Market dialogue on market area merger - Essen, 12 February 2020
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Agenda 13:00 Welcome and introduction Ralph Bahke, ONTRAS Gastransport GmbH Dr Heiko Lohmann 13:15 Kap+ and KOMBI Jürgen Fuhlrott, Open Grid Europe GmbH 14:00 Coffee break 14:30 Operational issues relating to the Torsten Frank, NetConnect Germany market area managers GmbH & Co. KG Dr Sebastian Kemper, GASPOOL Balancing Services GmbH around 16:00 End of event 3
33rd Madrid Forum } Trigger } Impact on 24 January 2020 } Outlook 34th Madrid Forum; 29/30 April 2020 5
KAP+ and KOMBI Interconnected and goal-orientated 7
KAP+ (BK7-19-037) – Status I } What happened so far? } 23.05.2019 – Opening decision ("Einleitungsverfügung") } 05.07.2019 – End of 1st consultation period } 01.10.2019 – Presentation of concept } 08.11.2019 – End of 2nd consultation period } 03.12.2019 – Submission of the process description } 24.01.2020 – End of consultation with neighbouring Member States } 10.02.2020 – Start of hearing of party to the proceedings } 21.02.2020 – End of hearing 8
KAP+ (BK7-19-037)- Status II } Design of decision tenor } Cancellation of decision BK7-13-019 from 20.09.2013 for the duration of the test phase, in order to enable the offering of overbooking capacities } The TSO concept for the overbooking an rebuying system (incl. process description MBI and capacity buy-back) is approved with the following changes } No price cap for MBI and capacity buy-back } In case of capacity buy-back the prohibition of network harmful renominations does only occur, if a threat for the network integrity is expected according to estimation of the TSO } Additional capacity can be offered for 2 years } Acceptance of costs is decided by KOMBI } In addition following regulations apply } Information about offered additional capacity to BNetzA yearly until 1 May } Submission of a joint report on the usage of MBI and capacity buy-back until 1.12 every year (first-time 1.12.2022) 9
KOMBI (BK9-19-606) – Status } What happened so far? } 16.10.2019 – Start of process } 20.12.2019 – Publication of draft decision } 28.01.2020 – Comment by gas TSOs on the draft decision } 31.01.2020 – End of consultation period } What is still unresolved? } Recognition of MBI and buy-back costs as volatile or permanently non-controllable costs } Reference to unbiassed review of this matter for the period after the test phase planned for KAP+ } What happens next? } Wait for draft decision 10
Annual auctions from 2020 Annual auction Offer for additional capacity Comments Period prior to market GY 2020/2021: no additional capacity area merger Probably the first GY GY 2021/2022: additional capacity after the market area merger GY 2021/2022: additional capacity GY 2022/2023: additional capacity GY 2023/2024: additional capacity } Decisions on KAP+ and KOMBI required } Additional capacity offer must come from the individual TSOs } During the test phase, the additional capacity will be offered for one GY only } Total capacity offered is expected to be in line with 2018 NDP 11
Operational issues relating to the market area managers
Agenda 1. Introduction 2. Update on network balancing 3. Update on levies 4. (Biogas) balancing groups and network accounts 5. Traders’ Christmas wish list for the new MAM 13
Introduction
One year into the implementation project... Review and outlook Status overview; First information e.g. on … balancing groups and network accounts Start of MAM Publication of Market dialogue Market dialogue implementation project the name THE in Düsseldorf in Berlin Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2019 2019 2019 2019 2020 2020 2020 2020 2021 2021 2021 2021 Market dialogue Market dialogue Market dialogue Planned start of in Essen in Berlin in Essen THE market area Implementation project presented for the first time; Status overview; Presentation of THE logo Overview of questions to be clarified 15
MAM project status } Overall, the MAM project is making good progress } Progress is in line with the respective timetables } The requirements to be met by the future THE systems have been recorded and described } The selection process for the IT systems required has been completed } The contracts have been awarded and the programming work has started } The MAMs still have to make a multitude of operational process decisions, which may have an impact on the implementation of the IT systems } Hence, further market and BNetzA involvement is planned where it makes sense and is possible 16
Update on network balancing
Future network operator areas / balancing zones Today’s 11 network operator areas / balancing zones (zones) are to be left unchanged: H-gas zones L-gas zones GSC GTG GUD GUD Central ("Mitte") NWG North (“Nord") East (“Ost") ONTRAS West South (“Süd") 18
Future portfolio of exchange products Expected use of short-term exchange products (MOL 1 and 2) Within Day/Day Ahead/Bank Holiday Hour Global Global* H-Gas L-Gas L-Gas* TTF TTF H-gas zones (GSC, GUD, Mitte, Nord, ONTRAS, Süd) L-gas zones (GTG, GUD, NWG, Ost, West) L-gas zones (Ost, West, GUD**) * Hourly products (if any) will be shown and traded by THE as ‘flat’ products (“Bandprodukt”) ** Used temporarily use as part of the L/H-gas conversion 19
Future portfolio of bilateral products Bilateral products likely to be used (MOL 4) Long-Term Options Short-Term Balancing Services Short-Call Balancing Services Flexibility Services 20
Update on balancing neutrality charges
Planning model for balancing neutrality accounts } There are some structural differences between the two market areas } These differences include in particular the network topology and the market/customer situation (e.g. SLP vs. RLM vs. EXITSO) } As a result, there are different approaches to implementing GaBi Gas and Konni Gas under the existing decisions } In a future joint market area, these different aspects will be brought together in a common planning approach } This will result in some overall changes compared with the current (still separate) balancing neutrality calculations. The exact impact of these changes cannot be predicted at this stage. } The balancing neutrality charges applicable to THE for the first time during the 2021/2022 period will be published in August 2021 in accordance with regulatory requirements 22 12.02.2020
Merging of the balancing neutrality accounts } All balancing neutrality account balances will be transferred to THE’s balancing neutrality accounts at the end of the 2020/2021 balancing neutrality period } The existing balances will be the starting balances for THE balancing neutrality accounts } The new THE balancing neutrality accounts will be continued after 1 Oct. 2021 in accordance with the provisions of the GaBi Gas and Konni Gas rulings, as amended } The MAMs will liaise with BNetzA (among others) to ensure that the balancing neutrality accounts are merged in a way that complies with GaBi Gas and Konni Gas requirements 23
(Biogas) balancing groups and network accounts Balancing group management from October 2021
Dealing with balancing groups: Existing balancing groups receive new nomenclature GPL THE NCG THE 1 Jun 2021 1 Oct 2021 } All balancing group contracts will remain in place and will be transferred to the Trading Hub Europe } The balancing group designations of the old balancing groups will be migrated to the new nomenclature } The contracts for connecting balancing groups will be remain in force will be transferred Impact on BGMs: } BGMs with business activities in both market areas can decide for themselves which contracts they want to continue } BGMs may have to adjust BG connection à Obligation to connect H- and L-gas balancing groups Impact on network operators: } Old BG designation can be used until 30 Sep 2021 or longer for periods prior to 1 Oct 2021 } New BGs may not have to be communicated via the GeLi-Gas process because a mapping list will be published 25
Traders' proposals for continuing the balancing groups } Following the market area merger, the balancing groups of NCG and GPL will be continued under a new nomenclature à current mandate for project } The following alternative implementation proposals were made from within the group of traders: n-to-one mapping: A BGM can (but does not have to) merge NCG and GPL balancing groups in advance but will then have to independently (re-)structure the BG hierarchy. Traders who do not make use of this option will continue to be governed by the one-to-one mapping arrangements: i.e. no obligation to take action. 26 05.11.2019
MAMs' proposals for continuing the balancing groups } First step: Direct migration of the GPL and NCG BGs to the new THE BG nomenclature } The BGMs will have the opportunity to reorganise their balancing group structures during the period from 1 Jun to 1 Aug 2021 (GeLi deadlines to be observed) before the start of the THE market area } Every BGM will see the migration table in the THE Portal along with an overview of all valid BGs } The THE Portal will offer the option to terminate BGs and SBGs no longer needed (which will require an additional agreement) or to enter into new BGs and SBGs } Furthermore, there will be the option to terminate and then re-establish BG connections } Market locations will have to be allocated to BGs/SBGs using the regular master data change process (UTILMD) via the shipper-to-network operator route } The MAM can no longer intervene in contractual relationships, which means: } no transfers from SBG to another BG } BG connections can only be changed by the BGMs affected 27
(Biogas) balancing groups and network accounts Biogas balancing group management from October 2021
Dealing with balancing groups: Existing biogas balancing groups receive new nomenclature Dealing with biogas bálancing groups in balancing period 2021 • Existing NCG and GPL biogas balancing groups receive new THE biogas balancing nomenclatur as of 1 October • Biogas balancing group managers are able to check existing balaincing group linkings and reassign as of 1 June 2021. Constructs of the two market areas can brought together in order to follow the provisions of KONNi Gas • Important on biogas balancing groups (in contrast to natural gas balancing groups) is,that the biogas balancing period is usually one calender year and the year 2021 therefore includes three market areas (1 January to 1 October NCG/GPL and 1 October to 1 January THE) • Due to the continuation of the biogas balancing groups in the THE market area and due to the possible balancing group linking (as of 1 October 2021) the following settlement process with regard to the billing is aspired: • One balancing period for 2021 • One flexibility transmission process • One settlement of the biogas balancing groups for 2021 (price for the settlement of conversion fee, overrun of flexibility frame and end balance in vote) • Biogas balancing groups with balancing period gas year are going to be settled per market area 29
(Biogas) balancing groups and network accounts Network account management from October 2021
Network account migration: New network account also valid for old periods Special feature: market area overlaps ("MGÜ") THE nomenclature GPL Migration of billing data NCG/GPL THE "data" "data" THE nomenclature Migration of billing data NCG 1 Oct 2021 1 Jun 2021 1 Oct 2021 } Trading Hub Europe will introduce new nomenclature } From 1 Oct 2021, market area overlaps will only have for network accounts effective 1 Oct 2021. one THE network account } The existing network accounts will be migrated to } For cancellations still relating to the NCG and GPL the new nomenclature, so all old periods will be market areas, the network operators will only send two processed via the new network account cancellation INVOICs and one new SSQNOT to THE Impact on network operators: Impact on network operators: } The network operators will use the old network } The network operators will use the old network account numbers up to and including 30 Sep 2021 account numbers up to and including 30 Sep 2021 (also for declarations made for October 2021) (also for declarations made for October 2021) } From 1 Oct 2021, only the new nomenclature can be } From 1 Oct 2021, only the new nomenclature can be used for old periods prior to 1 Oct 2021 (correction used for old periods prior to 1 Oct 2021 notification, clearing, MMMA) 31
Traders’ Christmas wish list for new MAM
Traders' Christmas wish list for the market area merger 33
Publications: Wishes and their planned implementation (1/3) Wish Planned implementation "[...] The homepage of the MAM website The homepage will have a news module should show all news, press releases and which will feature news, press releases and information about data updates [...] which information on the availability of new data. are not provided on daily basis [...]" "[...] Updates should be made available as an All news published in the news module will RSS feed. All new information should be be made available in an RSS feed. sent out on a monthly basis [...] by Furthermore, THE is planning a newsletter, newsletter [...]" containing the latest news as well as further information. The newsletter will require separate subscription. 34
Publications: Wishes and their planned implementation (2/3) Wish Planned implementation "[...] Published data [...] should be displayed Where appropriate, information on the THE both in tabular and graphical form, with the website will be provided both graphically option of adjusting the time range and and in tabular form. selecting additional filter settings [...]". A free filter has been selected as "standard filter", but it cannot be used for every display. Useful additional filter options will be implemented. "[...] data should allow downloads as a csv or All presentations will be available for xlsx file and should be retrievable via an download from the THE website as csv files. XML interface [...]". XML retrieval will also be implemented. "[...] messages from TSOs or other The THE MAM will only publish information information which have no relation to the relating to THE. functions of the MAM should not be available on the MAM pages [...]". 35
Publications: Wishes and their planned implementation (3/3) Wish Planned implementation "[...] All old messages should be made Implementation options to be checked available in an archive [...] Information and data prior to the market area merger should also be preserved [...]". "[...] Nice-to-have: Information such as Will be implemented updated network balancing trends, call orders for the previous day, new market participants, news updates from homepage, the previous day's balancing gas price and current key figures made available at a glance in the form of a daily report or a kind of cockpit [...]". "[...] Clearing window shown on Implementation options to be checked homepage or portal [...]" 36
Portals: Wishes and their planned implementation (1/4) Wish Planned implementation "Nice-to-have: Show clearing window on the Option for portal: homepage or portal (also graphically)." Clearing window on portal could include automated display of the current clearing periods (e.g. "Clearing period for 01/2020 starts on ...", "Clearing period for 12/2019 ends on ...") "The proposal to have only one MAM recommendation: Could be comprehensive portal in future makes implemented after the merger as and sense. However, it is unclear to us why the when necessary tender platform cannot be integrated into such a portal. This could perhaps be done in a subsequent step after the market area merger." 37
Portals: Wishes and their planned implementation (2/4) Wish Planned implementation "Allocation of clearing numbers is more Implementation options to be intuitive and better with Gaspool. The checked allocation process for clearing numbers should therefore be taken over by Gaspool. […]“ "[...] but the export options [for reports] as Implementation options for download Excel files are better at GPL (Download processes to be checked Manager). Gaspool should in particular look at the download function for hourly data. Hourly reports will also be available in the new portal. "The option of transferring biogas This functionality will also be available flexibility in the portal should be retained." after the merger. 38
Portals: Wishes and their planned implementation (3/4) Wish Planned implementation "The situation concerning contact person Please specify requirement more changes at the companies should be precisely. improved." "The very clear and intuitive display of the BG This functionality will also be available structures as well as the functions for after the merger. concluding balancing group contracts and the administration of balancing group allocations should be maintained. There should still be an automatic message when the BG connection expires". Finally, a contact person (single-point-of- This is planned. The assigned account contact) at the MAM during the changeover manager will be displayed in the phase for specific queries would be welcome. portal. 39
Portals: Wishes and their planned implementation (4/4) Wish Planned implementation "A simplified termination process for Under review for BGs. balancing groups no longer required after market area merger should be provided via In addition, there will be a function in the portal." the portal to terminate sub-BGs with three months’ notice at the end of the month. For this purpose, a new button will be provided for each contract. The customer will be able to determine the time of termination. 40
Market communication: Wishes and their planned implementation (1/3) Wish Planned implementation "[...] establishing an AS4 connection in AS4 connections will be offered for market connection with Ediga's XML [...] " communication / nominations. "[...] In principle, as many formats as possible When THE starts, it will be possible to use should be made available [...]." the current news version and the previous version on the input side. On the output side, only the current format will be used. 41
Market communication: Wishes and their planned implementation (2/3) Wish Planned implementation "[...] one AS2 connection each for VTP and THE will adhere to the regulatory GaBi Gas [...]" requirements and will only set up one communication link per market partner for the purpose of one-to-one communication. "[...] fallback option for when the Still to be assessed as part of the THE nomination system is down would be project desirable [...]" "[...] nomination of only net values instead of The proposal has been included in the MAM both directions of flow would be desirable project. A review of the (technical as well as [...]" regulatory) options has not yet been completed. 42
Market communication: Wishes and their planned implementation (3/3) Wish Planned implementation "[...] NOMRES should include the To be implemented by THE counterpart’s nomination track [...]" "Number of VTP identifiers, depending on Still being looked at the REMIT messages for ACER [...]" "[...] technical changes should be defined 12 Planned for THE as early as possible, but this months before the market area merger [...]" will also depend on the KOV process (among others), so THE cannot give a guarantee. Further information regarding the planned system adjustments and their effects are intended for the next market dialogue event in June 2020. 43
Thank You! 44