be effective for hours or for days. When water is
                   applied alone, it provides a short- term reduction in dust. Regular, light watering is better than
                   less frequent, heavy watering.
              -    Mud Mat or Covering Unpaved Roads - Applying gravel to a dirt road surface can reduce dust.
                   Gravel provides a hard surface protecting soils from vehicle wheels. Local road maintenance
                   specialists or ADOT contacts can provide information about effective ways of gravelling roads.
                   Gravel does not reduce the strength of air currents caused by vehicles themselves, so traffic
                   can still blow loose soil particles into the air. Without a good road base of crushed aggregate,
                   traffic will push surface gravel down into the ground, especially when the road is wet. If the road
                   surface does not have enough fine material to cement the surface gravel in place, traffic will
                   push the gravel away from the driving lanes.
              -    Slow the Wind - Windbreaks are barriers designed to slow the speed and redirect the flow of
                   wind. Green silt fence on hoarding will be installed on either a chain-link fence or plywood
                   hoarding will slow the wind speed.

              All will be used to maintain dust and mud.

C (2.3) Road Cleaning Schedule
     While on site and during construction, a street sweeper and water truck will be on site at the end of the
     to maintain a clean site. Town requirements will be maintained as well.

D (2.4) Emissions and Air Quality Control
     While on site no car or truck will idle.
Title: Project Management Plan
                                                                                 Project Name: Sporting Life
                                              Project Number: TBD
                                                                                 Collingwood

                                              Version: 1.0                       Page 14 of 25

 E (2.5) Noise

  Administrative controls, (such as reducing the length of time the worker is required to work in a noisy area), and
  the use of personal protective equipment (PPE) are measures that control the noise at the worker. Depending
  on the type and level of noise; number of workers exposed, and the type of work, engineering controls might not
  always be considered as reasonable solutions. Where the exposure would not justify the implementation of more
  expensive solutions, a combination of administrative control (limitation of exposure length) and personal
  protection equipment may be considered.

  Work will commence as per towns regulations and remain within the requested decibals.

  PPE must be worn at all times and additional COVID measures will be put in place.

  F (2.6) Key Project Milestones

MILESTONE                                                        START DATE               END DATE
Envelope                                                      March 9, 2021         June 15, 2021
Title: Project Management Plan
                                                                            Project Name: Sporting Life
                                           Project Number: TBD
                                                                            Collingwood

                                           Version: 1.0                     Page 15 of 25

3. Site Management

  A (3.1) Site Access and Haul Route Map
Title: Project Management Plan
                                                                                     Project Name: Sporting Life
                                                    Project Number: TBD
                                                                                     Collingwood

                                                    Version: 1.0                     Page 16 of 25

B (3.2) Fill Source and/or Disposal Site

Below is the location for the Fill/Disposal site.
Title: Project Management Plan
                                                                   Project Name: Sporting Life
                                  Project Number: TBD
                                                                   Collingwood

                                  Version: 1.0                     Page 17 of 25

C (3.3) Traffic Management Plan
Title: Project Management Plan
                                                                                Project Name: Sporting Life
                                               Project Number: TBD
                                                                                Collingwood

                                               Version: 1.0                     Page 18 of 25

C (3.4) Construction Trailer and Materials Storage Location
Title: Project Management Plan
                                                                                  Project Name: Sporting Life
                                               Project Number: TBD
                                                                                  Collingwood

                                               Version: 1.0                       Page 19 of 25

C (3.5) Off-Site Requirements

None

   C (3.6) Delivery Times and Loading Areas

        Delivery times will consist of morning drop off times. The site will be open at 7am and will remain open
        until 4-5pm daily

   C (3.7) Worker Access and Parking
Title: Project Management Plan
                                                             Project Name: Sporting Life
                            Project Number: TBD
                                                             Collingwood

                            Version: 1.0                     Page 20 of 25

C (3.8) Pedestrian Access
Title: Project Management Plan
                                                                                      Project Name: Sporting Life
                                                  Project Number: TBD
                                                                                      Collingwood

                                                  Version: 1.0                        Page 21 of 25

C (3.9) Adjacent Property Access Impacts

None necessary. Hoarding will separate properties and separate access is available to gas station.

4. Waste Management

   A (4.1) General Waste Management

Daily garbage removal will be done by all trades as per their contract. A 40 yard mixed garbage bin will be on site and
emptied on a weekly basis.

   B (4.2) Site Tidiness

General cleaning will be done at the end of every day. Each trade will be responsible for site tidiness with the
supervision of Integricon. Upon failure to maintain site tidiness a warning will be sent to the subcontractors
management and if the problem continues, Integricon will clean and back charge the subcontractor.

5. Environmental Management

A (5.1) Erosion and Sediment Control

Integricon will conduct site erosion and sediment control as if the site was a LEED project. This includes filter cloth
under all catch basin covers, mud mats and silt fence along the bottom of the hoarding to keep all run off contained.

   B (5.2) Water Quality Control

Water supply is city supplied.
Title: Project Management Plan
                                                                                 Project Name: Sporting Life
                                              Project Number: TBD
                                                                                 Collingwood

                                              Version: 1.0                       Page 22 of 25

C (4.3) Tree Protection

        Tree protection will consist of plywood hoarding (minimum 19mm or ¾”) or equivalent barriers. The
        barriers will be made of 2.4m (8’) high plywood hoarding. If tree branches are lower than 8’, we will use
        a lower and approved height.
Title: Project Management Plan
                                                                                      Project Name: Sporting Life
                                                  Project Number: TBD
                                                                                      Collingwood

                                                  Version: 1.0                        Page 23 of 25

D (4.4) Spill Response Plan

Integricon’s Spill Response Plan is as follows:

    1)   Make sure area is safe for entry and the spilled material or liquid does not pose an immediate threat to health
         and safety of responder.
    2)   Check for hazards (flammable material, noxious fumes, cause of spill).
    3)   If serious hazards are present leave the area and call 911.
    4)   If possible, stop the source of spill (plug hole, upright the container, shut off valve) following all health and
         safety procedures
    5)   Prevent spill from entering stormwater drain using absorbent or other spill response material as necessary or
         as directed by Workplace Hazardous Material Information System (WHMIS) and Safety Data Sheets (SDS).
    6)   If spilled material has entered the sanitary sewer contact Regional Source Control Program
    7)   Clean up spilled material/absorbent (do not flush area with water).
    8)   Dispose of cleaned material/absorbent in secure container for disposal as hazardous waste.
You can also read