N ew - California High Speed Rail ...

Page created by Brett Manning
 
CONTINUE READING
N ew - California High Speed Rail ...
C O N ST R U C T I O N         FEB
                                                                           2018

   ew ct
  N oje
  Pr
     o                     W OR K BEGINS I N C P 4
F I RS T C O NS TR UCTI ON
IN C P 4 BE GI N S AT
GA RCE S H IGHWAY
With the start of the New Year comes
new construction in the South Valley for
Construction Package 4 (CP 4). Though
utility relocation and clearing and grub-                     Garces Hwy
bing have been underway, the first con-
struction activity began recently with ge-
otechnical testing at Garces Highway in
Kern County. At right, a blue drill rig is
boring a shaft about 70 feet deep. Below
that, crews can be seen constructing the
rebar cage that will be lowered into the
shaft and covered with concrete. Crews
are testing the soil conditions for future
construction of a viaduct that will carry
high-speed trains over the Garces High-
way.

                                                                           BUILDHSR.COM
N ew - California High Speed Rail ...
FEB
                                                                      C O N ST R U C T I O N            update                  2018

GRA D E S E PA R AT I ON P R OJEC TS
                                                                                               Madera County
AVEN UE 7 |New               Project
Crews install rebar at one of the abutments for the alignment and crossing for
Avenue 7. The roadway is being realigned at the point where it will cross over the
high-speed rail line. Utility and irrigation relocation work have also begun in the
area, which is important for the eventual realignment of Road 33 and future dirt
embankment work for the overcrossing.

                                                                 AVENUE 12
                                                                 Construction of the abutments for the high-speed rail crossing progresses
                                                                 alongside Avenue 12 in Madera County. The overpass structure will carry
                                                                 traffic over the high-speed rail line and existing freight tracks. In January,
                                                                 rebar was installed for the western abutment wall and 615 cubic yards of
                                                                 concrete was poured. Next, forms will be removed and installed on the
                                                                 eastern abutment wall to pour the other side of the bridge.

                                                                                                                          BUILDHSR.COM
N ew - California High Speed Rail ...
FEB
                                                                      C O N ST R U C T I O N             update                  2018

AVEN UE 11
Abutment construction is beginning for the overcrossing at Avenue 11 in Madera
County. The embankment work is largely complete, foundations have been poured
for the abutments and crews have begun installing rebar for the abutment walls. The
work has closed Avenue 11 between Road 30 ½ and 33 ½ as crews construct a
single span overcrossing that will take traffic over the high-speed rail line.

AVEN UE 15          |New Project                                             ROAD 27
At Avenue 15 in Madera County, crews have closed the road and                Workers construct part of the overcrossing for Road 27 in Madera
removed the existing pavement in preparation for the construction            County, installing pier cap reinforcing steel in preparation for a
of another overcrossing. The contractor is now moving utility lines          concrete pour. The crossing will take traffic over freight and high-
out of the way to begin the structures and embankment work. The              speed rail lines. Utility work has also begun to relocate a power
crossing will take Avenue 15 traffic over high-speed rail lines and          line which impacts one of the piers of the bridge.
existing freight lines.

                                                                                                                           BUILDHSR.COM
N ew - California High Speed Rail ...
FEB
                                                                          C O N ST R U C T I O N               update                   2018

                                                                             SAN JOAQUIN RIVER VIDUCT |FRESNO
                                                                             Workers are making good progress installing the decking on the per-
                                                                             gola section of the San Joaquin River Viaduct. The viaduct will carry
                                                                             high-speed trains over the San Joaquin River and existing freight tracks,
                                                                             forming one of the largest structures on this first phase of high-speed
                                                                             rail construction. Closer to the river, support pier construction is nearly
                                                                             complete for the section of the viaduct that will carry trains over the
                                                                             Fresno/Madera County line, while pier caps are being formed and
                                                                             poured tying the piers together. The last of the pergola pre-cast girders
                                                                             were set recently which was a major highlight for the team.

TUL ARE STREET UNDERPASS
DOWNTOWN FRESNO
Work continues on an undercrossing for Tulare Street between G and H streets in
downtown Fresno. Crews are constructing the substructure walls for the crossing
that will take Tulare Street traffic under high-speed and existing freight rail lines. A
later phase of construction will build a new bridge for G Street traffic to cross over
Tulare as it goes below grade. A similar undercrossing and G Street bridge will be
constructed at Ventura Street later this spring.

                                                                                                                                  BUILDHSR.COM
N ew - California High Speed Rail ...
FEB
                                                                     C O N ST R U C T I O N              update                 2018

                                                                         CEDAR VIADUCT |SOUTH FRESNO
                                                                         Workers on the Cedar Viaduct tie rebar prior to an upcoming concrete
                                                                         deck pour. This will connect the two sections of the viaduct over North
                                                                         Avenue. Spans between bents are approximately 120’ each, and with
                                                                         the completion of the deck span over North Avenue, the viaduct will
                                                                         be a half mile long. Ultimately, the completed Cedar Viaduct will span
                                                                         about three-quarters of a mile. An irrigation canal pipe bypass is also
                                                                         being installed on the viaduct.

STATE ROUTE 99 REALIGNMENT
CENTRAL FRESNO
Crews work on the construction of curb, gutter and sidewalk on the Clinton Avenue
bridge over State Route 99. The new bridge reopened to traffic late last year, and
the northbound exit ramp reopened shortly afterward. The other three ramps are
still being constructed and are scheduled to be open to traffic by spring. The next
phase of work will now include demolition and reconstruction of the Ashlan Avenue
bridge.

                                                                                                                           BUILDHSR.COM
N ew - California High Speed Rail ...
FEB
                                                                      C O N ST R U C T I O N              update                 2018

FRESNO TRENCH & SR 180 PASSAGEWAY
FRESNO
At the Fresno Trench, crews are about to break through to the south side of State
Route 180 (SR 180). The trench will run under the highway, two rail spurs and the
Dry Creek Canal. With steel beams in place to provide additional support for the
trench walls under SR 180, excavation will continue until the trench is about 40
feet below ground level. On Dry Creek Canal, crews have demolished a section of
the old canal and graded the site. The canal improvements are included in Fresno
Trench construction, as the canal will eventually cross over the trench. Crews are
working quickly to form the invert (bottom) and walls of the box culvert. Canal work
has a limited work period due to the irrigation season.

AMERICAN AVENUE GR ADE SEPAR ATION                                       |FRESNO COUNTY
Columns and abutments have been poured for the American Avenue overcrossing at the end of Construction Package 1, south of Fresno and
crews have begun constructing the bent cap falsework for the section of the crossing that will carry traffic over the existing freight tracks and
high-speed tracks.

                                                                                                                            BUILDHSR.COM
N ew - California High Speed Rail ...
FEB
                                                        C O N ST R U C T I O N         update                 2018

 L ATEST VID EO S |YOUTUBE.COM/CAHIGHSPEEDRAIL

           W OR KER P R OFI LES                                     BA RT’S FLE E T OF T H E F U T U R E

    CONSTRUCTION                             JOB NUMBERS AS OF DECEMBER 31
   PACKAGE 1 - 4 MAP                                CONSTRUCTION                              CP 1:            INCREASED
                                                                                                                           1215
                                                   LABOR WORKERS

                                                    1648
MADERA         CP 1                                                                        CP 2-3:             INCREASED
                                                                                                                           305
STATION
                                                                                             CP 4:                         120
                                            INCREASED
                                                                                                               INCREASED

     FRESNO
     STATION
                                                         SMALL BUSINESS NUMBERS
                                                            AS OF OCTOBER 31
   KINGS/TULARE
                                                                                                 SMALL
       REGIONAL                                         PAID TO SMALL
        STATION        CP 2-3                            BUSINESSES
                                                                                               BUSINESSES
                                                                                                WORKING
                                                        CP 1:   INCREASED
                                                                            $143.5 M                       120
                                CP 4             CP 2-3:        INCREASED
                                                                               $13 M           INCREASED
                                                                                                            86
                                                        CP 4:   INCREASED
                                                                              $4.3 M           INCREASED
                                                                                                            26

      tact            TONI TINOCO                                       DAN GALVIN

   con                CALIFORNIA HIGH-SPEED RAIL
                      (559) 274-8975 | TONI.TINOCO@HSR.CA.GOV
                                                                        CALIFORNIA HIGH-SPEED RAIL
                                                                        (559) 490-6863 | DANIEL.GALVIN@HSR.CA.GOV

                                                                                                           BUILDHSR.COM
N ew - California High Speed Rail ... N ew - California High Speed Rail ... N ew - California High Speed Rail ...
You can also read