Lessons from Clapham Junction - SNCF WAY OF TESTING December 5th 2013 - IRSE Conference 05/12/2013
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Agenda 1. Major accidents in SNCF at the time of Clapham Junction 2. Signalling issue 3. French Railway maintenance and works organisation 1. New works on a new line 2. New works on an Operational Railway 3. Maintenance Works 4. Comparison between UK and French ways of testing 5. Conclusion CONFIDENCE MOVES THE WORLD IRSE Conference 05/12/2013
1. Major accidents on SNCF network at the time of Clapham Junction disaster. Summer 85 was bloody for SNCF 4 IRSE Conference 05/12/2013
July the 8th 1985. Saint Pierre‐du‐Vauvray : collision of a « Corail» train Le Havre ‐ Paris with a truck at a Level Crossing The train was continued to be pushed by the locomotive after the collision had occurred. 10 people were killed and more than 60 injured. • A system was then introduced to switch off the locomotive’s engine if train integrity is no longer detected. • In parallel, a campaign of subtitution by bridges of dangerous Level Crossings began. 5 IRSE Conference 05/12/2013
August the 3rd 1985. Flaujac : Face to face collision on a single line between a « Corail » train Paris‐Capdenac and an «autorail» Rodez‐Brive Both trains were running at 120 km/h. The signaller of one station made a fatal error. He sent a train before the Autorail arrived in the station. He had no way to contact any of the trains after he had realized his mistake. 35 people were killed. • A controversy raised from this catastrophe. SNCF was reproached for priorising TGV instead of investing in the Classic Network. • A new token block “CAPI” was created to reinforce the safety of secondary lines with simplified Signalling. • The implementation program of track to train radio was re-enforced. 6 IRSE Conference 05/12/2013
August the 31st 1985. Argenton‐sur‐Creuse : Deraillment of a night train Paris to Port‐Bou. The train derailed at 100Km/H. It should had run at 30. With the activation of EB some of the coaches derailed and were foul of the other track, then a Mail Post crossing train hit 2 of the sleeping coaches. The driver was confused by multiple permanent and temporary speed restrictions in the same section. 43 corpses were excavated from the wreckage. • Change of rules for TSR implementation. • The decision to implement an overspeed control system on SNCF Network was re-enforced. 7 IRSE Conference 05/12/2013
3 majors disasters occurred within 2 months in summer 1985. The President of SNCF was fired. In the following years some majors accidents occurred again. The most deadly happened in Paris. 8 IRSE Conference 05/12/2013
27 juin 1988. Paris Gare de Lyon, underground station: A train full of passengers parked on a dead end was strucked at 60km/h by a train with the braking system partially disabled. Following multiple activation of the EB system by rough passengers, the braking system of several coaches was damaged. To carry on the trip, the driver isolated the braking system of several coaches of the train. This was completely forbidden on this old class of train. 56 people died and hundreds were trapped and injured. • Afterwards in suburban Parisian Trains, the Emergency Stop has been replaced by an interphone connected to the driver. • The renewal of trains has been accelerated . • Procedures and systems have been improved to avoid disabling the braking system. 9 IRSE Conference 05/12/2013
Drivers follow up improved In the nineties several Driver/Signaller errors created other deadly accidents: - Train starts without authorization. - Signals passed at danger. - Misunderstanding between Signaller and Driver. Training, audits and follow up of the drivers were improved. 10 IRSE Conference 05/12/2013
Improvement of the Signalling System In parallel to prevent human errors: Some changes in Signalling principles were implemented: - Repeater “crocodile” (equivalent to AWS) were to be installed at every “Sémaphore” (Stop signals) on single lines in order to implement a train stop function. New Systems were introduced or deployed on most of the lines. - KVB (Over-speed and SPAD detection and action on braking) - CAPI (Computer Aided Token Block) for non signalled lines - HBD (hot box detection) 11 IRSE Conference 05/12/2013
2. Signalling issues on SNCF Network In the last decades no major accident was due to SNCF Signalling System fault... 12 IRSE Conference 05/12/2013
Signalling issues ….Except on the 12/12/2001 where a train collided with the one in advance… IRSE Conference 05/12/2013 Page 13
December the 12th 2001. Lyon St Clair. A Fret train collided with an other Fret train. The wire’s poor insulation of an old cable allowed signalling circuits to be bypassed (despite double cutting!). Then a green light was displayed to the second train with the ahead Track Circuit occupied. Nobody was killed but drivers of the second train where injured. • Once the issue was known, a national Campaign was immediately set up to measure the insulation of the same sort of cables. The more deteriorated cables were replaced in emergency. • A plan to change the old cables (and the type of the faulty one in priority) has been implemented… 14 IRSE Conference 05/12/2013
3. French Railway maintenance and works organisation Since the end of the nineties, RFF is the owner of the infrastructure. RFF has delegated the railway maintenance to SNCF which was the historical owner and maintainer. Therefore SNCF is the only one company approved to work on the Operational Railway. A contractor can work in a protected area put in place by SNCF staff. Therefore only SNCF staff is allowed to manage possessions. Things will change with “PPP” process… 15 IRSE Conference 05/12/2013
Signalling Works 3 sorts of works are to be considered in French Railway 1. New works on a new line 2. New works on an Operational Railway 3. Maintenance Works IRSE Conference 05/12/2013 Page 16
3.1. New Works on a New Line Validation Process for a New Signalling System is now international This process is for computer- based interlokings 17 IRSE Conference 05/12/2013
Application of the « V » cycle on a French Project Each step of testing is certified by a « Procés Verbal » 18 IRSE Conference 05/12/2013
Signalling testing phases on New Lines Signalling Testing Phases Factory On site Phase Phase 1 Phase 2.1 Phase 2.2 Phase 2.3 Phase 3 Phase 4 Phase 5 Name Trial Run Factory Acceptance Test Technical Verifications Pre‐tests Line Side Integration Integration of others Dynamic Tests Drivers, Signallers Cert Checkings/Tests in Factory Installation check Power up the equipement Track Side connected Integration with other Dynamic Validation tests Runs with theTime Table Site Acceptance Tests Local Integration of Systems Dynamic System Integration Degraded Mode Tunning of sub systems Line side Equipments Operationnal Tests Drivers, Signallers Cert Sub Systems Integration from IXL and from SCC Dedicated "pre" Activity I/O testing with dummy TS dynamic tests Local tests Factory Test Plan Static Int Test Plan Static Int Test Plan Static Int Test Plan Static Test Plan Dynamic Test Plan Factory Test specifications Maintenance procedures Maintenance procedures Maintenance procedures Test Specifications Dynamic Test Scenarios Input Docs TV Test Specifications Test Specifications Test Specifications Operationnal Scenarios Scheme Plan, CT Scheme Plan, CT Factory Acceptance Cert Static Int Test Plan Site Acceptance Cert Maintenance sheets Static Integration TC Dynamic integration TC Drivers, Signallers Maintenance procedures Maintenance Sheets Static Test Certificates Commissioning Certificate Certifications TV Test Specifications (TC1) Certificates All SP, CT DD validated Output docs Transfert to the Operator Hardware Chipment & Installation for sig Rooms and SCC AQ Process Building& Equipemnt Room Ready Chipment & Site Installation for Track Side Equipment AQ Process to monitor quality of implementation Power Supply Installation and Tests Other Activities FTN SCC Installation and tests FTN Trackside Installation and tests IXL, RBC Software Production & Factory Integration & Validation GSMR Installation and tests EMC Measurments Trains fitment and tests Maintenance Cycle to be implemented for sub systems put in use Maintainers Training and Certification Drivers, Signallers Training and Certification 19 IRSE Conference 05/12/2013
Phases of Tests for a new Line ‐ Factory Tests ‐ Installation Check ‐ Technical Verification ‐ Pre‐Tests ‐ Integration Tests ‐ Integration Tests with Others ‐ Dynamic Tests ‐ Commissioning ‐ Trial Run IRSE Conference 05/12/2013 20
Phase 1 Factory Tests ‐ Hardware Factory Acceptance Tests to ensure hardware is fit for purpose ‐ Software Tests (Validation and integration) IRSE Conference 05/12/2013 21
Installation check The PAQ (Assurance Quality Plan) application ensures good practice and defines steps of verification and tests to be completed up to the installation achievement. 2 gates of control are applied during installation ‐ “Point d’arrêt”: predefined step where the client must attend to witness a certain task (e.g. first installation of an equipment). The work only carries on if the client is happy with the task he has witnessed. ‐ “Point de contrôle”: predefined step where the contractor must inform the client when and where a task is to be undertaken. If the client is not there, the contractor carries on the work. IRSE Conference 05/12/2013 22
Phase 2.1: Technical Verifications Technical Verifications consist in checking the quality of installation Location of equipment Installation conformity Label check Continuity of wires Wire counting Insulation check Mark up of drawings Earth Measurement Earth connexion Cable Testing Mechanical adjustments 23 IRSE Conference 05/12/2013
Phase 2.2: Pre‐tests Pre‐testing Power up equipment Insulation measurment I/O allocations check (computerised systems) Adresses check (computerised systems) Local integration with dummy track side… Calibration of equipment Double cutting of external circuit Local tests for each individual circuit Build up of calibration references Safety tests 24 IRSE Conference 05/12/2013
Phase 2.3: Integration tests • Local Integration from Signalling equipment room to track side • Remote Integration from the SCC (end to end tests) • Tests between interlockings (SR to SR) • Functional and Operational Tests • Degraded Mode Tests IRSE Conference 05/12/2013 Page 25
Phase 3: Integration tests with other Systems • Interface Tests with other Lines • Integration with other Systems • Interface degraded mode tests • Dedicated Technical Verification before OHLE is supplied • Dedicated tests for others including some special trains for Track, OHLE, Radio…. • OHLE is powered up IRSE Conference 05/12/2013 Page 26
Phase 4: Dynamic Tests • Dynamic specific runs • Dynamic integration • Dynamic Operational Tests • Dynamic degraded mode tests IRSE Conference 05/12/2013 27
Commissioning • Test of the System in the Operational Configuration • Static Confidence Tests • Dynamic Confidence Tests IRSE Conference 05/12/2013 28
Phase 5: Trial Run • Time table tests • Safety tests • Final Operators’ Training • Operational tests • Permit to Use IRSE Conference 05/12/2013 29
3.2. New works on an Operational Railway On operational lines phases of test are sequenced by the construction phases Stage test works are to be designed to coordinate with the construction phase and to not affect the operation. A migration strategy is to be built up. Over‐and‐back process is implemented in order to give back the System to the Operator at the end of each test shift. The works on operational lines are mostly during night shifts once the passenger service is over; therefore the work and test duration is reduced for operation to be able to resume early in the morning. IRSE Conference 05/12/2013 30
New works on an Operational Railway (2) Stage works and relevant documentation supported by a robust configuration management and methodology of wiring change are the only way to not interrupting the operation in a safe way. IRSE Conference 05/12/2013 31
3.3. Maintenance Works Maintenance Works Maintenance works are like for like replacement of equipment. They are performed by maintenance people or specialized SNCF team and carried out between trains during day shift (at night in some big centres). IRSE Conference 05/12/2013 32
4. Comparison between UK and French ways of testing (1) Responsibility for testing phases for New Works and Maintenance Stage France UK Comments Platform tests SNCF** Contractor* Data integration & validation Installation Contractor Contractor* Installation check Contractor Contractor AQ Process Technical Verifications SNCF ** Contractor* Hand over to test Pre‐Tests SNCF ** Contractor* Static Tests SNCF ** Contractor* Dynamic Tests SNCF ** Contractor* Principle Tests NR Commissioning SNCF Contractor*/NR * NR supervision ** PPP with SNCF supervision Tests after maintenance works and before handing over to operation are exclusively made by SNCF staff. IRSE Conference 05/12/2013 33
Comparison between UK and French ways of testing (2) Testing Documentation Document France UK Comments Strategy Stratégie d’essais Test Strategy Test Plan Programme de Test Plan Now « Contrat de Travaux Travaux » for SNCF References IN SNCF NR Standards Test Procedure Procédure d’essais Test Procedure/ New systems Specification Test record sheet Fiche d’essais Test record sheet Fault record Fiche d’analyse Test Log Design copies for Collections essais Testing sets Design Documents are testing validated by ticking in both countries Updated drawing Retour Chantier Red Line Final issue from Copie Conforme As Built Design Certificates PV VT et Essais Test certificates IRSE Conference 05/12/2013 34
Comparison between UK and French ways of testing (3) Organisation of works and tests France UK Work generally in day shift (excepted Work in night shift when the Lines are where it is not possible with the traffic) closed for traffic. With competent Persons In Charge SNCF manages the safety for contractors Routine Maintenance is completed on day Maintenance during night shift. shift by SNCF staff. On call system out of the shift Duty maintainer all the time on site. 35 IRSE Conference 05/12/2013
Comparison between UK and French ways of testing (4) Formation / Habilitation of Testers France UK Training Training Testers are from SNCF staff therefore they are trained IRSE with the individual technical and experience and qualified in Signalling works and tests. follow up guaranties the competence of tester. 2 complementary Modules for testers: ‐ Essais simples ‐ Essais complexes The certification of Testers for PPP is made through a training approved by EPSF Assessment Assessment Testers are assessed by the SNCF Technical Manager TIC assessed by NR Testing & Commissioning Manager (Project or Maintenance) Testers assessed by TIC. Follow up Follow up Plan de veille held by the Manager Individual IRSE Log Book and follow up by the Company 36 IRSE Conference 05/12/2013
5. Conclusion Until now SNCF has kept the Management of Maintenance and Testing. With the introduction of PPP for new lines (SEA, CNM, BPL…) SNCF GID (Gestionnaire de l’Infrastructure Délégué) only completes the final integration and the Commissioning. MOE and the contractor performs all the tests with the approval of the GID. This is possible only in an isolated environment from operation. This safe environment is created by the Project (New Line or part of line frozen for the works or by SNCF Maintenance Staff during the period of Work and Test) SNCF performs confidence tests to hand back System to operation. Also with PPP contractors have got the Maintenance for 10 or 25 years. Certification of Maintainers and Testers from other companies is becoming possible through training centres approved by EPSF. 37 IRSE Conference 05/12/2013
You can also read