Social Monitoring Report

Semestral Report
Project Number: 45508-002
January 2021

PRC: Xinjiang Integrated Urban Development Project

Prepared by Xinjiang Linshuishe Engineering Technical Consulting Company for the Asian
Development Bank.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily
represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or
reference to a particular territory or geographic area in this document, the Asian Development Bank does
not intend to make any judgments as to the legal or other status of any territory or area.
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

ADB-Financed
    ——Xinjiang Integrated and Urban
    Development Project

Xinjiang Integrated and Urban Development Project-

                      Kuitun Subproject

   External Monitoring for Resettlement Plan (RP)

       External Monitoring Report for the Second Half of 2020

                           (No. 10)

  Xinjiang Linshuishe Engineering Technical Consulting Company

                         Xinjiang · Urumqi

                          January 2021

                                 1
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

Monitor Institution:    Xinjiang Linshuishe Engineering Technical
                        Consulting Company

Director:               Zhou Shengbin

Evaluator:              Yan Lei   Jiangaguli    Zhang Jin

Report Writing Staff:   Yan Lei Jiangaguli Yang Fangfang Yang Shuying

Address:                Hebei East Road No.430, Shanghai Mansi on
                        Comprehensive-A Ro om 1206, Urumqi City
                        Xinjiang Uygur Autonomous Region

Postcode:               830011

Phone:                  0086- 0991- 3638030

Fax:                    0086- 0991- 3638030

Email:                  xjlss@xjlss.com
                        xjlssec@163.com

                            2
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

                                                       CONTENT
1.   Overview ..................................................................................................................... 15
     1.1 Introduction ........................................................................................................... 15
     1.2 Project Content ..................................................................................................... 15
     1.3Involuntary Resettlement....................................................................................... 17
          1.3.1. The Scope of Monitoring and Evaluation .................................................. 18
          1.3.2 The Purpose of Monitoring and Evaluation................................................ 19
          1.3.3. The Work Steps of Monitoring and Evaluation ......................................... 19
          1.3.4. The Content of the Monitoring and Evaluation ......................................... 19
          1.3.5. The Method of Monitoring and Evaluation ................................................ 20
          1.3.6. Tasks and Schedules of Annual Monitoring and Evaluation ..................... 22
2.   Project Progress ......................................................................................................... 24
     2.1 Construction Progress .......................................................................................... 24
     2.2 Project Resettlement Progress ............................................................................ 34
3.   Project Impact............................................................................................................. 36
     3.1 Land Acquisition ................................................................................................... 36
     3.2 Residential House Demolition .............................................................................. 37
     3.3 Demolition Shops along the Street....................................................................... 39
     3.4 Demolition of Enterprise ....................................................................................... 40
4.   Project Compensation Standards and Funds ............................................................ 42
     4.1. Compensation Rates for State-owned Land ....................................................... 42
     4.2 Compensation Rate for State-owned Farmland .................................................. 42
     4.3 Compensation Rate for State-owned Woodland.................................................. 44
     4.4 Compensation Standard of Housing Demolition .................................................. 45
          4.4.1 Compensation Rates for Residential Houses ............................................ 45
          4.4.2 Compensation Rates for Commercial Stores ............................................ 47
          4.4.3 Compensation Rates for Enterprises ......................................................... 48
5.   Survey on the Level of Production and Living of Affected People ............................. 50
     5.1 Monitoring Survey................................................................................................. 50
          5.1.1 Survey Description ..................................................................................... 50
          5.1.2 Survey of Population Statistics .................................................................. 50
          5.1.3 Age ............................................................................................................. 51
          5.1.4 Cultural level .............................................................................................. 53
          5.1.5 Occupation ................................................................................................. 55
          5.1.6 Family Income ............................................................................................ 56
          5.1.7 Household Expenses ................................................................................. 57
     5.2 Interview Survey ................................................................................................... 59
          5.2.1 Interview Content ....................................................................................... 59
          5.2.2 Interview Evaluation ................................................................................... 61
6.   Resettlement and Restoration .................................................................................... 63
                                                                 2
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

     6.1 Resettlement of House Demolition....................................................................... 63
7.   Public Participation and Grievance Redress.............................................................. 66
     7.1 Public Participation ............................................................................................... 66
          7.1.1 Public Participation Organized by the Project Units .................................. 66
          7.1.2 Public Participation Organized by the External Monitoring Units .............. 69
     7.2 Grievance and Redress........................................................................................ 72
     7.3 Appeal Contact Information .................................................................................. 73
8.   Organizational Structure............................................................................................. 75
     8.1 Resettlement Action Agencies.............................................................................. 75
     8.2 Organization Function .......................................................................................... 76
     8.3 Organizational Qualifications and Staff ................................................................ 77
     8.4 Staff and Facility Allocation .................................................................................. 79
          8.4.1 Staff ............................................................................................................ 79
          8.4.2 Office Facilities ........................................................................................... 79
     8.5 Organizational Capability Assessment................................................................. 80
9.   Conclusions and Recommendations.......................................................................... 82
     9.1 Conclusions .......................................................................................................... 82
     9.2 Suggestion............................................................................................................ 85
     Appendix 1: Dongchong Ditch Status of Kuitun City (September 2020) ................... 87
     Appendix 2: Xichong Ditch Status in Kuitun City (September 2020) ......................... 88
     Appendix 3: Nangan Ditch Status in Kuitun City(September 2020) ..................... 89
     Appendix 4: Demolished Households’ Compensation Agreements in Dongchong ditch
     of Kuitun City .............................................................................................................. 90
     Appendix 5: Resettlement Community in Kuitun City ................................................ 92
     Appendix 6: Windbreak on Both Sides of River Channel .......................................... 93
     Appendix 7: Hired Worker Lists of Subproject Construction Site in Kuitun ............... 95
     Appendix 8: Household Interview (September 2020) ................................................ 96

                                                                3
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

                                           TABLE CONTENT
Table 1-1: Overview of the Components........................................................................... 17
Table 1-3: External Monitoring Task Arrangement........................................................... 22
Table 2-1: Each Subproject Implementation Progress ................................................... 27
Table 3-1: Statistics of State-Owned Land ....................................................................... 36
Table 3-2: The Completed Residential Houses in Xichong ditch .................................. 38
Table 3-3: The Completed Residential Houses in Dongchong Ditch............................ 38
Table 3-4: Completed Demolished Shops along the Street ........................................... 40
Table 3-5: The Completed Demolished Enterprise Demolition...................................... 41
Table 4-1: Land Prices of Kuitun City ................................................................................ 42
Table 4-2: Compensation Rate for State-owned Cultivated Land ................................. 43
Table 4-3: Statistics of State-owned Land Acquired........................................................ 44
Table 4-4: Compensation Rate for State-owned Woodland........................................... 44
Table 4-5: Forest Vegetation Restoration Fees ............................................................... 44
Table 4-6: Compensation Rates for Residential Houses Demolished for Xichong ditch
    Subproject...................................................................................................................... 45
Table 4-7: Compensation Rates for Residential Houses Demolished for Dongchong
    Ditch Subproject ........................................................................................................... 46
Table 4-8: Compensation Rates for Commercial Stores of Xichong Ditch. ................. 47
Table 4-9: Compensation Rates for Affected Enterprises in Kuitun City ...................... 48
Table 5-1: Sample Population in Community Surveyed ................................................. 50
Table 5-2: Base Survey of Family Population .................................................................. 51
Table 5-3: Age Structure ...................................................................................................... 52
Table 5-4: Cultural Level...................................................................................................... 54
Table 5-5: Occupational Classification .............................................................................. 55
Table 5-6: Sources of Household Income......................................................................... 56
Table 5-7: Survey of Household Expenditure Based on the Survey............................. 58
Table 6-1 Property Exchange Information ........................................................................ 64
Table 7-1: Public Participation Activities Organized by Project Units ........................... 68
Table 7-2: Public Participation Activities Organized by External Monitoring Group ... 70
Table 7-3: Agency and Staff for Accepting Grievance and Appeals.............................. 73
Table 8-1:Kuitun ADB Project Personnel Contact List ................................................. 78
Table 8-2: Equipment of the Resettlement Organization................................................ 80

                                                               4
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

                                         FIGURE CONTENT
Figure 5-1: Marital Status .................................................................................................... 51
Figure 5-2: Age Structure .................................................................................................... 53
Figure 5-3: Cultural Level .................................................................................................... 54
Figure 5-4: Occupational Distribution ................................................................................ 56
Picture 6-1: Return Visit for APs............................................ Error! Bookmark not defined.
Picture 7-1: Public Participation ......................................................................................... 67
Picture 7-2 Internal Training Meeting of Kuitun PMO ..................................................... 67
Figure 7-1: Grievance Redress Flowchart ........................................................................ 73
Figure 8-1: Resettlement Organizational Chart ............................................................... 75

                                                            5
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

     PART I The Clarification on Resettlement for Xinjiang
 Integrated and Urban Development Project Mission MOU on

                            November 25-28, 2019.

     The Statement in MOU:8 of the 11 civil engineering contracts for the Kuitun
project (KT-C01, 02, 03, 04, 05, 06, 07 and 08) involves land acquisition and resettlement

impacts. The updated Resettlement Plan for Dongchong ditch, Xichong ditch and Nangan

channel sections (C01, 02 and 03) under the jurisdiction of Kuitun City was approved by

the ADB and posted on the ADB website in November 2016. As of November 30, 2019, 60

residential houses and 47 shops and enterprises affected by the Dongchong ditch and

Xichong ditch contracts have been relocated. Consultations with the last household and

one shop owner have not been completed. After field investigation, the PMO and the

external monitoring unit found that the last household and shop are located in the area

along the bank of Dongchong ditch planted with shelterbelts, which will not affect the

construction of Dongchong ditch. If the affected households and shops do not agree with

the compensation and resettlement measures, the Kuitun PMO will optimize the design to

remove them from the resettlement impact of the project. The Mission requested Kuitun

PMO to report to ADB on the progress of the resettlement of the last household and one

shop.

    During this external monitoring, the staff from external monitoring unit asks Kuitun

PMO to understand relevant resettlement and field investigation and found that Kuitun

PMO had shift out the last household and 1 shop involved in Dongchong ditch from the

project resettlement impact through the design optimization. At present, the relevant civil

engineering works of Dongchong ditch and the shelter forest project on the bank have been

basically completed, and the affected people of the above two households are no longer

within the affected scope of the project. See schematic diagram below:

                                            6
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

The Kuitun PMO has adjusted the design scheme, and the affected residential
           houses are no longer in the original demolition scope

                                     7
Social Monitoring Report - Asian ...
External Monitoring for Resettlement Plan

   The Kuitun PMO has adjusted the design scheme, and the last one shop is no
                longer involved in the original demolition scope

    The following conclusions are drawn from this external monitoring:

    (1) it is indicated that 156HHs of residents’ houses would be demolished based on

the original RP, including 61 households in Kuitun city (including 32 households in Xichong

ditch and 29 households in Dongchong ditch). Tianbei New District involves 95 households.

    Finally, according to the actual situation of the project and the optimization of the

project, the number of resident housing demolition in Kuitun city reduced from 61 to 60

(including 32 households in Xichong ditch and 28 households in Dongchong ditch), as

shown in table 1.

    (2) 58 small-scale shops would be demolished based on the original RP, including

48 shops in Kuitun city (46 in Xichong ditch section and 2 in Dongchong ditch section), and

10 shops in Tianbei New District.

    Finally, according to the actual situation of the project and the project optimization, the

number of shops along the street in Kuitun city was reduced from 48 to 47 (including 46 in

Xichong ditch and 1 in Dongchong ditch), as shown in table 2.

    (3) According to the final design scheme, DMS and third-party evaluation, it is

confirmed that the project involves the demolition of three enterprises, including two

                                              8
External Monitoring for Resettlement Plan

           enterprises in Kuitun city, one in Tianbei New District, and two enterprises in Kuitun city

           have completed the demolition work and have been properly resettled.

                                      (1)Impact of Residential House Demolition
 Impact of Planned House Demolition (Original RP)                                Impact of Actual House Demolition
       Area              Subproject       Affected HHs          Subproject          Affected HHs   Completed Demolition Area (m2)
                       Dongchong ditch         29         Dongchong ditch                28                     5312.09
      Kuitun
                        Xichong ditch          32              Xichong ditch             32                     9713.97
Tianbei New District                           95                                        95                        0
     Subtotal                                  156                                      155                     15026.06

                         (2)Impact of Demolition of Small-scale Shops along the Street
    Impact of Planned Demolition (Original RP)                                      Impact of Actual Demolition
       Area              Subproject       Affected HHs          Subproject          Affected HHs   Completed Demolition Area (m2)
                       Dongchong ditch          2         Dongchong ditch                 1                      149.11
      Kuitun
                        Xichong ditch          46              Xichong ditch             46                     14032.05
Tianbei New District                           10                                         0                        0
     Subtotal                                  58                                        47                     14181.16

                                         (3)Impact of Demolition of Enterprises
  Impact of Planned Demolition (Original RP)                                     Impact of Actual Demolition
        Area           Subproject     Affected HHs   Subproject      Affected HHs             Completed Demolition Area (m2)
       Kuitun              ---             2             ---                 2                           2042.42
Tianbei New District       ---             1             ---                 0                              0
      Subtotal             ---             3             ---                 2                           2042.42

                 Conclusion:above mentioned, except for the demolition in Tianbei New District, the

           rest of the house demolition in Kuitun had been finished already, the affected people had

           been well resettled. As of this monitoring, there is no legacy or outstanding issues.

                                                                 9
External Monitoring for Resettlement Plan

PART II           Resettlement Impact Clarification for the Location

            Change of Sediment Tank in Dongchong Ditch

    Background: The original design location of sediment tank (including sedimentation

area and clear water area) of Dongchong Ditch river regulation project is 195 meters away

from Beijing East Road in the north, 218 meters away from Kuerle East Road in the south,

20 meters away from the regulated Dongchong Ditch River in the East and East Park to

be built in the West.

    During the detailed design, PMO found that the north side of the original design

location of the sediment tank will involve the demolition of 2 households (6 people) in

Dongtingyuan community, Beijing East Road Street, with an area of about 160m2 and a

courtyard wall of about 50m. Therefore, in order to reduce the impact on the demolition

and ensure the smooth implementation of the project, the overall construction position of

the sediment tank was shifted to the south 130 meters without changing its use function.

Meanwhile, the layout and total area of the sediment tank were optimized, and the water

storage area was adjusted from 12100 square meters to 9326 square meters. After the

relocation, the new location is about 120 meters away from Dongtingyuan community

residence of Beijing East Road Street in the north, 48 meters away from Kuerle East Road

in the south, 20 meters away from the already treated Dongchong gully in the East, and

close to the East Park to be built in the west, which does not involve house demolition. As

the construction land is all state-owned unused land in the city, it can be directly allocated

as the construction land of this subproject, so the project does not involve LA and HD.

                                             10
External Monitoring for Resettlement Plan

Location Map of Sediment Tank

             11
External Monitoring for Resettlement Plan

12
External Monitoring for Resettlement Plan

               Current Situation of Sediment Tank in January 2021

    Summary: After the project optimization design, the project office has effectively

avoided the impact of the demolition of 2 households with 6 people. Through field

investigation, the external supervision unit found that the completed sediment tank was far

away from residential areas and had no other impact on Residents' production and life.

                                            13
External Monitoring for Resettlement Plan

    PART III          Clarification on Scope Change (Newly added

                   Components) for Kuitun Subproject

     On January 19, 2021, both Xinjiang and Kuitun PMO received an e-mail notice from

the ADB that “Considering the loan has been extended by two years with the total loan

period about 8 years already, ADB is not in favor of additional loan extension, and therefore

nor the proposed scope change of Kuitun subproject which will take about 1.5 years to

complete.”

     Based on the notice from ADB, it is confirmed that the closing date of the subproject

will be June 30, 2021, and the scope change project components are not agreed by ADB.

Therefore, the external monitoring has deleted the contents of the proposed components

in this report.

                                             14
External Monitoring for Resettlement Plan

                                     1. Overview
1.1 Introduction
     In order to further improve Kuitun City’s urban infrastructure, ecological and living

environment, and image, improve flood control capacity, and adapt to economic and social

development, Kuitun City Government (KCG - executing agency, EA) plans to implement

the Subproject using an ADB loan. The Subproject consists of five components: (1) river

channel management; (2) construction of flood drainage channel facilities; (3) shelter forest

cultivation; (4) waste disposal and sewage interception; (5) non-profit water management.

The Subproject is a subproject of the ADB-financed Xinjiang Integrated Urban

Development Project, and the implementing agency (IA) of the Subproject is Kuitun City

Construction Bureau (KCCB).

1.2 Project Content
      (1) River channel management:
     3 flood drainage channels in the urban area will be improved, with a total length of

6996.20 m (including Dongchong ditch KT-C01, 0+000-0+660, Dongyizhi channel 0+000-

0+999.2, Xichong ditch KT-C02, 0+000-1+605, Nangan channel KT-C03, 0+000-3+372.

Flood control and emergency response roads with a total length of 39.43km will be

constructed along the channels.

      (2) Shelter forest cultivation:
     Shelter forests with a total area of 83.2 ha along the river, cultivation of 200,400 trees,

with drip irrigation using treated water. The land for planting the trees will be within the red

line of the flood channel component. This will not only improve urban landscaping area and

protect flood banks from winds, but also improve the city’s climatic system and people’s

quality of life.

      (3) Construction of flood drainage channel facilities:
     Construction of 14 ladders 1 steep slope and two grit chambers; construction and

reconstruction of 5 aqueducts each; construction of 26 bridges, maintenance of 2 bridges,

                                               15
External Monitoring for Resettlement Plan

6 culverts, and 40 hydraulic structures with 96 structures in total will be within existing

ROWs or within the red line of the flood channel component.

     (4) Urban      Water     Supply      network       improvement          and     leakage
monitoring:
    The preliminary design on Non-profit water management and improvement of

community networks KT-012 was approved on June 16, 2014, the water supply pipelines

explosion occurred for many times on Beijing Road and Tacheng Street, the normal life of

local residents and industries was affected badly, in order to address this kind of situation,

the construction of water supply networks and environment protection equipment on

Beijing Road, Tacheng Street as well as Lvboli district has been completed using the local

fiscal funds. Therefor the contact package of KT-C12 need to be adjusted, the adjusted

construction contents as follows:

    Reconstruct 6.27 km water supply pipeline; and set up the GPRS urban water supply

network monitoring system; purchase water quality safety testing equipment; equip with

water supply network leak detectors.

    1. Shawan Street (Yili Road - Beijing Road) intends to transform pipeline 1019 meters

long, diameter 300mm.

    2. Kuerle Road (Tuanjienan Street – Hefeng Street) intends to transform the line 3141

meters long, diameter 400mm.

    3. Tuanjiedong Street (Urumqi Road - The gate of Qinmingli community) intends to

transform the line 380 meters long, diameter 300mm.

    4. Beijing West Road (Tuoli Street - Hefeng Street) intends to transform the line 936

meters long, diameter of 400mm.

    5. Beijng East Road (Manasi Street –Shawan Street) intends to transform the line

791meters long, diameter of 400mm.

     (5) Waste disposal:
    7 public toilets will be constructed in four residential communities – Fengdeng Garden,

Wenying Garden, Tunfu Garden and Hulanbrak Community, including two in Fengdeng

                                             16
External Monitoring for Resettlement Plan

Garden, two in Wenying Garden, one in Tunfu Garden, and two in Hulanbrak Community.

95 fixed container waste bins for domestic waste will be set up, including 18 in Fengdeng

Garden, 55 in Wenying Garden, 6 in Tunfu Garden and 16 in Hulanbrak Community; 400

waste bins will be set up along flood control roads.
                             Table 1-1: Overview of the Components
No.       Component                                         Brief Description

                             3 flood drainage channels in the urban area will be improved, with a total
                             length of 6996.20 m (including Dongchong ditch KT-C01, 0+000-0+660,
         River channel       Dongyizhi channel 0+000-0+999.2, Xichong ditch KT-C02, 0+000-1+605,
 1
         management          Nangan channel KT-C03, 0+000-3+372. Flood control and emergency
                             response roads with a total length of 39.43km will be constructed along the
                             channels.

                             Construction of shelter forests with a total area of 83.2 ha along the flood
         Shelter forest
 2                           control channel 10-20m, cultivation of 200,400 trees, irrigation by dripping and
           cultivation
                             spraying

        Construction of      14 ladders 1 steep slope and two grit chambers; construction and
 3       flood drainage      reconstruction of 5 aqueducts each; construction of 26 bridges, maintenance
        channel facilities   of 2 bridges, 6 culverts, and 40 hydraulic structures with 96 structures in total.

                             Reconstruct 6.27 km water supply pipeline; and set up the GPRS urban water
                             supply network monitoring system; purchase water quality safety testing
                             equipment; equip with water supply network leak detectors.
                             (1). Shawan Street (Yili Road - Beijing Road) intends to transform pipeline
                             1019 meters long, diameter 300mm.
      Urban water supply
                             (2). Korla Road (Tuanjienan Street – Hefeng Street) intends to transform the
            network
 4                           line 3141 meters long, diameter 400mm.
       improvement and
                             (3). Tuanjiedong Street (Urumqi Road - Yili Road) intends to transform the line
       leakage monitoring
                             380 meters long, diameter 300mm.
                             (4). Beijing West Road (Torrey Street - Hefeng Street) intends to transform the
                             line 936 meters long, diameter of 400mm.
                             (5) Beijng East Road (Manas Street –Shawan Street) intends to transform the
                             line 791meters long, diameter of 400mm.

                             Construction of 7 public toilets, setup of 95 fixed container waste bins for
 5      Waste disposal
                             domestic waste and 400 waste bins along flood control roads

1.3Involuntary Resettlement
      According to ADB’s policies, Kuitun PMO will hire qualified and independent agency

experienced in ADB-financed projects as the external M&E agency. The external M&E staff

                                                      17
External Monitoring for Resettlement Plan

should:

    (1) Have participated in similar tasks, have rich experience in socioeconomic survey,

and understand ADB’s policy on involuntary resettlement, and the state and local

regulations and policies on resettlement;

    (2) Be able to conduct socioeconomic survey independently, have good

communication skills; and

    (3) Include a certain percentage of females.

    The external M&E agency will conduct follow-up M&E of resettlement activities

periodically, monitor resettlement progress, quality and funding, and give advice. It shall

also conduct follow-up monitoring of the APs’ production level and living standard and

submit M&E reports to Kuitun ADB PMO and ADB.

    Independent external monitoring for involuntary resettlement is undertaken by Xinjiang

Linshuishe Engineering Technical Consulting Company.

1.3.1. The Scope of Monitoring and Evaluation
    This monitoring is the annual monitoring report for the second half of 2020, which is

mainly fromAugust 2020 to January 2021 for the project progress and content, as well as

the resettlement situation and livelihood recovery of the affected people.

    In addition, the project of Kuitun city including 3 ditches there are Xichong ditch,

Dongchong ditch, and Nangan ditch; among which, the construction of Nangan ditch will

not involve the LA and HD, and the construction of Xichong ditch and Dongchong ditch are

involved in HD. The monitoring will pay attention to the construction progress, LA and

resettlement progress of Xichong ditch and Dongchong ditch.

    The monitoring found that, because the LA, HD and resettlement of Tianbei New

District has difficulties. After discussion and decision of Xinjiang PMO, Kuitun municipal

government and inspection team, Kuitun city government flood drainage improvement

project financed by domestic funds (5 contract packages including KT – C04, C05, C06,

C07 and C08).

                                            18
External Monitoring for Resettlement Plan

1.3.2 The Purpose of Monitoring and Evaluation
    The survey of the monitoring, aimed at collecting project content, project impact,

resettlement implementation agency, internal monitoring mechanism, social and economic

characteristics of the affected residents and other materials and data to provide a basis for

comparison of post-monitoring and evaluation.

1.3.3. The Work Steps of Monitoring and Evaluation
    ♦ Preparation of resettlement monitoring and evaluation framework

    ♦ The design of the sampling plan

    ♦ Baseline survey

    ♦ Establishment of monitoring and evaluation information system

    ♦ Understand the schedule of land acquisition, the demolition and resettlement.

    ♦ Grasp the land acquisition, demolition and resettlement of converting and variation,

♦ Compensation standard and compensation funds allocated and changes the situation

    ♦ Site surveys, interviews

    ♦ Collating information and establishing a Database

    ♦ Comparative analysis and assessment

    ♦ The preparation of monitoring and evaluation reports

1.3.4. The Content of the Monitoring and Evaluation
    According to the specific implementation schedule of the project, the External

independent monitoring and evaluation mechanism has monitored the resettlement activity.

Monitoring and evaluation institutions will conduct a post-assessment when the entire

project ended to track the land acquisition and resettlement, incomes and recovery of the

affected people.

    According to the resettlement plan, this project mainly affects residents for land

expropriation, housing demolition, temporary occupation of land and the parts of the

ground appendages of compensation. Therefore, the project monitoring contents are

mainly the following several aspects.

    ♦ The schedule of the project

                                             19
External Monitoring for Resettlement Plan

    ♦ Land of progress, quantity, compensation standards, the use of funds allocated and

compensation funds

    ♦ Housing demolition quantity, compensation standards, the use of funds allocated

and compensation funds

    ♦ The number of temporary occupations of land and compensation standard,

appropriated funds and land restoration

    ♦ The recovery of vulnerable groups

    ♦ Resettles revenue expenditure sampling analysis

    ♦ Resettlement on land requisition compensation and resettlement opinions and

suggestions

    ♦ The organization and its capacity building

    ♦ Internal supervision of immigration

    ♦ Public participation methods and effect

    ♦ Complaints and complaints

1.3.5. The Method of Monitoring and Evaluation
    FromJanuary 12 to 13, 2021, with assistant of Kuitun PMO, project-related units and

communities and the district, town, and communities, an external monitoring team from

Xinjiang Linshuishe engineering technical consulting company, conducted field

investigation for monitoring and evaluation on LA and HD and meanwhile interviewed the

relevant departments, to understand the progress of the project implementation, land

acquisition and resettlement and the actual change and so on. According to the

arrangements for monitoring task, the following methods were applied in monitoring and

evaluation:

    Agency interview: interview immigration implementing agencies at all levels of

project owner and, through the field visit resettlement departments at different levels,

understand the comprehensive information on the implementation of resettlement, grasp

the main migration activities during the reporting period and its progress, the main

problems of implementation and its processing and immigration agency.

                                            20
External Monitoring for Resettlement Plan

    Symposium: external monitoring and evaluation personnel in the affected population

is concentrated community, held the immigration representative to attend the symposium,

collect the following information: the compensation funds allocated and use, production

and employment of settlement status of the affected population, community, the change of

the production and living environment, information disclosure, public participation and

consultation, complaints complaint and its solution, the affected population of resettlement

work of opinions and Suggestions, etc.

    Household Interview: external monitoring and evaluation personnel go deep into the

affected in immigrant families, face-to-face interview with them, understand the situation of

the implementation of the immigrants. In-home interviews mainly to understand the

affected social and economic condition with a population of individuals, families,

immigration policy implementation, all kinds of loss compensation standard and the cash

situation and situation of production and living place, information release and transfer,

public participation, vulnerable groups protection measures, complaints and complaints

and its condition.

    Literature Research: on resettlement activities related to land expropriation of

demolition and resettlement file, protocols, statistical reports, such as special investigation

information system and targeted collection, and verify.

    Typical Case Study: in view of the problems need to study, through in-depth has a

typical representative of the affected areas, the typical affected objects (such as,

immigration, women, head of the household, director of the office for a typical minority and

disadvantaged groups, etc.) to investigate interview seized first-hand information, analysis

and study, puts forward the ways to solve the problem.

    Field Observation: through the different levels of immigration way learn resettlement

measures such as the introduction of implementing agencies, progress and effect, and

found that the implementation of existing or potential problems.

    Monitoring Survey: in order to follow the affected households in the project before

and after the change of production and living level, the external monitoring team for the

                                              21
External Monitoring for Resettlement Plan

monitoring of the affected households survey.

1.3.6. Tasks and Schedules of Annual Monitoring and Evaluation
       According to the Asian Development Bank security policy (SPS, 2009), as well as

Kuitun city comprehensive development and environmental improvement project

immigration external monitoring program (TOR) requirements, Kuitun city project office

commissioned by our company of project immigrant’s resettlement external monitoring and

assessment.

       Land expropriation and housing removal and resettlement of the progress of the

project, capital, management, analysis comparison is affected by changes in the land

acquisition and relocation of production and living standard of resettlement and recovery,

on the project land acquisition and resettlement work tracking assessment and regularly to

the Asian Development Bank, Kuitun city project office and the relevant competent

departments provide reports, information and advice and reference for the decision-making

departments. In order to make the Asian Development Bank and the project unit in charge

of the work in progress of resettlement of the project land acquisition and resettlement in

the, the quality and effect of a full understanding, pointed out the problems, and puts

forward suggestions for improvement.

       The external monitoring of the main tasks and time arrangements as detailed in table

1-3.
                      Table 1-2: External Monitoring Task Arrangement
               Time                        Schedule                           Contents
                                                                   To know about the complaint
                                                                   situation. The current production
                                                                   and living conditions of the
                                                                   people affected by the land
                                    To people affected by the
                                                                   acquisition. Make the basal
                                 project, conducting a survey of
         January 12, 2020                                          investigation    for    affected
                                 into the home, and carrying out
                                                                   residents; to collect the first
                                          a discussion.
                                                                   hand of the basis data, in order
                                                                   to facilitate the late monitoring
                                                                   data for comparative analysis.
                                                                   Return visits to APs. Conduct

                                               22
External Monitoring for Resettlement Plan

                                                     field investigation learn about
                                                     the   project   progress    and
                                                     implementation of the project.
                                                     Field observation to understand
                                                     the current project progress and
                                                     construction status.
                                                     To    verify    the     relevant
                                                     compensation funds for the
                    Complete and improve the
                                                     resettlement.
                   materials, visit the demolition
                                                     docking and     discussing the
                     and relocation office, the
January 13, 2020                                     problems existing in the project
                     project office, Kuitun city
                                                     construction and solutions with
                   housing and urban and Rural
                                                     PMO       and      summarizing
                       Construction Bureau
                                                     problems found in the current
                                                     monitoring.

                                 23
External Monitoring for Resettlement Plan

                             2. Project Progress
2.1 Construction Progress
    The sub-project of the ADB loan Kuitun Xinjiang urban comprehensive development

projects including flood control works and non-profit water management two parts, the main

construction content and scale: (1) River channel management: Improve of 3 flood

drainage channels in the urban area, with a total length of 6996.20m and construction of

the flood control and emergency road of 39.43 km; construction of flood control 96 hydraulic

structures; garbage collection and sewage intercepting facilities surrounding the spillway,

including seven public toilets, 95 fixed garbage collection facilities, 400 classification

recycling bin and pickup vehicles. (2) Shelter forest cultivation: Construction     of   shelter

forests with a total area of 83.2 ha, cultivation of 200,400 trees. (3) Non-profit water

management part. Reconstruction for 6.35 km pipeline and setup GPRS monitoring system,

urban water supply pipe network for water quality security monitoring equipment, equipped

with water supply pipeline leak detection equipment, etc.

    The total investment of the project was 766.4 million yuan ($766.4 million, the ADB

loan, 444.5 million yuan, the exchange rate 1:6. 35; local counterpart funds 321.9 million

yuan). Among them: Direct engineering fee: 450.82 million yuan; Other engineering

construction fee: RMB 242.1 million, including the land requisition compensation and

resettlement fee for 195.43 million yuan and other fees 46.67 million yuan; Basic reserve

funds 52.44 million yuan; loan interest during constructing period is 21.04 million yuan.

    Up to this monitoring, the progress of Kuitun project as follows:

    (I) Dongchong ditch + Yizhi channel (Kuitun city section) (KT-C01)

    The contract amount is RMB 13.18 million with a construction period of 488 calendar

days. The contract starts on June 16, 2017 and plans to complete the construction on

November 16, 2018. At present, has the completed investment of 10.91 million-yuan,

accounting for about 82% of the value of progress aspects, including Dongchong ditch D0

+ 000 - D0 + 660 section of the completed 100% of the work amount, Dongchong ditch

                                             24
External Monitoring for Resettlement Plan

sediment basin completed 100% of the work amount. Dongyizhi ditch completed 100% of

the work amount; 40% of flood control and emergency roads were completed.

     (II) Xichong ditch (0+000~1+605 including sand basin) management project

(KT-C02)

     The contract sum is 16.36 million yuan, with a construction period of 488 days. The

contract commences on August 22, 2016 and plans to complete the construction on

December 22, 2017. At present, a total of 16.36 million yuan for investment has been

completed, accounting for 100% of the contract amount. In terms of progress, 100% of

Xichong ditch (K0+000-K1+605) flood control channel has been completed; 100% of the

bridge project (K1+592.20 1-10m small bridge) has been completed, reinforced concrete

hollow slab bridge and 99% of bridge engineering (K0+671.00 2-10.0m small bridge)

reinforced bridge has been completed.

     (III) Nangan channel management (Kuitun) (KT-C03)

    The contract sum is 29.29 million yuan, with a construction period of 488 days. The

contract commences on July 20, 2017 and plans to complete the construction on

December 20, 2018. At present, a total of 18.26 million yuan for investment has been

completed, accounting for 62.3% of the contract amount. In terms of progress, 100% of

Nangan channel N2+050-N3+400 (about 1.35 km) flood control channel project. 100% of

water supply pipeline improvement project has been completed; 100% of N0+000-3+400

roads and pedestrians has been completed , and 100% of N0+000-3+400 culvert

engineering project has been completed.

    ( IV ) Non-profit water management network and community management

network renovation project (KT-C12)

    The contract sum is 11.50 million yuan, which is undertaken by Shaanxi Construction

No.2 construction co. LTD, and supervised by Kuitun engineering construction supervision

center, with a construction period of 488 days.

    The contract commences on June 30, 2017. In terms of progress, 3020 m of Korlaxi

road pipeline network, 66 chambers; 663 m of Beijingdong road pipeline network, 23

                                            25
External Monitoring for Resettlement Plan

chambers; 380 m of Tuanjiedong street pipeline network, 17 chambers; 1019 m of Shawan

street pipeline network, 28 chambers; 850 m of Beijingxi road pipeline network, 19

chambers have been completed. Up to now, the main part of the contract has been

basically completed, and the network has been put into use.

                                          26
External Monitoring for Resettlement Plan

                                                            Table 2-1: Each Subproject Implementation Progress

 The
            The project                                                 The early stage of the        Starting
serial                                A brief description                                                               Progress for Last Monitoring                  Progress for This Monitoring
              content                                                           procedure              Time
number

                                                                           By this monitoring                        (1) Dongyizhi channel + Dongchong ditch        (I) Dongchong ditch + Yizhi channel

                              3 flood drainage channels in the         found that:                               (Kuitun city) (KT-C01)                         (Kuitun city section) (KT-C01)

                              urban area will be improved, with a          1.        Project                         The contract sum is 13.18 million yuan,        The contract amount is RMB 13.18

                              total length of 6996.20 m (including     permission     notes     for              which is undertaken by Anhui communication     million with a construction period of 488

                              Dongchong ditch KT-C01, 0+000-           location      (         been              and navigation engineering co. LTD, and        calendar days. The contract starts on June

                              0+660, Dongyizhi channel 0+000-          approved)                                 supervised by Xinjiang Yintong construction    16, 2017 and plans to complete the
             River channel                                                                             August
   1                          0+999.2, Xichong ditch KT-C02,               2.        Land      pre-              supervision co., LTD., with a construction     construction on November 16, 2018. At
         regulation project                                                                            2017.
                              0+000-1+605, Nangan channel KT-          trial comments involved                   period of 488 days.                            present, has the completed investment of

                              C03, 0+000-3+372. Flood control          in Kuitun area ( been                         The contract starts on June 16, 2017 and   10.91 million-yuan, accounting for about

                              and emergency response roads with        approved)                                 plans to complete the construction on          82% of the value of progress aspects,

                              a total length of 39.43km will be            3.        Land      pre-              November 16, 2018. At present, has the         including Dongchong ditch D0 + 000 - D0 +

                              constructed along the channels.          trial comments involved                   completed investment of 11.79 million yuan,    660 section of the completed 100% of the

                                                                       in Tianbei new area(in                    accounting for about 89.4% of the value of     work amount, Dongchong ditch sediment

                                                                                                      27
External Monitoring for Resettlement Plan

  processing)                      progress aspects, including Dongchong ditch      basin completed 100% of the work amount.

      4.    Preliminary            D0 + 000 - D0 + 660 section of the completed     Dongyizhi ditch completed 100% of the work

  design (been approved)           95% of the work amount, Dongchong ditch          amount;     40%   of    flood    control   and

                                   sediment basin completed 100% of the work        emergency roads were completed.

                                   amount. Dongyizhi ditch completed 96% of              (II)   Xichong    ditch    (0+000~1+605

                                   the work amount; 40% of flood control and        including sand basin) management project

                                   emergency roads were completed.                  (KT-C02)

                                       (2)    Xichong    ditch   (0+000~1+605            The contract sum is 16.36 million

                                   including sand basin) management project         yuan, with a construction period of 488

                                   (KT-C02)                                         days. The contract commences on August

                                        The contract sum is 16.36 million yuan,     22, 2016 and plans to complete the

                                   which is undertaken by Nanchang Luqiao           construction on December 22, 2017. At

                                   engineering co. LTD, and supervised by           present, a total of 16.36 million yuan for

                                   Xinjiang Yintong construction supervision co.,   investment has been completed, accounting

                                   LTD., with a construction period of 488 days.    for 100% of the contract amount. In terms of

                                       The contract commences on August 22,         progress, 100% of Xichong ditch (K0+000-

                                   2016 and plans to complete the construction      K1+605) flood control channel has been

                           28
External Monitoring for Resettlement Plan

                                   on December 22, 2017. At present, a total of    completed; 100% of the bridge project

                                   16.36 million yuan for investment has been      (K1+592.20 1-10m small bridge) has been

                                   completed, accounting for 100% of the           completed, reinforced concrete hollow slab

                                   contract amount. In terms of progress, 100%     bridge and 99% of bridge engineering

                                   of Xichong ditch (K0+000-K1+605) flood          (K0+671.00     2-10.0m     small    bridge)

                                   control channel has been completed; 100% of     reinforced bridge has been completed.

                                   the bridge project (K1+592.20 1-10m small            (III) Nangan channel management

                                   bridge) has been completed, reinforced          (Kuitun) (KT-C03)

                                   concrete hollow slab bridge and 99% of              The contract sum is 29.29 million yuan,

                                   bridge    engineering    (K0+671.00   2-10.0m   with a construction period of 488 days. The

                                   small bridge) reinforced bridge has been        contract commences on July 20, 2017 and

                                   completed.                                      plans to complete the construction on

                                       (3)    Nangan       channel   management    December 20, 2018. At present, a total of

                                   (Kuitun) (KT-C03)                               18.26 million yuan for investment has been

                                       The contract sum is 29.29 million yuan,     completed, accounting for 62.3% of the

                                   which is undertaken by Xinjiang Beifang         contract amount. In terms of progress,

                                   construction co. LTD, and supervised by         100% of Nangan channel N2+050-N3+400

                         29
External Monitoring for Resettlement Plan

                                                                                                     Xinjiang Yintong construction supervision co.,   (about 1.35 km) flood control channel

                                                                                                     LTD., with a construction period of 488 days.    project. 100% of water supply pipeline

                                                                                                         The contract commences on July 20,           improvement project has been completed;

                                                                                                     2017 and plans to complete the construction      100%    of   N0+000-3+400       roads   and

                                                                                                     on December 20, 2018. At present, a total of     pedestrians has been completed,and 100%

                                                                                                     22 million yuan for investment has been          of   N0+000-3+400     culvert   engineering

                                                                                                     completed, accounting for 75.1% of the           project has been completed.

                                                                                                     contract amount. In terms of progress, 100%

                                                                                                     of Nangan channel N2+050-N3+400 flood

                                                                                                     control channel project. 100% of water supply

                                                                                                     pipeline improvement project has been

                                                                                                     completed; 100% of N0+000-3+400 roads

                                                                                                     and pedestrians has been completed,and

                                                                                                     100% of N0+000-3+400 culvert engineering

                                                                                                     project has been completed.

        Shelter forest   Construction of shelter forests with a                                 —        Windbreaks and ancillary projects on              25 million yuan has been invested,
2                                                                       ——
    construction         total area of 83.2 ha along the flood                             —         both sides of Dongchong ditch and Xichong        accounting for 87% of the contract value. In

                                                                                           30
External Monitoring for Resettlement Plan

                            control channel 10-20m, cultivation of                                          ditch have been completed, and windbreaks         terms of image progress, windbreaks and

                            200,400 trees, irrigation by dripping                                           on both sides of the Nangan channel are           ancillary works on both sides of Xichong

                            and spraying                                                                    scheduled to be completed by the end of the       ditch and Dongchong ditch and Nangan

                                                                                                            year.                                             channel have been completed, and the rest

                                                                                                                                                              will be replanted in spring.

                            14 ladders 1 steep slope and two grit

                            chambers;        construction       and

          The spillway      reconstruction of 5 aqueducts each;
                                                                                                        —       The content has been included into the            The content has been included into the
3   construction       of   construction      of   26       bridges,         ——
                                                                                                   —        flood prevention works                            flood prevention works
    ancillary facilities    maintenance of 2 bridges, 6 culverts,

                            and 40 hydraulic structures with 96

                            structures in total.

          Urban water       Reconstruct 6.27 km water supply                 The   approval   of                The contract sum is 11.50 million yuan,           The contract sum is 11.50 million yuan,

    supply          pipe    pipeline; and set up the GPRS urban updated            environmental            which is undertaken by Shanxi Construction        with a construction period of 488 days.
                                                                                                        —
4   network                 water   supply    network   monitoring impact assessment and                    No.2 construction co. LTD, and supervised by          In terms of progress, 3020 m of Korlaxi
                                                                                                   —
    transformation          system; purchase water quality safety the relevant files of kuitun              Kuitun engineering construction supervision       road pipeline network, 66 chambers; 663 m

    and         leakage     testing equipment; equip with water Development and Reform                      center, with a construction period of 488 days.   of Beijingdong road pipeline network, 23

                                                                                                   31
External Monitoring for Resettlement Plan

monitoring   supply network leak detectors.             Commission is onging               The contract commences on June 30,           chambers; 380 m of Tuanjiedong street

             (1). Shawan Street (Yili Road - Beijing                                   2017. In terms of progress, 3020 m of Korlaxi    pipeline network, 17 chambers; 1019 m of

             Road) intends to transform pipeline                                       road pipeline network, 66 chambers; 663 m of     Shawan     street    pipeline   network,    28

             1019 meters long, diameter 300mm.                                         Beijingdong   road    pipeline   network,   23   chambers; 850 m of Beijingxi road pipeline

             (2). Korla Road (Tuanjienan Street –                                      chambers; 380 m of Tuanjiedong street            network,   19       chambers    have       been

             Hefeng Street) intends to transform the                                   pipeline network, 17 chambers; 1019 m of         completed. Up to now, the main part of the

             line   3141   meters   long,   diameter                                   Shawan     street    pipeline    network,   28   contract has been basically completed, and

             400mm.                                                                    chambers; 850 m of Beijingxi road pipeline       the network has been put into use.

             (3). Tuanjiedong Street (Urumqi Road -                                    network, 19 chambers have been completed.

             Yili Road) intends to transform the line                                  Up to now, the main part of the contract has

             380 meters long, diameter 300mm.                                          been basically completed, and the network

             (4). Beijing West Road (Torrey Street -                                   has been put into use. This project is

             Hefeng Street) intends to transform the                                   preparing the completion acceptance.

             line 936 meters long, diameter of

             400mm.

             (5) Beijng East Road (Manas Street –

             Shawan Street) intends to transform

                                                                               32
External Monitoring for Resettlement Plan

                      the line 791meters long, diameter of

                      400mm.

                          7      new   public   toilets,   living                                      It has been basically completed, ready for    It has been basically completed, ready for

        Garbage and   garbage      processing     with     fixed                                       completion acceptance                        completion acceptance

5   sewage            container system, set up 95; Set the                ——                      —

    intercepting      bin 400 along the route of flood

                      control.

                                                                                             33
External Monitoring for Resettlement Plan

2.2 Project Resettlement Progress
    The People’s government of Kuitun City has approved the RP and budget in February

2013. In April 2013, some staff of the PMO, Construction Bureau, House Levy Office,

Department of Natural Resources, Tianbei New District and affected state-owned farmland

are transferred to form a resettlement group.

    At present the resettlement progresses are as following:

    (1) Residential house demolition

    During this monitoring, the residents of the housing demolition projects involving a

total of 155 households, of which Kuitun City, involving 60 households, (including 32

households in Xichong ditch and 28 households in Dongchong ditch) 95 households are

involved in Tianbei New District.

    (a) By the end of this monitoring, HD work of 32 households in Xichong ditch has been

completed, and all APs have signed the compensation agreement and been well resettled.

    (b) By the end of this monitoring, all the demolition work of 28 residential houses in

Dongchong ditch has been completed, and the APs have signed a compensation

agreement for house demolition and have been properly resettled. According to the

investigation, the affected 28 households have chosen the monetary compensation.

    (c) By the end of this monitoring, 95 residential houses’ demolition are involved in

Tianbei New District. However, due to the change of the project, the PMO is doing the final

design, LAR work has not carried out yet, the EM will continue to follow the resettlement

and implementation of LAR for the following stage.

    (2) The shops along the street

    The last monitoring found that there were total of 57 shops along the street, including

47 shops (46 shops in the Xichong ditch, 1 shop in the Dongchong ditch) in Kuitun city; 10

shops in Tianbei New District.

    Up to this monitoring: (1) all 46 shops along the street have been demolished in the

Xichong ditch section, and all the affected shops have been properly settled. (2)

Dongchong ditch involves 1 shop along the street has completed demolition, the affected
                                            34
External Monitoring for Resettlement Plan

people choose monetary compensation; The affected shop has been resettled properly. (3)

The demolition work of the 10 shops involved in Tianbei New District has not been carried

out yet. However, due to the change of the project, the PMO is doing the final design, LAR

work has not carried out yet, the EM will continue to follow the resettlement and

implementation of LAR for the following stage.

    (3) The demolition of enterprises

    By the end of this monitoring, 2 enterprises in Kuitun city have completed the

demolition work and have been properly resettled. One enterprise in Tianbei New District

has not completed the demolition work, because the LA, HD and resettlement of Tianbei

New District has difficulties. After discussion and decision of Xinjiang PMO, Kuitun

municipal government and inspection team, Kuitun city government flood drainage

improvement project financed by domestic funds (5 contract packages including KT – C04,

C05, C06, C07 and C08).

    Because Kuitun PMO and HDO have done full consultation and introduction to the

residents before the house demolition and held a public participation meeting to the

affected people, there are no complaints happened.