Presentation to ARPA-E, January 14, 2022 Award No. DE-FE0031848/0000 Post-Combustion Capture
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Front-End Engineering Design Study for a Carbon Capture Plant Retrofit to a Natural Gas-Fired Turbine Combined Cycle Power Plant (2x2x1 Duct-Fired 758-MWe Facility with F Class Turbines) In Partnership with: Presentation to ARPA-E, January 14, 2022 US DOE/NETL Award No. DE-FE0031848/0000 EPRI Post-Combustion Capture Nexant
Project Scope and Objectives § FEED Study encompasses the engineering required for the design, construction, and operation of the carbon capture and compression unit, including modifications to the existing facility per the retrofit – Transportation of CO2 and ultimate use were not part of this study, but were factors in identifying the location § Open-access philosophy was adhered to for this project and all aspects of the capture unit design are non-proprietary § Project’s Objectives: ✓ Utilize a low-cost generic solvent ✓ Provide balances and process data details, open for public review ✓ Provide cost estimates and material quantities, open for public review ✓ Provide implementation schedule and operation economics (accounting for current operation regimes in Texas/ERCOT) ✓ Allow the study deliverables be available to the public © 2021 Bechtel | 2 Level 3 - Bechtel Internal & Select External Distribution
Sherman Energy Center, Sherman, Texas, USA Why Sherman Energy Center? § F-class gas turbines (state of the art technology) § Sufficient land available contiguous to the power plant § Proximity to oil fields, saline aquifers, and sedimentary basis, for recovered CO2 storage § Cooperative host that is a Bechtel customer © 2021 Bechtel | 3 Level 3 - Bechtel Internal & Select External Distribution
Project Background – Process & Operation § This FEED is based on a prior study led by Bechtel, for a similar plant in Kårstø, Norway (also publicly available) § Carbon capture process encompasses a conventional absorber-stripper configuration using a low-cost amine-based solvent – Using generic solvent facilitates procurement at competitive prices. There will be no wide-reaching restrictions on knowledge transfer to and from the project. R. R. Bottoms Patent, 1930 © 2021 Bechtel | 4 Level 3 - Bechtel Internal & Select External Distribution
Results: Layout DP (Integrated Layout) Carbon Capture Plant Power Plant © 2021 Bechtel | 5 Level 3 - Bechtel Internal & Select External Distribution
Results: Cost Estimation DP Capital cost of the five major portions of the PCC plant: – Flue Gas Conveyance and Conditioning: $102M – CO2 Absorption: $151M – Solvent Regeneration: $75.6M – CO2 Compression and Conditioning: $84.5M – Stack Modification: $31.1M Total: $444M Cost for PCC Areas as Percent of Contractor’s Cost © 2021 Bechtel | 6 Level 3 - Bechtel Internal & Select External Distribution
Results: Cost Estimation DP § Capital cost of the PCC plant broken down into the commodities and classes of costs used in the EPC estimating process − Material/Equipment: $116M − Piping: $17.8M − Instrumentation: $13.3M − Electrical Equipment: $17.8M − Field Indirect: $40M − Total Field Services: $22.2M − Engineering/Other Office Services: $44.5M − Labor: $48.9M − Sub-Contractor: $22.2M − Contingency: $35.6M − Fee, Risk, and Misc: $57.8M − Civil Works: $8.90M Total: $444M Costs as Percentage of Contractor’s Cost © 2021 Bechtel | 7 Level 3 - Bechtel Internal & Select External Distribution
Results: Cost Estimation DP Basis of Operating Cost © 2021 Bechtel | 8 Level 3 - Bechtel Internal & Select External Distribution
Results: Cost Estimation DP Cost Sensitivities and Uncertainty Levels Tornado Diagram © 2021 Bechtel | 9 Level 3 - Bechtel Internal & Select External Distribution
Pilot Plant Purpose: • Understand amine degradation in the atmosphere • Confirm efficacy of reclaimer • Analyze long-term solvent health/confirm degradation rates • Confirm loadings and packing heights required for given capture rates (models may not be fully reliable) © 2021 Bechtel | 10 Level 3 - Bechtel Internal & Select External Distribution
Summary of Key Findings Estimated baseline of CO2 capture: $114.50 / tCO2 (includes both annualized capital and annual operations/maintenance) Energy penalty on power plant: 67.3 MW (supplying steam and electricity requirements) Average forgone electricity revenue: $25 / MWh, contributing $13 / tCO2 captured A pilot testing program is proposed to resolve design uncertainties © 2021 Bechtel | 11 Level 3 - Bechtel Internal & Select External Distribution
Closing Remarks § Pilot plant implementation is crucial for full-scale carbon capture projects, to address the process uncertainties arising from the lack of operational data available in the public domain. § Open technology PCC projects using a generic, non-proprietary solvent, facilitates procurement at competitive prices. § Open technology enables owners to work with a range of suppliers to modify/upgrade the PCC plant hardware and solvent, as the industry progresses. © 2021 Bechtel | 12 Level 3 - Bechtel Internal & Select External Distribution
Acknowledgements This work was completed as part of National Energy Technology Laboratory (NETL) research for the U.S. Department of Energy’s (DOE) Carbon Capture Program. The authors wish to acknowledge Naomi O’Neil, the NETL Project Manager for this FEED study for her counsel and support throughout the study. The authors would like to thank August Benz (Independent) and Jonathan Gibbins (University of Sheffield) for their technical contributions throughout the study; Kunlei Liu (University of Kentucky) for reviewing the process and providing technical comments; Des Dillion, Adam Berger, Abhoyjit Bhown, and Yang Du from the Electric Power Institute (EPRI), the sub awardee of this study, for their many technical contributions and for serving as the final report editor and publisher; and Nexant, the technical subcontractor to EPRI. We are also grateful to Siemen’s, the power island equipment supplier, for their assistance in steam turbine interface decision. Finally, and most notably, we thank Joe Lloyd and Darryl Nitschke of Panda Power for allowing the Sherman Power Plant to serve as the basis for this study. © 2021 Bechtel | 13 Level 3 - Bechtel Internal & Select External Distribution
You can also read