MAJOR PROJECTS
   2017-2021

        MINISTRY OF PUBLIC WORKS
               MAY 2017
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
DIRECT PUBLIC
         INVESTMENT
-   Upgrade and Rehabilitation of Route 11 CH
-   Optimization of Route 41 CH
-   Improvement of Route E-30-F
-   Upgrade of Route 7 by sections
-   Canelillo Reservoir
-   Pocuro Reservoir
-   Cautín Reservoir
-   New Hospital of Puente Alto
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
PROJECT DATA SHEET                                                            NATIONAL ROAD DEPARTMENT
 UPGRADE AND REHABILITATION ROUTE 11 CH                                        Updated: MAY 2017

                      Project Information
 Location             Arica & Parinacota Region

                      Improvement of the international highway Arica                    Location Map
 Objective            to Tambo Quemado (border with Bolivia), 192
                      km.

                      Maintenance and upgrade of Route 11 CH.                                                              127
                                                                                                                                 1

                      Main works 2016-2019: Asphalt repair,
                      construction of auxiliary tracks, road safety
                      measures, path rectification, bridge construction
                      and environmental measures.                                                                    100

                                                                                                   36
 Description of                                                                               18
                                                                                                                76
 Works

                      2016-2019: US$ 130 million
 Estimated
 Investment
                      2020-2023:US$ 150 million
 Type of
                       Public
 Investment
                      Improvement of connectivity between Chile and
                      Bolivia and the Port of Arica.
 Benefits
                      Reduction of risk of accidents and travel times
                      and improving road safety.

                        Current Situation                                                   Timetable
                                                                          Activity          Date
                                                                          Section km.
 Working section km. 36-60, asphalt repair, path rectification,                                          st
                                                                          36-60 and 137-    End of works 1 Semester 2017
 construction of auxiliary tracks, road safety measures
                                                                          147
 From first term 2016, works on km. 170-192, asphalt replacement, road
                                                                          Section km.                    th
 safety measures, path rectification, and environmental measures in                         End of works 4 Quarter 2018
                                                                          170-192
 Lauca National Park
 In process design studies sections km 18-36; 76-100 and 100-
                                                                                             nd
 127. Construction begins at the end of 2018. All projects consider       End of works      2 Semester 2023
 citizen consulting process

Source: Sub-Department of Development, Sub-Department of Works
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
PROJECT DATA SHEET                                                        NATIONAL ROAD DEPARTMENT

              -   OPTIMIZATION OF ROUTE 41 CH                             Updated: MAY 2017

                      Project Information
Location          Coquimbo Region
                  Improvement of the international connection from                   Location Map
Objective         Coquimbo - La Serena to Argentina (San Juan) and
                  the Mercosur.

                  Improvement works and expansion in some sections.
Description
                  Construction of bridges and protection structures in
of Works
                  an international route of 233 km in the Chilean side.

Estimated         2016-2019: US$ 34 million
Investment        2019-2024: US$ 81 million
Type of
                  Public
Investment
                  To improve connection between Chile, Argentina and
                  the Mercosur, and the access to the Port of
Benefits          Coquimbo as well the touristic areas in La Serena
                  and Vicuña. Reduce the risk of accidents, reduce
                  travel times and improve safety on the route.

                           Current Situation                                              Timetable
                                                                          Activity                         Date
                                                                          Call for tender:
                                                                          Design of expansion Las Rojas-   2017
                                                                          Marqueza
Design Project of section La Serena-Las Rojas ready
                                                                          Design of expansion Marqueza-    2018
                                                                          Puclaro bridge
New call for tender to finish section Juntas del Toro y Puente El
Camarón (km 147-162) during first term 2017
                                                                          Design of expansion Works        2018
                                                                          Puclaro Tunnel - Vicuña
Plans for Citizen Participation during the whole Project.
                                                                          Improvement Works: La            2020
Environmental management measures should be taken even if the
                                                                          Laguna- Llano Las Liebres
Project is not located in a National Park
                                                                          Enlargement La Serena-Las        2019
                                                                          Rojas (exprop)

      Source: Sub-Department of Development, Sub-Department of Works
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
PROJECT DATA SHEET                                                           NATIONAL ROAD DEPARTMENT
              -   IMPROVEMENT OF ROUTE E-30-F                                Updated: MAY 2017

                      Project Information
                      Valparaíso Region, from the crossing of
Location              National Highway 5 to Zapallar - Puchuncaví -
                      Concón.
                                                                                    Location Map
                      Improve the standard of urban and interurban
Objective
                      roads between Zapallar and Concón.

                      Route of 83 km.

                      The first section will have 7 m. wide and an outer
Description of        berm of 2 m.
Works
                      In the urban section (2 km.) a roundabout is
                      considered together with a new bridge over the
                      Aconcagua river

Estimated             2016-2019: US$ 44 million
Investment            2020-2024: US$ 108 million
Type of
                      Public
Investment
                      Improvement of coastal connectivity in Northern
                      Valparaiso Region with a reduction of travel
Benefits
                      times, reduction of the risks of accidents and
                      improvement in safety of the route.

                         Current Situation                                                    Timetable
                                                                           Activity                       Date
                                                                           Call for tender:
Expropiation process and Interurban section works in progress
                                                                           - Improvement of section       2017
Engineering studies for section Concón - Quintero (17 km) ready at the     Concón-Cantonera Norte
end of 2017                                                                Concón Bridge

Improvement of Route F30-E sector Cementerio Concón-Límite urbano          - Upgrading works of section   2018
under progress ending july 2017                                            Concón-Cantonera Norte II
                                                                           phase
Citizen Participation during the whole process                             -Expansion Cantonera Norte-    2021
                                                                           Road Junction F-240

      Source: Sub-Department of Development, Sub-Department of Works
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
PROJECT DATA SHEET                                                     NATIONAL ROAD DEPARTMENT
                                                                        Updated: MAY 2017
     - UPGRADE OF ROUTE 7 BY SECTIONS

                  Project Information                                         Location Map
Location      Los Lagos and Aysén Regions
                 -     Improvement of connectivity in Route 7
                       between Coyhaique and Puerto Montt with
                       only 3 seatransfers

                 -     Studies for road construction of section
                       Pichanco - Caleta Gonzalo and beginning of
                       expropiation process.
Objective
                 -     Paving of central section in Villa Ortega

                 -     Paving from Cerro Castillo to South Access
                       of Cochrane (250 km)

                 -     Design studies       road    Cochrane-Puerto
                       Yungay (120 km)

                 -     Length of the road: 1,075 km (Pto. Montt –
                       Coyhaique – Cochrane – Pto. Yungay), 475
                       km paved in asphalt or concrete.

Description      -     Construction of a paved road for average
of Works               speed of 50-70km/hr.

                 -     Sections of mountain road will be 4-6 mt.wide
                       to allow average speed of 40 km/hr.

Estimated     US$ 1,200 million for improvement of remaining 600
Investment    kms
Type of
              Public
Investment

              Improve connectivity of the Region, with the
              reduction of travel times, risk of accidents and the
Benefits      improving of road safety.
              Benefits for the population, tourism and economic
              activities of 16 % of the national territory.
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
Current Situation                                           Timetable 2016 – 2018
                                                                                 Activity                   Date
  This initiative is part of the portfolio of projects of the Special Plan for
  the Development of Extreme Areas (PEDZE) of the Region of Aysén.
  Citizen participation plans are considered.
                                                                                 Northern Section, Call
                                                                                 for bids                     nd
                                                                                                             2 sem 2016
                                                                                  Section Puñon – Ex
                                                                                   Pte. Parafina, 8 km        nd
                                                                                                             2 sem 2016
                                                                                  Section Pte. Cisnes –
                                                                                   Pichicolo, 11 km
                                                                                                             2018 - 2019
                                                                                  Section Pte. El Blanco
                                                                                   – Pichanco, 25 km
  The Project has been divided in 3 sections:                                     Section Leptepú –
                                                                                                             2018 - 2019
     - Northern Section: Pto. Montt – Coyhaique                                    Fiordo Largo, 11 km
     - Central: Intersection R 240 CH – Intersection Route X-50,                  Section C. Gonzalo –
                                                                                                             2017 - 2018
     - Southern: Villa Cerro Castillo – Cochrane – Pto. Yungay.                    Pte. Bonito, 35 km
                                                                                  Section Lím. Reg – La      st
                                                                                                             1 sem 2017
                                                                                   Tolva, 22 km
                                                                                  Section Lago               nd
                                                                                                             2 sem 2017
                                                                                   Risopatrón, 14 km
                                                                                  Section Las Pulgas –       nd
                                                                                                             2 sem 2016
                                                                                   F. Queulat, 12 km
                                                                                 Sector F. Queulat – Bif.
                                                                                                            2018 - 2019
                                                                                 Cisnes, 27 km
                                                                                 Central Section, Call
  Northern Section: Puerto Montt – Coyhaique:
                                                                                 for bids
   Not paved section: 230 km                                                                                 nd
                                                                                                             2 sem 2016
                                                                                  Section 1 Intersection
   Studies under progress: 96 km                                                                             – 2018
                                                                                   R 240 CH – V. Ortega
   Paving under progress: 65 km
                                                                                 
                                                                                 Southern Section, Call
                                                                                 for bids:
                                                                                  Section V. Cerro          2017-18
                                                                                   Castillo – Laguna
  Central Section: Intersection R 240 CH and Route X-50:                           Verde
   Not paved section: 52 km
   Studies under progress: 28 km                                                 Section 1 Acc. Murta      2017-18
                                                                                   – Pto. Tranquilo
                                                                                  Section 1 Confluence      2017-18
                                                                                   River Baker/Nef –
                                                                                   Cochrane
  Southern Section: Villa Cerro Castillo – Cochrane:
   Not paved section: 245 km
   Studies under progress: 65 km
   Basic Works under progress: 30 km

Source: Sub-Department of Development, Sub-Department of Works
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
NATIONAL DEPARTMENT FOR
PROJECT DATA SHEET                                                        HYDRAULIC WORKS
         - CANELILLO RESERVOIR                                            Updated: MAY 2017

                    Project Information                                                       Location Map

Location        Province of Choapa in Coquimbo Region,

                Capacity: 200 Hm3
Description     Flood area 800 ha
of Works        Wall height: 84 m.
                Netwrk of new irrigation channels: 300 kms.
Irrigation
                15.000 ha.
Area

Communes        Illapel, Canela, Los Vilos

Estimated                                                                                     Wall of the dam
                US$ 169 million
Investment
Hydroelectric
                Under analysis
generation

                The National Department for Hydraulic Works has
Water Rights                     3
                rights for 150 Hm /year. Possibilities to capture the
                water near the reservoir under study

                       Current Situation                                                  Timetable
                                                                        Activity                 Date
                                                                        Feasibility studies      Ready

                                                                        Study of environmental
                                                                                                 2017 – 2018
Feasibility studies are been executed by Empresa SMI.                   assessment
Design of Project and environmental studies 2017-2018                   Design studies           2018 – 2019

                                                                        Construction             2020 – 2024

      Source: Department of Irrigation Projects
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
NATIONAL DEPARTMENT FOR
PROJECT DATA SHEET                                                              HYDRAULIC WORKS
                         - POCURO RESERVOIR                                       Updated: MAY 2017

Project Information                                                               Location Map
                   Province of los Andes, Commune of Calle Larga,
Location
                   Valparaíso Region
                   Volume of the reservoir: 100 Hm3
                   Dam wall height: 100 m
Description
                   Feeder Channel: 17 km (from Aconcagua River) and a
of Works
                   capacity of 20 m3/s
                   Main channel: 10 km
Irrigation
                   30.000 Has
Area

River               st       nd
                   1 and 2        sections of Aconcagua river
sections
                                                                                       Area of the Wall
                                                                                        Dam
Estimated
                   US$ 290 million
Investment

Hydroelectri       5 to 10 MW installed capacity
c generation

                   The National Department has permanent water rights
                             3
Water Rights       for 400 Hm /year in the first section of Aconcagua river.

                           Current Situation                                                   Timetable
                                                                               Activity                   Date
                                                                                                           st
                                                                                                          1 sem. 2017
                                                                               Social and economic
    1. Feasibility studies and environment assessment under progress,
                                                                               State Evaluation System
       ending first semester 2017
                                                                                                           st
                                                                                                          1 sem 2017
                                                                               Council of Ministers
    2. Working on a model to run in a single contract both design and
       construction
                                                                               Allocation of budgetary     st
                                                                                                          1 sem. 2017
                                                                               resources

                                                                               Expropiaton                 nd
                                                                                                          2 sem. 2017

                                                                               Call for bids               nd
                                                                                                          2 sem. 2017

             Source: Department of Irrigation Projects
MAJOR PROJECTS 2017-2021 - MINISTRY OF PUBLIC WORKS MAY 2017 - Flanders Investment & Trade
NATIONAL DEPARTMENT FOR
PROJECT DATA SHEET                                                     HYDRAULIC WORKS
                     - CAUTIN RESERVOIR                                  Updated: MAY 2017

                       Project Information                                             Location Map

Location                 Province of Cautín, Araucanía Region
                                            3
                         Capacity: 142 Hm                                                                   CAUTÍN
Description of
                         Dam wall height: 62 m
Works

Irrigation Area          32.274 Has

Communes                 Victoria, Perquenco and Lautaro

Estimated
                         US$ 427 million
Investment
Hydroelectric
                         Under evaluation
generation

                         The National Department has permanent water
Water Rights             rights for 670 Hm3/year and temporal water
                                          3
                         rights for 534 Hm /year.

                          Current Situation                                                  Timetable
                                                                       Activity                     Date
                                                                       Feasibility studies          2017- 2018

                                                                       Environmental                2019 – 2020
Prefeasibility studies ready since 2013                                Assessment

Feasibility studies from 2017                                                                       2020 - 2021
                                                                       Design

                                                                       Construction                 2022 - 2024

           Source : Department of Irrigation Projects
NATIONAL DEPARTMENT OF
PROJECT DATA SHEET                                                           ARCHITECTURE
       - NEW HOSPITAL OF PUENTE ALTO                                         Updated: MAY 2017
   Project Information

   Location                 Commune of Puente Alto, Santiago
                            Metropolitan Region

                            Set up a health infrastructure to give high
                            complexity coverage to 1.5 millon
   Objective
                            inhabitants in the south of Santiago city

   Description of           It will have 400 beds (48 for critical
   Works                    patients), 10 surgical pavilions

    Estimated
                             US$ 243 million (including equipment)
   Investment

                             Public. Ministry of Health
   Type of Investment

   Other Priorities         It should cover: open care,
                            hospitalization, therapeutic procedures,
                            emergency telemedicine and a nursery.

               Current Situation                                                              Timetable
                                                                           Activity                       Date
Proyecto delayed                                                                                           nd
                                                                          CCall for bids                  2 semester 2017
Design studies by the Ministry of Health in progress

      Source: Planning and Coordination Division

                                                                           Término de obras
CONCESSIONS
-   The Loa Route
-   Route 5, Section Antofagasta – Iquique
-   Route 5: Section Caldera - Antofagasta
-   Re-tender of Route N° 5 Los Vilos – La Serena and
    Conurbation
-   Route 5, Section Santiago - Los Vilos
-   Interconnection Santiago-Valparaíso-Viña del Mar
    (Route 68) + Alternatives
-   Costanera Central Highway - Section Av. La Florida –
    Camilo Henríquez
-   Eastern Américo Vespucio Urban Highway - Príncipe
    de Gales – Grecia
-   Interconnection Highway 68 with Highway 78
-   Highway Santiago – San Antonio (Route 78)
-   Transversal Route of O’higgins Region
-   Fruit Highway, G-66
-   Re-tender Route 5 - Talca – Chillán
-   Re-tender Route 5 - Chillán – Collipulli
-   Nahuelbuta Route
-   Route Freire – Villarrica – Pucón
-   Re-tender Route 5: Temuco – Rio Bueno + Access to
    Valdivia
-   Metropolitan Highway of Puerto Montt
-   North-South Route of Chiloé
-   Las Palmas Reservoir
-   Los Angeles Reservoir
-   Catemu Reservoir
-   La Jaula Reservoir
-   La Tranca and Murallas Viejas Reservoirs
PROJECT DATA SHEET                                               PUBLIC WORKS PPP
                     - THE LOA ROUTE                                                 Updated: MAY 2017

                     Project Information                                                   Location Map
               Communes of Sierra Gorda and Calama in Antofagasta
Location
               Region

               Increase service levels and improving connectivity and
Objective
               territorial integration of the Region                                                      Rutas del Loa

                  Revamping and expansion up to 2 lanes each side
Description
                   of the Route 25
of Works
                   Construction of the Eastern bypass to Calama
                   connecting Routes 21, 23, 24 and 25

Economic          It considers MGI and ITC
Conditions
                                                                                      R
Estimated                                                                             ut
               US$ 293 million
Investment
                                                                                      as
Type of
               PPP – BOT                                                              de
Investment
                                                                                       l
                  Improvement of service and standard levels of                      Lo
                   Route 25.
Benefits                                                                               a
                  Improvement of safety conditions and shorter travel
                   times                                                              (1
                                                                                      36
                                                                                      K
                           Current Situation                                          m.     Timetable
                                                                         Call for Bids )            nd
                                                                                                   2 Quarter 2017
                                                                                                    h
•      Bidding conditions ready                                          Receipt of Tenders        4t Quarter 2017

                                                                         Contract award            1st Semester 2018

            Source: CCOP
PROJECT DATA SHEET                                                PUBLIC WORKS PPP
      - ROUTE 5, SECTION ANTOFAGASTA –
                                                                                         Updated: MAY 2017
                    IQUIQUE

Project Information:                                                                       Location Map

                  Route 5 between the cities of Antofagasta and
Location
                  Iquique

                  Improvement of the standard in Route 5, Carmen
Objective
                  Alto and Humberstone in the junction with Route 16.

Description of        Two lanes in each side.
Works                 Max speed 120km/h

Economic              Road tolls
Conditions            State subsidy 30% aprox.

Estimated
                  US$ 458 million
Investment
Type of
                  PPP - BOT
Investment
                      Rehabilitation and improvement of a section of
                       the Route 5.
Benefits              Improvement of safety conditions and shorter
                       travel times
                      More secondary access roads

                           Current Situation                                              Timetable
                                                                                                 st
                                                                        Call for Bids           1 Semester 2020
   Private initiative                                                                           nd
                                                                        Receipt of Tenders      2 Semester 2020
   Studies under progress
                                                                                                 nd
                                                                        Contract award          2 Semester 2021

            Source: CCOP
PROJECT DATA SHEET                                               PUBLIC WORKS PPP
       -         ROUTE 5: SECTION CALDERA -
                                                                                        Updated: MAY 2017
                    ANTOFAGASTA

Project Information:                                                                      Location Map

                   Route 5 between the cities of Caldera and
Location
                   Antofagasta

                   Improvement of the standard in this section of the
Objective          Route 5

Description of         Two lanes in each side.
Works                  Max speed 120km/h

                       Road tolls
Economic
Conditions             State subsidy 30 %

Estimated
                   US$ 640 million
Investment
Type of
                   PPP – BOT -
Investment

                       Expansion of the 4 lanes highway from
                        Antofagasta to the south
Benefits               Improvement of safety conditions and shorter
                        travel times
                       More secondary access roads

                           Current Situation                                               Timetable
                                                                                                 rd
                                                                        Call for Bids           3 Quarter 2018
                                                                                                 st
   Studies of this private proposal under progress                     Receipt of Tenders      1 Quarter 2019
                                                                                                 nd
                                                                        Contract award          2 Semester 2019

            Source: CCOP
PROJECT DATA SHEET                                            PUBLIC WORKS PPP
  - RE-TENDER OF ROUTE N° 5 LOS VILOS – LA                                          Updated: MAY 2017
         SERENA AND CONURBATION

                      Project Information                                               Location Map
Location         North of Santiago from km 229 to km 474
                 Re- tender of the contract for Route N° 5 from Los
Objective        Vilos to Coquimbo, including urban sector between
                 Coquimbo and La Serena

Description of       229 km 4-lanes intercity road
Works                17 km of urban highway with three lanes in
                      each direction

Economic
                     Road tolls
Conditions

Estimated
                  US$ 328 million
Investment
Type of
                  PPP – BOT
Investment

                     Improve urban connectivity
                     Increase transport capacity on the urban sector
Benefits             Reduce accidents
                     With this section the concessioned highway
                      from Caldera to Pargua goes up to 1.955 km

                        Current Situation                                                Timetable
      Private Initiative                                               Call for bids           rd
                                                                                               3 Quarter 2017
      Developing studies for: design, expropriations, environmental
       assessment                                                       Reception of bids      End of 2017
      Finishing project proposal                                                               st
      Preparation of bidding conditions                                Contract award         1 Semester 2018

       Source: CCOP
PROJECT DATA SHEET                                                    PUBLIC WORKS PPP
   -        ROUTE 5, SECTION SANTIAGO - LOS
                                                                                           Updated: MAY 2017
                       VILOS
Project Information:                                                                           Location Map

                    Communes of Quilicura, Colina, Lampa, Til Til,
Location            Llay Llay, Hijuelas, La Calera, Nogales, Zapallar,
                    La Ligua, Papudo and Los Vilos in Central Chile

                    Increase service levels and improving connectivity
Objective           and territorial integration of this part of the national
                    territory

                    Improvement of the standard of the Route 5
Description of
                    between Santiago and Los Vilos.
Works

Economic
                    Road tolls - Not subsidies
Conditions

Estimated
                     US$ 225 million
Investment
Type of
                     PPP – BOT
Investment

                    • Standard improvement of a section of the
                      Route 5.
Benefits            • Improvement of safety conditions and shorter
                      travel times
                    • More secondary access roads

                           Current Situation                                                     Timetable
                                                                               Call for Bids         End of 2019
                                                                                                      rd
Evaluating necessary studies to develop this re-tender project                 Receipt of Tenders    3 Quarter 2020
                                                                                                      st
                                                                               Contract award        1 Quarter 2021

            Source: CCOP
PROJECT DATA SHEET                                                      PUBLIC WORKS PPP
    -      INTERCONNECTION SANTIAGO-VALPARAÍSO-
                                                                                           Updated: MAY 2017
         VIÑA DEL MAR (ROUTE 68) + ALTERNATIVES

Project Information:                                                                            Location Map

Location              Provinces of Valparaíso and Santiago

                      Increase service levels and improving the standard
Objective
                      of the highway

                      Route 68, has 110 km. It needs a better standard
Description of
                      with different secondary roads, junctions and
Works
                      additional lanes.

Economic
                         Road tolls
Conditions

Estimated
                      US$ 600 million
Investment

Type of
                      PPP – BOT
Investment

                         Promotes regional economic growth and
Benefits                  territorial integration of 2 of the most important
                          metropolitan areas of the country and
                          Valparaíso seaport

                              Current Situation                                                 Timetable
                                                                                                        st
                                                                               Call for Bids           1 Semester 2019
       Studies of demand and Social Evaluation under progress
                                                                               Receipt of Tenders      End of 2019
       Re-tender Route 68 Santiago – Valparaíso – Viña del Mar.
                                                                                                        nd
                                                                               Contract award          2 Quarter 2020

               Source: CCOP
PROJECT DATA SHEET                                                       PUBLIC WORKS PPP
    -        COSTANERA CENTRAL HIGHWAY - SECTION
             AV. LA FLORIDA – CAMILO HENRÍQUEZ                                                Updated: MAY 2017

Project Information:                                                                              Location Map
                       South-east     side   of   Santiago
Location               Metropolitan Area. Communes of La Florida and
                       Puente Alto.

                       Improvement of transport system, connectivity and
Objective
                       infrastructure standard of the city
                               Building a high standard underground
                                highway of 12 km.. 9 km is an underground
                                route with 3 lanes in each side and the
Description of                  other 3 km will have 2 lanes in each side.
Works
                               The project includes connections to local
                                roads and Américo Vespucio Sur Highway.

                          Road tolls
Economic
                          State subsidies 36 %
Conditions
                          Free flow tolls

Estimated
                       US$ 1.1 Billion
Investment
Type of
                       Private Initiative - PPP – BOT
Investment

                               Improvement of connectivity between
                                south-east districts and downtown
                               Reduction of traffic congestion
Benefits                       New public transport corridor
                               Reduction of operational costs.
                               Improvement of safety conditions and
                                shorter travel times.

                               Current Situation                                                  Timetable
                                                                                                         nd
                                                                             Call for bids              2 Quarter 2018
       Developing of technical studies and bidding conditions
                                                                                                         st
       Citizen participation in local communities                           Receipt of tenders         1 Quarter 2019
                                                                                                         th
                                                                             Contract award             4 Quarter 2019

                Source: CCOP
PROJECT DATA SHEET                                             PUBLIC WORKS PPP
      -       Eastern Américo Vespucio Urban
                                                                                      Updated: MAY 2017
          Highway - Príncipe de Gales – Grecia

                       Project Information                                                 Location Map

Location          Eastern side of Santiago

                  Complete the Americo Vespucio ring road with high
Objective
                  quality and service standard
                      Construction of two underground double tracks
                       with 3 lanes each side
Description of
Works                 Urban redeveloping in surface considering
                       larger green areas and more facilities for public
                       urban transportation.
                        Road tolls
Economic
                        Estimated 15% of state subsidy
Conditions
                        Free flow tolls
Estimated
                   US$ 786 million
Investment
Type of
                   PPP – BOT
Investment
                      Complete the Américo Vespucio ring road in
                       Santiago with a high service standard
                      Reduce accidents and traffic jams, mainly
                       during rush hours.
Benefits
                      Reduce commuting time and pollution
                       emissions.
                      Improve public transportation and connectivity
                       in the city.

                         Current Situation                                                   Timetable
                                                                           Call for Bids          August 2016
   Finishing technical studies and bidding bases
                                                                                                   nd
   Prequalification process re-open                                       Receipt of Tenders     2 Quarter 2017
   Closing agreements and approval with authorities                                                h
                                                                           Contract award         4t Quarter 2017

             Source: CCOP
PROJECT DATA SHEET                                                             PUBLIC WORKS PPP
INTERCONNECTION HIGHWAY 68 WITH HIGHWAY 78
                                                                                           Updated: MAY 2017

Project Information:                                                                            Location Map
                               Western       side  of Santiago
Location                       Metropolitan Area. Communes of
                               Pudahuel and Maipú.
                               Improvement of        transport system,
Objective                      connectivity and infrastructure standard
                               of Western Santiago
                                    Construction of a 9.4 km 4-
                                      lanes road, to reduce traffic
                                      impact in urban zones
                                    Internal roads, lighting and
                                      drainage
Description of Works
                                    Construction of different flyovers
                                      and structures in the junctions
                                      with Route 68 and Route 78
                                    Internal roads and road safety
                                      measures
                                Road tolls
Economic Conditions             Free flow tolls
                                Not subsidies

Estimated Investment           US$ 250 million

Type of Investment             Private Initiative - PPP – BOT
                                     Improve connectivity between
                                      central and western areas of
                                      Santiago
                                     Improve connection to the main
Benefits                              national seaports avoiding to
                                      cross through Santiago.
                                     Better local urban development
                                     Reduction of accidents, travel
                                      times and pollution emissions
                           Current Situation                                                  Timetable
                                                                                                     rd
                                                                          Call for bids             3 Quarter 2017
   Finishing technical studies and developing of bidding contracts       Reception of bids         End of 2017
                                                                                                     st
                                                                          Contract award            1 Semester 2018

            Source: CCOP
PROJECT DATA SHEET                                                   PUBLIC WORKS PPP
        -    HIGHWAY SANTIAGO – SAN ANTONIO
                                                                                           Updated: MAY 2017
                     (ROUTE 78)

Project Information:                                                                         Location Map
                  Provinces of Santiago, Talagante, Melipilla and
Location
                  San Antonio.
                  Upgrade the standard of the route
Objective
                  Better service levels
                      Route 78 highway has 4 lanes and an extension
                       of 105 kms

Description of        It needs a better standard with different
Works                  secondary roads, junctions and local roads.

                      Replacement of old bridges and construction of
                       a few new ones.
                      Road tolls
Economic              Not subsidies
Conditions            One trunk toll area in Melipilla and in some
                       junction roads.
Estimated
                  US$ 300 million
Investment
Type of
                  PPP – BOT
Investment
Benefits
                      Promotes regional economic growth and
                       territorial integration in medium size localities
                       and between Santiago and the main national
                       port: San Antonio

                           Current Situation                                                  Timetable
                                                                                                    st
                                                                           Call for Bids           1 Quarter 2020
   Re-tender of Route 78 Santiago-San Antonio                                                      rd
   Studies of demand and social evaluation under progress                 Receipt of Tenders      3 Quarter 2020
                                                                                                    st
                                                                           Contract award          1 Quarter 2021
            Source: CCOP
PROJECT DATA SHEET                                            PUBLIC WORKS PPP
TRANSVERSAL ROUTE OF O’HIGGINS REGION                                                 Updated: MAY 2017

Project Information:                                                                       Location Map

Location           From south-west Rancagua to the village of Alhué

                   Create a new connection to the port of San Antonio
Objective
                   from Rancagua and the commune of Alhué
                       Building of a new road (68 km.) including
Description of
                        auxiliary tracks and road safety measures.
Works
                       Tunnel of 6 km.

Economic               Road tolls
Conditions             State subsidy almost 30%

Estimated
                    US$ 306 million
Investment
Type of
                    PPP – BOT
Investment

                       Improve travel time between Rancagua and
                        San Antonio
                       Create a better connection to the Fruit Highway
Benefits
                        G-66
                       Complementary to the future binational tunnel
                        Las Leñas between Chile and Argentina

                           Current Situation                                               Timetable
                                                                                                  st
                                                                          Call for Bids          1 Semester 2020
                                                                                                  nd
   First stages of a private initiative. Studies under progress          Receipt of Tenders     2 Semester 2020
                                                                                                  st
                                                                          Contract award         1 Semester 2021

            Source: CCOP
PROJECT DATA SHEET                                               PUBLIC WORKS PPP
             -         FRUIT HIGHWAY, G-66                                          Updated: MAY 2017

                       Project Information                                                Location Map
                   120 km south from Santiago to the port of San
Location
                   Antonio
                   Improve connectivity for small and medium scale
                   producers (fruits, vegetables and wine) from
Objective
                   O’Higgins and Maule Regions to the port of San
                   Antonio
                    Restore and improve 138 km of the existing
                       road and construction of a bidirectional road to
                       reduce traffic impact in urban zones
Description of
                    Construction of a 21 km 4-lanes road
Works
                    Construction of different flyovers and
                       structures to reduce negative impact on
                       population
                    Road tolls
Economic
                    State subsidies 50-60 %
Conditions
                    Free flow tolls
Estimated
                   US$ 600 million
Investment
Type of
                   PPP – BOT
Investment
                       Improvement of connectivity
                       Reduction of transport costs for local
Benefits
                        producers
                       Reduction of accidents

                         Current Situation                                                  Timetable
                                                                                                   rd
                                                                          Call for Bids           3 Quarter 2017
   Technical studies ready
   Agreements with local authorities and citizen participation           Receipt of Tenders       st
                                                                                                  1 Quarter 2018
   Preparation of bidding contracts
                                                                                                   st
                                                                          Contract award          1 semester 2018

            Source: CCOP
PROJECT DATA SHEET                                           PUBLIC WORKS PPP
RE-TENDER ROUTE 5 - TALCA – CHILLÁN                                                 Updated: MAY 2017

Project Information:                                                                        Location Map
                  Communes of Río Claro, San Rafael, Talca,
                  Maule, San Javier, Villa Alegre, Linares, Longaví,
Location
                  Retiro, Parral y Ñiquén, San Carlos, San Nicolás,
                  Chillán and Chillán Viejo.
                  Increase service levels and improving the standard
Objective
                  of the highway with additional works

                  4-lanes road and 193.3 km, It will have:
Description of     New local roads
Works              Junctions – bridges
                   Bypass sectors
                   Free flow toll system

Economic              Road tolls
Conditions            Not subsidies

Estimated
                  US$ 225 million
Investment
Type of
                  PPP – BOT
Investment

                      Improve connectivity between central and
                       southern Chile
                      Better     local   and   regional economic
Benefits
                       development and integration
                      Reduction of accidents, travel times and
                       pollution emissions

                           Current Situation                                            Timetable
                                                                                                st
                                                                       Call for Bids           1 Quarter 2019
   Studies of demand and social evaluation under progress                                      rd
                                                                       Receipt of Tenders      3 Quarter 2019
   TOR of basic engineering studies in preparation.
                                                                                                st
                                                                       Contract award          1 Quarter 2020

            Source: CCOP
PROJECT DATA SHEET                                                  PUBLIC WORKS PPP
           - RE-TENDER ROUTE 5 - CHILLÁN –
                                                                                          Updated: MAY 2017
                     COLLIPULLI

Project Information:                                                                           Location Map
                  Communes of Chillán, Bulnes, Cabrero, Los
Location
                  Ángeles, Mulchén and Collipulli in Biobío Region
                  Improvement of actual highway standard, including
Objective         additional works and the increase of service levels
                  while improving user safety
                  Section of 160 km. in Route 5 with 2-lanes in each
                  side.

                  To include:
Description of
Works
                      New local roads
                      Junctions – bridges
                      Bypass sectors
                      Free flow toll system

Economic              Road tolls
Conditions            Not subsidies

Estimated
                  US$ 225 million
Investment
Type of
                  PPP – BOT
Investment
                      Improvement of connectivity
                      Reduction of transport costs for local producers
                      Reduction of accidents
                      Improve connectivity between central and
Benefits
                       southern Chile
                      Better local and regional economic
                       development and integration

                           Current Situation                                                 Timetable
                                                                                                    st
                                                                          Call for Bids            1 Semester 2019
   Studies under progress                                                Receipt of Tenders        rd
                                                                                                   3 Quarter 2019
                                                                                                    nd
                                                                          Contract award           2 Quarter 2020
            Source: CCOP
PROJECT DATA SHEET                                            PUBLIC WORKS PPP
              -        NAHUELBUTA ROUTE                                              Updated: MAY 2017

                       Project Information                                                Location Map

Location          Km 520 south of Santiago

                  Improve connectivity and maximize economic and
Objective         social benefits in an area mainly focused on forests
                  and forestry
                   55 km road
Description of
                   4-lanes highway
Works
                   Uneven junctions
                      Road tolls
Economic
                      Estimated 41% of state subsidy
Conditions
                      Manual tolls
Estimated
                   US$ 245 million
Investment
Type of
                   PPP – B5OT
Investment

                      Connectivity improvement
Benefits              Reduction of transport costs for local producers
                      Reduction of accidents

                            Current Situation                                               Timetable
                                                                          Call for Bids            November 2016
                                                                                                    nd
   Bidding bases and procedures in progress                              Receipt of Tenders       2 Quarter 2017
   Agreements with local authorities and indigenous communities
                                                                                                    th
                                                                          Contract award           4 Quarter 2017

             Source: CCOP
PROJECT DATA SHEET                                  PUBLIC WORKS PPP
    - ROUTE FREIRE – VILLARRICA – PUCÓN                                           Updated: MAY 2017

Project Information:                                                                            Location Map

Location           Freire, Villarrica and Pucón

                   Improvement of Route 199 CH between Freire and
Objective
                   Villarrica and additional works
                       Construction of a road with 2-lanes in each side
Description of
                       High safety standard
Works
                       40.8 km. of auxiliary roads

Economic               Road tolls
Conditions

Estimated
                    US$ 330 million
Investment
Type of
                    PPP – BOT
Investment

                       Connectivity improvement
Benefits               Reduction of transport costs for local producers
                       Reduction of accidents and congestion

                           Current Situation                                                Timetable
                                                                           Call for Bids            End of 2019
                                                                                                     st
   Private initiative under study                                         Receipt of Tenders       1 Quarter 2020
                                                                                                     rd
                                                                           Contract award           3 Quarter 2020

            Source: CCOP
PROJECT DATA SHEET                                                     PUBLIC WORKS PPP
    -   RE-TENDER ROUTE 5: TEMUCO – RIO BUENO +
                                                                                       Updated: MAY 2017
        ACCESS TO VALDIVIA

                                                                                            Location Map
Project Information:
                   Communes of Gorbea, Loncoche, Lanco, San José
Location           de la Mariquina, Máfil, Los Lagos, Paillaco, La
                   Unión, Río Bueno and Valdivia

                   Improvement of actual highway standard, including
Objective          additional works and the increase of service levels
                   while improving user safety and better access to
                   Valdivia city
                       Improvement of 172 km. of the 4 - lanes road
                       Upgrade to 2-lanes in each side to Valdivia (88
Description of          km.)
Works                  New local roads
                       Junctions – bridges
                       Bypass sectors.
Economic                -    Road tolls
Conditions              -    Not subsidies

Estimated
                    US$ 250 million.
Investment
Type of
                    PPP – BOT
Investment
                       Increase of safety standard to decrease
                        accident rate in acess to Valdivia

                       Connectivity improvement

                       Reduction of transport costs for local producers
Benefits
                       Reduction of accidents and congestion

                       Better local and regional economic
                        development

                            Current Situation                                               Timetable
                                                                           Call for Bids          End of 2017
   Private initiative. Proponent R y Q Ingeniería. Time limit for                                 th
                                                                           Receipt of Tenders     4 Quarter 2018
    presentation of first studies: April 2017
                                                                                                   nd
                                                                           Contract award         2 Quarter 2019

            Source: CCOP
PROJECT DATA SHEET                                       PUBLIC WORKS PPP
    -       METROPOLITAN HIGHWAY OF PUERTO
                                                                                    Updated: MAY 2017
                      MONTT

                           Project Information                                           Location Map
Location              Puerto Montt - 1.000 km. south of Santiago

                      • Improvement of transport system, connectivity
Objective             and infrastructure standard of Puerto Montt
                      • Improvement of connection between Puerto Varas
                      and El Tepual Airport
Description of            4-lanes highway in 32 km.
Works                     Urban highway standard
                          Road tolls
Economic
                          Estimated State subsidy; 30 %
Conditions
                          Free flow tolls
Estimated
                      US$ 321 million
Investment
Type of
Investment            PPP – BOT
                          Improvement of connectivity between Puerto
                           Montt and Puerto Varas
Benefits                  Reduction of traffic congestion.
                          Reduction of operational costs.
                          Improvement of safety conditions.

                             Current Situation                                             Timetable
       Private initiative                                               Call for Bids            End of 2017
       Developing of technical studies (demand, environmental
                                                                                                   nd
        assessement, business model, etc..)                              Receipt of Tenders       2 Quarter 2018
       Defining economic conditions

                                    nd                                   Contract award           End of 2018
        Citizen participation from 2 Semester 2016

               Source: CCOP
PROJECT DATA SHEET                                            PUBLIC WORKS PPP
    -        NORTH-SOUTH ROUTE OF CHILOÉ                                              Updated: MAY 2017

                        Project Information                                                Location Map

Location           1,100 km south of Santiago

                   Improve and extend the transportation system in the
Objective
                   island of Chiloé
                       Improvement of 101 km road with 2-lanes each
                        side
Description of         Construction of auxiliary tracks, road safety
Works                   measures, path rectification, construction of
                        new bridges and maintenance of existing ones
                        and environmental measures.
Economic               Road tolls
Conditions             Not subsidies

Estimated
                   US$ 250 million
Investment
Type of
                   Private initiative – PPP BOT
Investment
                       Improve connectivity
                       Increase transport capacity on the trunk road of
                        the island
Benefits
                       Reduce accidents
                       Contribute to the economic development of the
                        island

                          Current Situation                                                  Timetable
                                                                                                     rd
                                                                           Call for Bids            3 Quarter 2017
   Private initiative (Constructora Internacional). Developing of
                                                                                                     nd
    studies until MAY 2017                                                 Receipt of Tenders       2 Quarter 2018
   Preparation of bidding conditions                                                                st
                                                                           Contract award           1 Quarter 2019

             Source: CCOP
NATIONAL DEP. FOR HYDRAULIC
PROJECT DATA SHEET                                                    WORKS - PUBLIC WORKS PPP
    - LAS PALMAS RESERVOIR                                            Updated: MAY 2017

                    Project Information:                                              Location Map

                  Petorca Province, Petorca Commune
Location
                                                3
                  Volume of the reservoir: 55 Hm .
Description of
                  Feeder channel: 58 km
Works
                  .

Irrigation área   2.932 Ha and 1,285 rural properties

River sections    In communes of Petorca and Cabildo

Estimated         VAN MM$ 35,000.
investment and    TIR = 8,9 %
economic
conditions        US$ 161 million – State subsidy near 100 %

Hydroelectric     Not
generation
                  The National Department has water rights for 10
Water rights
                  Hm3/year, in rivulet Las Palmas.

                     Current Situation                                                Timetable
                                                                           Activity                  Date
                                                                    End of design              December 2016
                                                                    Environment
                                                                                               December 2016
    1. Design studies under process                                 Assessment
                                                                                               rd
                                                                    Call for bids             3 Quarter 2017
    2. Project in the National System for Environment Assessment

                                                                    Receipt of Tenders            End of 2017
                                                                    End of construction              2022

        Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC
PROJECT DATA SHEET                                                     WORKS - PUBLIC WORKS PPP
   - LOS ÁNGELES RESERVOIR                                             Updated: MAY 2017

                   Project Information                                                 Location Map

Location              Petorca Province, Commune of La Ligua.

                      Multipurpose reservoir with capacity of 30
Description of            3
                      Hm and a feeder channel of 24 km (from
Works
                      Alicahue River).

Irrigation Area       2,160 Ha. and 676 rural properties

Socio-economic
indicators            VAN: MM$ 280

Estimated
                      US$ 161 million – State subsidy near 100 %
Investment

Hydroelectric
                      No
Generation
                      Water rights under study. The reservoir has
Water rights
                      water rights from users.

                      Current Situation                                                  Timetable
                                                                    Activity                   Date
                                                                                                      st
                                                                    Design Studies                   1 Semester 2017
   1. Environment assessment studies under progress.
                                                                                                     nd
                                                                    Environment Assessment       2 Semester 2017
   2. Complementary design studies are developing                                                      th
                                                                    Call for bidding                 4 Quarter 2017
   3. The MOPW is analyzing PPP conditions                                                             st
                                                                    Receipt of Tenders               1 Quarter 2018

        Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC
PROJECT DATA SHEET                                                        WORKS - PUBLIC WORKS PPP
    - CATEMU RESERVOIR                                                    Updated: MAY 2017

                     Project Information                                                  Location Map

                San Felipe Province, Commune of Catemu in
Location
                Valparaiso Region

                                                  3
                Volume of the reservoir: 180 Hm
Description     Dam wall height: 65 m
of Works        Feeder Channel: 25 km (from Aconcagua River) and
                                  3
                a capacity of 20 m /s

Irrigation
                33,100 Ha and 4,160 rural properties
área
                                   nd   rd   th
River           Lower areas of 2 , 3 and 4 sections of Aconcagua
sections        River

Estimated
                 US$ 423 million – State subsidy near 100 %
investment

Hydroelectric    5 to 10 MW
generation

                The National Department has water rights for 630
Water rights                      nd
                Hm3/year in the 2 section of Aconcagua River. Water
                rights of users equivalent to 70 % during winter.

                        Current Situation                                              Timetable
                                                                        Activity                 Date

                                                                        Environment
                                                                                                 nd
                                                                        Assessment               2 Sem. 2017
Technical studies to review and complement the feasibility of the dam
are performed                                                                                    nd
                                                                        Expropiation             2 Sem. 2017
Study of environmental assessment under progress.                                                nd
                                                                        Bidding process          2 Sem. 2017
Tender conditions in elaboration                                                                 st
                                                                        Receipt of Tenders       1 Sem. 2018

        Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC
   PROJECT DATA SHEET                                                  WORKS - PUBLIC WORKS PPP

                                                                        Updated: MAY 2017
    - LA JAULA RESERVOIR

                     Project Information                                                      Location Map

Location           Commune El Romeral (Teno river), Maule Region                                          SECTOR LA
                                                                                                            JAULA

                                     3
Description of     Capacity: 160 Hm
Works              Dam Wall height: 115 m

Irrigated área     53,045 Has.- Commune of Teno
                                                                                 CURICÓ

Estimated
                   US$ 384 million
Investment

Hydroelectric
                    20 MW (estimated)
Generation

                   The National Department has water rights for 320
Water rights          3
                   Hm in the Teno River from October to January

                         Current Situation                                                  Timetable
                                                                      Activity                    Date

                                                                      Feasibility Studies                2017 - 2019
Prefeasibility studies developed during 2014.
                                                                      Environment
Feasibility studies to be developed by the National Department for                                       2019 – 2020
                                                                      Assessment
Hydraulic Works 2017-2019
                                                                      Design                             2020 – 2021
2017 Evaluation as a potential PPP project
                                                                      Construction                       2022 - 2024

           Source: Department of Irrigation Projects
NATIONAL DEP FPR HYDAULIC WORKS –
PROJECT DATA SHEET                                                PUBLIC WORKS PPP
LA TRANCA RESERVOIR                                               Updated: MAY 2017

                 Project Information

Location
                   Limari Province, commune of Combarbalá,
                   Cogotí River
                   Multipurpose reservoir type CFRD
                                    3
Description of     Capacity: 50 Hm .
Works              Dam wall height: 120 m
                   It includes some complementary works.

Benefits           Commune of Combarbalá inhabitants
                   4,940 Ha of irrigation area and 432 rural
                   properties.
Estimated
Investment         US$ 177 million and 100 % subsidy

Hydroelectric
Generation         2.4 MW

Water rights       Mainly from rural users

                   Current situation                                                 Timetable
                                                               End of basic design          nd
                                                                                           2 Semester 2017
   Complementary design studies under progress                 studies
                                                                                            nd
   Environment assessment studies developing                   End of EAS                  2 Semester 2017
                                                               Call for bidding            End of 2017
                                                                                            rd
                                                               Receipt of Tenders          3 Quarter 2018

           Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC
PROJECT DATA SHEET                                                 WORKS – PUBLIC WORKS PPP
MURALLAS VIEJAS RESERVOIR                                          Updated: MAY 2017

                 Project Information

Location            Limarí Province, commune of
                    Combarbalá, Combarbalá River

Description of
Works                Multipurpose reservoir type CFRD
                                      3
                     Capacity: 50 Hm
                     Dam wall height: 107 m
                     It includes some complementary
                     works

                    Inhabitants and agriculture producers
                    of Combarbalá commune
Benefits
                    2,370 Ha irrigation area and 500 rural
                    properties
                    Rural drinking water programme
Estimated
                    US$ 118 million with 100 % subsidies
Investment

Hydroelectric
                    1 MW
Generation
                    .
Water rights        Mainly from rural users

                  Current Situation                                                  Timetable
                                                               End of basic design        nd
                                                                                         2 Semester 2017
   Complementary design studies under progress                 studies

   Environment assessment studies developing
                                                                                          nd
                                                               End of EAS                2 Semester 2017

                                                               Call for bidding           nd
                                                                                         2 Semester 2017
                                                                                          st
                                                                                         1 Semester 2018
                                                               Receipt of Tenders
       Source: Department of Irrigation Projects

            La Tranca and Murallas Viejas reservoirs will be jointly tendered
BINATIONAL PROJECTS
- Agua Negra Binational Tunnel
PROJECT DATA SHEET                                          CHILE-ARGENTINA
       - AGUA NEGRA BINATIONAL TUNNEL                                              Updated: MAY 2017

                        Project Information                                              Location Map
                   Coquimbo region in Chile and San Juan Province
Location
                   in Argentina
                   Improve integration between Chile and Argentina
Objective          and extend the transportation system with Mercosur
                   countries

Description of          Construction of a tunnel of 13.9 km in the
Works                    Andes Mountains at 3,600 mt of altitude

Economic           Total costs according to the territorial part: 72 %
Conditions         Argentina and 28 % Chile

Estimated
                    US$ 1.4 billion
Investment
Type of
                    Direct public investment financed by IABD
Investment

                        Improve connectivity of Chile and Mercosur
                         countries
Benefits
                        Contribute to the economic development mainly
                         of Coquimbo region and San Juan Province

                           Current Situation                                                Timetable
                                                                         Call for
                                                                                               October 19th, 2016
                                                                         prequalification
   Institutional organization of a binational entity: EBITAN                                   nd
                                                                         Call for Bids         2 Semester 2017
   Prequalification in progress
                                                                                                st
                                                                         Contract award        1 Quarter 2018

           Source: MOP
CONTACTS

PUBLIC DIRECT INVESTMENTS
    Road Projects: Walter Bruning, Director of the National Road
     Department, Morandé 59, 2º piso, Santiago, Chile, email:
     walter.bruning@mop.gov.cl

    Public Building Projects: Claudia Silva, Director of the National
     Department of Architecture, Morandé 59, 10º piso, Santiago, Chile,
     email: claudia.silva.p@mop.gov.cl

    Reservoir Projects: Reinaldo Fuentealba, Director of the National
     Department for Hydraulic Works, Morandé 59, 5º piso, Santiago, Chile,
     email: reinaldo.fuentealba@mop.gov.cl

CONCESSIONS
    Concessions Coordinator: Eduardo Abedrapo, Merced 753, Santiago,
     Chile, email: eduardo.abedrapo@mop.gov.cl

INTERNATIONAL COORDINATION
    International Coordinator MOP: Rigoberto García G., Morandé 59, 6º
     piso, Santiago, Chile, email: rigoberto.garcia@mop.gov.cl