Developers' Manual Version 1.35

Page created by Kyle Chavez
 
CONTINUE READING
Developers' Manual Version 1.35
Developers’ Manual

Version 1.35
Developers' Manual Version 1.35
Developers Manual

Revisions
The following clauses in this manual were revised on the dates shown.
Revision Issue Date              Reason for Change
Number
    1.0      4 August 1999       Initial Issue

    1.1      6 April 2000        Amendments to clauses 2.1, 2.3.2, 4.1, 5.1, 18.1, 19.1.3, 19.1.5,
                                 22.2, 23.1.2, 23.1.4, 26.1.1, 26.1.4, 26.2.1 and 27.1
                                 Clauses 4.2 and 27.1.1 deleted
                                 New sections 28 and 29 added
                                 Modifications to table of contents, maps, glossary of terms and minor
                                 editorial changes
    1.2      16 January 2001     Amendments to clauses 2.1, 2.2, 2.3.2, 2.3.3, 9.4.2, 9.4.3, 18.1.1,
                                 18.1.2, 19.1.5, 22.1.2, 22.1.3 (deleted), 24.3.6, 25.1.3 (added),
                                 25.2.5, 25.2.6, 25.3, 26.1.1, 26.1.2, 27.1.1 and 29
                                 Modifications to table of contents, glossary of terms and minor
                                 editorial changes
    1.3      10 September 2001   Amendments to clauses 2.1, 2.2, 10.1.3, 19.1.5, 24.1.1, 24.3.7
                                 (added)
                                 Modification to table of contents
    1.4      May 2002            Amendments to clauses 2.1,18.1.1, 19.1.5, 24.3.1, 24.3.6, 29.3
                                 (added)
                                 Section 18 renamed and Section 10.1 clarified
                                 Modifications to table of contents and glossary of terms
    1.5      September 2003      Amendments to Clauses:-
                                 2.3 numbered in body of document,
                                 9.4.3 Category g) added; drawing guidelines changed to” WCX CAD
                                 Standard (formerly WCX Pack)”,
                                 2.2 Wastewater Manual Volume 2 replaced with “Design Standard
                                 Number 51” and “for drawing standards WCX CAD Standard (formerly
                                 WCX Pack)” added, and “Vacuum Sewerage Manual” added.
                                 6. amended.
                                 10.1.12 Vacuum Sewerage added.
                                 25.2.6 inserted and existing 25.2.6 & 25.2.7 re numbered,
                                 22.6.2 amended and 22.6.2.1, 22.6.2.2 and 22.6.2.3 added.
                                  “Design Standards” added to Glossary of Terms and in general text
                                 throughout manual as required.
                                 Modifications to table of contents
    1.6      January 2006        Contact details in Clauses 5.1 5.2 & 5.3 amended
                                 Clause 2.2 – list of manuals amended to include External Approvals
                                 Manual
                                 Clause 8 Title changed to External Approvals – modifications to text
                                 to accommodate External Approvals Manual and new location of
                                 Prelims to Works
                                 Clause 10 – Initial Submission. General amendments to replace
                                 covering letter with Submission cover sheet included at Clause 10.1
                                 Clause 12 – Final Submission. General amendments to replace
                                 covering letter with Submission cover sheet included at Clause 14.1
    1.7      July 2006           Requirement for Serviceable Lots list added at clause 10.1.7 – other
                                 clauses renumbered to suit and Submission Cover Sheet for Review of
    1.8      May 2007            Initial Engineering Design Submissions amended
                                 Amendment to clauses
                                 Clause 2.3.3 Added “The Construction Engineer is responsible for
                                 arranging the construction of the works to meet the requirements of
                                 the relevant manuals, codes and standards”.
                                 Section 11 Numbering reformatted on Submission Cover Sheet

    1.9      February 2008       External Approvals
                                 Paragraph to added outlining requirement to obtain comment from

2         Developers’ Manual
Developers' Manual Version 1.35
Developers Manual

Revision Issue Date         Reason for Change
Number
                            external agencies regarding developments adjacent to or crossing a
                            road reserve or asset under control of an external agency.
    1.10   February 2008    Modifications to table of contents
                            Clause 9.6 Deleted “from the Design Coordination by fax request on
                            9420 2203” and replaced it with “by completing the Application Form
                            at
                            Attachment 3 and forwarding it to your Submission Contact.”
                            Added Attachment 3 ‘”Application for single use of Water Corporation
                            example drawings for pumping station facility in electronic format”.
    1.11   April 2008       Submission Cover Sheet for Acceptance of Final Engineering
                            Submissions paragraph 5 external approvals amended to ensure that
                            the required actions are completed
    1.12   May 2008         Clause 2.3.4 Paragraph to serve notice that the Corporation has the
                            right to accept or reject nominated engineers.
    1.13   September 2008   Clause 10.1.13 paragraph amended following request from Principal
                            Engineer Infrastructure Design Branch
                            Clause 10.1.14 Paragraph titled “Low Pressure Sewerage” and
                            amended to explain in what circumstances Grinder Pumps are
                            permitted.
    1.14   October 2008     Clause 6 of the Submission Cover Sheet for Review of Initial
                            Engineering Design Submission redrafted to indicate if adjacent lots
                            are likely to become serviceable as a result of the works.
                            Clause 6 of the Submission Cover Sheet for Acceptance of Final
                            Engineering Submission redrafted to indicate property details of lots
                            of lots rateable as a result of the works
    1.15   February 2009    Paragraph 5.3 As Constructed Contact details amended
                            Clause 15.2 re drafted to outline the requirement relating to the Final
                            Design Submission for Urban Drainage works.
           March 2009       Contact details for Kalgoorlie para 5.2 amended also 5.3 amended to
                            ensure all “as constructed” details are forwarded to the Spatial
                            Information Management Group
    1.16   April 2009       Submission Cover Sheet for Acceptance of Final Engineering
                            Submissions paragraph 5 External Approvals amended to ensure that
                            all requirements relating to the External Works Manual and the
                            Utilities Code of Practice are met.
    1.17   August 2009      Clauses 10.1, 11,22.5, 24, 24.5.3 and 26 aligned to similar provision
                            in the Advanced Works Agreement Manual .
                            Additional checklist examples added clause 11.2 also Attachment 4
                            (i.e. example of a Wastewater As Constructed plan)
    1.18   September 2009    Amended the Wastewater Reticulation and Water Reticulation Initial
                            Design Checklists Paragraphs 10.4.4 and 11.4 deleted
                            Paragraph 24.5.2 relating to as constructed information for Water
                            Reticulation works revised
           October 2009     Clause 22.7 Joint Final Inspection changed to Final Takeover
                            Inspection
                            Clause 24.5.3 Amended to attachment 4
                            Clause 24.5.4 Typographical error amended
                            Clause 24.5.5 amended to reflect details contained in 24.5.2
    1.19   December 2009    Clause 5.1 Main Extension contact details amended
                            Appendix 4 Example Wastewater Reticulation As Constructed Plan
                            reformatted as A3
    1.20   January 2010     Clauses 10.1, 11.3, 11.4 & 11.5 changed to incorporate requirements
                            of Urban Main Drainage Manual.
    1.21   July 2010        Section 3 Process Flowchart Prerequisites to Works amended to
                            External Approvals and Prerequisites to Works
                            Section 5 Perth Contacts amended to include Main Relocations
                            Section 11 amended to include Design Standard Variation Request

3      Developers’ Manual
Developers' Manual Version 1.35
Developers Manual

Revision Issue Date         Reason for Change
Number
                             criteria
                             Section 13 Manager Land Development amended to Manager
                             Development Services Branch
    1.22   October 2010      Section 11.2 Submission cover sheet for review of initial engineering
                             design amended
                             Section11.3 Water and wastewater reticulation initial design
                             checklists amended
    1.23   March 2011        Section 24 Incomplete submissions will not be accepted or captured
                             until requested information is received.
    1.24   June 2011        Section 5 Corporation Contacts
                            Section 5.2 Inspection Contacts
                            Section 5.3 As- Constructed Information
                                                                              Amended following
                            Contacts
                                                                              country re alignment
                            Section 5.4 State Map
                            Section 5.5 South West Region Map
                            Section 5.6 Metropolitan Map
    1.25   December 2011    Point 10.1.7 deleted from Initial Submission Requirements
                            Section 28 Added reference to Section5 of the Working Near Water
                            Corporation Pipeline Guidelines
    1.26   January 2012     Section 5.2 Amended contact numbers for the Southwest Region
                            Added Plan Number field to the Submission Cover Sheet for Acceptance
                            of Final Engineering Submissions.
                            Section 24 Added Water and Wastewater Reticulation As-Constructed
                            Submission Checklist
                            Section 28 Attachment 1 amended to include open drains
    1.27   March 2012       Submission Cover Sheet for acceptance of final engineering
                            submissions – section headings numbered
                            Clause 24.1 Recording of as constructed information amended to
                            include Licensed Surveyors or Engineering Surveyors
    1.28   May 2012         Section 5.1 Amended submission contact details
                            Section 5.2 Amended North West Region telephone / Fax numbers
    1.29   February 2013    Section 2.2 Amended reference to Design Standards
                            Section 4.1.2 Revised paragraph 2_Connection to Existing Works
                            Section 5.3 As Constructed Information Contact details amended
                            Section 11 Added Water and Wastewater Headworks Initial design
                            checklists
    1.30   July 2013        Amended the maps in Sections 5.4, 5.5 and 5.6
                            Section 11.1 amended to make reference to the Design Standard
                            variation Request Form and Inserted new form (page 27)
    1.31   December 2013    Section 8 Amended legislative requirement to provisions of the Water
                            Services Act 2012
                            Section 9.4 Change phone contact to email inbox address
                            Section 9.5 Amended fax number
                            Section 11 Added Drainage Works Initial Design Check list
                            Section 20.3 Added Construction of assets without all relevant approval
                            requirements
    1.32   April 2014       Amended Initial submission coversheet, Water and Wastewater retic
                            and Drainage works check lists
    1.33   August 2014      South West Region map removed
                            Initial Submission Cover sheet removed
                            Headworks assets removed as scope of works
                            Process diagram revised
                            Application/Submission forms located at rear as appendices
                            Additional Pre-calculated information included
    1.34   December 2014    Section 10.2 Site plan information to be included with digital copy of
                            design drawings

4      Developers’ Manual
Developers Manual

Revision Issue Date         Reason for Change
Number
                            Section 15.4 amended to include requirement where drawing
                            amended and cost of project increases a revised Final Subdivision
                            Cover Sheet must be included
                            Section 23 revised sub paragraphs 23.1.3 and 23.1.5 removed
                            Appendix 5 Final submission Cover Sheet added additional dot point
                            under Important information for Design Engineers
    1.35   May 2015         Section 14 Additional information required i.e. Name of Construction
                            Engineer, Contractor , Sub contractor
                            Section 17 redrafted - Constructed Phase – Start-up
                            Section 18 redrafted.-. Construction Phase - Design amendment –
                            alterations to an accepted final submission
           July 2015        Country Inspection Contacts amended

5      Developers’ Manual
Developers Manual

                                      Feedback Form
To provide feedback on the Developers’ Manual, please complete this form.

 Publication Information                      Revision Status:

 Title: Developers’ Manual
 Your Information                             Address:

 Name:                                        Fax:

 Phone:
 Proposed Change Information
                                              Page No.:
 Section:

 Para Reference (e.g. 1.2.3):
 Description of change:

 Reason for change:

 Do you require a response to your suggestion/request?       Yes           No   
 Your signature:                              Date:

 Please return completed form to:

 Development Services Branch
 Water Corporation
 PO Box 100
 LEEDERVILLE WA 6902
 Fax: 9420 3193

6      Developers’ Manual
Developers Manual

                                                CONTENTS

    1         Glossary of Terms                                                        10

    2         Introduction                                                             12

    3         Fees                                                                     13

    4         Corporation Contacts                                                     14

    5         Process                                                                  18

    6         Planning Phase - Preliminary Investigation                               19

    7         Planning Phase – Land Requirements                                       19

    8         Planning Phase – External Approvals                                      19

    9         Design Phase – Design of Works                                           20

    10        Design Phase – Initial Submission                                        20

    11        Design Phase – Design Standard Variation Requests                        21

    12        Design Phase – Review of the Initial Design                              22

    13        Design Phase – Objections to the Corporation’s requirements              22

    14        Design Phase – Final Submission                                          22

    15        Design Phase – Acceptance of the Final Submission                        23

    16        Design Phase – Alterations to an accepted Final Submission               23

    17        Construction Phase – Start-up                                            23

    18        Construction Phase - Design Amendment (Alteration to an accepted final   24
              submission)
    19        Construction Phase – Construction Requirements                           25

    20        Construction Phase – Isolation of New Works (Wastewater only)            25

    21        Construction Phase – Inspection of Works during construction             26

    22        Construction Phase – Connecting to existing assets                       28

    23        Takeover Phase – As-constructed Drawings                                 28

    24        Takeover Phase – Takeover of the Works                                   29

    25        Takeover Phase – Warranty Period                                         29

    26        Takeover Phase – Final Acceptance Certificate                            30

7        Developers’ Manual
Developers Manual

              Appendices

    27        Appendix 1: Water Initial Design Checklist             31

    28        Appendix 2: Wastewater Initial Design Checklist        32

    29        Appendix 3: Drainage Submission Checklist              33

    30        Appendix 4: Request for Variation to Design Standard   34

    31        Appendix 5: Final Submission Cover Sheet               35

    32        Appendix 6: Clearance to Works Guidelines              36

    33        Appendix 7: Pre-handover Checklist                     37

    34        Appendix 8: As-Constructed Plan Checklist              38

    35        Appendix 9: Example Wastewater As-Constructed Plan     39

8        Developers’ Manual
Developers Manual

Foreword

The Developers’ Manual is an initiative by the Water Corporation in response to feedback from the
development industry for greater standardisation of requirements for water, wastewater and urban
drainage assets. The manual is made up of topics extracted from the technical manuals that deal
with administrative rather than technical requirements. In bringing these requirements together
considerable effort has been made to standardise, clarify and simplify them. The terminology of the
manual reflects the reality that the only agreement the Corporation has is with the developer, not
with any construction engineer or contractor.

Please use the feedback form on page 3 if you have other ideas for improvements. Any feedback is
welcome and all suggestions for improvement will be carefully reviewed and acknowledged.

This manual refers to the Corporation’s technical manuals and design standards for technical
information relating to water, wastewater and drainage works. These manuals will be updated in
the future to remove information that is in this new manual and bring them in line with it where
necessary. Should material in a technical manual or design standard conflict with information in
this manual, this manual takes precedence.

This manual does not apply to works required to serve large developments. For this type of
development please refer to the Multi-Staged Development Works Manual.

9      Developers’ Manual
Developers Manual

1     Glossary of Terms

In this Manual the following words and expressions shall have the following meanings. These
meanings do not necessarily comply with the meanings given in the Water Corporation Act and
other Water Corporation publications.

Agreement                The formal legal document between the developer and the
                         Corporation with respect to delivering fit for purpose assets that
                         are acceptable to the Corporation.
Alignment                The line on which the pipes are laid and measured from the
                         adjacent cadastral boundary.
As-constructed           The document on which details of the constructed works are
Document                 recorded and submitted to the Corporation.
Asset Inspector          An officer of the Corporation responsible for assessing and or
                         inspecting the works.
Beneficiary Lot          Lots that acquire water supply or wastewater service availability,
                         as a result of an extension of the reticulation, without the owner
                         having paid, or been deemed to have paid, Headworks
                         Contributions.
Clearance to Work        A permitting procedure to authorise a contractor to conduct work
Permit                   on, or near a designated asset, other than where the personnel
                         carrying out the work are being directly supervised by a person
                         who has operational control of the asset.
Construction             The engineer or engineering firm appointed by the developer to
Engineer                 manage the construction of the works.
Contract                 The agreement between the developer and the contractor for the
                         execution of the works.
Contractor               A person or organisation bound to execute the works under a
                         contract.
Contract Price           The amount payable to the contractor for the execution of a
                         contract.
Corporation              The body corporate known as the Water Corporation, Western
                         Australia.
Design Drawings          The drawings prepared by the design engineer, showing the
                         proposed works.
Design Engineer          The engineer or engineering firm appointed by a developer to
                         prepare design drawings and documents for submission to the
                         Corporation.
Design Standard          The Corporation’s design standard relevant to the works being
                         undertaken.
Developer                The person or organisation that has made an agreement with the
                         Corporation to provide drainage, water or wastewater
                         infrastructure.
Distribution Main        A water supply pipeline to which standard services are not normally
                         connected.

10    Developers’ Manual
Developers Manual

Easement               A defined area of land over which the Corporation has a right to
                       enter for purposes defined by agreement or statute and subject to
                       any conditions/restrictions implied therein. Such purposes can
                       include for example, access, construction, maintenance and repair.
Engineer               A person qualified to be a chartered professional engineer, and who
                       has appropriate engineering experience.
Final Acceptance       A certificate issued by the Corporation at the end of the warranty
Certificate            period provided conditions have been met.
Final Inspection       A letter issued by the asset inspector confirming that the Works are
Clearance              acceptable.
Final Inspection       The inspection by the asset inspector, with the construction engineer in
                       attendance, to assess acceptance of the assets.
Headworks              The infrastructure that provides water, wastewater and drainage
                       services, excluding reticulation and private plumbing e.g. dams,
                       wastewater treatment plants, main drains, etc.
Inspection             Any activity undertaken to assess the condition of the works.
Land Development       The formal legal document between the developer and Corporation
Agreement              with respect to fulfilling any WAPC conditions imposed on a
                       subdivision application.
Main Drain             An existing or proposed drain within the metropolitan area that is
                       controlled by the Corporation.
Main Sewer             A wastewater collection sewer to which connections are not
                       normally made.
Precalculated          A surveyor’s precalculated cadastral plan of the proposed
Cadastral Plan         subdivision development.
Prerequisites To       The procedure necessary to address the Corporation’s statutory
Works                  requirements under the Water Services Act 2012 for general and
                       major works as set out in the External Approvals Manual.
Pre-handover           The inspection conducted by the construction engineer prior to booking a
inspection             final inspection.
Region                 An area of the state designated as a region of the Corporation.
Regional Office        The principal office of that region.
Reticulation           The pipelines that connect private works to major works, and are
                       constructed to provide a water supply or wastewater service to a
                       property.
Shall                  A mandatory requirement.
Should                 A requirement to be adopted unless circumstances justify a
                       variation.
Specification          The document containing the technical clauses to be read in
                       conjunction with the design drawings for the works.
Standard Drawings      Registered Corporation drawings.
Takeover               When the Corporation assumes ownership of the works and the
                       warranty commences.
Technical Manual       The Corporation’s technical manual relevant to the works being
                       undertaken.
Warranty Period        The period commencing from takeover.

11    Developers’ Manual
Developers Manual

2      Introduction
2.1         Scope
This manual explains the administrative requirements for the provision of works that are covered
by an agreement, so they can be incorporated into the Corporation’s schemes and taken over by
the Corporation. It covers all aspects from the preliminary investigation stage to final acceptance of
the works by the Corporation. Works consist of the following categories:
       a) Water and wastewater reticulation involving land subdivision
       b) Water and wastewater reticulation extensions not involving land subdivision
       c) Relocating existing headworks assets to facilitate land development*
       d) Urban main drainage works*
Works covered by a MSWA are not included in the scope of this Manual.

* Any works performed on headworks assets (category c & d) will be assessed to determine the
scope of works and level of risk to the asset. Works that are deemed significant may be required to
follow additional procedures that are not contained in this manual. Prior to lodging a submission,
you should contact us on 9420 2099 or email land.servicing@watercorporation.com.au to discuss
your options.

2.2          Technical and Other Manuals
The Corporation has design standards and manuals that outline how each type of asset should be
constructed. These are shown in the below table.

 Asset Type/Process                            Design Standard or Manual
 Water reticulation                            Design Standard 63
 Wastewater mains                              Design Standard 50 and the Water Services
                                               Association of Australia Sewerage Code.
 Vacuum Sewerage                               Design Standard 53
 Water distribution mains                      Design Standard 60
 Urban main drainage                           Design Standard 66
 Drawing Standards                             Design Standard 80
 Prerequisites to Works                        External Approvals Manual
 To protect pipelines from AC interference     Earth Potential Rise Manual

To enquire about our design standards please email:
idb.standardsenquiries@watercorporation.com.au
Where this manual conflicts with another manual or standard, this manual takes precedence.

2.3         Roles and Responsibilities
      2.3.1   Developer
      The developer is the proponent of the works. The developer is responsible for:
            Carrying out the requirements of this manual for the provision of the works,
            Appointing a design engineer, a construction engineer and a contractor to carry out
             the works in accordance with this manual, the technical manuals and design
             standards.
      2.3.1    Design Engineer
      The design engineer is responsible for designing the works required to service land.
      The design engineer must be a registered holder of all of the Corporation’s manuals and
      design standards.

12     Developers’ Manual
Developers Manual

      2.3.2   Construction Engineer
      The construction engineer is responsible for managing and arranging the construction of the
      works in accordance with relevant manuals, codes and design standards, and to ensure the
      works are acceptable to the Corporation.

2.4          Notification
The Developer should inform the Corporation in writing of the details of all the parties engaged to
deliver the works. The Corporation reserves the right to accept or reject nominations based on its
assessment of the capability, capacity and past performance of the nominated party.

3      Fees
The following fees are payable by the developer to the Corporation. Fees will remain valid for the
life of the submission.

3.1          Water Reticulation Planning
Fee – is a payment for water supply reticulation planning which is based on 3.75 per cent of the
Corporation’s estimate of the construction of the cost of the works.

3.2          Connecting to existing works
Fee – is a payment for the Corporation to connect new works to existing live works. This fee is
dependent on the type and size of connection and is required to be paid prior to the connection
being performed. Refer to 3.3, 3.4 and 3.5 for further information.

3.3           Potable and Non-potable Water Reticulation Connections
      3.3.1    Metropolitan Perth Region
         Standard connection fees may be provided as part of an agreement. Where the works
         contain non-standard or complex connections, the land servicing consultant may direct the
         design/construction engineer to obtain a quote from ‘Reimbursements’, Perth region, prior
         to the start-up meeting.

      3.3.2    Non-metropolitan Regions
         As part of the works design, the land servicing consultant may give direction to the
         design/construction engineer as to how the connections may be arranged. Connection
         requirements shall be discussed at the start-up meeting with the asset inspector. The fees
         and actions involved in connecting works in non-metropolitan regions may vary depending
         on the location and circumstances.

3.4           Wastewater Reticulation Connections
      3.4.1    Metropolitan Perth Region
         All connection fees shall be paid prior to the connection. The design/construction engineer
         shall obtain a quote from ‘Reimbursements’. The isolation and connection requirements
         shall be discussed with the asset inspector at the start-up meeting.

      3.4.2    Non-metropolitan Regions
         As part of the works design, the land servicing consultant may give direction to the
         design/construction engineer as to how the connections may be arranged. Connection
         requirements shall be discussed at the start-up meeting with the asset inspector. The fees
         and actions involved in connecting works in non-metropolitan regions may vary depending
         on the location and circumstances.

13     Developers’ Manual
Developers Manual

3.5          Headworks Connections
When connecting to headworks infrastructure there is the potential for negative impact on many of
the Corporation’s end customers. Options such as tankering and limited shutdown periods must be
considered as part of the works design to minimise any disruption. The design engineer shall
discuss these requirements with the land servicing consultant in the early stages of the design to
determine any specific requirements.

4      Corporation Contacts
The Corporation contacts are shown below:

4.1         Submissions Contact
        State-wide -   Manager Land Servicing                            Phone: 9420 2099
        Subdivision    Development Services Branch                       Fax: 9420 3193
        Works          Water Corporation
                       John Tonkin Water Centre
                       629 Newcastle Street, Leederville
                       PO Box 100 LEEDERVILLE WA 6902

4.2         Inspections Contact
        Metropolitan    Inspection Services                              Phone: 9424 8462
        Perth Region    Perth Region                                     Fax:   9424 8535
                        273 Bannister Road , Canning Vale
                        PO Box 1525
                        CANNING VALE Delivery Centre 6970

        Agricultural      Regional Works Inspector                       Phone: 9622 4814
        Region            Agricultural Region                            Fax:   9622 4866
                          Water Corporation
                          263 Fitzgerald Street
                          PO Box 265
                          Northam, WA, 6401

        Great             Regional Works Inspector                       Phone: 9791 0495
        Southern          Great Southern Region                          Fax:   9842 4255
        Region            Water Corporation
                          215 Lower Stirling Terrace
                          Albany, WA, 6331

        Mid-West          Regional Works Inspector                       Phone: 9923 4906
        Region            Mid-West Region                                Fax:: 9923 4966
                          Water Corporation
                          SGIO Building, Cathedral Avenue
                          PO Box 43
                          Geraldton, WA, 6531

        North-West        Regional Works Inspector                       Phone: 9186 8237
        Region            North-West Region                              Fax:   9186 8210
                          Water Corporation
                          Welcome Road
                          PO Box 84
                          Karratha, WA, 6714

14     Developers’ Manual
Developers Manual

       South-West        Regional Works Inspector                      Phone: 9797 0495
       Region            South-West Region                             OR     9791 0464
                         Water Corporation                             Fax:   9622 4866
                         PO Box 305
                         Bunbury, WA, 6231

4.3          As-constructed Contact
All water and wastewater as-constructed drawings are to be submitted to:
spatial.datacapture@watercorporation.com.au

15    Developers’ Manual
Developers Manual

4.4        State Map

16    Developers’ Manual
Developers Manual

4.5        Metropolitan Perth Region

17    Developers’ Manual
Developers Manual

5    Process

18   Developers’ Manual
Developers Manual

6      Planning Phase - Preliminary investigation
To ensure that the concept and capacity of the proposed works are compatible with the
Corporation’s overall planning requirements; the design engineer shall discuss the broad planning
concepts of the design with a land servicing consultant. If a vacuum sewerage system is required
or another alternative servicing arrangement is proposed, its planning must be acceptable to the
Corporation. The requirements shall be discussed at an early stage in the planning of the works.
Any requirements that will be imposed by other authorities on the operation of the works must be
discussed and agreed to by the Corporation.

7      Planning Phase - Land requirements
7.1          All easements, reserves and land to be owned by the Corporation required for a
      project shall be shown on the design drawings.

7.2          Where easements or reserves are required and are outside the developer’s land
      holding: written in-principle agreement of the arrangements necessary to acquire the
      easements or reserves from the registered landowner is required.

8      Planning Phase - External approvals
8.1          During the preliminary stages of designing any works, the design engineer shall take
      into account the requirements of the Corporation’s External Approval Manual. This includes
      the statutory ‘Prerequisites to Works’ notification requirements as per the Water Services Act
      2012.

      8.1.1    Particular attention and early liaison needs to take place where any works are
         adjacent to, within or crossing a reserve or asset that is controlled by Main Roads (WA),
         Public Transport Authority, Western Power or Telstra.

      8.1.2   Prior to discussing proposed works with all affected parties, the design engineer
         should consider alternative options that reduce impacting any parties. The Corporation
         may provide comments on a design prior to formal or informal approvals being sought.

8.2          Prerequisites to Works
Works are classified in Part 6 of the Water Services Act 2012 as either major, general or exempt.
Reticulation works will be either general or exempt works depending on where they are located.
The design engineer is responsible for determining the class of works and completing all
prerequisites to works requirements in accordance with the Act. If the proposed works are classed
as general, all relevant documentation, E.G. notice plan/letters etc. shall be included in the initial
design submission.

8.3          Objections
The design engineer should make every reasonable effort to resolve any objections. Any objections
that cannot be resolved shall be referred to the land servicing consultant.

8.4         Completion required
Confirmation that all requirements of the prerequisites to works process is required before the
Corporation accepts final design drawings. This includes full resolution of all objections.

19     Developers’ Manual
Developers Manual

9      Design Phase - Design of works
9.1         Design requirements
Design drawings for the reticulation works shall be submitted by a design engineer.

9.2           Drawing certification
Each drawing and document that is submitted shall be signed by the design engineer who has the
authority to act on the behalf of the design engineer making the submission.

9.3           Design Responsibilities
The design engineer is responsible for ensuring the design of the works complies with the
Corporation’s manuals and design standards. Acceptance by the Corporation of a submission shall not
relieve the design engineer of this responsibility or the responsibility for any discrepancies, errors or
omissions in the submission or for the adequacy of the design.

9.4          Drafting Standards
The drafting for all submissions shall be in accordance with Australian Standard 1100, Part 101.
Drawings shall be suitable for microfilming.

9.5           Pre-Calculated Cadastral Plan
A digital copy of the precalculated cadastral plan will expedite the incorporation of information into the
Corporation’s spatial database. The digital file shall be in MGA94 coordinates. The plan shall be clear
and legible and only include information that is relevant. Unnecessary information that should not be
included is typically:
           Road kerb lines,
           Trees,
           Power/light poles,
           Stormwater pipes and gullies,
           Other utilities services e.g. electricity, gas, Telstra etc.

9.6         Standard Drawings
Example standard drawings are available in the design standards.

10     Design Phase - Initial Submission
10.1        The purpose of the initial submission is to enable the Corporation to:
          Ensure that the planned works conform with the overall planning,
          Provide administrative details that are required to be shown on the final design drawing;
           and,
          Ensure that the prerequisites to works process has begun, if required.

* An initial submission will not be accepted where the relevant documents are not supplied, or are
incomplete.

10.2          The initial submission shall contain:
            The Initial Submission Design Checklist for the relevant asset type.
            A digital copy (PDF) of the design drawings, including site plan information.
            The prerequisites to works documentation if the works are classed as general.
            A letter from the owner of any land other than the developer’s, agreeing in principle, to
             granting any easements or reserves required for the works.

20     Developers’ Manual
Developers Manual

          A list of any existing lots that becomes serviceable as a result of the works. The list shall
           show the property address, owners name and mailing address and a description of the
           land use (e.g. residence, industrial etc.)

10.3          Drainage
In addition to the documents required in section 10.2, submissions for drainage works shall also
contain:
          One copy of the local water management strategy for the area.
          One copy of the urban water management plan for the area.
          A letter that includes:
             A reference to the Department of Water’s drainage strategy for the area.
             A statement setting out the developer’s understanding of who is responsible for
               funding of any proposed future connection of a catchment to any part of the drain
               covered by this submission.
          A letter from the appropriate waterway/wetland catchment management agency (e.g.
            Swan River Trust) detailing its comments on the drainage proposal where appropriate.
          One copy of a soils investigation report where an investigation is required.
          One copy of the summary of the proposed pollutant removal processes and mechanisms
            within the drainage system including sizing calculations, where appropriate.
          Two copies of the technical specification. The technical specification shall consist of the
            technical clauses covering the work, or a statement shall be included in the covering
            letter confirming that the specification is the same as one previously submitted.

10.4          Vacuum Sewerage systems
In addition to the points contained in section 10.2, any vacuum sewerage system submissions will
also require:
          A statement from a supplier of an approved vacuum valve, as listed in the DS 36
            Product Atlas stating that the supplier has received the system design prepared by an
            approved designer. The statement must guarantee the hydraulics of the system and
            confirm that the guarantee is transferable to the benefit of the Corporation. The review
            must be carried out by a suitably experienced engineer and the engineer must be
            explicitly identified in the statement referred to above.
Current approved vacuum valves are:
          Air vac (contact Watercon) and,
          Flovac (contact Flovac Vacuum Sewerage Systems)

*The initial submission should be emailed to dsbdesign.submission@watercorporation.com.au

11      Design Phase - Design standard variation requests
11.1          The Corporation’s design standards are developed to ensure fit for purpose assets that
       achieve their economic design life with minimal operating and maintenance costs are delivered.

11.2           Occasionally a design may not meet the requirements of the design standard or proposes
       an alternative solution. Where this occurs, the design engineer shall complete the request for
       design standard variation form (refer to Appendix 4) and include it with the initial submission
       documents.

11.3           When proposing a variation, the design engineer shall include at a minimum, the
       following:
            Details of the reasons/circumstances for the variation.

21      Developers’ Manual
Developers Manual

          An assessment of the impacts and benefits for the Corporation and the developer.
          Details of options considered to negate the variation.

11.4         The following reasons for a variation will not generally be accepted by the Corporation:
          Inadequate site investigation that results in obstacles or constraints of a non-latent nature.
          Seasonal impacts that will resolve themselves over time.
          Where the design engineer’s assessment will cause a significant impact to the
           Corporation’s fundamental objectives.
          Where the request’s fundamental objective relates to financial benefit for the developer.
          Where the request is lacking sufficient information to be able to assess.

12      Design Phase - Review of the Initial Submission
12.1           The submission will be checked for conformity with the Corporation’s overall planning
       requirements. The submission will be:
           Accepted - if the submission is acceptable to the Corporation, it will be stamped as
             accepted, the Corporation reference numbers and one copy of the drawings will be
             returned to the design engineer. The design engineer will then be in a position to
             proceed with the final submission; or
           Accepted with amendments – if the submission is acceptable to the Corporation with
             minor amendments, it will be stamped as accepted conditional to the amendments
             being made, or
           Rejected – if the initial submission is not acceptable, the Corporation will reject the
             submission and request that the design be reconsidered.

13      Design Phase - Objections to the Corporation’s requirements
Any objections to planning or design requirements by the Corporation shall be made in writing to
the land servicing consultant. The objection shall state the reasons and efforts made to resolve any
issues. Any unresolved objections between the design engineer and the land servicing consultant
shall be referred to the Manager, Development Services.

14      Design Phase - Final Submission
The Final Submission shall consist of:
         The final submission cover sheet (refer appendix 5).
         An agreement in writing that formalises the arrangements for the Corporation to acquire
           any easements or reserves required as a result of the works.
         Confirmation that the prerequisites to works process has been completed, including
           resolving any objections.
         Six (6) A1 hard copies of the design drawings which shall incorporate the comments and
           details provided by the Corporation.
         Two (2) A1 hard copies of the design data plan (for wastewater submissions only).

Where already known:
         The name of the construction engineer and contact details
         The name and contact details of the contractor and any sub-contractors.
         The contract price for the works.
         The proposed date of commencement of work.

Where contract details are not known at the time of submitting the final submission these details
are to be provided prior to booking a Start Up Meeting.

22      Developers’ Manual
Developers Manual

*Final submissions that are related to a subdivision application cannot be accepted prior to the
application reaching conditional approval.

15      Design Phase - Acceptance of the Final Submission
15.1         The final design drawings will be signed by the Corporation to indicate that the
       submission is acceptable and one copy will be returned to the design engineer.

15.2           The final submission is valid for 12 months from the date of acceptance. If construction
       has not begun within this period, the submission will no longer be valid and a new submission
       will be required.

15.3          Acceptance of the design does not relieve the design engineer of any responsibilities for
       any discrepancies, errors, omissions or for the adequacy and conformance of the design with the
       relevant manuals and design standards.

15.4           Amended drawings
       When drawings are amended and resubmitted, they shall be distinguished from previous
       submissions by a new revision identifier. A brief description and date of the amendment shall
       be included in the title block. If the revised amendment alters the overall cost of the project,
       a Final Subdivision Cover Sheet must be included with the revised plans.

16      Design Phase - Alterations to an Accepted Final Submission
16.1          Once a plan has been accepted and before construction has started, any alterations to
       the design shall be discussed with the land servicing consultant who will determine whether a
       revised submission is required.

17      Construction Phase – Start-up
     17.1     Prior to the start of the works, the construction engineer shall arrange and attend a
              ‘start-up’ meeting with the asset inspector

     17.2     Once the design engineer receives the Corporation’s acceptance of a final design and
              contract details have been provided, if not provided with the final submission (see
              clause 14), the construction engineer can book a Start Up Meeting by contacting the
              relevant Inspections Contact (see clause 4.2).

     17.3     The Corporation requires a minimum of 5 business days’ notice to arrange a Start Up
              Meeting

     17.4     The construction engineer shall ensure that a record of the meeting is made. This record
              shall detail any key information and agreements reached.

     17.5      The following matters shall be addressed at the ‘start-up’ meeting:
                Indicative dates for the start and completion of construction of works.
                Method of isolating the new works from the existing works during construction.
                Inspection plan, detailing which parts of the works (including testing) the asset
                 inspector will inspect, when these inspections are proposed to take place and any
                 requirements necessary to facilitate these inspections.
                Nomination of additional staff that will access the site of the proposed works to carry
                 out Inspections.
                Contact and reporting arrangements including signing of site inspection reports.

23      Developers’ Manual
Developers Manual

                 Arrangements for the protection of Water Corporation assets.
                 Arrangements for the connection of new work to existing infrastructure.
                 Milestone meetings at which joint attendance is required.
                 Arrangements for inspection and testing processes.
                
      17.6      A copy of the meeting record shall be forwarded to the asset inspector within five days
                of the ‘start-up’ meeting occurring.

      17.7      Before construction begins the construction engineer shall ensure:
                 The inspector has authorised construction to start.
                 A Clearance to Works Permit has been obtained from the Corporation’s Customer
                  Service Delivery group, where necessary.
                 The contractor employs personnel that are capable and accredited to perform the
                  works. Refer to the relevant manual or design standard for details of the appropriate
                  accreditation required.

     17.8 Notice of Proposed Works
     Where property, other than that owned by the developer, will be affected by the proposed works,
     the construction engineer shall ensure that written notice has been given to the occupiers of such
     property at least 10 days prior to the start of works.

18       Construction Phase – Design Amendment (Alterations to an
         accepted final submission)
18.1           Prior to the start of the works, the construction engineer shall arrange and attend a
       ‘start-up’ meeting with the asset inspector

18.2       If construction has started, any requests for minor realignments of pipes, alterations to
       connections and relocation of access chambers and valves shall be discussed with the asset
       inspector. The asset inspector will provide guidance on these matters or may refer complex
       matters to be dealt with by the land servicing consultant

18.3           A copy of the meeting record shall be forwarded to the asset inspector within five days of
       the ‘start-up’ meeting occurring.

19       Construction Phase – Construction Requirements
19.1          During construction the construction engineer shall liaise with the asset inspector for any
       matters that arise. The construction engineer shall ensure:
             If a change of contractor becomes necessary, the construction engineer notifies the
               Corporation of the new contractor’s name and contact information.
             Any requirements by the Corporation regarding the contractor’s work are directed to
               the construction engineer and NOT to the contractor.
             Work shall be carried out in accordance with the requirements of the relevant technical
               manual or design standard, relevant acts and by-laws and this manual.
             The construction engineer shall ensure that the contractor is aware of, and agrees to
               comply with, the requirements of any authority in regard to the protection, diversion or
               relaying of any service affected by the works.
             The construction engineer shall ensure that the contractor is conversant with any
               agreement with any authority such as the Department of Aboriginal Affairs or
               Department for Planning and Infrastructure into which the design engineer, the
               developer or the Corporation may have entered for the works.

24       Developers’ Manual
Developers Manual

             The construction engineer shall ensure that the contractor verifies by survey the
              location and level of the point of connection of the works to the existing system.

19.2          Protection of Corporation Assets
       19.2.1 Corporation assets shall not be disturbed without the approval of the appropriate
         regional office on each and every occasion, OR excavation or construction work shall not be
         performed in close proximity to any existing Corporation asset until:
             A joint inspection of the asset has been performed by the Corporation and construction
               engineer to ascertain the condition of the asset, and
             The asset inspector has been given two working days’ notice of the intention to
               commence working.

       19.2.2 The construction engineer ensures adequate measures are taken to protect the
         Corporation’s assets from damage during construction of the works
       .
       19.2.3 If any damage occurs to existing assets, the construction engineer shall immediately
         notify the Corporation. The Corporation will assess the damage and advise what action is to
         be taken. This may include the developer being charged the costs to repair any damage.

19.3          Construction of Assets without All relevant approvals
Where the Corporation becomes aware that construction has commenced and due process has not
been followed, the following actions will result:
     19.3.1 The Corporation will instruct that works cease immediately. Should a cease work
         instruction not be complied with the Corporation may decline to accept any further
         involvement in the works.

       19.3.2 A third party certified assessment of the works already constructed will need to be
         provided, at the developers’ cost, for the Corporation’s review.

       19.3.3 The Corporation reserves the rights to refuse and accept the choice of the third party
         assessor.
       19.3.4 Where the third party assessment identifies non-compliance with the relevant standard,
         faults will need to be remedied where possible, or the works removed.

       19.3.5 Only after points 18.3.1 – 18.3.4 have been resolved and the requirements of any
         manual have been met, will works be able to recommence.

       19.3.6 The Corporation will not offer the availability of early clearance of subdivision conditions
         associated with these works.

       19.3.7 The Corporation may at its discretion decline to accept the involvement of the
         engineering consultant in future Corporation funded projects.

       19.3.8 The warranty (defects liability) period for the works will be increased to two years.

20      Construction Phase – Isolation of new works (wastewater only)
20.1           The purpose of isolating non-commissioned sewers from live sewers is to provide a safe
       working environment for construction, testing and inspection of the new work. Where the non-
       commissioned sewer system is not isolated from the live sewer, entry to and work within the
       new sewer system is subject to the provisions of Australian Standard AS.2865, ‘Safe working in
       a confined space’.

25      Developers’ Manual
Developers Manual

20.2           The construction engineer shall make the necessary arrangements for the new works to
       be isolated from the live sewer prior to the commencement of construction and ensure that the
       isolation is maintained until the final inspection clearance has been issued by the asset
       inspector.

20.3           The new works shall be either not connected (physical break) or shall be physically
       isolated from the live sewer. A physical break is the preferred method and should be used
       wherever practical.

20.4          Where a physical break is not practical, the construction engineer shall apply to the
       Corporation’s Building Services department to have the live sewer sealed off prior to
       construction and removed following the issue of the final inspection clearance of the works.

20.5          The Water Corporation will notify the construction engineer in writing when the line has
       been isolated (seal installed and ready for testing) and again when the isolation has been
       removed.

20.6          Where the live sewer has been plugged (150 or 225mm sewers), the construction
       engineer shall arrange for the plug to be tested to 50 kPa for one minute with no drop in
       pressure. The test shall be conducted on the ‘upstream’ side of the plug prior to any entry by
       Corporation staff. The test shall be logged in the construction engineer’s log of inspections and
       tests.

20.7           Where an isolation of a live sewer involves sealing with a plastic membrane and
       brickwork (sewers 300mm and above), it is the responsibility of the construction engineer to
       develop and administer a test plan over the period of isolation to ensure the integrity of the
       isolation.

21      Construction Phase – Inspection of works during construction
21.1          In general, inspections will not be undertaken by the Corporation during construction of
       the works; however the Corporation reserves the right to request an inspection at any time for
       the purposes of auditing compliance.

       21.1.1 The construction engineer shall make provision for access by Corporation officers or its
         representatives to inspect the works during construction when requested.

       21.1.2 The asset inspector (including additional staff) shall have access to the site at any time
         provided the construction engineer or contractor is on site.

       21.1.3 Inspections by the Corporation do not in any way relieve the construction engineer of
         the responsibility for ensuring that construction of the works is in accordance with the design
         documents and that it complies with the requirements of the technical manual or design
         standard.

       21.1.4 The construction engineer shall arrange for the provision of all personnel and
         equipment required for any scheduled inspection and testing.

21.2          Construction Engineer’s Log of Inspections and Tests
       21.2.1 The construction engineer shall arrange and undertake inspection and testing of the
         works to ensure that the requirements of the technical manual or design standard are
         satisfied. The construction engineer shall maintain a log of all inspections and tests
         undertaken, which shall be presented to the Corporation, if requested. The log shall record
         the following information:

26      Developers’ Manual
Developers Manual

             Inspections and/or tests witnessed by the construction engineer of the works, which
              were considered satisfactory. To this effect the construction engineer shall sign the
              following statement on the construction engineer’s log: “I am satisfied that the above
              inspection and tests have been carried out.”
             Inspections and / or tests witnessed by the construction engineer of the works, which
              were considered unsatisfactory.
             Any remedial action undertaken to the works as a result of an unsatisfactory inspection
              prior to re-inspection.

       21.2.2 A copy of the construction engineer’s inspection log and test results shall be submitted
         to the asset inspector prior to a final inspection being undertaken. The log shall include but
         not be limited to the date, time, item tested, type of test, result of test and the name of the
         witness.

21.3         Site Safety
       21.3.1 Asset inspectors will comply with the contractor’s site safety procedures while on site.

       21.3.2 Asset inspectors will not enter sites that they consider unsafe by Worksafe Standards.

       21.3.3 Where safety issues relating to the inspection cannot be resolved between the
         construction engineer and the asset inspector they shall be referred to Worksafe for
         advice/resolution.

21.4         Pre-Handover Inspection and booking of a final inspection
       21.4.1 At least two (2) weeks prior to a planned final inspection date the
         construction engineer shall contact the Corporation’s inspections contact and make a
         tentative booking for a final inspection.

       21.4.2 The construction engineer shall then confirm and book a final inspection giving a
         minimum of 5 business days notice.

       21.4.3 Prior to confirming a booking for a final inspection the construction engineer shall
           undertake a pre-handover inspection.

       21.4.4 A pre-handover inspection checklist shall be completed by the construction engineer
         and provided to the asset inspector with all test logs at the time of confirming a final
         inspection date.

21.5         Final Inspection
       21.5.1 When the works have been completed and the construction engineer has conducted a
         pre-handover inspection, the construction engineer shall arrange a final inspection with the
         asset inspector.

       .The asset inspector will inspect the works with the construction engineer in attendance.

       21.5.2 Where the number and/or seriousness of non-conformances indicate that the pre-
         handover inspection has been inadequate the asset inspector shall terminate the final
         inspection and require the construction engineer to carry out further inspection of the works
         before booking another final inspection. A fee may be charged to the developer where a pre-
         handover inspection is deemed to have been inadequate.

27      Developers’ Manual
Developers Manual

       21.5.3 Where the works are deemed to be acceptable the asset inspector shall arrange for a
         final inspection clearance to be issued to the construction engineer.

22      Construction Phase – Connecting to existing assets
22.1          Connections or alterations required to the Corporation’s existing infrastructure as a result
       of new works shall be made by prior arrangement with the Corporation. All such work shall be at
       the developer’s expense.

22.2           The construction engineer shall make the necessary arrangements for the payment of
       fees for the connection of the new works to the existing assets.

22.3          When the works are deemed to be acceptable, the asset inspector shall initiate the
       connection of the works upon the request from the construction engineer.

22.4         Works will not be connected to existing assets until payment of all associated fees has
       been made and a final inspection clearance has been issued.

23      Takeover Phase – As-Constructed drawings
23.1           The as-constructed drawings shall be certified "as-constructed", signed and dated by the
       design engineer, the construction engineer and by the surveyor (who is eligible for membership
       of I.E.M.S.A. or I.S.A.) responsible for the survey. The as-constructed drawings shall be in
       accordance with the relevant technical manual, design standard or this manual.

23.2          The completed and signed as-constructed submission shall be submitted to the as-
       constructed submission contact.

23.3        All as-constructed plans shall clearly display the Planset number which shall have the
     bundle number revised to indicate that it is an as-constructed plan, as per DS 80.
23.4        One copy of the as-constructed submission shall be submitted except where specified
     below.

23.5         As-constructed Information for Water works
        The as-constructed information shall consist of:
       23.5.1 The as-constructed plan in accordance with the typical information provided in Water
         Corporation Design Standard 60 or 63.

       23.5.2 A precalculated cadastral plan for areas which are not sewered, in electronic form
         whenever possible and particularly for large areas; otherwise a hard copy for small
         subdivisions.

       23.5.3 A copy of the final new works site inspection report.

23.6         As-constructed Information for Wastewater works
       23.6.1 The as-constructed plan in accordance with the typical information provided at
         Appendix 9 of this manual.

28      Developers’ Manual
Developers Manual

       23.6.2 All aspects of Section 6 of Design Standard 50 must be complied with, other than the
         as-constructed plan mentioned at 22.5.1. replacing all references to field notes.

       23.6.3 A precalculated cadastral plan, in electronic form whenever possible and particularly for
         large areas; otherwise a hard copy for small subdivisions.

       23.6.4 A copy of the final new works inspection report.

       23.6.5 A contour plan if earthworks have been carried out that has changed a contour by 0.5
         metre or more.

24      Takeover Phase – Takeover of the works

24.1         Requirements for takeover
Subject to connection to the existing system being available, takeover is achieved when:
     24.1.1 A final inspection has been completed and a final inspection clearance has been issued
         by the asset inspector.

       24.1.2 The construction engineer has certified that the works have been constructed in
         accordance with the documents accepted by the Corporation and the requirements of the
         technical manual or design standard.
       .
       24.1.3 The construction engineer has certified that restoration has been performed to the
         satisfaction of any affected property owner and authorities.

24.2        Date of Takeover
The Corporation will notify the developer in writing that takeover has been achieved.

The date the Corporation takes over the works will be the date that final inspection clearance has
been issued
25      Takeover Phase – Warranty Period
25.1          The warranty period shall commence on the date of take-over.

25.2          The warranty period shall be for one year.

25.3         During the warranty period, the Corporation shall be responsible for operational
       maintenance of the Works.

25.4          Remedial repairs during warranty
       25.4.1 During the warranty period the developer shall be responsible for ensuring that
         satisfactory remedial repairs arising from faulty design, workmanship or materials are carried
         out. The cost of any consequential damage and claims resulting from such defects shall be
         charged to the developer.

       25.4.2 During the warranty period, the Corporation may, at its discretion carry out remedial
         repairs where the fault affects the service to customers and/or public safety. The Corporation
         will notify the developer of the work carried out as soon as practicable where the remedial
         repairs are attributable to the construction of the works. The cost of the remedial repairs shall
         be charged to the developer.

29      Developers’ Manual
You can also read