Melbourne Airport AGL Upgrade Project - Presented by Peter Parsons and Scott Bailey-Erturk
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
1 Background to Melbourne Airport 2 Project Objectives 3 Scope and Design Solutions 4 Key Challenges 5 What's Next AAA Pavement & Lighting Forum 26th May 2021
Background to Melbourne Airport • Second Busiest Airport in Australia • Curfew free (24 hours Operations) Pre-Covid • Total Annual Passengers ~37 million • Total Annual Freight ~450,000 tonnes • Total Annual Aircraft Movement ~250,000 • Greater than 600 movements per day • Up to 60 movements per hour Current • 45% pre Covid Passenger Numbers • 65% of pre Covid Aircraft Movements AAA Pavement & Lighting Forum 26th May 2021
Background to Melbourne Airport Airfield Lighting Facts – Melbourne Airport • Over 6,000 Aeronautical Ground Lights • 700 kilometres of underground cable • 5 Standby Diesel Generators (400 – 440 KVA) • Providing 15 second backup power in VMC • Providing 1 second backup power in LVP • Generators run as primary source of supply during LVP • 5 Airfield Lighting Equipment Rooms (ALER) • Every nut and bolt on the runways are torque checked every 4 months using MALMS Torque Solution together with MALMS Engineer • Every light on the runway is photometric tested on a monthly basis to ensure compliance using MALMS Mobile • Australia's first CAT IIIB aerodrome - 2009 • Aircraft can land in visibility down to 50m RVR (RWY 16) AAA Pavement & Lighting Forum 26th May 2021
Project Objectives Compliance - Achieve CAT III spacing on all taxiways (Allows operations down to 50m visibility) - Replace strobe lighting on Runway 34 with Runway Threshold Identification Lights - Standardisation of AGL system design Safety - Improved safety for AGL maintenance staff - New earthing system - Reduce primary voltage down to less than 1000 volts (Avoids HV classification) Embrace New Technology LED Lights - Reduced energy consumption - Longer between failures - Reduction in OPEX ILCMS - Reduced operational impacts to facilitate closure of aircraft movement area - Increase maintenance efficiency - Significant reduction in system maintenance and inspection requirements. AAA Pavement & Lighting Forum 26th May 2021
Project Team Client – Airport Operator Project Management Design, Equipment Supply and Software Contractor (Supported by ADB) Key Stakeholders APAM operations Airservices CASA Airlines AAA Pavement & Lighting Forum 26th May 2021
Delivery Program 2018 2019 2020 2021 2022 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 May May May May Aug Aug Aug Aug Nov Nov Nov Nov Sep Sep Sep Sep Dec Dec Dec Dec Feb Feb Feb Feb Feb Mar Jun Mar Jun Mar Jun Mar Jun Mar Jan Jan Jan Jan Jan Apr Apr Apr Apr Oct Oct Oct Oct Jul Jul Jul Jul Scoping &Concept Design 5 Months Design Schematic & Detailed Design 10 Months Equipment Supply – Long Lead Delivery 18 Months Procurement / Construction Tender Tender Process 4M Early Works 2M Main Works 21 Months Construction Commissioning Smart System 6 Months Vic 1st Vic 2nd Current Lock Lock Status Down Down AAA Pavement & Lighting Forum 26th May 2021
Scope and Design Solutions AAA Pavement & Lighting Forum 26th May 2021
Scope • ~3,000 new LED lights and transformers • ~250km new primary cabling (screened) • ~200km new secondary cabling • ~180 new SIT pits • ~180km earthing cabling • ~1,000 new earthing pits • 18 new CCRs • Upgraded Safecontrol software Not in scope • Areas impacted by Taxiway Zulu Project (sections of Taxiway Echo and Alpha) • Areas impacted by Melbourne Airport’s Third Runway Program (Runway 09-27) AAA Pavement & Lighting Forum 26th May 2021
Solution • AGL fittings - (SafeLED IQ – programable for ILCMS) • Mounting equipment Locations Locationsof ofIHP’s IHP’sininthe thedesign design • Inset fixtures: Shallow side entry base, reuse of existing bases where practicable • Elevated (Wing bar lights and RTIL): New base plate with frangible coupling to achieve mechanical frangibility requirement • Secondary cables: 6mm2 or 4mm2 secondary wire • Either in existing conduits, slots in pavement or in pavement joints • AGL series isolating transformers • New low attenuation transformers to support power line communications • Primary series circuits • Maximum 1000V to avoid HV classification • Interleaving all circuits • Screened cables for power line communication • New constant current regulators • Pure sine wave CRE • ILCMS equipment • Addressable switching unit at each individual light • Additional SCM cabinets in each ALER AAA Pavement & Lighting Forum 26th May 2021
Products - Lights Taxiway Lighting Taxiway Centreline Lights Intermediate Hold Position Lights Runway Lead on Lights Runway Lead off Lights Runway Stop Bar Lights (Existing LED and ILCMS) Runway Lighting Runway Threshold Identification Lights Runway Threshold/End Lights Runway Threshold Wing Bar Lights Runway Centreline Lights Runway Touchdown Zone Lights Runway Edge Lights Approach lighting (Existing LED and ILCMS) AAA Pavement & Lighting Forum 26th May 2021
Typical works New Earth Pit New Wing Bar Lights New LED Re-spacing Lights Threshold/End Lights (existing bases) New Secondary Slots On pavement New RTIL New Secondary Trench Off pavement New LED Lead New LED Lead On Light using Off Light using existing base existing base AAA Pavement & Lighting Forum 26th May 2021
Halogen Vs LED AAA Pavement & Lighting Forum 26th May 2021
Earthing Solution Single LED Light Single LED Light • Typically SELV in Australia to date • Global trend moving towards PELV (protective extra-low voltage) Airfield Lighting Equipment Room Transformer Pit Transformer Pit SCM Com . Tr. CCR SFU SIT. SIT. SIT SIT. SCI SCI Earth Bar Earth Bar Earth Bar Earth Stake Earth Stake Earth Stake AAA Pavement & Lighting Forum 26th May 2021
Intermediate Holding Positions (IHP’s) Locations of IHP’s in the design Intermediate holding position markings are provided at the location of a Taxiway/Taxiway intersection to support ATC in aircraft holding AAA Pavement & Lighting Forum 26th May 2021
Major Control System Update AAA Pavement & Lighting Forum 26th May 2021
Airfield Lighting Control and Monitoring System – Benefits of moving to ILCMS • Real time feedback from each light individually (on/off or in fault) • Ability to extinguish individual lights on a circuit (MOWP stages) • Ability to set parameters for sections of Taxiways or Runways for downgrade warnings/alarms • Integrated with Airservices INTAS system Photo of Safecontrol with LMS turned on AAA Pavement & Lighting Forum 26th May 2021
Key Challenges AAA Pavement & Lighting Forum 26th May 2021
Covid-19 Impacts Negative Impacts - Uncertainty around Melbourne Airport Capital Plan and which project would proceed - FY21 pre Covid plan was ~$1B. At the end of FY21 we are forecast to spend ~$300M - Majority of capacity related projects were cancelled or put on hold - Available spend fluctuated throughout FY21 - Lockdowns - Vic restrictions on construction sites (reduce workforce to 25%), managed to secure exemption from Chief Health Officer due to critical nature of the works - Aircraft operations we did have were valuable - Parked aircraft made access to taxiways difficult - Difficulty in bringing in construction staff from inter-state Positive Impacts - Improved access due to reduced traffic - Reduced need for night works (improved safety) AAA Pavement & Lighting Forum 26th May 2021
Construction Staging - 92 Individual Works Stages - Most areas returned to service after each shift AAA Pavement & Lighting Forum 26th May 2021
Approvals Airspace – Prescribed Airspace (OLS and Environmental approvals PANSops) • Minimise impact to Natural Temperate Grassland of the Lead time for runway closures 4-5 Months Victorian Volcanic Plain (NTGVP) – threatened ecology • Part-13 permit for disturbance areas under the As a leased Commonwealth airport, Melbourne Airport is Environmental Protection and Biodiversity Conservation subject to the Airports Act 1996 (Cth) (Airports Act) and the Action 1999 Airports (Protection of Airspace) Regulations 1996 (Cth) (Airports Airspace Regulations). Part 12 of the Airports Act and the Airports Regulations establish a framework for the designation and protection of prescribed airspaces at, and around, airports. - Identify works area, verify impacts, consider mitigations - Application submitted to Airservices (~6 Weeks) - Application then submitted to CASA (~6 Weeks) - Final submission to the Department -28 Days AAA Pavement & Lighting Forum 26th May 2021
What's Next AAA Pavement & Lighting Forum 26th May 2021
Follow the Green • An ILCMS system incorporated into a ALCMS system, is Follow the Green Ready. • What is Follow the Green? • As the name suggests – follow the green taxiway lighting from runway to gate though intelligent routing and guidance • Different levels of FtG • From basic – designated lit routes from runway to the apron area - all other lighting turned off • Through to a fully automatic system – The ALCMS knowing the aircraft position via input from Airservices Advanced Surface Movement Guidance and Control System (A-SMGCS), the centreline lighting illuminates ahead of the aircraft directing the pilot to the gate, with the lighting extinguished behind the aircraft • Benefits of FtG • Provides one lit taxi route for pilots to follow removing multiple options at taxiway intersections • Less chance of taking incorrect taxiways • Reduced radio traffic • Reduces fuel burn AAA Pavement & Lighting Forum 26th May 2021
Follow the Green AAA Pavement & Lighting Forum 26th May 2021
Questions AAA Pavement & Lighting Forum 26th May 2021
You can also read