Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk

Page created by Michelle Perry
 
CONTINUE READING
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Melbourne Airport
                       AGL Upgrade Project

Presented by Peter Parsons and Scott Bailey-Erturk
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
1   Background to Melbourne Airport

2   Project Objectives

3   Scope and Design Solutions

4   Key Challenges

5   What's Next

            AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Background to
Melbourne Airport

  AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Background to Melbourne Airport
• Second Busiest Airport in Australia
• Curfew free (24 hours Operations)
Pre-Covid
• Total Annual Passengers ~37 million
• Total Annual Freight ~450,000 tonnes
• Total Annual Aircraft Movement ~250,000
• Greater than 600 movements per day
• Up to 60 movements per hour
Current
• 45% pre Covid Passenger Numbers
• 65% of pre Covid Aircraft Movements
                 AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Background to Melbourne Airport

          AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Background to Melbourne Airport
Airfield Lighting Facts – Melbourne Airport
• Over 6,000 Aeronautical Ground Lights
• 700 kilometres of underground cable
• 5 Standby Diesel Generators (400 – 440 KVA)
      • Providing 15 second backup power in VMC
      • Providing 1 second backup power in LVP
      • Generators run as primary source of supply during LVP
• 5 Airfield Lighting Equipment Rooms (ALER)
• Every nut and bolt on the runways are torque checked every 4 months
  using MALMS Torque Solution together with MALMS Engineer
• Every light on the runway is photometric tested on a monthly basis to
  ensure compliance using MALMS Mobile
• Australia's first CAT IIIB aerodrome - 2009
      • Aircraft can land in visibility down to 50m RVR (RWY 16)

                   AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Project
Objectives

  AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Project Objectives
   Compliance
   -   Achieve CAT III spacing on all taxiways (Allows operations down to 50m visibility)
   -   Replace strobe lighting on Runway 34 with Runway Threshold Identification Lights
   -   Standardisation of AGL system design

   Safety
   -   Improved safety for AGL maintenance staff
   -   New earthing system
   -   Reduce primary voltage down to less than 1000 volts (Avoids HV classification)

   Embrace New Technology
   LED Lights
   -   Reduced energy consumption
   -   Longer between failures
   -   Reduction in OPEX
   ILCMS
   -   Reduced operational impacts to facilitate closure of aircraft movement area
   -   Increase maintenance efficiency
   -   Significant reduction in system maintenance and inspection requirements.

                    AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Project Team
                                                     Client – Airport Operator

                                                     Project Management

                                                     Design, Equipment Supply and Software

                                                     Contractor (Supported by ADB)

                                Key Stakeholders
                                      APAM operations            Airservices

                                              CASA                Airlines

AAA Pavement & Lighting Forum 26th May 2021
Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
Delivery Program
                                                  2018                                                                    2019                                                                    2020                                                                    2021                                      2022
                          Q1                Q2                Q3                Q4                Q1                Q2                Q3                Q4                Q1                Q2                Q3                Q4                Q1                Q2                Q3                Q4                Q1

                                                                                                                                                                                                                                                                    May
                                            May

                                                                                                                    May

                                                                                                                                                                                            May
                                                              Aug

                                                                                                                                      Aug

                                                                                                                                                                                                              Aug

                                                                                                                                                                                                                                                                                      Aug
                                                                                Nov

                                                                                                                                                        Nov

                                                                                                                                                                                                                                Nov

                                                                                                                                                                                                                                                                                                        Nov
                                                                    Sep

                                                                                                                                            Sep

                                                                                                                                                                                                                    Sep

                                                                                                                                                                                                                                                                                            Sep
                                                                                      Dec

                                                                                                                                                              Dec

                                                                                                                                                                                                                                      Dec

                                                                                                                                                                                                                                                                                                              Dec
                          Feb

                                                                                                  Feb

                                                                                                                                                                          Feb

                                                                                                                                                                                                                                                  Feb

                                                                                                                                                                                                                                                                                                                          Feb
                                Mar

                                                  Jun

                                                                                                        Mar

                                                                                                                          Jun

                                                                                                                                                                                Mar

                                                                                                                                                                                                  Jun

                                                                                                                                                                                                                                                        Mar

                                                                                                                                                                                                                                                                          Jun

                                                                                                                                                                                                                                                                                                                                Mar
                    Jan

                                                                                            Jan

                                                                                                                                                                    Jan

                                                                                                                                                                                                                                            Jan

                                                                                                                                                                                                                                                                                                                    Jan
                                      Apr

                                                                                                              Apr

                                                                                                                                                                                      Apr

                                                                                                                                                                                                                                                              Apr
                                                                          Oct

                                                                                                                                                  Oct

                                                                                                                                                                                                                          Oct

                                                                                                                                                                                                                                                                                                  Oct
                                                        Jul

                                                                                                                                Jul

                                                                                                                                                                                                        Jul

                                                                                                                                                                                                                                                                                Jul
                    Scoping &Concept
                         Design
                        5 Months
          Design                                                    Schematic & Detailed
                                                                          Design
                                                                       10 Months

                                                                                                                                Equipment Supply –
                                                                                                                                Long Lead Delivery
                                                                                                                                 18 Months
    Procurement /                                                                                  Construction
           Tender                                                                                 Tender Process
                                                                                                       4M

                                                                                                                          Early Works
                                                                                                                             2M
                                                                                                                                                                                              Main Works
                                                                                                                                                                                            21 Months
     Construction                                                                                                                                                                                                                                                                     Commissioning
                                                                                                                                                                                                                                                                                       Smart System
                                                                                                                                                                                                                                                                                         6 Months

                                                                                                                                                                                 Vic 1st                Vic 2nd                                                           Current
                                                                                                                                                                                 Lock                   Lock                                                              Status
                                                                                                                                                                                 Down                   Down

             AAA Pavement & Lighting Forum 26th May 2021
Scope and
Design Solutions

  AAA Pavement & Lighting Forum 26th May 2021
Scope
•   ~3,000 new LED lights and transformers
•   ~250km new primary cabling (screened)
•   ~200km new secondary cabling
•   ~180 new SIT pits
•   ~180km earthing cabling
•   ~1,000 new earthing pits
•   18 new CCRs
•   Upgraded Safecontrol software

Not in scope
• Areas impacted by Taxiway Zulu Project (sections
  of Taxiway Echo and Alpha)
• Areas impacted by Melbourne Airport’s Third
  Runway Program (Runway 09-27)

                  AAA Pavement & Lighting Forum 26th May 2021
Solution
•   AGL fittings - (SafeLED IQ – programable for ILCMS)
•   Mounting equipment                                                                   Locations
                                                                                          Locationsof
                                                                                                    ofIHP’s
                                                                                                       IHP’sininthe
                                                                                                                 thedesign
                                                                                                                     design
          •   Inset fixtures: Shallow side entry base, reuse of existing bases where practicable
          •   Elevated (Wing bar lights and RTIL): New base plate with frangible coupling to achieve mechanical frangibility
              requirement
•   Secondary cables: 6mm2 or 4mm2 secondary wire
          •   Either in existing conduits, slots in pavement or in pavement joints
•   AGL series isolating transformers
          •   New low attenuation transformers to support power line communications
•   Primary series circuits
          •   Maximum 1000V to avoid HV classification
          •   Interleaving all circuits
          •   Screened cables for power line communication
•   New constant current regulators
          •   Pure sine wave CRE
•   ILCMS equipment
          •   Addressable switching unit at each individual light
          •   Additional SCM cabinets in each ALER

                         AAA Pavement & Lighting Forum 26th May 2021
Products - Lights

Taxiway Lighting
Taxiway Centreline Lights
Intermediate Hold Position Lights
Runway Lead on Lights
Runway Lead off Lights
Runway Stop Bar Lights (Existing LED and ILCMS)

Runway Lighting
Runway Threshold Identification Lights
Runway Threshold/End Lights
Runway Threshold Wing Bar Lights
Runway Centreline Lights
Runway Touchdown Zone Lights
Runway Edge Lights
Approach lighting (Existing LED and ILCMS)

                  AAA Pavement & Lighting Forum 26th May 2021
Typical works
                                                              New Earth Pit

 New Wing Bar Lights

             New LED                                          Re-spacing Lights
 Threshold/End Lights
      (existing bases)                                        New Secondary Slots
                                                              On pavement
          New RTIL
                                                              New Secondary Trench
                                                              Off pavement
       New LED Lead                                           New LED Lead
       On Light using                                         Off Light using
       existing base                                          existing base

                AAA Pavement & Lighting Forum 26th May 2021
Halogen Vs LED

        AAA Pavement & Lighting Forum 26th May 2021
Earthing Solution                                                                                 Single LED
                                                                                                     Light
                                                                                                                             Single LED
                                                                                                                                Light
•   Typically SELV in Australia to date
•   Global trend moving towards PELV (protective extra-low voltage)
                       Airfield Lighting
                       Equipment Room                                              Transformer Pit             Transformer Pit
                                                                    SCM
                                                                           Com
                                                                           . Tr.

                                 CCR                          SFU
                                                                    SIT.                  SIT.                        SIT                       SIT.

                                                 SCI

                                                       SCI

                                    Earth Bar                                         Earth Bar                                     Earth Bar

                                                Earth Stake                                             Earth Stake              Earth Stake

                  AAA Pavement & Lighting Forum 26th May 2021
Intermediate Holding Positions (IHP’s)

                                                                       Locations of IHP’s in the design

Intermediate holding position markings are provided at the location
of a Taxiway/Taxiway intersection to support ATC in aircraft holding

                       AAA Pavement & Lighting Forum 26th May 2021
Major Control System Update

         AAA Pavement & Lighting Forum 26th May 2021
Airfield Lighting Control and Monitoring System
– Benefits of moving to ILCMS
• Real time feedback from each light individually (on/off or in fault)
• Ability to extinguish individual lights on a circuit (MOWP stages)
• Ability to set parameters for sections of Taxiways or Runways for downgrade warnings/alarms
• Integrated with Airservices INTAS system

     Photo of Safecontrol
     with LMS turned on

                 AAA Pavement & Lighting Forum 26th May 2021
Key
Challenges

  AAA Pavement & Lighting Forum 26th May 2021
Covid-19 Impacts

Negative Impacts
-   Uncertainty around Melbourne Airport Capital Plan and which
    project would proceed
         - FY21 pre Covid plan was ~$1B. At the end of FY21 we are
             forecast to spend ~$300M
         - Majority of capacity related projects were cancelled or put
             on hold
         - Available spend fluctuated throughout FY21
-   Lockdowns
         - Vic restrictions on construction sites (reduce workforce to
             25%), managed to secure exemption from Chief Health
             Officer due to critical nature of the works
-   Aircraft operations we did have were valuable
-   Parked aircraft made access to taxiways difficult
-   Difficulty in bringing in construction staff from inter-state

Positive Impacts
-   Improved access due to reduced traffic
-   Reduced need for night works (improved safety)

                      AAA Pavement & Lighting Forum 26th May 2021
Construction Staging
- 92 Individual Works Stages
- Most areas returned to service after each shift

              AAA Pavement & Lighting Forum 26th May 2021
Approvals
Airspace – Prescribed Airspace (OLS and                            Environmental approvals
PANSops)                                                           • Minimise impact to Natural Temperate Grassland of the
Lead time for runway closures 4-5 Months                             Victorian Volcanic Plain (NTGVP) – threatened ecology
                                                                   • Part-13 permit for disturbance areas under the
As a leased Commonwealth airport, Melbourne Airport is
                                                                     Environmental Protection and Biodiversity Conservation
subject to the Airports Act 1996 (Cth) (Airports Act) and the
                                                                     Action 1999
Airports (Protection of Airspace) Regulations 1996 (Cth)
(Airports Airspace Regulations).
Part 12 of the Airports Act and the Airports Regulations
establish a framework for the designation and protection
of prescribed airspaces at, and around, airports.

- Identify works area, verify impacts, consider
  mitigations
- Application submitted to Airservices (~6 Weeks)
- Application then submitted to CASA (~6 Weeks)
- Final submission to the Department -28 Days

                     AAA Pavement & Lighting Forum 26th May 2021
What's Next

  AAA Pavement & Lighting Forum 26th May 2021
Follow the Green
• An ILCMS system incorporated into a ALCMS system, is Follow the Green Ready.
• What is Follow the Green?
  • As the name suggests – follow the green taxiway lighting from runway to gate though intelligent routing and
    guidance
• Different levels of FtG
  • From basic – designated lit routes from runway to the apron area - all other lighting turned off
  • Through to a fully automatic system – The ALCMS knowing the aircraft position via input from Airservices
    Advanced Surface Movement Guidance and Control System (A-SMGCS), the centreline lighting illuminates
    ahead of the aircraft directing the pilot to the gate, with the lighting extinguished behind the aircraft
• Benefits of FtG
  • Provides one lit taxi route for pilots to follow removing multiple options at taxiway intersections
  • Less chance of taking incorrect taxiways
  • Reduced radio traffic
  • Reduces fuel burn

                   AAA Pavement & Lighting Forum 26th May 2021
Follow the Green

         AAA Pavement & Lighting Forum 26th May 2021
Questions

    AAA Pavement & Lighting Forum 26th May 2021
You can also read