Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture

Page created by Erica Vazquez
 
CONTINUE READING
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Front-End Engineering Design Study for a Carbon Capture Plant Retrofit to a Natural Gas-Fired
           Turbine Combined Cycle Power Plant (2x2x1 Duct-Fired 758-MWe Facility with F Class Turbines)

                                                                                                 In Partnership with:
Presentation to ARPA-E, January 14, 2022
                                                                                                    US DOE/NETL
Award No. DE-FE0031848/0000                                                                         EPRI
Post-Combustion Capture                                                                             Nexant
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Project Scope and Objectives

                     § FEED Study encompasses the engineering required for the design, construction, and
                       operation of the carbon capture and compression unit, including modifications to the
                       existing facility per the retrofit
                         – Transportation of CO2 and ultimate use were not part of this study, but were factors in
                           identifying the location
                     § Open-access philosophy was adhered to for this project and all aspects of the capture
                       unit design are non-proprietary
                     § Project’s Objectives:
                         ✓ Utilize a low-cost generic solvent
                         ✓ Provide balances and process data details, open for public review
                         ✓ Provide cost estimates and material quantities, open for public review
                         ✓ Provide implementation schedule and operation economics (accounting for current operation
                           regimes in Texas/ERCOT)
                         ✓ Allow the study deliverables be available to the public

© 2021 Bechtel | 2                                         Level 3 - Bechtel Internal & Select External Distribution
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Sherman Energy Center, Sherman, Texas, USA

   Why Sherman Energy Center?
   § F-class gas turbines (state of the art
     technology)
   § Sufficient land available contiguous to the
     power plant
   § Proximity to oil fields, saline aquifers, and
     sedimentary basis, for recovered CO2
     storage
   § Cooperative host that is a Bechtel customer

© 2021 Bechtel | 3                                   Level 3 - Bechtel Internal & Select External Distribution
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Project Background – Process & Operation

                     § This FEED is based on a prior study led by Bechtel,
                       for a similar plant in Kårstø, Norway (also publicly
                       available)
                     § Carbon capture process encompasses a conventional
                       absorber-stripper configuration using a low-cost
                       amine-based solvent
                         – Using generic solvent facilitates procurement at
                           competitive prices. There will be no wide-reaching
                           restrictions on knowledge transfer to and from the
                           project.

                                                                                                                          R. R. Bottoms Patent, 1930

© 2021 Bechtel | 4                                            Level 3 - Bechtel Internal & Select External Distribution
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Results: Layout DP (Integrated Layout)

                                                Carbon Capture Plant

                                                             Power Plant

© 2021 Bechtel | 5                        Level 3 - Bechtel Internal & Select External Distribution
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Results: Cost Estimation DP

           Capital cost of the five major portions of the
           PCC plant:
                     –   Flue Gas Conveyance and Conditioning: $102M
                     –   CO2 Absorption: $151M
                     –   Solvent Regeneration: $75.6M
                     –   CO2 Compression and Conditioning: $84.5M
                     –   Stack Modification: $31.1M

                     Total: $444M

                                                                                                           Cost for PCC Areas as Percent of Contractor’s Cost

© 2021 Bechtel | 6                                         Level 3 - Bechtel Internal & Select External Distribution
Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
Results: Cost Estimation DP

                     § Capital cost of the PCC plant broken down into
                       the commodities and classes of costs used in the
                       EPC estimating process
                         −   Material/Equipment: $116M
                         −   Piping: $17.8M
                         −   Instrumentation: $13.3M
                         −   Electrical Equipment: $17.8M
                         −   Field Indirect: $40M
                         −   Total Field Services: $22.2M
                         −   Engineering/Other Office Services: $44.5M
                         −   Labor: $48.9M
                         −   Sub-Contractor: $22.2M
                         −   Contingency: $35.6M
                         −   Fee, Risk, and Misc: $57.8M
                         −   Civil Works: $8.90M
                         Total: $444M
                                                                                                                                 Costs as Percentage of Contractor’s Cost

© 2021 Bechtel | 7                                                   Level 3 - Bechtel Internal & Select External Distribution
Results: Cost Estimation DP

                     Basis of Operating Cost

© 2021 Bechtel | 8                             Level 3 - Bechtel Internal & Select External Distribution
Results: Cost Estimation DP

                     Cost Sensitivities and Uncertainty Levels Tornado Diagram

© 2021 Bechtel | 9                                               Level 3 - Bechtel Internal & Select External Distribution
Pilot Plant

                                                                                            Purpose:

                                                                                            • Understand amine
                                                                                              degradation in the
                                                                                              atmosphere
                                                                                            • Confirm efficacy of
                                                                                              reclaimer
                                                                                            • Analyze long-term solvent
                                                                                              health/confirm degradation
                                                                                              rates
                                                                                            • Confirm loadings and
                                                                                              packing heights required for
                                                                                              given capture rates (models
                                                                                              may not be fully reliable)

© 2021 Bechtel | 10             Level 3 - Bechtel Internal & Select External Distribution
Summary of Key Findings

                      Estimated baseline of CO2 capture: $114.50 / tCO2 (includes both annualized
                      capital and annual operations/maintenance)

                      Energy penalty on power plant: 67.3 MW (supplying steam and electricity
                      requirements)

                      Average forgone electricity revenue: $25 / MWh, contributing $13 / tCO2 captured

                      A pilot testing program is proposed to resolve design uncertainties

© 2021 Bechtel | 11                             Level 3 - Bechtel Internal & Select External Distribution
Closing Remarks

                  § Pilot plant implementation is crucial for full-scale carbon capture projects, to address the
                    process uncertainties arising from the lack of operational data available in the public
                    domain.
                  § Open technology PCC projects using a generic, non-proprietary solvent, facilitates
                    procurement at competitive prices.
                  § Open technology enables owners to work with a range of suppliers to modify/upgrade the
                    PCC plant hardware and solvent, as the industry progresses.

© 2021 Bechtel | 12                                      Level 3 - Bechtel Internal & Select External Distribution
Acknowledgements

              This work was completed as part of National Energy Technology Laboratory (NETL) research for the U.S.
              Department of Energy’s (DOE) Carbon Capture Program. The authors wish to acknowledge Naomi O’Neil, the
              NETL Project Manager for this FEED study for her counsel and support throughout the study.

              The authors would like to thank August Benz (Independent) and Jonathan Gibbins (University of Sheffield) for
              their technical contributions throughout the study; Kunlei Liu (University of Kentucky) for reviewing the process
              and providing technical comments; Des Dillion, Adam Berger, Abhoyjit Bhown, and Yang Du from the Electric
              Power Institute (EPRI), the sub awardee of this study, for their many technical contributions and for serving as
              the final report editor and publisher; and Nexant, the technical subcontractor to EPRI.

              We are also grateful to Siemen’s, the power island equipment supplier, for their assistance in steam turbine
              interface decision.

              Finally, and most notably, we thank Joe Lloyd and Darryl Nitschke of Panda Power for allowing the Sherman
              Power Plant to serve as the basis for this study.

© 2021 Bechtel | 13                                        Level 3 - Bechtel Internal & Select External Distribution
You can also read